You are on page 1of 52

KNOW YOUR CONTRACT #17

PART -1

50
CONTRACT
MANAGEMENT
TERMINOLOGIES
YOU NEED TO KNOW AS A CONTRACTS PRO

parithi
Ilam
01

CONTRACT

A legally binding agreement


between two or more parties

parithi
Ilam
02

SCOPE OF WORK
(SOW)
Detailed description of the
work to be performed under
the contract.

parithi
Ilam
03

BID DOCUMENT
The set of documents that
provide information to
potential bidders for a
construction project

parithi
Ilam
04

REQUEST FOR
PROPOSAL (RFP)
A document that solicits
proposals from potential
contractors.

parithi
Ilam
05

CONTRACTOR
The party responsible for
executing the construction
work as per the contract.

parithi
Ilam
06

OWNER
The party who owns the
construction project and enters
into the contract

parithi
Ilam
07

SUBCONTRACTOR
A contractor hired by the main
contractor to perform a specific
portion of the work

parithi
Ilam
08

CHANGE ORDER
An amendment to the original
contract that outlines changes
in scope, time, or cost

parithi
Ilam
09

LIQUIDATED
DAMAGES
Pre-determined damages
payable by the contractor for
specific delays or breaches

parithi
Ilam
10

FORCE MAJEURE

Unforeseeable events that may


excuse a party from fulfilling
contractual obligations

parithi
Ilam
11

PERFORMANCE
BOND
A guarantee that the
contractor will perform the
work as specified in the
contract

parithi
Ilam
12

RETENTION
A percentage of the contract
amount withheld until the
completion of the project.

parithi
Ilam
13

INDEMNIFICATION
The act of compensating for
loss or damage

parithi
Ilam
14

PENALTY CLAUSE
A provision specifying penalties
for non-compliance with
contract terms.

parithi
Ilam
15

MILESTONE
A significant event or stage in a
construction project

parithi
Ilam
16

VALUE
ENGINEERING
A systematic review to improve
project value without
sacrificing performance

parithi
Ilam
17

DEFECTS
LIABILITY PERIOD
The timeframe during which
the contractor is responsible
for rectifying defects at no
additional cost

parithi
Ilam
18

PROGRESS
PAYMENT
Payments made to the
contractor based on the
completion of specific project
milestones

parithi
Ilam
19

COST-PLUS
CONTRACT
A contract in which the owner
agrees to reimburse the
contractor for the actual costs
of the work plus a fee

parithi
Ilam
20

CERTIFICATE OF
COMPLETION
A document confirming that
the construction work has been
completed as per the contract

parithi
Ilam
21

BID BOND
A guarantee that a bidder will
enter into a contract if awarded

parithi
Ilam
22

TIME EXTENSION

Additional time granted to the


contractor to complete the
project due to unforeseen
circumstances

parithi
Ilam
23

GENERAL
CONDITIONS
Standard terms and conditions
that apply to all contracts

parithi
Ilam
24

SUBSTANTIAL
COMPLETION
The stage where the project is
sufficiently completed for its
intended use

parithi
Ilam
25

CONTRACT SUM
The total amount agreed upon
for the construction project

parithi
Ilam
26

DISPUTE
RESOLUTION
Procedures for resolving
disagreements between parties

parithi
Ilam
27

OWNER'S
REPRESENTATIVE
A person or entity representing
the owner's interests during
the construction process

parithi
Ilam
28

PROCUREMENT
The process of acquiring goods,
services, or construction

parithi
Ilam
29

DESIGN-BUILD

A project delivery method


where the design and
construction are contracted to
a single entity

parithi
Ilam
30

DISBURSEMENT
SCHEDULE
A plan outlining when
payments will be made during
the project

parithi
Ilam
31

WARRANTY
PERIOD

The period during which the


contractor warrants the quality
of their work

parithi
Ilam
32

PUNCH LIST
A list of minor issues or
incomplete items that need to
be addressed before final
acceptance

parithi
Ilam
33

CLOSEOUT

The final phase of the project


involving paperwork,
inspections, and final payments

parithi
Ilam
34

CONSEQUENTIAL
DAMAGES
Damages that result indirectly
from a breach of contract

parithi
Ilam
35

BREACH OF
CONTRACT
Failure to fulfill contractual
obligations, leading to legal
consequences

parithi
Ilam
36

BACKCHARGE
The process of charging a
contractor for costs incurred
due to their failure to meet
contractual obligations

parithi
Ilam
37

LIQUIDATION
DAMAGES CAP
The maximum amount of
liquidated damages that can be
assessed against the contractor

parithi
Ilam
38

SUSPENSION OF
WORK
Outlines conditions permitting
one party to temporarily
suspend or delay the
construction work

parithi
Ilam
39

DEFAULT

The failure of either party to


fulfill contractual obligations,
along with the associated
consequences and procedures

parithi
Ilam
40

CONFIDENTIALITY

Protects sensitive information


shared during the contract,
restricting its disclosure

parithi
Ilam
41

GOVERNING LAW
Specifies the jurisdiction and
legal framework that govern
the interpretation and
enforcement of the contract

parithi
Ilam
42

HOLD HARMLESS
An agreement where one party
agrees to indemnify and shield
the other from specified
liabilities or claims

parithi
Ilam
43

NOTICES

Defines the formal


communication process,
specifying how and where
notices and communications
should be delivered

parithi
Ilam
44

SPECIAL
CONDITIONS
Additional terms and
requirements specific to the
project, supplementing the
general conditions and
addressing unique project
aspects

parithi
Ilam
45

LIEN WAIVER
A document by which a party
gives up the right to place a lien
on the owner's property

parithi
Ilam
46

EPC CONTRACT

A lumpsum contract for


Engineering Procurement and
Construction services

parithi
Ilam
47

NOTICE OF
DEFAULT
A written notice indicating that
a party has failed to fulfill its
contractual obligations

parithi
Ilam
48

JOINT VENTURE
A partnership between two or
more entities to jointly
undertake a construction
project

parithi
Ilam
49

ESCROW
AGREEMENT
A three-party agreement
where funds or documents are
held until specified conditions
are met

parithi
Ilam
50

DEFAULT
TERMINATION
The termination of a contract
due to a party's failure to fulfill
its obligations

parithi
Ilam
Was this Tip
helpful to you?

Like | Comment | Share | Follow

Disclaimer: The information in this book is distributed on an “as is” basis, without warranty. Although every precaution has been taken in the preparation of this

hi
work, neither the author nor the publisher shall have any liability to any person or entity with respect to any loss or damage caused or alleged to be caused directly

rit
or indirectly by the information contained in this book. Please contact us if you require Claim / legal assistance on ilam@pragmaticpc.com

lampa
I

You might also like