Mining

Work done
 D4 alternator repair done
 Repair of the exhaust damaged in the excavator 215: Done
 Replacement of final drive, brake and translation D4 seals: Done
 List of all the different filters in each machine: Done
Plan for next week
 Data preparation and acquisition for medium-term (tactical) and short-term (operational) mine
planning
 Transporter/Renault truck has to be in Fort Dauphin for diesel and construction materials.
 Big tire for TLB will be sent for fixing
 modeling of pit evolution
 If we have diesel, pit cleanup with dozer and excavator will continue

Constrains, action taken and possible solution:


 Batteries available not enough to start all machines in the pit.
 Need to order the following parts: one diesel filter and two oil filters for the Renault truck, New
injectors for the D9, New cylinder head gasket to the excavator 350 II, cable to the excavator
350 I
Civil and construction
Work done
 Setting up formwork for pouring concrete (Single bed bungalow): Done
 Property concrete pouring in the kitchen house: Done
 kitchen room foundation construction: ongoing
 Collecting wood for bricks firing: 2trips was done
 50 planks collected: which gives us a total of 80 planks delivered

Plan for next week


 kitchen room foundation construction will continue
 Other step of construction can begin if one obtains the iron and the cement.
Constrains, action taken and possible solution:
 Waiting for iron, cement, nail, annealed wire.