Professional Documents
Culture Documents
PART -1
50
CONTRACT
MANAGEMENT
TERMINOLOGIES
YOU NEED TO KNOW AS A CONTRACTS PRO
parithi
Ilam
01
CONTRACT
parithi
Ilam
02
SCOPE OF WORK
(SOW)
Detailed description of the
work to be performed under
the contract.
parithi
Ilam
03
BID DOCUMENT
The set of documents that
provide information to
potential bidders for a
construction project
parithi
Ilam
04
REQUEST FOR
PROPOSAL (RFP)
A document that solicits
proposals from potential
contractors.
parithi
Ilam
05
CONTRACTOR
The party responsible for
executing the construction
work as per the contract.
parithi
Ilam
06
OWNER
The party who owns the
construction project and enters
into the contract
parithi
Ilam
07
SUBCONTRACTOR
A contractor hired by the main
contractor to perform a specific
portion of the work
parithi
Ilam
08
CHANGE ORDER
An amendment to the original
contract that outlines changes
in scope, time, or cost
parithi
Ilam
09
LIQUIDATED
DAMAGES
Pre-determined damages
payable by the contractor for
specific delays or breaches
parithi
Ilam
10
FORCE MAJEURE
parithi
Ilam
11
PERFORMANCE
BOND
A guarantee that the
contractor will perform the
work as specified in the
contract
parithi
Ilam
12
RETENTION
A percentage of the contract
amount withheld until the
completion of the project.
parithi
Ilam
13
INDEMNIFICATION
The act of compensating for
loss or damage
parithi
Ilam
14
PENALTY CLAUSE
A provision specifying penalties
for non-compliance with
contract terms.
parithi
Ilam
15
MILESTONE
A significant event or stage in a
construction project
parithi
Ilam
16
VALUE
ENGINEERING
A systematic review to improve
project value without
sacrificing performance
parithi
Ilam
17
DEFECTS
LIABILITY PERIOD
The timeframe during which
the contractor is responsible
for rectifying defects at no
additional cost
parithi
Ilam
18
PROGRESS
PAYMENT
Payments made to the
contractor based on the
completion of specific project
milestones
parithi
Ilam
19
COST-PLUS
CONTRACT
A contract in which the owner
agrees to reimburse the
contractor for the actual costs
of the work plus a fee
parithi
Ilam
20
CERTIFICATE OF
COMPLETION
A document confirming that
the construction work has been
completed as per the contract
parithi
Ilam
21
BID BOND
A guarantee that a bidder will
enter into a contract if awarded
parithi
Ilam
22
TIME EXTENSION
parithi
Ilam
23
GENERAL
CONDITIONS
Standard terms and conditions
that apply to all contracts
parithi
Ilam
24
SUBSTANTIAL
COMPLETION
The stage where the project is
sufficiently completed for its
intended use
parithi
Ilam
25
CONTRACT SUM
The total amount agreed upon
for the construction project
parithi
Ilam
26
DISPUTE
RESOLUTION
Procedures for resolving
disagreements between parties
parithi
Ilam
27
OWNER'S
REPRESENTATIVE
A person or entity representing
the owner's interests during
the construction process
parithi
Ilam
28
PROCUREMENT
The process of acquiring goods,
services, or construction
parithi
Ilam
29
DESIGN-BUILD
parithi
Ilam
30
DISBURSEMENT
SCHEDULE
A plan outlining when
payments will be made during
the project
parithi
Ilam
31
WARRANTY
PERIOD
parithi
Ilam
32
PUNCH LIST
A list of minor issues or
incomplete items that need to
be addressed before final
acceptance
parithi
Ilam
33
CLOSEOUT
parithi
Ilam
34
CONSEQUENTIAL
DAMAGES
Damages that result indirectly
from a breach of contract
parithi
Ilam
35
BREACH OF
CONTRACT
Failure to fulfill contractual
obligations, leading to legal
consequences
parithi
Ilam
36
BACKCHARGE
The process of charging a
contractor for costs incurred
due to their failure to meet
contractual obligations
parithi
Ilam
37
LIQUIDATION
DAMAGES CAP
The maximum amount of
liquidated damages that can be
assessed against the contractor
parithi
Ilam
38
SUSPENSION OF
WORK
Outlines conditions permitting
one party to temporarily
suspend or delay the
construction work
parithi
Ilam
39
DEFAULT
parithi
Ilam
40
CONFIDENTIALITY
parithi
Ilam
41
GOVERNING LAW
Specifies the jurisdiction and
legal framework that govern
the interpretation and
enforcement of the contract
parithi
Ilam
42
HOLD HARMLESS
An agreement where one party
agrees to indemnify and shield
the other from specified
liabilities or claims
parithi
Ilam
43
NOTICES
parithi
Ilam
44
SPECIAL
CONDITIONS
Additional terms and
requirements specific to the
project, supplementing the
general conditions and
addressing unique project
aspects
parithi
Ilam
45
LIEN WAIVER
A document by which a party
gives up the right to place a lien
on the owner's property
parithi
Ilam
46
EPC CONTRACT
parithi
Ilam
47
NOTICE OF
DEFAULT
A written notice indicating that
a party has failed to fulfill its
contractual obligations
parithi
Ilam
48
JOINT VENTURE
A partnership between two or
more entities to jointly
undertake a construction
project
parithi
Ilam
49
ESCROW
AGREEMENT
A three-party agreement
where funds or documents are
held until specified conditions
are met
parithi
Ilam
50
DEFAULT
TERMINATION
The termination of a contract
due to a party's failure to fulfill
its obligations
parithi
Ilam
Was this Tip
helpful to you?
Disclaimer: The information in this book is distributed on an “as is” basis, without warranty. Although every precaution has been taken in the preparation of this
hi
work, neither the author nor the publisher shall have any liability to any person or entity with respect to any loss or damage caused or alleged to be caused directly
rit
or indirectly by the information contained in this book. Please contact us if you require Claim / legal assistance on ilam@pragmaticpc.com
lampa
I