Professional Documents
Culture Documents
Material deterioration is one of the major constituents causing defects in building. There are also some
other components: design fault, substandard material, poor workmanship, inadequate maintenance,
misuse. Some of the vulnerable building elements will be examined below, with particular analysis on
these components.
1. Foundation
➢ settlement of foundation is the major problem concerned
➢ serious foundation defects can affect the stability of the structure
➢ not a major problem in end-bearing piles except due to faulty design, poor workmanship or change
of use
o the ‘short’ pile incident in the Shatin public housing is due to insufficient supervision
o other indirect reasons causing the incident: conservative safety factor; Housing Authority’s
‘lowest-bid’ contract award policy, sampling for testing
o 100% testing – more reliable spot check conducted
o different testing methods: static loading, dynamic loading, sonic testing, concrete coring, etc.
(for more details, see ‘Pile Design and Construction’ Civil Engineering Dept., HKSAR, 1996)
➢ frictional piles or shallow foundation can be affected by soil movement
➢ major defects of frictional piles are:
(1) Soil movement causing settlement of foundation :
• change of water content of soils causing shrinking and swelling of soil volume
(particularly clay soil because clays contain very fine particles which can hold large
amount of water)
• soil consolidation under pressure of dead and imposed loads of building, which intends to
squeeze out the water from the soil
• vibration caused by traffic, machinery, construction works like piling or explosion
(2) Frost attack – due to expansion of ice in the sub-soil, the construction of foundation wall under
the perimeter wall to a depth under the frost line can reduce the risk of frost heave
(3) Vegetation effects – tree root attack and change of water content of soil
(4) Ground movements – mining, earthquake, landslides, etc.
(5) Faulty foundation design or construction – can result in differential settlement, e.g. short piles
(6) Cavernous marble – cavities in the upper surface of marble (found in Yuen Long and Ma On
Shan in Hong Kong) reclaimed land will settle
(7) Settlement of fill (reclaimed land) – forming of void and settlement, particularly for sites
containing domestic refuse. The bearing capacities are very weak for sites filled by refuse or
other organic substances and deep foundations are required if construction is going to be carried
how fast depends on filling materials eg, sand>domestic refuse
out. (The Code of Practice of Foundation 2004 issued by the HK Govt. defines ‘Newly
Reclaimed Land’ as the land reclaimed within 7 years and all structures and foundations built
on such land will be susceptible to settlement.)
(8) Overloading of foundation – misuse or change of use of building, extension or alternations.
Underpinning is used to strengthen existing foundation so as to support the additional loading.
previous exam:
remedy for short pile
abandon the short poiles,
construction new piles to replace it
Photo shows the static loading test of pile – test the bearing capacity of piles before
carrying out the superstructure work (such test is only suitable to light to medium load-
bearing capacity piles like H-piles or pre-bored H piles.
Further information:
http://www.bd.gov.hk/english/servic
es/index_faqH.html
5. movement – shrinkage, creep of concrete substrate, thermal movement (especially for external
wall tile). Allowance of 6 weeks for initial drying shrinkage of concrete is recommended.
➢ cure and repair methods:
(1) Patch Tile Repair / Re-tiling is the most popular method (but need to match with the old tiles in
appearance)
(2) Resin Grouting is another method to fix the debonding tiles problem.
⚫ location of debond tiles are located
⚫ holes are drilled at strategic corners of debond tiles
⚫ resin is injected through these holes in order to fill up the void behind the debond tiles
⚫ this technique requires higher technology and precision
⚫ more experienced labourer and closer supervision are required
⚫ noise is minimized as no need to hack-off the old tiles
⚫ appearance (colour, texture) remains intact and unchanged
⚫ if the debond area is too big, this technique is not suitable and re-tiling may be a better
alternative
(3) Overcladding
◆ installation of a new cladding panel to cover debond tiles (need to apply it to the whole building
and therefore much more expensive but is more durable and can give better appearance
◆ quieter operation because no need to hack off the existing tiles
◆ e.g. Jardine House in Central – overcladding with anodized aluminium panel over mosaic tiles.
◆ Other problems need to be solved include the extra loading of the panels and the extra gross floor
area (GFA) generated and therefore may need to seek the approval of the Building Authority.
incur extra GFA
Further Reference:
◼ APP68/PNAP173 – Design & Construction of Cantilevered RC Structures
◼ APP116/PNAP 248 – Aluminium Windows
◼ PNRC 67 – Building External Finishes – Wet-fixed Tiles
◼ http://www.info.gov.hk/bd - Practice Note for Authorized Persons and Registered Structural
Engineers