You are on page 1of 18

Expert Systems With Applications 169 (2021) 114471

Contents lists available at ScienceDirect

Expert Systems With Applications


journal homepage: www.elsevier.com/locate/eswa

Ordered fuzzy WASPAS method for selection of improvement projects


Katarzyna Rudnik a, *, Grzegorz Bocewicz b, Aneta Kucińska-Landwójtowicz a, Izabela D. Czabak-
Górska a
a
Faculty of Production Engineering and Logistics, Opole University of Technology, Sosnkowskiego 31, Opole, Poland
b
Faculty of Electronics and Computer Science, Koszalin University of Technology, Śniadeckich 2, Koszalin, Poland

A R T I C L E I N F O A B S T R A C T

Keywords: This paper proposes a new approach to selecting improvement projects (IPs). It allows the evaluation and pri­
Projects selection oritization of projects taking into account a proposed set of criteria as a key criteria for processes continuous
Improvement project (IP) improvement. The novelty of the research is the proposition of a OFN-WASPAS method (the WASPAS method,
MCDM
which uses the Ordered Fuzzy Numbers (OFNs)), in the selection of improvement projects. The advantage of the
Ordered Fuzzy Number (OFN)
proposed method is its ability to provide project assessments in the form of fuzzy numbers or qualitative as­
WASPAS method
sessments together with the description of likely direction of assessment change in the nearest future. This is
possible due to the use of orientation in OFNs. The approach verification is presented on the basis of the case
study considered five projects constituting the portfolio of IPs selected, using the 19 most important subcriteria
proposed within the 9 main criteria. The group AHP method is used to calculate the criteria weights. The
conducted research demonstrated that the proposed approach to IPs selection is, to a large extent, applicable in
an enterprise that operates per the CI concept. The resulting process improvement requires the implementation of
many improvement projects.
This approach handles the key aspects of decision making in a consistent and rational way and can be
especially useful for portfolio analysis with projects using the latest technologies and implemented in frequently
changing environmental conditions.

1. Introduction the organisation’s objectives (Meredith, Shafer, & Mantel, 2017). Proj­
ect prioritisation helps an organisation remain focused on its most
The concept of Continuous Improvement (CI) is a set of ubiquitous important strategic objectives, as it more effectively allocates scarce its
and continuous activities that contribute to achieving the goals of the resources. Research in project selection has shifted towards Project
organization and its processes. An organization operating in line with Portfolio Management (PPM) owing to its many benefits (Padhy, 2017).
the CI concept often implement several improvement projects (IPs), Since it is generally impossible to implement all initiatives simulta­
which are strongly focused on process advancement, simultaneously. neously, organisation must select a subset of the portfolio and then
Martinsuo and Lehtonen (2007) noticed that the performance of a single manage these projects (Kornfeld & Kara, 2011). The proposed method
project influences the final outcome of several related projects within a also includes a developed list of criteria and sub-criteria enabling project
company. The study indicated that the most common errors during evaluation taking into account various aspects, including those that are
project improvement plans related to poor selection of projects, project particularly important for modern organizations: impacts on the envi­
resources, too broad a scope (McLean, Antony, & Dahlgaard, 2017), and ronment, impacts on quality, and importance of the goal or problem.
weak connection between the project goal and the organization’s This is a new element in the field of research on portfolio management of
strategy (Kornfeld & Kara, 2013). Therefore, in this paper special improvement projects.
attention is required during the project selection stage. Zhang, Hill, Schroeder, and Linderman (2008) suggested that stra­
Project selection is the process of evaluating individual or groups of tegic portfolio selection and project management can positively impact
projects, and then choosing to implement those that will help achieve organizational performance, and decision-making during this part of the

* Corresponding author.
E-mail addresses: k.rudnik@po.edu.pl (K. Rudnik), bocewicz@weii.tu.koszalin.pl (G. Bocewicz), a.kucinska-landwojtowicz@po.edu.pl (A. Kucińska-
Landwójtowicz), i.czabak-gorska@po.edu.pl (I.D. Czabak-Górska).

https://doi.org/10.1016/j.eswa.2020.114471
Received 24 July 2020; Received in revised form 14 November 2020; Accepted 6 December 2020
Available online 13 December 2020
0957-4174/© 2020 The Author(s). Published by Elsevier Ltd. This is an open access article under the CC BY-NC-ND license
(http://creativecommons.org/licenses/by-nc-nd/4.0/).
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

process can have a substantial impact on whether strategic outcomes are improving the results of quality, efficiency, productivity or other process
successfully realised. The appropriate selection and staging of tactical indicators. Regardless of the specific area of their objectives, these are
actions – in this case improvement projects – are critical factors in projects aimed at broadly understood improvement achieved by intro­
successful strategy execution. According to Kornfeld and Kara (2011), ducing gradual changes.
adding structure to decision making can assist the organisation in Our research focused on improvement projects. We distinguish them
achieving more objective (though not necessarily rational) decisions. from innovative and innovation projects which are defined in research
Therefore, the purpose of the paper is to elaborated an approach of of e.g. Kerzner (2020) or Yordanova (2018).
selecting processes improvement projects that will allow for project In order to specify the area of our research, the term of Improvement
prioritization by accounting for uncertainty and the dynamics of as­ Project was defined. It was assumed that an IP is a unique undertaking,
sessments regarding several key criteria for continuous improvement. In aimed at achieving the goal of improving the organisation and its processes; it
particular, the present study selected the method of multi-criteria de­ is a sequence of completed and related activities (Kucińska-Landwójtowicz,
cision making – a Weighted Aggregated Sum Product Assessment Czabak-Górska, & Lorenc, 2019). It is planned in time and has allocated
(WASPAS) method – which uses the Ordered Fuzzy Numbers (OFNs), as resources necessary for its implementation (Kucińska-Landwójtowicz
an expansion of the fuzzy sets approach proposed by Zadeh. The notion et al., 2019).
of OFNs was introduced and developed by Kosiński, Prokopowicz, and Project or portfolio selection is a complex and multi-faceted decision-
Ślȩzak (2002); Kosiński, Prokopowicz, and Ślęzak (2003). In contrast to making activity that becomes increasingly complicated as organisa­
fuzzy numbers, arithmetic operations in this model are similar to the tional size and the number of potential projects increases (Kornfeld &
operations on real numbers, which are a special case of OFNs. The Kara, 2011). Project selection is part of any strategic management
WASPAS method was presented by Zavadskas, Turskis, Antucheviciene, framework, and there are various mathematical methods of decision-
and Zakarevicius (2012), and combined Weighted Sum and Weighted making available and applied for this purpose. Mittal, Tewari, and
Product Models (WSM and WPM). Zavadskas et al. (2012) suggested Khanduja (2017) compared three techniques, cost of poor quality,
that WASPAS method’s accuracy was more advantageous than using conditional probability, and fuzzy TOPSIS for selecting the right project,
only the weighted sum model or weighted product model. The current but they only focused on QIP. Otay and Kahraman (2018) employed an
literature though, fails to consider OFNs in the fuzzy WASPAS method interval neutrosophic TOPSIS method for evaluation Six Sigma projects.
and lacks research unifying the methods mentioned above into one Evaluating the performance of Six Sigma projects in organisations using
concept. DEA (data envelopment analysis) was proposed by Yüksel (2012). Wen,
The proposed method has the advantage of providing project as­ An, Xu, and Chen (2018) analyzed the advantages and disadvantages of
sessments in the form of fuzzy numbers or qualitative assessments (in the methods proposed in the literature to develop a modified model
linguistic description) together with directional assessment change in considering interval or imprecise data based on a common weight data
the nearest future. This is possible due to the use of orientation in OFNs. envelopment analysis (DEA) approach to solve problem on Six Sigma
The proposed method is especially useful in the cases of evaluation of project selection. Kalashnikov, Benita, López-Ramos, and Hernández-
processes improvement projects using the latest technologies and Luna (2017) developed a novel integrated methodology to formulate
implemented in rapidly changing realities, which keeps companies and solve the Lean Six Sigma project portfolio as a 0–1 Bi-objective
ahead of the competition. Quadratic Programming Problem. The fuzzy-TOPSIS approach was
The remainder of the paper is organized into the following sections. used to decide the selection of suitable Kaizen events that optimize the
Section 2 details the idea of IPs, the essence of the IP selection problem performance level of the organization (Kumar, Dhingra, & Singh, 2018).
and literature review about using the fuzzy MCDM methods in project The literature analysis showed that there are various method avail­
selection. Section 2 also outlines the notions of OFNs and WASPAS able and applied for improvement project selection. Scientists’ work
method. The problem statement and research methodology is described focuses on developing new solutions that will allow unbiased assessment
in Section 3. The proposed approach to IPs selection is presented in and prioritization of projects. An in-depth analysis (Kucińska-Land­
Section 4. Section 4 also determines the proposed set of criteria to wójtowicz, Czabak-Górska, Rudnik, & Lorenc, 2020) has allowed the
evaluate IPs, describes data preparation and discusses the OFN-WASPAS selection of the following types of Improvement Project Selection
method. Section 5 includes a case study of the application of this Methods (IPSM) (Fig. 1):
approach in a company, and Section 6 concludes the paper.
1) scoring and ranking (Kelly, 2002; Pande, Neuman, & Cavanagh,
2. Related work 2000; Pyzdek, 2003; Tague, 2005),
2) multiple criteria decision-making (MCDM) methods (Dinesh Kumar,
2.1. Improvement project and its selection Saranga, Ramírez-Márquez, & Nowicki, 2007; Hu, Wang, Fetch, &
Bidanda, 2008; Padhy & Sahu, 2011; Kalashnikov et al., 2017;
A project is defined as a temporary endeavour undertaken to create a Kendrick & Saaty, 2007; Mawby, 2007; Chen, Chen, Peng, & Wang,
unique product, service or result (Annex A1 the Standard for Project 2005; Kumar, Antony, & Rae Cho, 2009; Wang, Hsu, & Tzeng, 2014;
Management of A Pr., 2013). In the broadest sense, a project is a specific, Yüksel, 2012),
finite task to be accomplished. Whether large- or small-scale or whether 3) hybrid multiple criteria decision-making (MCDM) methods
long- or short-run is not particularly relevant. What is relevant is that the (Büyüközkan & Öztürkcan, 2010; Anand & Kodali, 2008; Kumar
project be seen as a unit (Meredith, Mantel, & Shafer, 2017). According et al., 2009; Kumar et al., 2018; Evans & Alexander, 2007; Su &
to Gonzalez Aleu and Van Aken (2016), common examples of Contin­ Chou, 2008; Chuang, 2001; Saghaei & Didehkhani, 2011; Bilgen &
uous Improvement Projects (CIPs) include Kaizen Events, Six Sigma Şen, 2012; Huang, Yeh, Lin, & Lee, 2009; Kahraman & Büyüközkan,
projects, and Lean Six Sigma projects. However, CIPs are also related to 2008; Yang & Hsieh, 2009; Otay & Kahraman, 2018; Tkáç & Lyócsa,
other CI techniques, especially Quality Improvement Project (QIP), 2010; Altintas, Erginel, & Kucuk, 2016; Mittal et al., 2017),
Quality Circles, and projects associated with the operation of suggestion 4) other methods (Abdulmalek & Rajgopal, 2007; Jung & Lim, 2007;
systems. Padhy (2017) whereas specified Process Improvement Project Hira & Parfitt, 2004; Larson, 2003; Pyzdek, 2003; Kovach & Ingle,
which are defined as a systematic approach for improving organiza­ 2018).
tional performance that consists of specific practices, tools, techniques
and technologies and implemented as a set of improvement projects. The literature research has shown that the universal approach to IPs
In the examples mentioned, the area to which the projects relate or is used only in a few studies, while not using sufficient methods to
concepts in which they are implemented appears. They are focused on conduct a thorough evaluation and selection of projects. Moreover, to

2
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Fig. 1. Classification of improvement project selection methods (Kucińska-Landwójtowicz, Czabak-Górska, Rudnik, & Lorenc, 2020). Description: AHP – Analytic
Hierarchy Process; QFD – Quality Function Deployment; TOPSIS – Technique for Order of Preference by Similarity to Ideal Solution; ANP – Analytic Network Process;
DEA – Data Envelopment Analysis; FMEA – Failure Mode and Effect Analysis; PROMETHEE – Preference Ranking Organization METHod for Enrichment Evaluations;
DEMATEL – Decision Making Trial and Evaluation Laboratory; ANFIS – Adaptive Neuro Fuzzy Inference System; PFMEA – Process FMEA; PDM – Precedence Diagram
Method; PICK – Possible Implement Challenge Kill; VSM – Value Stream Mapping.

our knowledge, there are no studies that would generalize the problem branch of decision making (Yapici Pehlivan, Şahin, Zavadskas, & Tur­
of evaluation and selection of the above-mentioned projects, and thus skis, 2018). When the judgments and decision makers’ preferences are
make it possible to compare different types of projects in one portfolio. uncertain, the using of crisp numbers or intervals in evaluations of al­
In the paper, Improvement Project Selection Methods are defined by ternatives is not appropriate. Then it is proposed to combine MCDM
authors as a set of tools, the use of which enables project evaluation and methods with the fuzzy set theory in so-called fuzzy MCDM (FMCDM)
prioritization based on adopted evaluation criteria and a dedicated methods. In FMCDM methods the assessments and preferences are
calculation algorithm. determined using linguistic expressions identified mostly with the fuzzy
In accordance with a review of the literature the single analytical sets. For example, the fuzzy AHP method was first proposed by van
method which is WASPAS method has not been used for improvement Laarhoven and Pedrycz (1983) as an extension of classical AHP method,
project evaluation in companies. The methods identified in the literature then the fuzzy TOPSIS method (Chen, 2000), fuzzy MULTIMOORA
do not take into account the uncertainty of assessments, and trends of method (Brauers, Baležentis, & Baležentis, 2011), fuzzy WASPAS
these assessments until the launch of projects. method (Turskis, Zavadskas, Antucheviciene, & Kosareva, 2015) etc.
were introduced.
2.2. Fuzzy MCDM method in project assessment In the literature, we can find the using of fuzzy MCDM methods for
assessment, prioritization and selection of the various kind of projects as
Multiple criteria decision making (MCDM) is the most well-known part of projects and projects portfolio management (Abbasianjahromi &

3
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Rajaie, 2012), (Ma, Harstvedt, Jaradat, & Smith, 2020). The above ap­ selection of more technical and engineering projects. Based on a neuro-
proaches were used in relation to projects for research, development and fuzzy network and TOPSIS method, the gas well-drilling projects were
creation of innovations in the enterprise (Dimova, Sevastianov, & Sev­ evaluated (Ahari & Niaki, 2014). The fuzzy inference system with the
astianov, 2006; Chen & Hung, 2008; Tsai & Chen, 2013; Thipparat & multiple inputs as assessment criteria was used to evaluation of in­
Thaseepetch, 2013; Hashemi, Hajiagha, Zavadskas, & Mahdiraji, 2016; vestments in the metallurgical industry (Rębiasz & Macioł, 2015). The
Yalcin, Kilic, & Guler, 2020; Ma et al., 2020). In Dimova et al. (2006), probabilistic fuzzy inference system with technical risk factors as inputs
the problem of investment project assessment is considerated as a more was used to assessment of innovative projects (Rudnik & Deptuła, 2015).
theoretical problem of FMCDM with hierarchical tree of criteria and The evaluation of risks in construction project with the using of fuzzy
fuzzy aggregation method. The fuzzy SAW (Simple Additive Weighting) analytic network process (FANP) and failure mode and effect analysis
method and zero-one linear goal programming as a multi-objective de­ (FMEA) was proposed in Yazdani, Abdi, Kumar, Keshavarz-Ghorabaee,
cision-making approach were considerated to selection of projects in and Chan (2019). Based on Pythagorean fuzzy sets (PFSs) and multi­
portfolio (Abbasianjahromi & Rajaie, 2012). The integrated VIKOR and ple criteria selection method, the construction projects were also
fuzzy AHP method for assessing a sustainable research project was selected (Mohagheghi, Mousavi, Mojtahedi, & Newton, 2020). In Yu and
presented in Thipparat and Thaseepetch (2013). A theoretic methodol­ Liu (2012) the fuzzy multi-criteria model with AHP method for priori­
ogy of combining soft sets as a generalization of fuzzy sets and AHP tizing highway safety improvement projects was considerated. There are
model for project management was considerated in Bakshi, Som, and also many solutions related to the selection of IT and high-technology
Sarkar (2015). The other approach is presented by Chen and Hung projects (e.g. (Mohagheghi & Mousavi, 2019)).
(2008). These authors used 2-tuple linguistic variables together with the As you can see (Fig. 2), many concepts have arisen to combine one or
ELECTRE method to evaluate and select R&D projects. The linguistic many multi-criteria methods with fuzzy set theory and its extensions in
information is expressed by means of 2-tuples, which are composed of a the form of e.g. soft sets, intuitionistic fuzzy sets, interval-valed intui­
linguistic term and a numeric value representing the difference between tionistic fuzzy sets, Pythagorean fuzzy sets, neutrosophic sets and 2-
calculated linguistic term and the closest index label in the initial lin­ tuple linguistic representation models. The concepts are designed to
guistic term set. This representation of information can represent any deal with the assessment of projects in quantitative and qualitative form
joining information obtained in a aggregation process without any loss in conditions where there is uncertainty or indecision decision-makers
of information (Herrera & Martínez, 2000). The 2-tuple linguistic vari­ or when the situation does not allow for certain and specific determi­
ables were also used to evaluation of new product development (NPD) nation of the assessment. According to our review of the literature and to
projects (Tsai & Chen, 2013). Hashemi et al. (2016) proposed the using the best of our knowledge, the combination of OFNs with the MCDM
of interval-valued intuitionistic fuzzy sets together with ELECTRE III method has not been proposed for any improvement project evaluation
method. This approach was illustrated by the solution of an investment in companies.
project selection problem. The intuitionist fuzzy sets (IFSs) were also
used together with DEMATEL (Decision Making Trial and Evaluation 2.3. Ordered fuzzy numbers – Definition, operations and using in MCDM
Laboratory) and TOPSIS methods to R&D project selection (Yalcin et al., methods
2020). The IFS is an extension of Lotfi Zadeh’s notion of fuzzy set, as a
set of elements and their degrees of membership and non-membership Fuzzy sets and numbers are useful in decision-making involving
and it capable of overcoming ambiguity in decision-making process situations with un-probabilistic and imprecise information. The fuzzy
are handled (Yalcin et al., 2020). The using of neutrosophic sets to Six sets and number can be used in many areas, for example, when there is
Sigma projects selection was proposed in Otay and Kahraman (2018). not a well-known area of knowledge, in experts’ systems for making
The neutrosophic sets was treated as elements with together truth- decisions about considered issues, as well as dealing with inaccuracies in
membership, indeterminacy-membership and falsity-membership. the obtained data. In addition, in many practical multi-criteria prob­
The fuzzy MCDM method are also used in relation to assessment and lems, decision making is based on the assessments of experts who are not

Fig. 2. Classification of fuzzy mcdm methods to project selection. Description: FSAW – Fuzzy Simple Additive Weighting; VIKOR – from Serbian Multicriteria
Optimization and Compromise Solution; FAHP – Fuzzy Analytic Hierarchy Process; FANP – Fuzzy Analytic Network Process; FMEA – Failure Mode and Effect
Analysis; TOPSIS – Technique for Order of Preference by Similarity to Ideal Solution; ELECTRE – ELimination Et Choix Traduisant la REalité; MOORA – Multi-
Objective Optimization on the basis of Ratio Analysis; DEMATEL – Decision Making Trial and Evaluation Laboratory.

4
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

able to exactly define their assessment of the situation. Therefore, represent OFNs. Then, according to Kacprzak, Kosiński, and Prokopo­
creating a need to explain an experts’ decision via a linguistic term. wicz (2012) and Prokopowicz (2019) arithmetic operations, denoted
However, the classic fuzzy numbers, defined by Zadeh (1965), and their C=A⊛B, are defined by the formula:
subsequent modification proposed by Dubois and Prade (1978) (so-
C = (aC , bC , cC , dC ) = (aA ⊛aB , bA ⊛bB , cA ⊛cB , dA ⊛dB ), (2)
called LR type numbers) have some imperfections that significantly limit
their applicability in certain areas. According to Prokopowicz (2016), where ⊛ ∈ {+, − , ∙, /}. Moreover, A / B is determined only if B does not
arithmetic operations (addition, subtraction, division, or multiplication)
contain zero values. The scalar multiplication is realized as C = r⋅A if ∀x,
performed on classic fuzzy numbers impacts rapidly growing impreci­ aC = r⋅aA ∧ bC = r⋅bA ∧ cC = r⋅cA ∧ dC = r⋅dA . We can say that C is the
sion, which in turn limits the usefulness of fuzzy numbers.
result of exponentiation of A raised to the power of r ∈ R, denoted C =
The concept of OFN and its properties is an area of growing interest Ar , if ∀x, aC = arA ∧ bC = brA ∧ cC = crA ∧ dC = drA . When the exponent is
for scientists. Therefore, the literature reflects a growing presence of
not an integer, the base of trOFNs cannot contain negative values.
studies in which the authors propose a modification of the OFN defini­
Particularly in arithmetic operations, improper OFNs can appear.
tion given by Kosiński et al. (2003). Kosiński et al. (2003) defined an
However, despite their unusual shapes, improper OFNs can still contain
OFN A (Fig. 3a) as a pair of continuous functions (fA , gA ) such that: fA ,
important information needed for calculations (Prokopowicz & Ślȩzak,
gA : [0, 1]→R, where fA , gA functions are called the up-branch (UPA ) and
2017).
the down-branch (DOWNA ) of fuzzy numbers, respectively. Further, the
In recent years, the concept of OFNs has continuously been devel­
authors assume that independent variable of both functionsf and g is
oped and used in various practical applications (Bocewicz et al., 2020),
denoted by y, and their values by x.
inter alia, OFNs have also been used for multi-criteria analysis in deci­
Kosiński (2006) highlighted that the continuity of both functions
sion making. So far, few approaches of this type have been developed.
implies that their images are bounded intervals called UPA and DOWNA ,
Roszkowska and Kacprzak (2016) proposed SAW and TOPSIS methods
as shown in Fig. 3b. The boundaries of these ranges are marked as fol­
using OFNs to assess variants against selected criteria. In this approach,
lows: UPA = (a, b) = fA ([0, 1]) = fA− 1 and DOWNA = (c,d) = gA ([0,1]) =
OFNs were employed to handle imprecise intermediate quantities and
gA− 1 . Using the normality condition from the definition of fuzzy numbers
orientation of OFNs indicated the type of criterion (benefit or cost). The
it is possible to include a constant function CONSTANT on the interval [b, TOPSIS with OFNs method was used in practice to control flow on the
c] which is equal to 1 (Fig. 3b). Then interval UPA ∪ [b, c] ∪ DOWNA forms production line (Rudnik & Kacprzak, 2017). Kacprzak also developed
the so-called support of the number A. this method for group decision making (Kacprzak, 2019, 2020) as well
Furthermore, in the present paper, the authors used the trapezoidal as extended the notion of Shannon entropy to fuzzy data represented by
membership relations of ordered fuzzy number (noted as trOFN). Ac­ OFNs (Kacprzak, 2017). The model combination of Shannon’s Entropy,
cording to Piasecki (2018) and Piasecki, Roszkowska, and Łyczkowska- Decision-Making Trial and Evaluation Laboratory (DEMATEL) and the
Hanćkowiak (2019) trOFN A = (a, b, c, d) can be defined for any COmplex PRroportional AS-sessment of alternatives with Gray relations
sequence {a, b, c, d}⊂R by its membership relation μA (x|a, b, c, d)⊂R × (COPRAS-G) methods and fuzzy data represented by OFNs was proposed
[0, 1] given by the equation: by Ehsanifar and Hemesy (2019) to prioritize risks in the construction

⎪ 0, x∕∈ 〈min{a, d}, max{a, d}〉 process. The above examples showed not only the possibility of using



⎪ OFNs in MCDM methods but mainly their advantages. This approach


⎪ x− a
⎪ effectively and adequate handles the lack of precision, vagueness and
⎨ b − a, x ∈ 〈min{a, b}, max{a, b})

uncertainty in the available information. Furthermore, the process of
μA (x|a, b, c, d) = , (1)

⎪ 1, x ∈ 〈min{b, c}, max{b, c}) decision making with using OFNs is rational and understandable and




⎪ becomes similar to that of human thinking (Roszkowska & Kacprzak,




d− x
, x ∈ 〈min{c, d}, max{c, d}〉 2016).
d− c

where b < c or (b = c and a < d), the trOFN A has a positive orientation.
2.4. WASPAS method
If condition b > c or (b = c and a > d) is fulfilled, then the trOFN A has a
negative orientation. Otherwise, if a = b = c = d, then the trOFN A
In case of a finite number of variants (alternatives), such in related
describes a crisp number a ∈ R without orientation. The positively and
with project assessment, Multi-Attribute Decision-Making (MADM)
negatively oriented trOFNs are illustrated in Fig. 4.
methods as a branch of MCDM can be used. The assessments (values) of
Let A = (aA , bA , cA , dA ), B = (aB , bB , cB , dB ), and C = (aC , bC , cC , dC )
each variant in relations to criteria are most often presented in the form

Fig. 3. Ordered fuzzy number (OFN) presented as a) in classical meaning, b) a fuzzy number in classic meaning.

5
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Fig. 4. The membership function μA (x|a, b, c, d) of trOFN A with: a) positive orientation, b) negative orientation.

of decision matrix X = (xmn )MxN (Table 1). In the Table 1, xmn is the according to the value Qm . The variant for which the value Qm is the
evaluation of m-th (m = 1,⋯,M) variant in relations to n-th (n = 1,⋯,N) largest is the best variant.
criterion and wn is the weight of n-th criterion. Criteria weights follow The WASPAS method is still developed so that it is possible to apply

the requirement Nn=1 wn = 1. this approach to solving various decision-making problems. For example
The WASPAS method was presented by Zavadskas et al. (2012). It is an extension of the WASPAS method using fuzzy sets can be found in
an approach which combines Weighted Sum and Weighted Product Turskis et al. (2015) or Turskis, Goranin, Nurusheva, and Boranbayev
Models (WSM and WPM). The stages of WASPAS method are presented (2019). In turn Zavadskas, Turskis, and Antucheviciene (2015) proposed
below. It can be used to solve dynamically changing problems. to using the WASPAS approach with grey values (WASPAS-G) to deal
with imprecise information. According to the authors, the combination
1. Calculate the weighted sum model as an aggregate of the total of these two methods in this case gives the opportunity to maintain the
relative variant importance in the form: ranking of the development strategy, selecting the most effective in­
vestment or management decisions. Ghorabaee, Amiri, Zavadskas, and
∑ Antuchevičienė (2017) proposed integration of CRiteria Importance
N
Q(1)
m = wn ∙ymn , (3)
n=1 Trough Inter-criteria Correlation (CRITIC) with WASPAS methods. The
authors proved that determining objective weights using CRITIC in­
where wn is the weight of n-th criterion and ymn is an element of the creases the accuracy of the assessment of alternative solutions in the
normalized decision matrix calculated as: decision-making process. Stojić, Stević, Antuchevičiene, Pamučar, and
⎧ x Vasiljević (2018) undertook to solve the problem of improving the
⎪ mn



if n ∈ Cben methodology of treating imprecision in the field of group decision-
⎨ max xmn
ymn =
n
(4) making according to multiple criteria. For realize this purpose they



minxmn based on rough numbers in WASPAS approach. In Morkunaite, Bausys,

⎩ n
xmn
if n ∈ Ccost and Zavadskas (2019), the authors applied the expansion of the WASPAS
method, namely, WASPAS-SVNS, which is based on the Single-Valued
Symbol Cben is the set of benefit criteria (the highest value of variant Neutrosophic Set (SVNS). The broadly review of the WASPAS method
evaluation is preferred) and Ccost is the set of cost criteria (the lowest was presented by Mardani et al. (2017).
value is preferred).
3. Problem statement and research methodology
2. Determine the weighted product model (WPM) as a product of the
total relative importance of variant as follows: Together with the growing interest in continuous improvement, the

N role of project portfolio management is growing, where proper selection
Q(2)
m = (ymn )wn . (5) is a very important stage. Project or portfolio selection is a complex and
n=1 multi-faceted decision-making activity that becomes increasingly
complicated as organisational size and the number of potential projects
increases (Kornfeld & Kara, 2011).
In-depth analysis of the proposed project selection methods has
3. Determine the total importance of m-th variant in the following form
shown that project evaluation should take into account both qualitative
(Zavadskas et al., 2012; Turskis et al., 2015):
and quantitative criteria. Inadequate selection of projects leads to the
Qm = λ∙Q(1) (2)
(6) missed opportunity to improve the organization (Carazo et al., 2010).
m + (1 − λ)∙Qm , λ ∈ [0, 1],
However, it is not enough to take account of their current status. Given
where λ is calculated as: the dynamic changes taking place in the organization and its environ­
∑M ment, it is also worth considering perspective thinking of experts about
future implementation and changes related to the assessment of projects
(2)
m=1 Qm
λ = ∑M ∑M . (7)
in terms of the indicated criteria. They should be given the opportunity
(1) (2)
m=1 Qm + m=1 Qm
to consider trends of these assessments until the launch of projects. A
The last stage of the WASPAS method is the ranking of the variants
deep analysis of the methods proposed in the literature indicates a lack
of such an approach.
Table 1 Identification of the research gap prompted the authors to pose the
Example of decision matrix. following research questions:
Criterion 1 Criterion 2 … Criterion N
• RQ1. How can selection of improvement projects be made to take
Weights
into account qualitative and quantitative criteria?
w1 w2 … wN
Variant 1 x11 x12 x1N
• RQ2. What approach should be used to include in the project eval­

Variant 2 x21 x22 x2N
uation knowledge about their future implementation which is often

xmn
incomplete or imprecise?
… … … …
Variant M xM1 xM2 … xMN

6
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Fig. 5. Diagram of the conducted research.

Fig. 6. Algorithm of proposed approach to IPs selection.

The research was carried out according to defined stages (Fig. 5): Because the implementation of IP is often associated with risk, and
knowledge about their future implementation is often incomplete or
1. Literature review literature regarding: Improvement Projects Selec­ imprecise, the use of OFNs as assessments of projects concerning a
tion Methods, fuzzy MCDM methods for assessment, prioritization proposed set of subcriteria is suggested. The orientation of OFNs is
and selection of the projects, Ordered Fuzzy Number (OFN) and interpreted in the proposed approach as the dynamics of changing the
WASPAS method. project evaluation regarding the selected criterion. For example, the
2. Selection of tools suitable for evaluation of improvement projects, evaluator may state that external customer satisfaction of a given project
which allow to take into account knowledge about their future is average, but in the future, the supposition may increase; therefore, the
implementation (selection of a model class). orientation of the OFN labeled “average” is positive (we can say that as
3. Development of an algorithm of a proposed approach to IPs selec­ OFN with positive trends). In the event that the evaluator is convinced of
tion, together with OFN-WASPAS method. a decreasing trend for this assessment or at least the status quo, the
4. Verification of the developed approach in a production company. orientation of OFN labeled “average” is negative (we can say that as OFN
5. Comparison of the proposed OFN-WASPAS method results with without positive trends). This approach is novel from other MCDM
WASPAS, F-WASPAS methods results. methods described thus far when assessing projects. In particular, an
6. Analysis of the results obtained, sensitive analysis, conducting dis­ expanded version of the WASPAS method, named OFN-WASPAS
cussions and indicating the direction of future research. method, is proposed, and the algorithm of proposed approach to
improvement projects selections are described in Fig. 6.
4. The proposed approach to improvement projects selection
4.1. Determine the important criteria to improvement project evaluation
In the paper, the novel approach to IP evaluation is proposed. The
approach constitutes methodology based on the MCDM method. The criteria for evaluating IPs have been developed based on the

7
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Table 2 weight values for assessing their improvement projects.


Proposed of criteria structure to improvement project evaluation.
Criteria Subcriteria Types of 4.2. Data preparation
subcriteria

C1: Project feasibility C11: Technical feasibility Quality, Benefit In cases of a finite number of variants (alternatives), such in related
C12: Availability of appropriate Quality, Benefit with IP assessment, Multi-Attribute Decision-Making (MADM) methods
resources Quality, Benefit which is a branch of MCDM can be used. Let A = {A1 , ⋯, Am , ⋯, AM }
C13: Project risk (M ≥ 2) be a set of IPs (alternatives). Let C = {C1 , ⋯, Cn , ⋯, CN } be a set
C2: Financial impacts C21: Cost reduction (PLN per Quantity, Benefit
month) Quantity, Benefit
of IPs assessment criteria, which has been proposed in the paper and
C22: Revenue generation (PLN chosen by experts as the most important. The important of the criteria is
per month) determined by the following vector w = {w1 ,⋯,wn ,⋯,wN }, such that 0 ≤
C3: Impacts on employees C31: Improved skills and Quality, Benefit ∑
wn ≤ 1 and Nn=1 wn = 1. The problem consists in ranking improvement
knowledge Quality, Benefit
C32: Improved work safety Quality, Benefit projects and choice the best improvement project, with is best assessed
C33: Improved ergonomics at the Quality, Benefit against the proposed set of criteria and can be implemented with the
workplace lowest risk in an enterprise.
C34: Attract/retain Since the implementation of improvement projects is often associ­
C4: Impact on operational C41: Reduction in cycle time (%) Quantity, Benefit
ated with risk, and knowledge about their future implementation is
goals C42: Stock reduction in progress Quality, Benefit
C43: Compliance with operational Quality, Benefit often incomplete or imprecise, the use of trOFNs in project evaluation is
objectives proposed. In such cases, the fuzzy decision matrix in the following form
C5: Impact on customers C51: Internal customer Quality, Benefit is considered:
satisfaction Quality, Benefit
C52: External customer C … CN
satisfaction
⎡ 1→
← ← ⎤


← ←
→ A x11 ⋯ x1N
C6: Impact on suppliers C61: Mutual benefits Quality, Benefit X = [ xmn ]M×N = 1 ⎣ ⋮ ⋱ ⋮ ⎦, (8)

respectively C62: Improved capability Quality, Benefit ←
→ ←

C7: Impact on the C71: Waste reduction Quality, Benefit
AM xM1 ⋯ xMN
environment C72: Saving energy/water Quality, Benefit
consumption ←

where xmn = (amn , bmn , cmn , dmn ) is a trOFN with positive or negative
C8: Impact on quality C81: Reduction the number of Quantity, Benefit
product defects (%) Quantity, Benefit orientation and represents the assessment of m-th IP according to n-th
C82: Reduction of failures in the criterion.
process (%) For the quality criteria, we proposed using a linguistic scale (Table 3
C9: Importance of the C91: Duration of the problem Quantity, Cost
and Fig. 7), which is identified via trOFNs. The assessment also considers
goal/ problem (number of days) Quality, Cost
C92: The extent of the problem Quality, Benefit
assumptions about the trends of the assessment. If the evaluator assumes
C93: Compliance with strategy that the indicated assessment may change in a decreasing direction, then
trOFN with positive orientation x̅→ mn is used, and trOFN xmn is used for the
←̅
opposite case.
results of Adebanjo, Samaranayake, Mafakheri, and Laosirihongthong Due to the precise quantity assessments of IP, certain criteria pa­
(2016) study. In their study, six main criteria are identified: project rameters (such as revenue generation, reduction in cycle time etc.) are
feasibility, financial impacts, impacts on employees, impact on opera­ difficult to obtained. To address this, authors proposed use the trOFNs
tional goals, impact on customers, and impact on suppliers, respectively, and recommend constructing them in the following way:
along with twelve subcriteria. Nevertheless, they do not consider criteria
related to the environmental impact, which is becoming an increasingly • for assessment, which may shift in the decreasing direction or remain
analyzed factor. unchanged: ←̅
xmn = (xmn +2ε,xmn + ε,max(xmn − ε,0),max(xmn − 2ε,0)),
Final analysis, in this research, was carried out by experts dealing • for assessment, which may change in the increasing direction: x̅→mn =
with continuous improvement. Additional main criteria related to goals (max(xmn − 2ε,0), max(xmn − ε,0),xmn + ε,xmn + 2ε ),
important for many organizations were introduced: impacts on the
environment, impacts on quality, and importance of the goal or prob­ where xmn is a probable (presumed) assessment value of n-th project
lem. New subcriteria have been developed regarding the expanded with regard to m-th criterion, and ε is an approximate error value
criteria, which are listed in Table 2. In summary, nine main criteria and (ε > 0).
23 subcriteria were defined (Table 2). Next, to ensure comparability of project assessments against
To determine the weights w (i.e., significance, importance) for the different criteria, the fuzzy decision matrix is normalized as follows:
hierarchical structure of criteria, the Analytic Hierarchy Process (AHP),
as suggested by Saaty (1980), has been proposed. In the method, the
experts compare all the evaluation criteria in pairs, which is straight­
forward to understand and easy to perform. It allows the qualitative
estimates received from experts to be converted into quantitative data as Table 3
Linguistic scale for project assessment according to quality criteria.
criteria weights. It is recommended that the AHP method be performed
by several experts dealing with continuous improvement in the enter­ Linguistic variables Without positive trend With positive trend
prise. Then, due to a uniform group of experts (experts in one field), Very low ←̅
VL =(3,2,1,1)
̅→
VL =(1,1,2,3)
based on the results of the AHP method for each expert (criteria Low ← →
L =(5,4,3,2) L =(2,3,4,5)
weights), the average weights are calculated that will assess the
Average ←
A =(7,6,5,4)

A =(4,5,6,7)
importance of criteria (and subcriteria) in the enterprise.
In the case study (Section 5), the weights of the proposed project High ←
H =(9,8,7,6)

H =(6,7,8,9)
evaluation criteria were analyzed using the group AHP method via a Very high ←̅
VH =(10,10,9,8)
̅→
VH =(8,9,10,10)
survey tool among employees of several companies. Hence, the results
obtained can also be a hint for enterprises wishing to use universal

8
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Fig. 7. Graphical interpretation of proposed linguistic scale identified via trOFNs.

C … CN
⎡ 1→
← ← ⎤
→ → (1) ( (1) (1) (1) (1) ) ∑
← N
← ∑→

N


← ←
→ A
Y = [ymn ]M×N = 1
y11 ⋯ y1N
(9) Q m = amn , bmn , cmn , dmn = wn ⋅ymn = zmn , (12)
⋮ ⎣ ⋮ ⋱ ⋮ ⎦ n=1 n=1
AM ←
→ ←

yM1 ⋯ yMN

→ ( ′ )
where wn is the weight of n-th criterion and ymn = amn , bmn , cmn , dmn is
′ ′ ′



where ymn is calculated following the mathematical relationship and the an element of the normalized fuzzy decision matrix with OFNs and zmn =


assessments of cost criteria are directly proportional to the inverse of ( ) ←

wn ⋅a’mn , wn ⋅b’mn , wn ⋅c’mn , wn ⋅d’mn . The sum of zmn is realized with the
assessments of benefits criteria:
formula (2).
• for benefit criteria Cn (means that if more than better), n ∈ Cben :
( ) 2. Determine the weighted product model (WPM) as a product of the
← ( ′
→ ′ ′ ′ )
ymn = amn , bmn , cmn , dmn =
amn bmn cmn dmn
, , , , (10) total relative importance of project as follows:
en en en en
→ (2) ( (2) (2) (2) (2) ) ∏
← N

→ ∏
N →

{ } Q m = amn , bmn , cmn , dmn = ( ymn )wn = lmn , (13)
n=1 n=1
en = max max dmn , max amn
m m

→ ( ) →

where lmn = a’mnwn , b’mnwn , c’mnwn , d’mnwn . The product of lmn is also real­
• for cost criteria Cn (means that if less than better), n ∈ Ccost : ized with the formula (2).
( )
← (
→ ) en en en en
ymn = a’mn , b’mn , c’mn , dmn

= , , , , (11) ← (1) →
→ ← (2)
amn bmn cmn dmn 3. Determine the crisp values from Q m , Q m using defuzzification
methods. In paper, we use the gravity center (GC) functional ϕ:

⎧( )2 ( (1) )2 ( (1) )2 ( (1) )2



⎪ a(1)
mn + a(1) (1)
mn ⋅bmn + bmn − cmn − c(1) (1)
mn ⋅dmn − dmn
( (1) ) ⎪
⎨ ( ) if a(1)
mn ∕
(1)
= dmn


(14)
(1) (1) (1) (1)
ϕ Qm (1)
= Qm = 3 a mn + bmn − cmn − d mn



⎩ (1) (1) (1)
amn if amn = dmn

{ }
en = min min amn , min dmn
m m
( (2) )


Similarly, the value of ϕ Q m = Qm is calculated.
(2)

4.3. OFN-WASPAS method


4. Determine the total importance of m-th project in the following form
Authors proposed using an approach, which combines Weighted Sum (Zavadskas et al., 2012; Turskis et al., 2015):
and Weighted Product Models (WSM and WPM) for trOFNs (Zavadskas
et al., 2012; Turskis et al., 2015). The stages of OFN-WASPAS method Qm = λ∙Q(1) (2)
m + (1 − λ)∙Qm , λ ∈ [0, 1], (15)
are presented below.
where λ is calculated as:
1. Calculate the weighted sum model as an aggregate of the total
relative project importance in the form:

9
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Fig. 8. Results of weight calculation for a) main criteria, b) subcriteria (global weights).

10
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

∑M (2) 5.2. Determine the important criteria to improvement projects evaluation


m=1 Qm
λ = ∑M (1) ∑M (2)
. (16)
m=1 Qm + m=1 Qm
The AHP survey questionnaire was used to assess the global weights
The last stage of the WASPAS method is the ranking of the projects of individual subcriteria. The surveys were completed independently by
according to the value Qm . The IP for which the value Qm is the largest is a group of five experts in the field of CI. The final results were calculated,
the best project. Expert judgment includes, which projects with the accounting for the arithmetic mean of the weights for each expert, which
highest values of total importance will be implemented in the enterprise. were obtained by AHP procedure (Saaty, 1980). The study identified the
most important primary criterion, which included C8 impact on quality
5. Case study (0,19), C5 impact on customers (0,16). The values of others criteria are
presented on Fig. 8a.
The developed approach to IP selection was applied in a large en­ In the subcriteria group, the criteria of the highest importance based
terprise that produces electronic devices. The participating company is on global weights were: C52 external customer satisfaction (0.116), C81
an experienced supplier of components for organisations producing reduced number of product defects (0.107), C82 reduction of failures in
household appliances, which operate in the electrical and electronic the process (0.085), and C21 cost reduction (0.08). Those subcriteria
industries. This case was chosen because the company’s management were then followed in priority by C91 the duration of the problem
recognizes the principles of CI as a major element of the organisation’s (0.059), C11 technical feasibility (0.057), and C43 compliance with
strategy. The management implements and applies all key practices of operational objectives (0.055). Further subcriteria ranked according to
the CI concept including management of IPs in a thoughtful and orderly their importance are presented in Fig. 8b. The least important criteria
manner. Therefore, there is documentation confirming the IP practices, included C33 improvement ergonomics at the workplace (0.007), C32
which enables the use of documentation analysis. improvement work safety (0.009), C13 project risk (0.01), and C31
improved skills and knowledge (0.014). These criteria were eliminated
5.1. Improvement projects portfolio from the assessment due to their low weight, and the results were
normalized again. Experts pointed out that among these low weight
In the surveyed enterprise, process improvement through IPs is a criteria was project risk, which was attributed to the fact that IPs have a
permanent practice. IPs are characterized by their diversity and much lower risk than investment projects. Expert experience showed
uniqueness. In many cases, they arise interactively through consulta­ that the availability of resources and technical feasibility criteria were
tions and arrangements between top management and operational level related to technical and organizational risk.
managers, result from continuous improvement actions by teams and In Fig. 8b four bars are marked in red. These marked bars are rep­
systems of suggestions, as well as the application of Lean Manufacturing resenting subcriteria that weren’t taken to further analysis because of
principles and quality management. All combined, they all form a their little importance (with the smallest calculated weight).
portfolio of IPs, of which five projects were selected to verify the pro­
posed method. The IPs projects were related to, respectively: 5.3. Data preparation and OFN-WASPAS method

• A – reduction in the amount of material waste on the P3 production Based on the decision-making methodology outlined in Section 4.2,
line, an expert in the field of CI in consultation with a knowledge engineer,
• B – reduction in the change-over time of the M8 production machine, prepared the decision matrix for projects A-E, relative to the 19 most
• C – reducing the size of quality shortcomings in the blanks produced important criteria selected in the group AHP method (Fig. 8b, criteria in
by the M12 machine, blue). Qualitative and quantitative assessments are given in Table 4. The
• D – implementation of control cards monitoring the process on the P7 assessments have been approximated using trOFNs based on Table 3 for
production line, qualitative criteria and estimated using values together with a possible
• E – reduction of stock in progress on the P1 production line. ̅̅̅→
estimation error for quantitative criteria. For example, where 5000 in
C21 means that estimated cost reduction is approximately equal 5000
per month with the approximate error ε = 500 and likely to increase, so

Table 4
Rated IPs based on linguistic values and estimated quantity values.
Subcrit. C11 C12 C21 C22 C34 C41 C42 C43 C51 C52 C61

Project xmn ε xmn ε xmn ε

A →
A

H
̅̅̅→
5000 500 ̅̅̅→
3000 300 ←
L

2 1 →
L
̅→
VH

A

H

A
B →
H

H
̅̅̅→
2500 200 ̅̅̅→
1000 100 →
A

5 1 →
L
̅→
VH

L
̅→
VH
̅→
VL
C ←
A

H
̅̅̅→
2000 300 ̅̅̅→
1000 200 →
A

3 1 →
A

H
̅→
VH
̅→
VH
̅→
VL
D →
L

L
̅̅̅→
3500 1000 ̅̅̅→
2500 500 →
H

6 1 →
A

H

H

H
̅→
VL
E →
L

L
̅̅̅→
3000 500 ̅̅̅→
2000 300 →
A

3 1 ̅→
VH

H

H

L

L

Subcrit. C62 C71 C72 C81 C82 C91 C92 C93

Project xmn ε xmn ε xmn ε

A →
H
̅→
VL

L

1 1 →
1 1 ̅→
30 2 →
H

H
B ̅→
VL

L

A

1 1 →
1 1 ̅→
20 1 →
L

H
C →
L

H

A

5 1 →
3 3 ̅→
25 3 →
A

H
D ̅→
VL

H

L

4 2 →
8 2 ̅→
40 2 →
H

H
E →
A

H

L

1 1 →
1 1 ̅→
14 1 →
A

H

11
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

trOFN = (4000, 4500, 5500, 6000) is used (Table 5).

10

2
7
4
5
5

9
9
9
9
9
d

d
Table 6 shows a normalized fuzzy decision matrix. The benefit and

5
5
7
7
d
cost criteria are normalized based on Eqs. (10) and (11), respectively.
For example, the values in C11 (first criterion, benefit criterion) was

3
6
5
4
4
c
10
4
4
6
6
c

8
8
8
8
8
calculated as follows: the largest value of amn and dmn for all n projects

c
was selected (max am1 = 7 and max am1 = 9). Then, again the larger

4
5
6
3
3
b
3
3
5
5
9
b

m m
from these two values was selected and it was e1 = 9. Further, for each
C42

C72

7
7
7
7
7
b
project, according to equation (10), division was performed:
2
2
4
4
8
a

5
4
7
2
2
a
( )
am1 bm1 cm1 dm1
e1 e1 e1 e1 . Hence, the following results were finally obtained for
, , ,
4
7
5
8
5

C93
d

3
5
9
9
9
d

6
6
6
6
6
a
C11 and:
3
6
4
7
4
c

2
4
8
8
8
c



• project A: y 11 = (0.444, 0.556, 0.667, 0.778),

9
5
7
9
7
d
1
4
2
5
2
b

1
3
7
7
7
b



• project B: y 21 = (0.667, 0.778, 0.889, 1.000),
C41

0
3
1
4
1
a



C71

• project C: y 31 = (0.778, 0.667, 0.556, 0.444),


1
2
6
6
6

8
4
6
8
6
a

c ←

• project D: y 41 = (0.222, 0.333, 0.444, 0.556),
2
7
7
9
7
d



• project E: y 51 = (0.222, 0.333, 0.444, 0.556).
9
3
5
3
7
d
3
6
6
8
6
c

7
3
5
7
5
b

On the other hand, the values in C91 (17-th criterion, cost criterion)
8
2
4
2
6
c
4
5
5
7
5
b

were determined as follows: the smaller of am17 and dm17 for all projects
C92
C34

6
2
4
6
4
a

(n = 1, ⋯, 5) was selected (min am17 = 12 andmin dm17 = 16). Then,


7
1
3
1
5
b
5
4
4
6
4
a

m m
again the smaller from these two values was selected and it was e17 =
C62
3600
1200
1400
3500
2600

12. Further, for each project, according to equation (11), division was
6
1
2
1
4
a

34
22
31
44
16

( )
d
d

performed: aem17
17
, bem17
17
, cem17
17
, dem17
17
. Hence, the following results were finally
7
3
3
3
2
d
3300
1100
1200
3000
2300

obtained for C91 and:


32
21
28
42
15
c

c
6
2
2
2
3
c



• project A: y 11 = (0.462, 0.429, 0.375, 0.353),
2700

2000
1700
900
800

5
1
1
1
4
b



• project B: y 21 = (0.667, 0.632, 0.571, 0.545),
b

28
19
22
38
13
b



C61

• project C: y 31 = (0.632, 0.545, 0.429, 0.387),


4
1
1
1
5
a
2400

1500
1400
C22

800
600



• project D: y 41 = (0.333, 0.316, 0.286, 0.273),
a

C91

26
18
19
36
12



• project E: y 51 = (1.00, 0.923, 0.800, 0.750).
10
10

a
9

9
5
d
6000
2900
2600
5500
4000
d

Based on the OFN-WASPAS method outlined in Section 4.3, the


10
10
8

8
4
c

12

← (1)

3
3
5

3
d

weighted sum model Q m and weighted product model


5500
2700
2300
4500
3500
c

7
9
9
7
3
b

← (2)
→ ← (1)

Q m (m = 1, …, 5) were calculated and the crisp values from Q m ,
C52

10

← (2)
4500
2300
1700
2500
2500


2
2
4

2
c

Q m using the gravity center (GC) functional (14) were determined


6
8
8
6
2
a
b

(Table 7). The last stage of the WASPAS method calculated the total
importance of analyzed IPs Qm (formula (15)) and ranked according to
10
7
2

9
9
d
4000
2100
1400
1500
2000

0
0
2
6
0
b
C21

the values Qm (m = 1, ..., 5). Table 7 shows the results of above


a

mentioned calculations.
10

C82
6
3

8
8
c
6
6
6
5
5
d

0
0
1
4
0
a

5.4. Results and comparison


Fuzzy decision matrix X (rated projects with trOFNs).

5
4
9
7
7
b
7
7
7
4
4
c

The study considered five projects constituting the portfolio of IPs


C51

3
3
7
8
3
d
4
5
8
6
6
8
8
8
3
3

a
b

selected, using the 19 most important subcriteria proposed within the


C12

following main criteria: project feasibility, financial impacts, impacts on


9
9
9
2
2
a

10
10

employees, impact on operational goals, impact on customers, impact on


2
2
6
6
2
c
9
9
9
d

suppliers respectively, impact on the environment, impact on quality,


7
9
4
5
5
d

and importance of the goal or problem. It was assumed that the projects
10
10
8
8
8
c

would be implemented shortly after the decision on projects selection,


0
0
4
2
0
b
6
8
5
4
4
c

which meant that the experts had the opportunity to determine the

9
9
7
7
7
b

tendencies to change the assessment of projects relative to given criteria


5
7
6
3
3
b

C81

before the start of projects. Orientations of trOFNs determined these


0
0
3
0
0
a
C43
C11

trends and fuzzy evaluations of IPs, together with trends, influenced the
8
8
6
6
6
a
4
6
7
2
2
a

results of the evaluation. The final results (Table 7) indicated that in the
researched enterprise, the most important project is C (reducing the
Subcrit.

Subcrit.

Subcrit.
Project

Project

Project
Table 5

number of defects in the blanks produced by the M12 machine).


D

D
A

A
B

B
C

C
E

As such, Project C should be implemented first in the enterprise. This

12
K. Rudnik et al.
Table 6


Normalized fuzzy decision matrix y with trOFNs.
C11 C12 C21 C22 C34

a b c d a b c d a b c d a b c d a b c d

A 0.444 0.556 0.667 0.778 1.000 0.889 0.778 0.667 0.667 0.750 0.917 1.000 0.667 0.750 0.917 1.000 0.556 0.444 0.333 0.222
B 0.667 0.778 0.889 1.000 1.000 0.889 0.778 0.667 0.350 0.383 0.450 0.483 0.222 0.250 0.306 0.333 0.444 0.556 0.667 0.778
C 0.778 0.667 0.556 0.444 1.000 0.889 0.778 0.667 0.233 0.283 0.383 0.433 0.167 0.222 0.333 0.389 0.444 0.556 0.667 0.778
D 0.222 0.333 0.444 0.556 0.222 0.333 0.444 0.556 0.250 0.417 0.750 0.917 0.417 0.556 0.833 0.972 0.667 0.778 0.889 1.000
E 0.222 0.333 0.444 0.556 0.222 0.333 0.444 0.556 0.333 0.417 0.583 0.667 0.389 0.472 0.639 0.722 0.444 0.556 0.667 0.778
norm. wn 0.059 0.017 0.084 0.038 0.023

C41 C42 C43 C51 C52

a b c d a b c d a b c d a b c d a b c d

A 0.000 0.125 0.375 0.500 0.200 0.300 0.400 0.500 0.800 0.900 1.000 1.000 0.400 0.500 0.600 0.700 0.600 0.700 0.800 0.900
B 0.375 0.500 0.750 0.875 0.200 0.300 0.400 0.500 0.800 0.900 1.000 1.000 0.500 0.400 0.300 0.200 0.800 0.900 1.000 1.000
C 0.125 0.250 0.500 0.625 0.400 0.500 0.600 0.700 0.600 0.700 0.800 0.900 0.800 0.900 1.000 1.000 0.800 0.900 1.000 1.000
D 0.500 0.625 0.875 1.000 0.400 0.500 0.600 0.700 0.600 0.700 0.800 0.900 0.600 0.700 0.800 0.900 0.600 0.700 0.800 0.900
E 0.125 0.250 0.500 0.625 0.800 0.900 1.000 1.000 0.600 0.700 0.800 0.900 0.600 0.700 0.800 0.900 0.200 0.300 0.400 0.500
13

norm.wn 0.052 0.050 0.057 0.042 0.121

C61 C62 C71 C72 C81

a b c d a b c d a b c d a b c d a b c d

A 0.571 0.714 0.857 1.000 0.667 0.778 0.889 1.000 0.111 0.111 0.222 0.333 0.714 0.571 0.429 0.286 0.000 0.000 0.250 0.375
B 0.143 0.143 0.286 0.429 0.111 0.111 0.222 0.333 0.222 0.333 0.444 0.556 0.571 0.714 0.857 1.000 0.000 0.000 0.250 0.375
C 0.143 0.143 0.286 0.429 0.222 0.333 0.444 0.556 0.667 0.778 0.889 1.000 1.000 0.857 0.714 0.571 0.375 0.500 0.750 0.875
D 0.143 0.143 0.286 0.429 0.111 0.111 0.222 0.333 0.667 0.778 0.889 1.000 0.286 0.429 0.571 0.714 0.000 0.250 0.750 1.000
E 0.714 0.571 0.429 0.286 0.444 0.556 0.667 0.778 0.667 0.778 0.889 1.000 0.286 0.429 0.571 0.714 0.000 0.000 0.250 0.375
norm.wn 0.032 0.031 0.033 0.019 0.112

C82 C91 C92 C93

a b c d a b c d a b c d a b c d

Expert Systems With Applications 169 (2021) 114471


A 0.000 0.000 0.167 0.250 0.462 0.429 0.375 0.353 0.333 0.286 0.250 0.222 0.667 0.778 0.889 1.000
B 0.000 0.000 0.167 0.250 0.667 0.632 0.571 0.545 1.000 0.667 0.500 0.400 0.667 0.778 0.889 1.000
C 0.083 0.167 0.333 0.417 0.632 0.545 0.429 0.387 0.500 0.400 0.333 0.286 0.667 0.778 0.889 1.000
D 0.333 0.500 0.833 1.000 0.333 0.316 0.286 0.273 0.333 0.286 0.250 0.222 0.667 0.778 0.889 1.000
E 0.000 0.000 0.167 0.250 1.000 0.923 0.800 0.750 0.500 0.400 0.333 0.286 0.667 0.778 0.889 1.000
norm.wn 0.089 0.062 0.047 0.031
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Table 7
Results of OFN-WASPAS method calculations.
→ (1)
← Qm
(1) → (2)
← Qm
(2) λ Qm Rank
Q m Q m

a b c d a b c d

A 0.404 0.454 0.567 0.638 0.516 0.000 0.000 0.483 0.558 0.261 0.393 0.360 3
B 0.433 0.461 0.557 0.608 0.516 0.000 0.000 0.474 0.538 0.253 0.356 4
C 0.476 0.529 0.621 0.668 0.573 0.379 0.458 0.572 0.618 0.506 0.532 1
D 0.370 0.483 0.672 0.795 0.580 0.000 0.435 0.623 0.731 0.431 0.489 2
E 0.371 0.425 0.537 0.612 0.487 0.000 0.000 0.477 0.560 0.260 0.348 5

Fig. 9. Results of IPs assessments with using WASPAS, F-WASPAS and OFN-WASPAS methods.

project stood out because it focused on the reduction of defects, which


Table 8
will positively affect the level of satisfaction for internal and external
Sensitive analysis related to OFN orientation change.
customers and the reduction of waste. The project goal is highly
consistent with the operational goals of the process and the company’s Criterion rating change [%] Project

strategy. Project D’s final ranking was similar to that of C’s, while A B C D E
project E received the lowest scores, and holds the least importance for Criterion C11 0.0107 0.0077 0.0030 0.0163 0.0178
C12 0.0022 0.0022 0.0006 0.0046 0.0051
the company. The project rankings are as follows: C > D > A > B > E.
C21 0.0121 0.0095 0.0043 0.0340 0.0210
Fig. 9 shows the comparison of IPs scores obtained with the proposed C22 0.0056 0.0055 0.0028 0.0104 0.0087
method and the original WASPAS and fuzzy WASPAS (F-WASPAS) C34 0.0068 0.0041 0.0011 0.0028 0.0043
methods, using the same set of criteria weights (Fig. 8b). In the case of C41 0.1995 0.0154 0.0062 0.0117 0.0293
the F-WASPAS and OFN-WASPAS methods, the linear ordering of C42 0.0146 0.0143 0.0022 0.0085 0.0041
C43 0.0045 0.0045 0.0019 0.0071 0.0078
assessment results were similar. This is because, in the project portfolio
C51 0.0077 0.0125 0.0009 0.0053 0.0058
being analyzed, very few ratings were issued by experts with a negative C52 0.0159 0.0094 0.0023 0.0149 0.0356
(or stable) change tendency (with a negative OFNs orientation), which C61 0.0059 0.0133 0.0032 0.0119 0.0099
would yield a low weight criteria value. The results could vary if the C62 0.0042 0.0131 0.0023 0.0117 0.0059
C71 0.0142 0.0097 0.0011 0.0042 0.0046
method did not use the defuzzification function. It should be noted,
C72 0.0058 0.0035 0.0009 0.0054 0.0059
however, that the use of OFNs resulted in a reduction of all ratings in C81 0.4959 0.4884 0.0071 0.1780 0.5082
relation to the F-WASPAS method. In turn, failure to include un­ C82 0.4959 0.4885 0.0089 0.0307 0.5083
certainties in the WASPAS method assessments resulted in slightly C91 0.0060 0.0044 0.0030 0.0041 0.0067
different results. In WASPAS method, project D is the best project, and C92 0.0064 0.0141 0.0024 0.0059 0.0090
C93 0.0042 0.0041 0.0010 0.0039 0.0043
projects A and B are assessed as similar projects.
The influence of the OFN orientation on result is apparent e.g. when
we compare the evaluations of the same IPs given by the two experts. We

14
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

found that differences in the type of orientation (for the same fuzzy sets) case of cost criteria, changing the orientation from positive to negative
in the assessment relative to only one criterion differed in the final results in a decrease in the score for a total important of given project
assessment of the projects. For example, when project C was almost (this is the case for C91 and C92, the red background in Fig. 10).
identically assessed by two experts, with the exception of criterion C11, Therefore, the use of OFNs in the improvement projects selection
← →
where project C was rated “ A ” by first expert and “ A ” by second expert, method means that we can include additional information in the
then the final project evaluations differ by 0.0030 in favor of project assessment, which is the directional assessment change in the nearest
rated by second expert (rating of C11: 0.5322 and 0.5338 respectively). future. This orientation has an impact on project evaluation, and for
Similarly, the impact of changes in orientation of OFN assessment for similar projects, the differentiation of orientation can have a significant
all criteria was analyzed. The project assessments presented in Table 4 impact on final IP evaluation and selection.
were the basic fuzzy decision matrix. The evaluation of the m-th project
was read each time when the m-th project was assessed against the n-th 6. Conclusion
criterion using positive orientation as well as negative orientation. The
absolute difference in assessment was determined as a percentage The conducted research demonstrated that the proposed approach to
change in value of the total importance of m-th project Qm . Although, IPs selection is, to a large extent, applicable in an enterprise that oper­
only the OFN direction of the evaluation was changed with respect to ates per the CI concept. The resulting process improvement requires the
one selected criterion, the final evaluation of the analyzed project was implementation of many improvement projects.
changed each time (on average from 0.3% to 33.6%). Table 8 shows the Several IPs require support at the stage of evaluation and selection,
results for all criteria and projects. Thus, Table 8 presents a sensitivity which is possible through the application of the proposed approach. It
analysis of the project evaluation in relation to the change in the has been shown that the inclusion of the MCDM method is justified for
orientation of a single OFN assessment relative to the selected criterion. projects that are similarly consistent with the operational objectives of
It can be concluded that for most criteria a change in the future trend of the organization. The present study’s proposed a novel OFN-WASPAS
the assessment results in changing assessment value but it does not method, together with a set of criteria, enabled a more objective,
significantly affect (on average up to 1.6% change in the value of Qm ). meticulous, and substantive assessment of projects, which is a compli­
However, in some cases (C41 project A; C81 projects A B D E and C82 cated process during the subjective assessment of individual experts.
projects A B D), the change of OFN orientation causes a significant The developed approach accounted for the weights of individual
change in the assessment of a given project (from nearly 18% to over criteria as well as individual expert assessments expressed numerically,
50% of the total importance project Qm ). These are the cases for quan­ took into account the uncertainty of assessments, and trends of these
titative assessments, where the project is rated very low (close to 0 for assessments until the launch of projects. Uncertainty was determined
the benefit criteria and vice versa for the cost criterion). In this case, the using trapezoidal fuzzy sets that contained orientations. A positive
dispersion of ratings for all projects according to the m-th criterion is orientation allowed the expert to express his supposition regarding the
also important - the larger dispersion the smaller the impact of the upward direction of changes in project evaluation to a given criterion.
change in OFN orientation, and the smaller dispersion the greater the Similarly, a negative orientation allowed the expert to express his sup­
impact. position regarding a non-growth direction of change. Therefore, the use
The Fig. 10 presents average ranting change for each criterion. In the of orientations accounted for the anticipated tendency of changes in

Fig. 10. Average absolute change in criterion rating as a result of OFN orientation change.

15
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

assessments resulting from changes in the environment. The method can Büyüközkan, G., & Öztürkcan, D. (2010). An integrated analytic approach for Six Sigma
project selection. Expert Systems with Applications, 37(8), 5835–5847. https://doi.
be especially useful for portfolio analysis with projects using the latest
org/10.1016/j.eswa.2010.02.022
technologies and implemented in frequently changing environmental Carazo, A. F., Gómez, T., Molina, J., Hernández-Díaz, A. G., Guerrero, F. M., &
conditions. Caballero, R. (2010). Solving a comprehensive model for multiobjective project
The sensitivity analysis of the IPs evaluation in relation to the change portfolio selection. Computers & Operations Research, 37(4), 630–639. https://doi.
org/10.1016/j.cor.2009.06.012
of the OFN orientation has shown that taking trends into account has a Chen, C. T., & Hung, W. Z. (2008). Applying fuzzy linguistic variable and ELECTRE
big impact in the case of projects rated not highly but promising. As a method in R&D project evaluation and selection. In 2008 IEEE international
result, the proposed IP selection method allows for bolder strategic ac­ conference on industrial engineering and engineering management. https://doi.org/
10.1109/IEEM.2008.4738020
tions in the aspect of continuous improvement. This approach handles Chen, C.-T. (2000). Extensions of the TOPSIS for group decision-making under fuzzy
the key aspects of decision making in a consistent and rational way. environment. Fuzzy Sets and Systems, 114(1), 1–9. https://doi.org/10.1016/S0165-
The limitation of the approach is that the operations on OFNs 0114(97)00377-1
Chen, Y., Chen, W. D., Peng, J., & Wang, J. Y. (2005). TOPSIS approach to project
sometimes result in an improper OFN, therefore in the future, it is selection in Six-Sigma management. Industrial Engineering Journal-Guangzou, 8(4),
pertinent to develop an approach based on the revision theory of the 90–92.
Kosiński’s OFN, proposed by Piasecki (2018). Unfortunately, it demands Chuang, P.-T. (2001). Combining the analytic hierarchy process and quality function
deployment for a location decision from a requirement perspective. The International
an analysis of summands ordering. Journal of Advanced Manufacturing Technology, 18(11), 842–849. https://doi.org/
10.1007/s001700170010
CRediT authorship contribution statement Dimova, L., Sevastianov, P., & Sevastianov, D. (2006). MCDM in a fuzzy setting:
Investment projects assessment application. International Journal of Production
Economics, 100(1), 10–29. https://doi.org/10.1016/j.ijpe.2004.09.014
Katarzyna Rudnik: Conceptualization, Methodology, Validation, Dubois, Didier, & Prade, Henri (1978). Operations on fuzzy numbers. International
Formal analysis, Writing - original draft, Writing - review & editing. Journal of Systems Science, 9(6), 613–626. https://doi.org/10.1080/
Grzegorz Bocewicz: Supervision, Validation, Writing - review & edit­ 00207727808941724
Ehsanifar, M., & Hemesy, M. (2019). A new hybrid multi-criteria decision-making model
ing. Aneta Kucińska-Landwójtowicz: Conceptualization, Resources, to prioritize risks in the construction process under fuzzy environment (case study:
Data curation, Validation, Writing - original draft, Writing - review & the Valiasr Street underpass project). International Journal of Construction
editing. Izabela D. Czabak-Górska: Validation, Visualization, Formal Management, 1–16. https://doi.org/10.1080/15623599.2019.1569816.
Evans, G. W., & Alexander, S. M. (2007). Using multi-criteria modeling and simulation to
analysis, Writing - original draft, Writing - review & editing. achieve lean goals. Proceedings - Winter Simulation Conference, 1615–1623. https://
doi.org/10.1109/WSC.2007.4419781
Declaration of Competing Interest Ghorabaee, K. M., Amiri, M., Zavadskas, E. K., & Antuchevičienė, J. (2017). Assessment
of third-party logistics providers using a CRITIC–WASPAS approach with interval
type-2 fuzzy sets. Transport, 32(1), 66–78. https://doi.org/10.3846/
The authors declare that they have no known competing financial 16484142.2017.1282381
interests or personal relationships that could have appeared to influence Hashemi, S. S., Hajiagha, S. H. R., Zavadskas, E. K., & Mahdiraji, H. A. (2016).
Multicriteria group decision making with ELECTRE III method based on interval-
the work reported in this paper. valued intuitionistic fuzzy information. Applied Mathematical Modelling, 40(2),
1554–1564. https://doi.org/10.1016/j.apm.2015.08.011
References Herrera, F., & Martínez, L. (2000). A 2-tuple fuzzy linguistic representation model for
computing with words. IEEE Transactions on Fuzzy Systems, 8(6), 746–752. https://
doi.org/10.1109/91.890332
Abbasianjahromi, H., & Rajaie, H. (2012). Developing a project portfolio selection model
Hira, A., & Parfitt, T. W. (2004). Development Projects for a New Millennium. In
for contractor firms considering the risk factor. Journal of Civil Engineering and
Perspectives on politics. Greenwood Publishing Group. https://doi.org/10.1017/
Management, 18(6), 879–889. https://doi.org/10.3846/13923730.2012.734856
s1537592705510144.
Abdulmalek, F. A., & Rajgopal, J. (2007). Analyzing the benefits of lean manufacturing
Hu, G., Wang, L., Fetch, S., & Bidanda, B. (2008). A multi-objective model for project
and value stream mapping via simulation: A process sector case study. International
portfolio selection to implement lean and Six Sigma concepts. International Journal of
Journal of Production Economics, 107(1), 223–236. https://doi.org/10.1016/j.
Production Research, 46(23), 6611–6625. https://doi.org/10.1080/
ijpe.2006.09.009
00207540802230363
Adebanjo, D., Samaranayake, P., Mafakheri, F., & Laosirihongthong, T. (2016).
Huang, C.-T., Yeh, T.-M., Lin, W.-T., & Lee, B.-T. (2009). A fuzzy AHP-based performance
Prioritization of Six-Sigma project selection: A resource-based view and institutional
evaluation model for implementing SPC in the Taiwanese LCD industry. International
norms perspective. Benchmarking, 23(7), 1983–2003. https://doi.org/10.1108/BIJ-
Journal of Production Research, 47(18), 5163–5183. https://doi.org/10.1080/
09-2015-0086
00207540801935608
Ahari, R. M., & Niaki, S. T. A. (2014). A hybrid approach based on locally linear neuro-
Jung, J. Y., & Lim, S.-G. (2007). Project categorization, prioritization, and execution
fuzzy modeling and TOPSIS to determine the quality grade of gas well-drilling
based on six sigma concept: A case study of operational improvement project. Project
projects. Journal of Petroleum Science and Engineering, 114, 99–106. https://doi.org/
Management Journal, 38(1), 55–60. https://doi.org/10.1177/875697280703800106
10.1016/j.petrol.2014.01.010
Kacprzak, D. (2017). Objective weights based on ordered fuzzy numbers for fuzzy
Gonzalez Aleu, F., & Van Aken, E. M. (2016). Systematic literature review of critical
multiple criteria decision-making methods. Entropy, 19(7), 373. https://doi.org/
success factors for continuous improvement projects. Lean Six Sigma Journal, 7(3),
10.3390/e19070373
214–232. https://doi.org/10.1108/IJLSS-06-2015-0025
Kacprzak, D. (2019). A doubly extended TOPSIS method for group decision making
Altintas, M., Erginel, N., & Kucuk, G. (2016). Determining the criteria and evaluating six
based on ordered fuzzy numbers. Expert Systems with Applications, 116, 243–254.
sigma projects via fuzzy ANP method in group decision. IFAC-PapersOnLine, 49(12),
https://doi.org/10.1016/j.eswa.2018.09.023
1850–1855. https://doi.org/10.1016/j.ifacol.2016.07.852
Kacprzak, D. (2020). An extended TOPSIS method based on ordered fuzzy numbers for
Anand, G., & Kodali, R. (2008). Selection of lean manufacturing systems using the
group decision making. Artificial Intelligence Review, 53(3), 2099–2129. https://doi.
PROMETHEE. Journal of Modelling in Management, 3(1), 40–70. https://doi.org/
org/10.1007/s10462-019-09728-1
10.1108/17465660810860372
Kacprzak, M., Kosiński, W., & Prokopowicz, P. (2012). Implications on ordered fuzzy
Annex A1 The Standard For Project Management Of A Pr. (2013). In A guide to the
numbers and fuzzy sets of type two. Lecture Notes in Computer Science (Including
Project Management Body of Knowledge (PMBOK guide) (5th ed., pp. 417–462).
Subseries Lecture Notes in Artificial Intelligence and Lecture Notes in Bioinformatics).
Project Management Institute.
https://doi.org/10.1007/978-3-642-29347-4_29
Bakshi, T., Som, T., & Sarkar, B. (2015). A novel soft theoretic AHP model for project
Kahraman, C., & Büyüközkan, G. (2008). A combined fuzzy AHP and fuzzy goal
management in multi-criteria decision making problem. Springer Proceedings in
programming approach for effective six-sigma project selection. Journal of Multiple-
Mathematics and Statistics, 125, 201–213. https://doi.org/10.1007/978-81-322-
Valued Logic and Soft Computing, 14(6), 599–615.
2301-6_15
Kalashnikov, V., Benita, F., López-Ramos, F., & Hernández-Luna, A. (2017). Bi-objective
Bilgen, B., & Şen, M. (2012). Project selection through fuzzy analytic hierarchy process
project portfolio selection in Lean Six Sigma. International Journal of Production
and a case study on Six Sigma implementation in an automotive industry. Production
Economics, 186, 81–88. https://doi.org/10.1016/j.ijpe.2017.01.015
Planning & Control, 23(1), 2–25. https://doi.org/10.1080/09537287.2010.537286
Kelly, M. (2002). Three steps to project selection. Six Sigma Forum Magazine, 2(1), 29–33.
Bocewicz, G., Banaszak, Z., Rudnik, K., Witczak, M., Smutnicki, C., & Wikarek, J. (2020).
Kendrick, J. D., & Saaty, D. (2007). Use analytic hierarchy process for project selection.
Milk-run routing and scheduling subject to fuzzy pickup and delivery time
ASQ Six Sigma Forum Magazine, 22–29. http://dschoenherr.fatcow.com/sitebuilderc
constraints: An ordered fuzzy numbers approach. In 2020 IEEE International
ontent/sitebuilderfiles/analytic_hierarchy_process.pdf.
Conference on Fuzzy Systems (FUZZ-IEEE), Glasgow, United Kingdom, pp. 1–10, doi:
Kerzner, H. (2020). Innovation project management: Methods, case studies, and tools for
10.1109/FUZZ48607.2020.9177733.
managing innovation projects. In John Wiley & Sons Inc.
Brauers, W. K. M., Baležentis, A., & Baležentis, T. (2011). Multimoora for the EU member
States updated with fuzzy number theory. Technological and Economic Development of
Economy, 17(2), 259–290. https://doi.org/10.3846/20294913.2011.580566

16
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Kornfeld, B. J., & Kara, S. (2011). Project portfolio selection in continuous improvement. Piasecki, K. (2018). Revision of the Kosinski’s theory of ordered fuzzy numbers. Axioms,
International Journal of Operations and Production Management, 31(10), 1071–1088. 7(1), 16. https://doi.org/10.3390/axioms7010016
https://doi.org/10.1108/01443571111172435 Piasecki, K., Roszkowska, E., & Łyczkowska-Hanćkowiak, A. (2019). Simple additive
Kornfeld, B., & Kara, S. (2013). Selection of Lean and Six Sigma projects in industry. Lean weighting method equipped with fuzzy ranking of evaluated alternatives. Symmetry,
Six Sigma Journal, 4(1), 4–16. https://doi.org/10.1108/20401461311310472 11(4). https://doi.org/10.3390/sym11040482.
Kosiński, W., Prokopowicz, P., & Ślęzak, D. (2003). Ordered fuzzy numbers. Bulletin of Prokopowicz, P. (2016). Analysis of the changes in processes using the Kosinski’s fuzzy
the Polish Academy of Sciences. Mathematics, 51(3). numbers. Proceedings of the 2016 Federated Conference on Computer Science and
Kosiński, W. (2006). On fuzzy number calculus. International Journal of Applied Information Systems.
Mathematics and Computer Science. Prokopowicz, P. (2019). The use of Ordered Fuzzy Numbers for modelling changes in
Kosiński, Witold, Prokopowicz, P., & Ślȩzak, D. (2002). Fuzzy reals with algebraic dynamic processes. Information Sciences, 470, 1–14. https://doi.org/10.1016/j.
operations: Algorithmic approach. In Intelligent information systems 2002 (pp. ins.2018.08.045
311–320). Physica-Verlag HD. https://doi.org/10.1007/978-3-7908-1777-5_33. Prokopowicz, P., & Ślȩzak, D. (2017). Ordered fuzzy numbers: Definitions and
Kovach, J. V., & Ingle, D. (2018). An approach for identifying and selecting improvement operations. In Studies in Fuzziness and Soft Computing (Vol. 356, pp. 57–79). Cham:
projects. Total Quality Management & Business Excellence, 31(1-2), 149–160. https:// Springer. https://doi.org/10.1007/978-3-319-59614-3_4.
doi.org/10.1080/14783363.2017.1419055 Pyzdek, T. (2003). The Six Sigma handbook: The complete guide for greenbelts, blackbelts,
Kucińska-Landwójtowicz, A., Czabak-Górska, I. D., & Lorenc, M. (2019). Project and managers at all levels (Revised and Expanded Edition). New York: McGraw-Hill.
management as an element of continuous improvement in production companies. In Rębiasz, B., & Macioł, A. (2015). Comparison of classical multi-criteria decision making
K. S. Soliman (Ed.), Vision 2025: Education excellence and management of methods with fuzzy rule-based methods on the example of investment projects
innovations through sustainable economic competitive advantage. proceedings of evaluation. Smart Innovation, Systems and Technologies, 39, 549–561. https://doi.org/
the 34th international business information management association conference 10.1007/978-3-319-19857-6_47
(IBIMA) (pp. 7730–7742). International Business Information Management Roszkowska, E., & Kacprzak, D. (2016). The fuzzy saw and fuzzy TOPSIS procedures
Association. based on ordered fuzzy numbers. Information Sciences, 369, 564–584. https://doi.
Kucińska-Landwójtowicz, A., Czabak-Górska, I., Rudnik, K., & Lorenc, M. (2020) . org/10.1016/j.ins.2016.07.044
Classification of Improvement Project Selection Methods. In: Proceedings book of the Rudnik, K., & Deptuła, A. M. (2015). System with probabilistic fuzzy knowledge base and
4th International Conference on Quality Engineering and Management/Sampaio parametric inference operators in risk assessment of innovative projects. Expert
Paulo [et.al.] (red.), Proceedings of the International Conference on Quality Systems with Applications, 42(17-18), 6365–6379. https://doi.org/10.1016/j.
Engineering and Management, 2020, International Conference on Quality eswa.2015.04.025
Engineering and Management, ISBN 978-989-54911-0-0, pp. 532-549. Rudnik, K., & Kacprzak, D. (2017). Fuzzy TOPSIS method with ordered fuzzy numbers
Kumar, M., Antony, J., & Rae Cho, B. (2009). Project selection and its impact on the for flow control in a manufacturing system. Applied Soft Computing, 52, 1020–1041.
successful deployment of Six Sigma. Business Process Management Journal, 15(5), https://doi.org/10.1016/j.asoc.2016.09.027
669–686. https://doi.org/10.1108/14637150910987900 Saaty, T. L. (1980). The analytic hierarchy process. McGraw-Hill.
Kumar, S., Dhingra, A. K., & Singh, B. (2018). Kaizen selection for continuous Saghaei, A., & Didehkhani, H. (2011). Developing an integrated model for the evaluation
improvement through VSM-Fuzzy-TOPSIS in small-scale enterprises: An Indian case and selection of six sigma projects based on ANFIS and fuzzy goal programming.
study. Advances in Fuzzy Systems, 2018, 1–10. https://doi.org/10.1155/2018/ Expert Systems with Applications, 38(1), 721–728. https://doi.org/10.1016/j.
2723768 eswa.2010.07.024
Dinesh Kumar, U., Saranga, H., Ramírez-Márquez, J. E., & Nowicki, D. (2007). Six sigma Stojić, G., Stević, Ž., Antuchevičiene, J., Pamučar, D., & Vasiljević, M. (2018). A novel
project selection using data envelopment analysis. The TQM Magazine, 19(5), rough WASPAS approach for supplier selection in a company manufacturing PVC
419–441. https://doi.org/10.1108/09544780710817856 carpentry products. Information (Switzerland), 9(5). https://doi.org/10.3390/
Larson, A. (2003). Demystifying Six Sigma: a company-wide approach to continuous info9050121.
improvement. AMACOM Div American Mgmt Assn. Su, C., & Chou, C. (2008). A systematic methodology for the creation of Six Sigma
Ma, J., Harstvedt, J. D., Jaradat, R., & Smith, B. (2020). Sustainability driven multi- projects: A case study of semiconductor foundry. Expert Systems with Applications, 34
criteria project portfolio selection under uncertain decision-making environment. (4), 2693–2703. https://doi.org/10.1016/j.eswa.2007.05.014
Computers & Industrial Engineering, 140, 106236. https://doi.org/10.1016/j. Tague, N. R. (2005). The quality toolbox. ASQ Quality Press.
cie.2019.106236 Thipparat, T., & Thaseepetch, T. (2013). An integrated VIKOR and fuzzy AHP method for
Mardani, A., Nilashi, M., Zakuan, N., Loganathan, N., Soheilirad, S., Saman, M. Z. M., & assessing a sustainable research project. World Applied Sciences Journal, 22(12),
Ibrahim, O. (2017). A systematic review and meta-Analysis of SWARA and WASPAS 1729–1738. https://doi.org/10.5829/idosi.wasj.2013.22.12.2787
methods: Theory and applications with recent fuzzy developments. Applied Soft Tkáč, M., & Lyócsa, Š. (2010). On the evaluation of Six Sigma projects. Quality and
Computing, 57, 265–292. https://doi.org/10.1016/j.asoc.2017.03.045 Reliability Engineering International, 26(1), 115–124. https://doi.org/10.1002/
Martinsuo, M., & Lehtonen, P. (2007). Role of single-project management in achieving qre.1062
portfolio management efficiency. International Journal of Project Management, 25(1), Tsai, C. F., & Chen, Z. Y. (2013). Crossing the fuzzy front end chasm: Effective product
56–65. https://doi.org/10.1016/j.ijproman.2006.04.002 project concept selection using a 2-tuple fuzzy linguistic approach. Journal of
Mawby, W. D. (2007). Project Portfolio Selection for Six Sigma. ASQ Quality Press. Intelligent and Fuzzy Systems, 25(3), 755–770. https://doi.org/10.3233/IFS-120682
McLean, R. S., Antony, J., & Dahlgaard, J. J. (2017). Failure of Continuous Improvement Turskis, Z., Goranin, N., Nurusheva, A., & Boranbayev, S. (2019). A fuzzy WASPAS-based
initiatives in manufacturing environments: A systematic review of the evidence. approach to determine critical information infrastructures of EU sustainable
Total Quality Management & Business Excellence, 28(3-4), 219–237. https://doi.org/ development. Sustainability (Switzerland), 11(2), 424. https://doi.org/10.3390/
10.1080/14783363.2015.1063414 su11020424
Meredith, J. R., Mantel, S. J., Jr, & Shafer, S. M. (2017). Project management: A managerial Turskis, Z., Zavadskas, E. K., Antucheviciene, J., & Kosareva, N. (2015). A hybrid model
approach. John Wiley & Sons. based on fuzzy AHP and fuzzy WASPAS for construction site selection. International
Meredith, J. R., Shafer, S. M., & Mantel, S. J., Jr (2017). Project management: A strategic Journal of Computers, Communications and Control, 10(6), 873–888. https://doi.
managerial approach (10th ed.). John Wiley & Sons. org/10.15837/ijccc.2015.6.2078.
Mittal, K., Tewari, P. C., & Khanduja, D. (2017). On the right approach to selecting a van Laarhoven, P. J. M., & Pedrycz, W. (1983). A fuzzy extension of Saaty’s priority
quality improvement project in manufacturing industries. Operations Research and theory. Fuzzy Sets and Systems, 11(1-3), 229–241. https://doi.org/10.1016/S0165-
Decisions, 27(1), 105–124. https://doi.org/10.5277/ord170106 0114(83)80082-7
Mohagheghi, V., & Mousavi, S. M. (2019). A new framework for high-technology project Wang, F. K., Hsu, C. H., & Tzeng, G. H. (2014). Applying a hybrid MCDM model for six
evaluation and project portfolio selection based on pythagorean fuzzy WASPAS,s sigma project selection. Mathematical Problems in Engineering, 1, 1–13.
MOORA and mathematical modeling. Iranian Journal of Fuzzy Systems, 16(6), Wen, Y., An, Q., Xu, X., & Chen, Y.a. (2018). Selection of Six Sigma project with interval
89–106. https://doi.org/10.22111/ijfs.2019.5022 data: Common weight DEA model. Kybernetes, 47(7), 1307–1324. https://doi.org/
Mohagheghi, Vahid, Mousavi, S. M., Mojtahedi, M., & Newton, S. (2020). Introducing a 10.1108/K-07-2017-0250
multi-criteria evaluation method using Pythagorean fuzzy sets: A case study focusing Yalcin, A. S., Kilic, H. S., & Guler, E. (2020). Research and development project selection
on resilient construction project selection. Kybernetes. https://doi.org/10.1108/K- via IF-DEMATEL and IF-TOPSIS. Advances in Intelligent Systems and Computing, 1029,
04-2019-0225. 625–633. https://doi.org/10.1007/978-3-030-23756-1_76
Morkunaite, Z., Bausys, R., & Zavadskas, E. K. (2019). Contractor selection for Sgraffito Yang, T., & Hsieh, C.-H. (2009). Six-Sigma project selection using national quality award
decoration of cultural heritage buildings using the WASPAS-SVNS method. criteria and Delphi fuzzy multiple criteria decision-making method. Expert Systems
Sustainability (Switzerland), 11(22). https://doi.org/10.3390/su11226444 with Applications, 36(4), 7594–7603. https://doi.org/10.1016/j.eswa.2008.09.045
Otay, İ., & Kahraman, C. (2018). Six sigma project selection using interval neutrosophic Yapici Pehlivan, N., Şahin, A., Zavadskas, E. K., & Turskis, Z. (2018). A comparative
TOPSIS. Advances in Intelligent Systems and Computing, 643, 83–93. https://doi.org/ study of integrated FMCDM methods for evaluation of organizational strategy
10.1007/978-3-319-66827-7_8 development. Journal of Business Economics and Management, 19(2), 360–381.
Padhy, R. (2017). Six Sigma project selections: A critical review. International Journal of https://doi.org/10.3846/jbem.2018.5683
Lean Six Sigma, 8(2), 244–258. https://doi.org/10.1108/IJLSS-06-2016-0025 Yazdani, M., Abdi, M. R., Kumar, N., Keshavarz-Ghorabaee, M., & Chan, F. T. S. (2019).
Padhy, R. K., & Sahu, S. (2011). A real option based Six Sigma project evaluation and Improved decision model for evaluating risks in construction projects. Journal of
selection model. International Journal of Project Management, 29(8), 1091–1102. Construction Engineering and Management, 145(5), 04019024. https://doi.org/
https://doi.org/10.1016/j.ijproman.2011.01.011 10.1061/(ASCE)CO.1943-7862.0001640
Pande, P. S., Neuman, R. P., & Cavanagh, R. R. (2000). The Six Sigma way: How GE, Yordanova, Z. B. (2018). Innovation project tool for outlining innovation projects.
Motorola, and other top companies are honing their performance. Quality Progress, International Journal of Business Innovation and Research, 16(1), 63–78. https://doi.
34. https://doi.org/10.1036/0071376674 org/10.1504/IJBIR.2018.091084

17
K. Rudnik et al. Expert Systems With Applications 169 (2021) 114471

Yu, J., & Liu, Y. (2012). Prioritizing highway safety improvement projects: A multi- Zavadskas, E. K., Turskis, Z., Antucheviciene, J., & Zakarevicius, A. (2012). Optimization
criteria model and case study with SafetyAnalyst. Safety Science, 50(4), 1085–1092. of weighted aggregated sum product assessment. Elektronika Ir Elektrotechnika, 122
https://doi.org/10.1016/j.ssci.2011.11.018 (6), 3–6. https://doi.org/10.5755/j01.eee.122.6.1810
Yüksel, H. (2012). Evaluation of the success of Six Sigma projects by data envelopment Zavadskas, E. K., Turskis, Z., & Antucheviciene, J. (2015). Selecting a contractor by using
analysis. International Journal of Business and Management, 7(13). https://doi.org/ a novel method for multiple attribute analysis: Weighted aggregated sum product
10.5539/ijbm.v7n13p75 assessment with grey values (WASPAS-G). Studies in Informatics and Control, 24(2).
Zadeh, L. A. (1965). Fuzzy sets. Information and Control, 8(3), 338–353. https://doi.org/ https://doi.org/10.24846/v24i2y201502
10.1016/S0019-9958(65)90241-X Zhang, W., Hill, A. V., Schroeder, R. G., & Linderman, K. W. (2008). Project management
infrastructure: The key to operational performance improvement. Operations
Management Research, 1(1), 40–52. https://doi.org/10.1007/s12063-008-0008-9

18

You might also like