Score 1 of 1
Question:
How do you achieve frequent checkpoints with the End User in an?
There are 2 correct answers to this question.
Response:
Score 1 of 1
Question:
Response:
The three ceremonies are sprint planning, daily scrum, sprint review
(retrospective).
In Scrum, the team is Self-organized, define all task necessary for all
project life cycle.
Score 1 of 1
Question:
How can the project manager help to keep momentum in the project and help
to keep the customer involved?
There are 2 correct answers to this question.
Response:
Add customer resources to the project to reduce the need for formal trainin
Score 1 of 1
Question:
Response:
Baseline Build
Score 1 of 1
Question:
What is the key difference between Notes and Requirements in the Change and
Deploy capability of SAP Cloud ALM?
Please choose the correct answer.
Response:
How many deliverables are a part of the Key Deliverable 'Project Initiation'?
Please choose the correct answer.
Response:
Three
Two
Four
One
Score 1 of 1
Question:
What are the responsibilities of the Product Owner in release and sprint
planning?
There are 2 correct answers to this question.
Response:
Analyze the functional and technical dependencies between the user stories
Score 1 of 1
Question:
Which of the following activities are part of the Deploy Phase of a Landscape
Transformation journey to SAP S/4HANA On-Premise Edition?
There are 2 correct answers to this question.
Response:
Access organizational and production readiness
Training delivery
Solution Activation
Score 1 of 1
Question:
Response:
Score 0 of 1
(skipped)
Question:
Which key activities does the Guided Configuration support you with?
There are 3 correct answers to this question.
Response:
Score 0 of 1
Question:
In which phase of the SAP Activate methodology does the team complete the
Transformation Planning?
Please choose the correct answer.
Response:
Explore
Deploy
Realize
Prepare
Score 1 of 1
Question:
Response:
End a sprint when the sprint backlog items are all complete
Score 1 of 1
Question:
What are some of the values of SAP Cloud ALM for operations?
There are 3 correct answers to this question.
Response:
It provides reduced cost of operations.
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
How would you describe the Explore phase in the "New Implementation of SAP
S/4HANA Cloud" transition path?
Please choose the correct answer.
Response:
Fit-to-standard
Score 1 of 1
Question:
Which accelerator can help you document the detailed design of solution
extensions?
Please choose the correct answer.
Response:
Score 1 of 1
Question:
Response:
Explore
Prepare
Realize
Deploy
Score 1 of 1
Question:
What is the best target environment for a System Conversion journey is as
described in the SAP Activate methodology?
Please choose the correct answer.
Response:
SAP Hybris
Score 1 of 1
Question:
Response:
Predictable results
Fast Time-to-Value
Score 0 of 1
Question:
What capabilities does SAP API Business Hub pro ide to help you select
integration options for your project?
There are 3 correct answers to this question.
Response:
Score 0 of 1
Question:
What is the term used for workshops, which are intended to set value targets,
validate SAP Standard functionality against customer requirements.
Response:
Fit-to-Standard
Delta Design
Design Thinking
Solution Validation
Score 1 of 1
Question:
Arrange the following in the correct sequence of steps followed for a 'Fit to
Standard' workshop.
Please choose the correct answer.
Response:
Score 1 of 1
Question:
Which of the following activities are performed in the Explore phase of SAP
Activate in SAP S/4HANA Implementation?
There are 3 correct answers to this question.
Response:
Organizational structure
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
Which of the following tasks are part of the Production support after the Go
Live key deliverable?
There are 2 correct answers to this question.
Response:
Score 1 of 1
Question:
Response:
By work stream
By project phase
By job title
Score 1 of 1
Question:
Response:
Optional information that is NOT important for project activities
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
Response:
Integration topics
Backlog management
Response:
Enhancement Delivery
Sprint Execution
Development Build
Score 1 of 1
Question:
In which phase of the SAP Activate methodology does the team complete the
Cut-over Rehearsal?
Please choose the correct answer.
Response:
Prepare
Realize
Deploy
Explore
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
Response:
SAP Activate
Score 1 of 1
Question:
SAP now offers the ability to deploy and manage solutions in which of the
following environments?
Please choose the correct answer.
Response:
Cloud
On-premise
Score 1 of 1
Question:
What tool would you use for managing project tasks and Solution
Documentation when implementing SAP S/4HANA Cloud?
Please choose the correct answer.
Response:
Score 1 of 1
Question:
Response:
Prepare
Explore
Deploy
Realize
Score 1 of 1
Question:
Response:
Blueprint scheduling
Sprint planning
Release planning
Score 1 of 1
Question:
Response:
Fit/Gap Workshops
Value Determination
Score 0 of 1
Question:
Response:
Predictable results
Score 1 of 1
Question:
In which SAP Activate methodology phase does the team identify and design
functional quick wins in scope of the conversion project?
Please choose the correct answer.
Response:
Prepare
Explore
Deploy
Realize
Score 1 of 1
Question:
Response:
Value determination
Score 1 of 1
Question:
Response:
Waterfall approach
Design-based
Response:
Integration Content
End-User guides
Migration Content
Score 1 of 1
Question:
What term is used for a Ready-to-run SAP S/4HANA system with pre-built
Solution Documentation, which supports End-to-End Processes for a specific
industry so that the Project Team can focus on differentiation and innovation?
Please choose the correct answer.
Response:
Score 0 of 1
Question:
In which phase should you first run the SAP Readiness Check for SAP S/4HANA
in a "Selective Data Transition" transition path, in a System Consolidation
scenario that includes conversion from SAP ERP?
Please choose the correct answer.
Response:
Realize
Prepare
Explore
Discover
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
When does the Scrum Team receive formal confirmation that the User Stories
are completed to the satisfaction of the Product Owner?
Please choose the correct answer.
Response:
Who determines the priority of user stories in the backlog of an Agile project?
Please choose the correct answer.
Response:
Product Owner
SCRUM Master
Project Manager
Project Team
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
Which of the following are available in the initial SAP Methodologies JAM Page?
There are 2 correct answers to this question.
Response:
Task description
Roadmaps
Summary
Accelerators
Score 1 of 1
Question:
Response:
Because the project team uses the DEV system to confirm solution fit and d
requirements
Score 1 of 1
Question:
When does the project team receive formal confirmation that the user stories
are completed to the satisfaction of the product owner?
Please choose the correct answer.
Response:
Score 1 of 1
Question:
In which phase do you verify that the SAP Best Practice solution scenarios meet
the business needs of the customer?
Please choose the correct answer.
Response:
Explore
Deploy
Prepare
Realize
Score 1 of 1
Question:
Response:
Software configurations
Score 1 of 1
Question:
Which of the following is part of the Explore phase in the "New Implementation
of SAP S/4HANA Cloud' transition path?
Please choose the correct answer.
Response:
Fit-to-standard
Setup and Enablement
Score 1 of 1
Question:
How do you gain access to the SAP Activate Methodology Jam site?
Please choose the correct answer.
Response:
Score 1 of 1
Question:
In which phase should you create a Data Migration Strategy (LO) during a
Selective Data Transition?
Please choose the correct answer.
Response:
Realize
Discover
Explore
Deploy
Score 1 of 1
Question:
Response:
Iterative build with frequent inspections
Score 1 of 1
Question:
What tool provides guidance on replacing custom code developed for SAP ERP
with SAP S/4HANA functionality for the "System Conversion" transition path?
Please choose the correct answer.
Response:
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
After each Sprint
Score 1 of 1
Question:
What is the correct sequence of selected key deliverables across the project
phases?
Please choose the correct answer.
Response:
a. Code adjustment
b. Detailed System Assessment
c. Production Readiness Check
d. Validation of Migration
Score 1 of 1
Question:
Which of the following tools are used for rapid database migration?
There are 2 correct answers to this question.
Response:
Score 1 of 1
Question:
Which tool can you use to collaborate with other SAP Activate methodology
practitioners?
Please choose the correct answer.
Response:
SAP Jam
Roadmap Viewer
Score 1 of 1
Question:
Response:
Test Strategy
Backlog template
Score 1 of 1
Question:
Which of the following is not a characteristic that the quality principles are
based on?
Please choose the correct answer.
Response:
International standard
Best Practices
Score 1 of 1
Question:
Response:
Fixed scope
Cloud Ready
On premise only
Delta-based
Score 1 of 1
Question:
Score 1 of 1
Question:
Which of the following Key Deliverables do you complete in the Solution Design
work stream in the Explore phase?
There are 3 correct answers to this question.
Response:
Validation Workshops
Baseline Build
Score 1 of 1
Question:
Which of the following activities are part of the Realize Phase of a System
Conversion journey to SAP S/4HANA On-Premise Edition?
There are 3 correct answers to this question.
Response:
Delta configuration
Score 1 of 1
Question:
Response:
Guided Configuration
Score 1 of 1
Question:
What is the hierarchy level under Phase in the SAP Jam space for SAP Activate
on-premise?
Please choose the correct answer.
Response:
Scenario
Key Deliverable
Work Stream
Task
Score 0 of 1
(skipped)
Question:
What are the core capabilities in SAP Cloud ALM for operations?
There are 3 correct answers to this question.
Response:
Upgrade analysis
Operation automation
Monitoring
License management
Score 0 of 1
(skipped)
Question:
Response:
Relative estimate in ideal person days that reflects the best estimate
provided by the project team
Score 1 of 1
Question:
Response:
Deploy
Final Preparation
Realize
Score 0 of 1
Question:
Response:
Score 0 of 1
(skipped)
Question:
What does SAP Activate recommend to keep team members informed and
aligned?
Please choose the correct answer.
Response: