Work done
 Cleanup of the access road to the uranium pit and the WP area
 Developing access road in Antirimena pit
Plan for next week
 First trial blast in Ankaramavo
 Preparation of the second panel for blasting in Ankaramavo
 Start the work with machinery in Antirimena

Mining
Plan for three months
 Pit design and mine planning to be completed for Ankaramavo and Antirimena following the
Geological data
 Finalization of the optimum drill and blast parameters with jack drill
 Target in Ankaramavo: 500 T/blast. 2 times per week. Then, Around 4 000 T per month.
Manpower
 One blaster