Conclusion
The survey camp took five weeks to finish. the total no.of the established control points
are twenty (21). Four (4) in Tangid, four (4) in Nalbo, five (5) in Bengcag, four (4) in Buttong
and four (4) in Darayday. Including the kilometer post and monuments, the number of
established control points where the data is gathered are a total of twenty-six (26). Therefore, the
result of the observation has different outcomes, however, the PRS 92 serves as the country’s
standard coordinate reference system for all survey and mapping activities. It is based on
internationally recognized standards, making it easier to share and exchange data with other
systems globally. Local coordinate systems might be suitable for small-scale projects that are
confined to a specific region. However, if the project is expected to expand, or if the data need to
remain accurate over time, using a standardized system like PRS 92 can help ensure stability and
Recommendation
The survey took too long to finish due to the inclement weather. Before conducting the
survey, it is important to complete the necessities of the survey team. From proper attire for sun
and rain protection, to transportation, and also the instrument to be used and other materials for