You are on page 1of 2

WORK METHOD STATEMENT FOR AFAM III FLOW METER

INSTALLATION
TASK STEPS

1. Raise PTW/JHA and sign.


2. Carryout site inspection of the pipeline to be cut and the environment.
3. Gas Testing of the area.
4. Installation of flow meter.
5. Installation of Pressure and Temperature transmitters( EMERSON TRANSMITTERS)
6. Installation of the junction box on a junction box stand.
7. Installation of instrument cables from pressure thermocouple to the junction box.
8. Installation of cables from the junction box to control room.
9. Installation of FLOW COMPUTER, POWER PACK AND RITAL RACK at the control room.
10. Configuration.
11. Pre-commissioning and Commissioning.
12. Housekeeping.
13. Close PTW and work order in SAP.
14. Demobilize.

TOOLS/EQUIPMENTS AND MATERIALS


1. Gas Detectors.
2. Spirit Level.
3. Rags.
4. Copper Hammer.
5. W.D 40.
6. Lifting Aid/A frame.
7. Mechanical and Instrument Tool Boxes.
8. Multimeters.
9. Insulation and Resistance Testers(Negger Testers).
10. Earth Tester.
11. Cables and Installation accessories.
12. Drilling Machine.
13. Expansion Bolts and Accessories.
14. Climping Tools.

PPE & SAFETY EQUIPMENTS REQUIRED


1. Caution Tape.
2. Rubber Hand Gloves.
3. Rubber boots/ Insulated Safety Boots.
4. First Aid Box.
5. Fire Extinguishers.
6. Stretcher.
7. Eye Goggles.
8. Coverall.

You might also like