Professional Documents
Culture Documents
2020) Submitted by
Seal of
Signature Institution
Signature
The industrial training program is favorable to the students who wants to get actual site
experience for upgrading and amplification of their skills sets. It assists to leaners to adopt latest
upgrading technologies, skills and new different methods in the field of civil engineering. It helps
to construct strong base to their rising carrier in field of civil engineering.
In this report, the detail study of the Hindustan Construction Company and one of its major
milestone projects i.e., Pir Panjal Railway Tunnel is taken for online industrial training. Many
particulars of the Hindustan Construction Company include company profile, vision and mission,
policies, awards and other related data to the company details are studied and presented in the
given report.
The Pir Panjal Railway Tunnel is totally completed major and dream project of HCC. It is
the longest railway tunnel in India. The 11.267 km long was constructed as part of the Indian
Government’s plan to provide Jammu and Kashmir with reliable link to the rest of the country. It
takes approximately 9 minutes and 30 seconds for the train to cross the tunnel. The Pir Panjal
Railway Tunnel was the first tunnel in India to be accordance with the principles of the New
Austrian Tunneling Method (NATM).
The detailed project report includes factors such as construction methodology of the
NATM, construction materials & there IS specifications, survey carried out, special technology
and equipment’s used during construction of the tunnel. It is also consisting of special case study
about Ballast Less Tracks in tunnel.
On the occasion of the this tunnel inauguration the Honorable Railway Minister Shri C.P.
JOSHI (2009-2014) says that, “ Pir Panjal Railway Tunnel” is feather in the cap of the Indian
railways and will act a stepping stone future gigantic works in future. This online training upgrades
different skills of students such as leadership, unity in group, thinking power about particular topic
and quick decision-making quality of the student who appeared for industrials training. This
industrial training program gives magnificent experience to the students whose looking for their
bright future in the field of civil engineering.
INDEX
1. INTRODUCTION 1-16
1.1 Introduction 1
1.4.1 History
2.2 Preface 21
2.4 Concept 24
2.4.1 Tunnel
3.3.6 Materials
3.6.1 Shafts
3.7.1 Definition
3.12.2 Excavator
3.12.3 Boomer
3.13.1 General
5. CONCLUSION 85
6. REFERENCE 87
7. ACKNOWLEDGEMENT 88
LIST OF FIGURES
FIGURE 3 CERTIFICATE 8
FIGURE 4 CERTIFICATE 8
FIGURE 15 27
FIGURE 17 33
FIGURE 23 PILLARS 39
FIGURE 25 SPADE 46
FIGURE 34 EXPLODER. 56
FIGURE 35 OHMMETER. 56
FIGURE 40 SCALING 58
FIGURE 41 CHIPPING: 58
FIGURE 79 EXCAVATOR. 95
FIGURE 80 EXCAVATOR. 95
FIGURE 81 BOOMER 96
FIGURE 82 BOOMER 96
LIST OF TABLEs
9 RELIANCE. 17
10 DMRCL 17
ABBREVIATION DETAIL
IS Indian Standard
1.1} INTRODUCTION
The Industrial Training is compulsory for every student of Diploma in Civil engineering
(Programming) as a condition for the award of the diploma. This exercise is also intended to
provide exposure and experience to the students about the real situation in the field of Civil
engineering (Programming) and as an early preparation for students before entering the working
world. Today, nearly every Engineering & Professional graduate program in India require summer
training to be included as a crucial part of their curriculum. The objective is to improve the
knowledge of the students on different cutting-edge technologies which have become significant
part of relevant civil engineering industries.
The industrial training exposes the students to professional skills and experiences in
industrial engineering practices. In preparing the students for the real working environment as
engineers, industrial training helps to produce engineering graduates with technical and soft skills
competency. Summer industrial training program is of four weeks. Due to COVID-19 outbreak in
India this actual site experience training program is converted into online training program by the
orders of MSBTE.
1
1.2} INDUSTRIAL TRAINING.
1.2.1] Objectives of Industrial Training.
1. To expose students to the real working environment and to get linked with the outer world
2. Let’s students see the connection between theoretical learning with practical work in their
specific fields.
3. Adopt and follow the safety regulations in the industry.
4. To Establish and strengthen confidence of students and also in the performance of duties.
5. Instill teamwork and good relationships with other employees and in between teammates.
6. To install the Abilities to assess themselves to prepare for the working world after
graduation.
7. Raise awareness and increase student interest in the subject selected.
8. Uplifting honest, trustworthy, dedicated and responsible for the tasks assigned by the
specific group leaders and Mentors.
2
The group of 5 students Roll number from 211 to 215 have selected the industry for
industrial training that is Hindustan Construction Company [HCC].
Landmark projects executed by HCC include the Bogibeel Bridge- India's longest rail-
cum-road steel bridge; Kishanganga Hydro Power Project Largest EPC contract of NHPC;
BandraWorli Sea Link − India's first and longest open sea cable-stayed bridge; Kudankulam
Nuclear Power Plant - India’s first and largest light water reactors and the Kolkata Metro- India's
first metro.
HCC is the first construction company in India to implement ISO certified Quality,
Occupational Health & Safety and Environment Management systems. The Company has
invested in the early adaption of advanced engineering equipment, new and innovative
technology and strategic international association.
3
Fig.1:
4
1.4} INDUSTRIAL PROFILE DETAILS.
1.4.1] History.
Seth Walchand Hirachand is widely hailed as the Father of the Indian Transportation
Industry. He is remembered as the man who took an ambitious yet pragmatic stand in challenging
British monopolies, a feat that resulted in India’s first shipyard, aircraft factory and automobile
factory.
He began his entrepreneurial foray in the Construction industry, first as a railway contractor
and then as a contractor to other departments of Government. Some of the major projects executed
by him include tunneling through the Bhor Ghats for a railway route from Mumbai to Pune and
laying of water pipes from Tansalake to Mumbai. Other major projects executed by him include
the Kalabag Bridge over the Indus River and a bridge across the Irrawaddy River in Burma.
5
1.4.2] Company Directors :-
Table: 1.
6
1.4.3] Financial Information of HCC :-
The Highlights of the financial performance of HCC for 2018-19 are:
1. Turnover of Rs.4, 341 crore vs. Rs.4, 575 crore.
2. Net Loss of Rs.1, 962 crore vs. Net Profit of Rs.78 crore, owing to exceptional loss of
Rs.2, 400crore.
3. Gross debt has reduced by Rs.227 crore year-on-year to Rs.3, 749 crore as of March 31,
2019.
As of 31st March, 2019, HCC total workforce strength (HCC Engineering &
Construction business) was 19732. This comprised of 1386 Senior, Middle and Junior
Management Officers, 55 Trainees, Apprentices and Short-term Contracts, as well as 18291
Workmen (on project rolls, sub-contracted and piece rate workers).
At HCC, They take pride in their work and strive for excellence, leading to results that speak of
quality.
• Their prime focus is to meet the client's requirements and to strive to exceed their
expectations
• They also strive to improve processes and methodologies to achieve consistent and
predictable results. HCC aspires for Zero-defect by creating an environment of quality
awareness, rather than relying on inspections
• They keep their selves updated with the latest in equipment and technical know-how
• They endeavor to eliminate process wastage through lean construction
• They adapt to challenging and ever-changing conditions without compromising on due
process
• They evaluate performance through various statistical tools and take timely decisions in
pursuit of efficiency.
7
They integrate three quality management systems, viz. International standards for Quality
(ISO 9001), Occupational Health & Safety (OHSAS 18001) and Environment (ISO 14001), into
all our activities starting from marketing to handing over of projects. They possess ISO certificate
of ISO9001, ISO 14001 and OHSAS as granted by TUV Nord.
8
1.4.6] Vision and Mission :-
I. Vision
To be the industry leader and a market driven engineering construction company renowned
for excellence, quality, performance and reliability in all types of construction.
II. Mission
1. Constantly assess the needs, realities and values of the customer and set goals to satisfy
their needs
2. Continually innovate, develop and adopt state-of-the-art technologies, methodologies and
materials to deliver customer satisfaction through better, faster and cheaper construction
services
3. Continually aspire to deliver higher standards of safety, occupational health and
environment protection at work
4. Continually develop and maintain a robust supply chain that will help us deliver value to
the customer on time and to expectations
5. Continually improve the competence of our people through education and by inculcating
strict principles of conduct and responsibility, high standards of performance, and respect
for individuals and their work
6. Organize work for effectiveness in delivering results and always look to commit today’s
resources to the future
7. To build a reputation of trust and reliability amongst our customers, other stakeholders and
society.
9
1.4.7] Corporate Social Responsibility (CSR) :-
1. Responsible infrastructure:
At HCC, CSR has evolved from being passive philanthropy to corporate community
investments, which takes the form of a social partnership initiative creating value for stakeholders.
Such initiatives are an integral part of business ethos and goes well beyond regulatory
compulsions. Having said so, as per section 135 of The Companies Act 2013, HCC has formalized
a CSR policy keeping Schedule VII in mind. The IMS procedure for effective implementation of
the policy has been made. The Company’s CSR philosophy is ‘Do Good to Do Well and Do Well
to Do Good’.
2. Disaster relief and response
The Company provided timely interventions in a number of rescue and relief operations
within India and internationally during calamities / disasters, providing support by way be
technical help, as well as relief by way of water, food and other essentials.
During the FY2019, HCC responded to the following disaster:
10
1.4.8] Awards Grab By HCC For Their Works:-
Table 2.
11
1.4.9] Business Management and Services :
1. Power :
Nuclear Power
Thermal Power
Hydro Power
2. Transportation
Highways, Roads and Bridges
Railways
Mass Rapid Transit Systems
Ports and Harbors
3. Water
Water Supply and Sanitation
Irrigation
4. Industrial And Buildings
Manufacturing and Process Plants
Commercial and Institutional
Smart Cities and Townships
5. Quarry Operations (Drilling, Blasting and Transportation of Boulder /Muck).
6. Drilling and Grouting Work, Rock/Soil Stabilization, Permeation Grouting Work.
7. Fabrication and Erection Work Including That of Structural Steel Road Bridges.
8. Construction of RCC Bridges.
12
1.4.10] HCC Clients.
Sr. No CLIENTS
1 Central Government
2 Indian Railways
Table 3.
13
3. Department of Atomic Energy. 4. Bhabha Atomic Research Center.
Corporation
14
9. Reliance. 10.DMRCL
15
1.4.12] Construction Research and Development (CR&D).
CR&D is being carried out with the objectives of continual efficiency enhancement,
reductions in material costs, process development, improving speed, enhancement of construction
quality and sustainability. These efforts are undertaken through interdisciplinary engineering
within the organization and in technical collaboration with vendors, consultants, research
organizations and academia sharing similar interests.
Some of the CR & D efforts are listed below:
1. Optimizing concrete ingredients with specific focus on reducing cement content, reducing
carbon footprint and making Portland cement concrete a sustainable choice: This is partly
achieved using less energy intensive chemical additives, enhanced use of alternate
cementing materials (like fly ash, slag, micro silica, ultra-fine slag etc.) and optimal quality
assurance planning.
2. Controlled quarrying and crushing of aggregates for construction with an objective of
reducing wastage and environmental impact.
3. Through the use of the Philosophy of materials integrated design to maximize utilization
of locally available construction materials.
4. Development of alternate equivalent to lessen the consumption of expensive construction
materials through use of less expensive substitutes from industrial wastes in close
coordination with specialized vendors.
5. Speedier Construction technologies such as, roller compacted concrete (RCC) for the
construction of dams.
16
CHAPTER 2
CASE STUDY
SELECTION.
17
2.1.3] NH-34 – Bahrampore – Farakka Highway, West Bengal (Ongoing).
Fig 7: NH-34
2.1.5] Elevated Road from Park Circus to E.M. Bypass, Kolkata, West Bengal (2015)
18
2.1.7] NH-3 MP/Maharashtra Border - Dhule Highway, Maharashtra (2012).
Fig 9 : NH-3
19
2.1.10] Varanasi Bridge, Uttar Pradesh (1997).
20
2.2} PREFACE :-
The engineering work on a large tunnel project is so complex that number of engineers and
specialists in many areas are required to be involved in design and construction. The decisions, of
which there may be several, call for a vast amount of technical knowhow and sound judgement
based on many years of experience.
The 11 km. long tunnel the Par Panjal Railway Tunnel represents a highest point of
tremendous effort on the part of innumerable engineers who were involved in its planning, design
and construction – engineers from Northern Railway, the Contractor IRCON and their various
Subcontractors/consultants. Northern Railway’s engineers felt it worthwhile to pen down and put
on paper for the benefit of posterity the lots of the involved technical details and the lessons that
were learnt during design and construction of PirPanjal Railway Tunnel “the longest transportation
tunnel in India”.
These ‘Project’, stated in the format of a Report, give separate steps to decision making
and undoubtedly provide a comprehensive coverage of the subject for both the designer and the
constructor. At its heart lies the Capacity for Development which then is the ability to solve
problems, and make informed choices, and plan for future. The material in the Report is presented
in the vein of a comprehensive yet brief collection. The presentations have a flow that moves from
the ‘individual’ to the ‘organization’, with ‘practical skills’ and ‘theory’ woven together, offering
real-life engineering experience, from ‘problem formulation’ through to ‘implementation’.
This Project Report would educate the future creators in understanding the subject of tunneling,
thus enabling them to employ their grounding in engineering to become workmanlike partners in
future in such type of project.
21
2.3} BACKGROUND STUDY:-
Tunneling is both a ‘Science’ and ‘An art’ that over-arches the many disciplines of
engineering - civil, structural, geological, mechanical, electrical and computer as well as the
ecological and environmental constraints. Apart from being a highly expensive engineering
enterprise, tunnels can present very difficult problems in their construction. As more and more
tunnels are built, it calls for continued improvement in tunneling technology.
Here an attempt has been made to examine and evaluate the currently practiced construction
technologies i.e. Tunnel Boring Machine (TBM) method, Conventional Indian Method of
Tunneling and New Austrian Tunneling Method (NATM) for tunneling through different
medium i.e. through soil and rock.
With a view to provide a reliable alternative transportation system to the Kashmir Valley, the
Government of India sanctioned the construction of a 326 Km long railway line to the State’s
Summer Capital, Srinagar, taking off from its Winter Capital, Jammu. Terminating at Baramulla,
near Srinagar, the railway line connects Jammu with Udhampur, then Katra, Reasi, Banihal,
Qazigund and Srinagar.
It is one of the largest and toughest mountain – railway project undertaken in the country since
independence. The railway line traverses the young Himalayas, which is consequentially very
active and dotted with many Thrusts and Faults.
1) Work on the Jammu – Udhampur section (53 Km) was completed and commissioned in
April, 2005.
22
2) Then the section from Baramulla to Qazigund (119 Km) was completed and opened to
traffic in October, 2009.
3) Work on the Jammu – Udhampur section (53 Km) was completed and commissioned in
April, 2005.
4) Then the section from Baramulla to Qazigund (119 Km) was completed and opened to
traffic in October, 2009.
5) Work in the remaining stretch from Udhampur to Qazigund, totaling 154 Km, is in various
stages of construction.
6) The Udhampur-Srinagar-Baramulla rail link (USBRL-273Km) was declared as a ‘Project
of National Importance
7) In February, 1994 the Northern Railway suggested three alternative alignments between
Udhampur and Srinagar via Qazigund. These three alignments put up for the Railway
Board’s consideration are indicated below:
Section Udhampur - Quzigand Quzigand – Srinagar
Alt 1 1 in 40 (c)* 1 in 80 (c)*
Alt 2 1 in 100 (c)* 1 in 80 (c)*
Alt 3 1 in 100 (c)* 1 in 100 (c)*
23
2.4} CONCEPT
2.4.1] Tunnel:-
24
2.4.2] Site Topography.
i) The tunnel alignment traverses through the steeply sloping, highly undulating hill slopes
of the Par Panjal Range, which is part of the young Himalayas. Formation levels at tunnel portals
are at elevations 1713.63 m (South Portal) and 1756.70 m (North Portal). Respective ground
elevations at the tunnel axis are nearly 1729.40 m and 1775.62 m. The tunnel has a high point of
elevation, 1771.47 m, at approximately two thirds of the tunnel length from its South Portal i.e.
(CH 159+124).The minimum overburden above tunnel crown at the Portals is about 8 m in the
south and 12 m in the north while the maximum overburden is approximately 1100m. About 4 km
of the tunnel length has an overburden of more than 500 m and about 650 m of the tunnel length
has an overburden of more than 1000 m.
ii) Following the longitudinal section and starting at the south portal, overburden increases
gradually to about 300m over 3 km length, then the slope increases over 1.6 km to about 15°, and
following to 30° towards the highest peak at El 2890(CH 158+480) or about 1100 m overburden.
The highest peak of the mountain is at about 6.50 km from the south portal. Immediately on the
north side of the peak the mountain slopes with about 30° for about 1-2 km, following it stretches
with an overburden between 200 m and 300 m for about 2 km from where it slopes steeply with
almost 40° and finally it stretches with a shallow slope to the North Portal.
25
2.4.3] General Details of Project. :-
Table 4.
26
2.4.3] Technical Details:-
Table 5.
27
2.4.4] Cross Section of Pir Panjal Tunnel:-
I. Cost of the 11.2 km long PIR PANJAL (T-80) railway tunnel is around -1300 Crore.
II. Entire project of the 17 km long route between Banihal and Quzigund cost is -1691
Crore.
III. Total cost of the project is from Quzigand to Baramula section via Shrinagar of 118
km is -3658 Crore.
28
CHAPTER 3
THE PIR PANJAL
RAILWAY TUNNEL
For each tunnel tubes a contractual clearance area in form of a horseshoe was fixed
as shown in picture 4, with a semi-circle of 2.72 m radius and a trapezoidal lower part of 5.44 m
width at top at 5.03 m at about road level
29
3. The one-lane road pavement has a slope of 1:70 and is normally 3.20 m wide, on by-
passes it widens to 5.64 m,
4. The one-sided walkway has a railing at 1.25 width, the curbstone on the other side has a
width of 0.58 m, and both have been executed with a rounded-off curb as usually used in
this country. The clearance height is for Indian circumstances unusually high and even
sufficiently high for particular army vehicles.
Figure 16 : The Different Geometric Sections of the Tunnel (Length, Slope, Elevations and
Directions)
Table 6
30
3.2} SURVEYS CARRIED OUT IN CONSTRUCTION OF TUNNEL:-
31
3.3}. CONSTRUCTION MATERIALS AND SOME VITAL PROCESSESS: -
3.3.1] Different Types of Construction Materials Used In The Construction Of The Pir Panjal
Tunnel Are: -
1. Aggregate.
2. Water.
3. Cement.
4. Admixture and Accelerator.
5. Steel for Reinforcement.
6. Structural Steel.
32
3.3.3] Standards and Specifications :-
Table: 7.
33
3.3.4] Detail Construction Materials :-
1) Cement.
a) Cement used for Shotcrete conformed to IS 456: 2000.
b) Specific Fineness of the cement used, after Blaine, was between 4,000 and 5,000
cm2/g and this achieved.
2) Aggregate.
a) All Fine and Coarse Aggregate used were supplied from approved sources, which
were not allowed to be changed without permission in writing. These Aggregate
conformed to the requirements of IS 456:2000.
b) The maximum size of the Aggregate was limited to 12 mm for wet process and 16
mm for dry process. The proportion of aggregate larger than 8mm size was limited
to 15% for the wet process in order to minimize rebound.
3) Admixtures.
Water.
Water shall comply in all respect with IS 456: 2000.
4) Use of Fly Ash, Blast Furnace Slag, Silica Fume.
These have already been covered in the earlier part of the chapter
5) Shotcrete Mix Design.
The mix for shotcrete was designed by field suitability tests to meet the requirements of
the Specification.
❖ The following factors were taken into consideration :
a) The Gradation limits of the Aggregate.
b) Cement content.
c) Water-cement ratio.
d) Plasticizer /Super plasticizer: type and dosage, where used.
e) Hydration control admixture: type and dosage, where used.
f) Internal curing admixtures, where used.
g) Accelerating admixtures, where used.
h) Early and Final strength.
34
i) Strength vis-à-vis that of the reference shotcrete.
j) Rebound.
k) Temperature of the mix.
l) Target slump and slump retention of the mix for optimum placement and
performance.
35
3.3.6] Materials :-
1) SN-Bolts
a. SN-Bolts shall consist of rebars with a minimum diameter of 25 mm and steel
grade Fe 415.
b. The yield loads of the bolts also applied to its thread, nut, anchor plate and
coupling, if any.
c. Rock bolts were of deformed reinforcing steel with a corrugated surface, with one
end fitted with a suitable thread to receive the anchor plate and fixing nut.
\
Fig.18 : SN-Bolts
36
Fig.19 : Self Drilling Rock Bolts
3) Swellex-type Rockbolts
a. Swellex-type Rockbolts for local or systematic rock bolt patterns had a minimum
yield load of 150 KN.
b. Bolt face plates were such as allowed transfer of the anchor force at the head of the
rock bolt to the shotcrete, steel girder or rock surface, whichever the case.
c. For inflation of bolts, equipment recommended by the manufacturer of the bolts
was used.
37
4) Cement - Mortar Grout
a. The cement mortar grout consisted of sand, cement and water or neat cement and
water.
b. Ordinary Portland cement was used.
c. Sand for grouting purpose had to be clean mineral sand, uniform in quality and
from an approved source.
d. Water was clean, free from any oil, acid, salt and any alkaline, organic and other
deleterious substances.
2) Material
a) Stable Boreholes:
● Steel pipe a minimum outer diameter 40 mm, wall thickness not less than 4
mm.
● Dowels (spiles) consisting of deformed high yield steel bars grade Fe 415,
minimum diameter 32 mm, were used instead of steel pipes, when approved by
the DDC
b) Unstable Boreholes:
● Self-drilling bolts were used as Forepoling elements where stability of the
predrilled boreholes could not be achieved, because of encountered ground
conditions. Grouting was carried out simultaneously with drilling to achieve a
better grouting effect along the bolt.
38
3.3.8] Water Proofing and Protective Felt:-
1) General.
This covers the waterproofing for all underground structures by means of a
continuous waterproofing membrane installed to the outside of the final (inner) concrete
lining. It does not include provisions for other elements such as Water stops in concrete,
sealing of joints etc.
2) Description.
a) The purpose of the membrane waterproofing to underground structures is to
prevent leakage of groundwater into the tunnel and to protect the final concrete lining
against deleterious chemical influences. Waterproofing has been applied to crown and
sidewalls above footing /invert-arch level. The waterproofing membrane has been located
between primary shotcrete lining and the final (inner) concrete lining. No membrane
waterproofing has been pro-vided for tunnel inverts.
b) The waterproofing system consists of two layers: the first a protective felt
fastened to the shotcrete surface; the second is the actual waterproofing membrane
properly fixed by special means as recommended by the manufacturer.
3) Materials.
a) Protective Felt
The protective felt is a continuous filament, non-woven, poly-propylene, geo-textile, of
uniform thickness and surface texture.
b) Waterproofing Membrane
The waterproofing membrane is made up of one of the following mate-rails, or similar.
The membrane had been supplied in a single layer
39
3.4} INVESTIGATION.
40
3.4.3] Approach To Carrying Out The Investigations:-
For the Pir-Panjal tunnel, geological investigation was carried out in two stages -
I. Stage-I
➢ Planning and Design Stage:
For alignment fixing, planning the tunnel work, designing,
finalizing the construction methodology and the cost estimation.
II. Stage-II
➢ Construction Stage:
For excavation for the Tunnel.
41
3.5} METHODOLOGY OF THE PIR PANJAL RAILWAY TUNNEL;
The Himalayas, which stretch over 2400 km are the result of an ongoing orogeny,
the result of a collision between two continental tectonic plates. The Geology of the
Himalaya is a record of the most dramatic and visible creations of modern plate tectonic
forces. This immense mountain range was formed by huge tectonic forces and sculpted
by unceasing denudation processes of weathering and erosion, which resulted in varying
geology of this region.
42
With the presence of soft rock formations such as limestone, siltstone, clay stone with the
occurrence of active earthquake zones and faults it’s difficult for the civil industry to conduct
construction activities in this mountainous region. During excavation stage of tunnels at every 100
m interval the geology differs which means the same designs cannot be applied to every rock
formation. Henceforth, The NATM methodology is widely used for these kinds of geological
situations as it is based on observational approach and design measures are taken accordingly.
The sequence followed here for the initial support system through NATM is as follows;
1. Profile marking.
2. Face Drilling.
4. Defuming.
5. Mucking.
43
1) Profile Marking:
To achieve the designed shape profile marking is required. It has its own
significance in the sequential excavation method. Its main purpose is to define the
minimum excavation line on the working face. Accuracy in profile marking helps to
maintain the minimum excavation line and prevents over breaks. Points are defined and
marked by the survey team.
2) Face Drilling:
Once the profile is marked working face is drilled with the help of 2 boom
hydraulic boom Jumbo (figure31). The drilling pattern followed is VEG CUT. 107
number of holes (variable) are drilled having a diameter of 41mm.
44
Fig 24 : Face Drilling
Inserting the Explosives and charging them for blast is termed as charging and
blasting. Charging of holes is done manually by expert staff. Drill Jumbo’s basket is
used so lift the man-power to charge the holes which are on the upper portion of the
working face.
45
Fig.27 : Exploder Fig.28 : Ohmmeter.
4) Defuming ;
Once the blast is taken various harmful gases are emitted in the tunnel. Expelling
out these harmful gases is termed as defuming as shown in figure 36 and 37. Generally,
due to their lighter weight they travel along the crown portion of the tunnel. A proper
ventilation system with jet fans has been planned to maintain fresh air and to take out
harmful gases from the tunnel.
46
5) Mucking:
Material obtained from blasting/Fragmented rock after blasting is termed as Muck, shown in
figure 38, the whole procedure of gathering and removal of muck is known as mucking.
Fig.31: Muck in the tunnel. Fig.32: Hagg Loader used in removal of muck
47
7) Geological Mapping :-
Examining the types and number of joints and type of rock conditions of the
obtained face is termed as geological mapping (figure 40 and 41).
A protecting layer is applied on the obtained face and the periphery to avoid falling
of loose materials which is termed as face sealing shotcrete (figure 42 and 43). Minimum
30mm and maximum 50mm face sealing is applied depending on the site conditions.
48
9) 3d Monitoring Targets Installation :-
49
10) Lattice Girder Erection :-
Once the protecting layer is applied then survey team along with the supporting staff
reaches the face. Survey team with the help of total station marks the location of the Lattice
girders and executes the placing of LGs. Lattice girders act as initial support and provides a
defined shape to the tunnel (figure 47). Figure 48 shows layout system of lattice girder.
Fig 37: Lattice Girder Arch. Fig 38: Lattice Girder Arch
50
11) Fore Poling :-
The process of installing fore poles is termed as fore poling (figure 49). In case of
weak rock in the crown portion fore poles are provided for additional support.
51
Fig. 41: Construction Steps.
1. Sealing shotcrete
2. Installation of wire mesh (fixed to previous forepoling)
3. Erection of steel rib
4. Shotcreting: Complete 1st layer where no forepoling to be installed
5. Installation of forepoling
6. Completion of 1st layer shotcrete
52
12) Shotcreting :-
Shotcreting is considered as one of the main components of initial support system.
Shotcreting is of two types: sealing shotcrete and main shotcrete. Sealing shotcrete is used
to avoid lose ground and prevent fall-downs, whereas main shotcrete is used to carry load
introduced by ground in the lining. After the installation of LGs, a thick layer of shotcrete
is applied.
53
13) Rock Bolting :-
After the application of shotcrete rock bolts are installed to stitch the whole
shotcrete with the rock so compact that shotcrete and rock becomes one unit for
supporting the whole burden. The rock bolts help to stitch the joints and make it a bulk
body, bolts used here are Self-drilling Anchors with a diameter of 32 mm and length 3m
& 4m in general. Directions of installing rock bolts are shown in figure 53 and figure 54
shows the flow chart of different types of rock bolts.
54
3.5.5] NATM Method (Chronological) :-
NATM Process on site the simplified steps of an underground transition created with
NATM are shown below.
1. Step #1
Fig 44.
Fig 45.
55
2. Step#2
Applying layer of shot Crete on reinforcement mesh and there after Rock bit
Fig 48.
56
3. Step#3
Fig 49.
4. Step#4
Fig 50.
57
5. Step#5
Completed Tunnel
Fig 51.
58
3.6} IMPORTANT CONCEPTS OF THE PROJECT.
3.6.1] Shafts:-
When the length of the tunnel is small, it can be constructed by doing excavation
work from one side. But in case of considerable length and to complete the construction
work in short time, the excavation can be done from both the ends of the tunnel
simultaneously. The vertical openings or passages or wells constructed along the alignment
of a tunnel are known as shaft.
Shafts are constructed at suitable places along the center line of the tunnel. Since
each shat provides two additional faces to work, the excavation work of tunnel can be
started at several points at the same time and completed in a short time.
1. To start the excavation work from the both sides, to avoid delay in construction work.
2. To provide adequate natural ventilation during the construction of work.
3. To provide openings for removal of the excavated materials
4. To provide passageway for pumping out the water from the tunnel if any.
5. To provide passage way for construction tools, machinery, hoisting of muck, pipes for
ventilation, compressed air and water supply etc.
6. To transfer the center line inside the tunnel.
1) Details:-
a) Access shaft was constructed by top-down method and the of cross passage was
constructed using soft ground tunneling technique in the two top heading with temporary
invert, one benching and then permanent invert” format.
59
b) The 12mm dia Circular shaft was excavated from top to down at intervals of one meter
and strengthened with shortcrete, wiremesh, rock anchor and two reinforced concrete rings
before proceeding to the next meter of depth.
Table 8.
3) Image of The Shaft Constructed :-
Fig.52: Inside View of access Shaft Showing Muck Removal Using Winch,
Supply of Concrete and Ventilation Arrangement.
60
3.7 ] TUNNEL LINING :-
3.7.1) Definition :
A layer of timber, iron, masonry or concrete provided on the inside of the tunnel is
known lining.
Lining of tunnels is provided to give final shape to the tunnel cross-section and to give
strength to the sides and roof to prevent them from collapsing.
61
3.7.3) Types of Lining (In Pir Panjal Tunnel Concrete, Precast Block, Plain or Reinforced
Concrete Lining Is Used) :-
1) Concrete lining :-
Now a days, this method of lining becomes most popular, because of less leakage
and better finishing. It is also cheapest method of lining and used for tunnels of water
supply, water power, sewage, rail road etc.
For the quick lining, precast blocks are used for lining of tunnels. This method is
suitable for all types of tunneling. For shield tunneling several precast blocks have been
designed
The use of reinforced concrete section in lining wok has resulted in the introduction
of comparatively very thin linings. Now-a-days, lining of tunnels is usually done with plain
or reinforced cement concrete because of the following advantages:
62
3.8] TUNNEL VENTILATION: -
The ventilation means supply of air, light and keeping the level of noise to bearable
to human beings.
The technique of providing fresh air inside the tunnel during and after construction
is known at tunnel ventilation.
63
3. Also expensive elements like exhaust dampers, axial fans and corresponding
controls are not required.
4. Fast Reactivity
❖ Disadvantages of this ventilation system :
The tunnel cannot be divided into aerodynamic segments. Thus, the fresh air is
getting gradually contaminated on the way through the tunnel. With a pure longitudinal
concept, it is not possible to exchange or dilute the air inside the tunnel.
64
Fig. 54: Ventilation System Layout.
65
3.9] DRAINAGE OF TUNNELS :-
The art of collection and removal of water entering the tunnels during and after their
construction is known as drainage of tunnels.
If proper arrangements of drainage during construction are not adopted, the seepage water
affect the tunnel.
After the construction of tunnel is over, its drainage is also essential to reduce wear
and tear of the communication route and to achieve more safety of the moving vehicles.
➢ The main tunnel has a drainage system to collect groundwater inflow as well as the water
from condensation, leakage and spillage.
➢ The drainage is collected by 560 mm dia drainage tubes of HDPE pipe (main collectors)
which runs all along the tunnel from the high point, water flows through the collector
towards the portals.
➢ At the portals the collector connects to the outside drainage system, installed in the tunnel
approach ramps.
➢ Along the tunnel, manholes are provided at 50 m spacing surface water in the tunnel is
collected throughout the tunnel in shallow ditches, which run along the tunnel.
66
3.10} TUNNEL MAINTENANCE: -
Tunnel maintenance must be considered from the aspect of security and safety. It is also
required to carry out fearless movement of traffic.
Maintenance of tunnel increases the life of tunnel. It is also useful for proper and
safe movement of traffic.
67
3.11} DESIGN AND DIAGRAMS OF PIR PANJAL TUNNEL
68
3.11.2] Cross Section of Drainage of The Pir Panjal Tunnel.
Fig.57:- Layout of the Pir Panjal Tunnel(Image also showinh shaft of tunnel).
69
3.11.4] Excavation Section of The Pir Panjal :-
70
3.11.6] Lined Tunnel Profile of Pir Panjal Tunnel:-
71
3.12} INSTRUMENTS MAINLY USED IN CONSTRUCTION PROCESS.
72
3.12.2] Excavator.
73
3.12.3] Boomer.
Fig. 66 : Boomer
74
3.12.4] Tilting Loader.
75
3.12.5] Transit Mixer.
76
3.12.7] Hydraulic Excavator.
77
3.12.9] Batching Plant.
78
3.13} BALLAST-LESS TRACK (BLT) :-
3.13.1] General
1. Earlier ballast has been an integral part of railway track for many years. It has many
advantages. It is an economical medium providing an elastic support to the sleepers
and absorbs major part of the noise created by passing wheels. The ballast material
generally is locally available, but ballasted track calls for frequent maintenance
attention, and periodical screening and recoupment. It also causes dust pollution.
Hence, Railway authorities all over the world have been researching and
developing a more permanent track base, in the form of ballast less track (BLT)
for their high speed lines and urban transit lines. Though more expensive, BLT will
ultimately be most cost effective on the basis of whole-life-cycle-cost.
2. Now-a-days Rail traffic is reaching out toward new horizons on ballast-less track
systems. The arguments are indeed convincing: long life cycles, high speed, ride
comfort, and great load carrying capability. Practically maintenance free, ballast less
track systems ensure almost 100% service over many years.
79
i) Depth of ballast-less track is relatively low as compared to ballasted track, which reduces
tunnel construction cost.
j) The track can be accessible to road vehicles.
k) Less environment pollution.
l) Highly suitable for present and future scenario due to reduced maintenance requirement.
m) Easy and economical maintainability - ease of replacing parts with minimum dislocation
to traffic.
n) Electrical insulation for facilitating track circuiting control.
80
3.14} COMPLETION OF CONSTRUCTION OF THE PIR PANJAL TUNNEL :-
❖ On the Day of June 26, 2013. The Construction of Dream Project i.e., THE PIR PANJAL
Railway Tunnel Was Came to An End and Open to Traffic on Next Day (27 June, 2013)
81
3.15} TEAM OF DREAM PROJECT :-
Due to Hard Efforts of the Whole Team and Workers the Dream Realized
Fig. 79 : Workers
\ At Site.
82
CHAPTER 4
FINDINGS OF INDUSTRIAL
TRAINING
❖ CHAPTER 1
❖ CHAPTER 2
❖ CHAPTER 3
83
➢ Drainage system.
➢ Tunnel maintenance and their types.
➢ Safety concept.
➢ Design and diagram of tunnel.
➢ Ballast - less tracks tunnels (BLT).
❖ CHAPTER 4. 5, 6 & 7
84
CHAPTER 5
CONCLUSION
During the semester training period a lot of experience, knowledge and exposure that we
have handle all disclosure were awaken ourselves in a boost of self-confidence to face life more
challenging how practical how practical is complement to science or theory learned.
During the industrial training there are many changes from the point of learning
environment and discussion among group members. It can directly increase dedication and rational
attitude toward ourselves we can conclude that this industry is through training. We receive a lot
of exposure in computing world.
Immensely, studying/ working over the report on selected construction company I.e.HCC
(Hindustan Construction Company). The detailed information is interpreted likely to be a new
topics such as; Quality policy, Vision, Mission, Management and Services, CSR, Financial Details
and the most important about directorship/chairmanship of HCC and also we concluded that
milestones accomplished by the team of Hindustan construction company.
Ongoing the next week selection of the one of the milestone completed by HCC is done.
The dream project of PirPanjal tunnel (longest tunnel in India) is selected. And through the
references of Google, links, books, PDFs we interpreted all the information about project in
detailed; the terms used in Tunnel Engineering, Methodologies Requirements, Surveys,
Topographical Data, Geology of Himalayan Regions. Tunnel alignments, investigations,
Maintenance, Basic and Technological Details of Pir Panjal railway tunnel overall all statistics is
culminated and marked down in format of report.
Most beneficial thing of this industrial training is that students know the responsibility of
the Civil Engineers. Due to industrial training student discover their own abilities. Industrial
training useful for the students to increase interest in subject. Students see the connection between
the theoretical learning with practical specific field.
85
It is the conclusive fact that training is beneficial for students. It evinces that the program
has significantly improved their 'personal attitude', 'Communication skills' and 'Work attitude'. the
experience gained from training sharpen the business acumen of the students and open the doors
of better employment prospects. In essence, the new method of the student's placement need to be
reviewed and improved. However, this study needs an added insight. It is important for future
research to incorporate a wider range of soft skills e.g. Leadership, teamwork spirit to ascertain
the favorable outcomes. The training under Hindustan Construction Company is good eye opener
for us for bringing real life experience in construction field. This experience gives us self
confidence that we are able to face the beyond our college life.
86
CHAPTER 6
REFERENCE.
➢ JOURNAL PAPER
1. Ahmad Aejaz and Ahirwar Natasha 2019 “New Austrian Tunneling Method (NATM) in
Himalayan Geology: Emphasis on Execution Cycle Methodology”, Vol. 8 Issue 06, June-
2019,Pages 14
2. Bukhari Syed Kaiser and Dar Ayaz Mohmood 2016 “ TUNNEL CONSTRUCTION IN
PIR PANJAL (HIMALAYA) USING NATM [CASE STUDY T-74R RAILWAY
TUNNEL OF KATRA-BANIHAL SECTION OF KASHMIR RAIL PROJECT], i-
manager’s Journal on Civil Engineering, Vol. 6.No.1 December 2015 - February 2016
,Pages 5
➢ BOOKS
➢ WEB SITES
87
CHAPTER 7
ACKNOWLEDGEMENT
.T
At the very beginning, we would like to express our deepest gratitude to almighty god for
giving us the strength and the composure to complete our online industrial training report and
prepare this report within the scheduled time.
During the period of our internship work, we have received generous help from many
guides and mentors, which we like to put on record here with deep gratitude and great pleasure.
First and foremost, we are grateful our co-mentor Mr. A. P. Joshi, he allowed us to
encroach upon his precious time freely right from the very beginning of this online industrial
training work till the completion of our internship. His guidance, encouragement and suggestions
really helpful to us for completion this program excellently. We are also thankful to our mentor
Mr. A. T. Bari for providing this precious opportunity of online industrial training. We would not
forget to remember Prof.Mr. R. U. Kamodkar of our civil engineering department for their
support, guidance and valuable advice from time-to-time till the completion of the project. We
would also thankful to Prof. Mr. K. P. Wankhede for their vital suggestions for completion of
this online industrial training project report. We would also give thanks to Mr. M.V. Ingle as
principal of our college Government Polytechnic, Jalgaon. We have no hesitation to say that,
without our mentor’s constant support and valuable advices from time-to-time, we would probably
fail to complete the work in an appropriate manner.
We are also grateful to the Department of Civil Engineering for providing us such an
opportunity to come to actual site learning situation by means of online resources. We are also
thankful to Hindustan Construction Company for providing us relevant data related to industry.
88