You are on page 1of 1

CERTIFICATE OF MATE RIAL ISSUANCE

It is certified that quantities of steel in priority 1 issued from store to the contractor
M/s ___________________for __ __________ from Storm water drain at SWD-1 PMU Delta. is
vetted by PMU Delta SWD-1. Is

1. Steel ____________________________ 2. Grating Complete Set_________________________

3. Grating Frame_____________________ 4. Top Cover_______________________________

5. Inspect Chamber ______________________________________________


COUNTERSIGNED

a Store Keeper :_____________________________

b. Q.S :______________________________

c. D.P.M :______________________________

Lt Col,
SM Project,
PMU Delta NLC KCI, SWD-1
Muhamad Jibran
Dated:______________ 2023