LABOUR SCHEDULE

ITEM STAGE CHARGE

1 SETTING OUT AND SITE CLEARANCE 50


2 EXCAVATIONS 200
3 CONCRETE FOOTING 300
4 FOUNDATION BOX 250
5 CONCRETE SLAB 350
6 WINDOW LEVEL 250
7 DOOR HEIGHT 200
8 BEAM FILLING 200
9 ROOFING 900
10 PLASTERIG(IN & OUT) 500
11 FLOORING(SCREED ONLY) 420
12 TILING 600
13 PAITING 300
14 CEILING 900
15 DEMOLITIONS 80
16 VERANDA BEAM CASTING 100
17 PLUMBING 300
18 ELECTRICAL WORKS 700

6600