GENERAL INFORMATION

To be filled by the requester & checked by the Hot work Permit Approver.
Location:
Description of work 1.Welding 2. Brazing 3. Cutting 4. Grinding 5.Soldering 6.Torch-Applied Roofing (Tick√ whichever is applicable)
PRE-OPERATION
Are all welding operators trained/certified? Provide certificate Yes
Are all instructions clear and understood by operators? yes
OPERATORS Are all welding operators familiar with the welding machine? Yes
Are all welding operators aware of the type of materials to be welded? Yes
Do all welding operators wear proper PPE? Welding glove, glasses, shields/fire rated coverall? Yes
Are welding operators aware of all safety and emergency protocols? Yes
Are all welding cables, wirings, and electrode holder insulation in good working condition? Yes
WELDING MACHINE Are all welding terminals and joints in good working condition? Yes
Is suitable Cable provided for voltage supply? Yes
Is the work area clean and free of flammables and obstructions? Yes
Is the work area well ventilated? Yes
Is there a suitable Class ABC fire extinguisher nearby while welding? Yes
Are combustible floors protected? Yes
Are combustible walls shielded or guarded? Yes
Is a fire blanket available within the area? Yes
WORK AREA Are warning signs placed within the area? Yes
Is work area restricted to regular employees? Yes
Is the area of 35 ft radial “sphere” of work for potential fire hazards safely secured? As applicable. Yes
Are flammable liquids, dust, lint, combustible waste, oil deposits, etc., where possible removed?. Yes
Is Continuous fire watch provided by the contractor during and for at least 30 minutes after hot work, including all breaks ? Yes
Does the Fire watch trained in the use of fire equipment and sounding alarm? Yes
Area to be monitored hourly for a minimum 6 hours after job is completed, or longer if required. Yes
Does,Area smoke or heat detection disabled to eliminate false trip? Yes
Yes
No