You are on page 1of 12

Struct Multidisc Optim

DOI 10.1007/s00158-009-0404-2

INDUSTRIAL APPLICATION

Optimum topology and shape design of prestressed


concrete bridge girders using a genetic algorithm
Zekeriya Aydın · Yusuf Ayvaz

Received: 2 April 2008 / Revised: 5 May 2009 / Accepted: 5 May 2009


© Springer-Verlag 2009

Abstract The purpose of this study is to optimize the 1 Introduction


topology and shape of prestressed concrete bridge gird-
ers. An optimum design approach that uses a genetic The most important criteria in structural design are
algorithm (GA) for this purpose is presented. The cost safety and cost. The general aim of a designer is to
of girders is the optimum design criterion. The design guarantee the safety of the structure while using a
variables are the cross-sectional dimensions of the pre- minimum amount of material.
fabricated prestressed beams, the cross-sectional area Prestressing refers to the permanent internal stress
of the prestressing steel and the number of beams in a structure to improve performance by reducing the
in the bridge cross-section. Stress, displacement and effect of external forces. The compression performance
geometrical constraints are considered in the optimum of concrete is strong but its tension performance is
design. AASHTO Standard Specifications for Highway weak. The main idea of prestressing concrete is to coun-
Bridges are taken into account when calculating the teract the tension stresses that are induced by external
loads and designing the prestressed beams. A computer forces.
program is coded in Visual Basic for this optimization. The first application of prestressed concrete was per-
Many design examples from various applications have formed by P.H. Jackson in 1886. However, Eugene
been optimized using this program. Several of these Freyssinet truly pioneered modern prestressed con-
examples are presented to demonstrate the efficiency crete technology. He recognized the importance of pre-
of the algorithm coded in the study. stress losses and proposed ways to mitigate those losses
(Naaman 1982).
Keywords Prestressed concrete · Bridge girder · Today, prestressed concrete is used in bridges and in
Genetic algorithm · Optimum design · many structural components, such as beams, columns,
Simply supported beam plates, pipes, or piles. Many prestressing techniques
have been developed. They are categorized into three
groups: pre-tensioning, post-tensioning and chemical
prestressing.
Many studies on optimizations of different structures
have been reported in the literature, including Rozvany
(2008), Lewinski and Rozvany (2007a, b), Rozvany
Z. Aydın
et al. (2006).
ONTÜ Construction Engineering Consulting Co. Ltd.,
Ataköy 9.kısım Block B28 D:2, İstanbul, Turkey There are also many studies regarding topological
e-mail: zaydin.eng@gmail.com and shape optimizations of prestressed concrete bridge
superstructures (Totres et al. 1966; Jones 1985; Yu et al.
Y. Ayvaz (B)
1986; Lounis and Cohn 1993; Chon and Lounis 1994;
Department of Civil Engineering, Karadeniz Technical
University, 61080 Trabzon, Turkey Lounis et al. 1997; Sirca and Adeli 2005). However,
e-mail: ayvaz@ktu.edu.tr none of these studies use a genetic algorithm (GA).
Z. Aydın, Y. Ayvaz

The purpose of this study is to minimize the cost of 2.2 Design variables and design parameters
precast concrete and prestressing steel for middle span
bridge girders through topological and shape optimiza- The design variables considered in this study are as
tion. The considered bridge girders are composed of follows:
pretensioned prestressed concrete adjacent simply sup-
nb number of the girders at the bridge cross-section
ported I section beams. The topological optimization
h height of the precast beam
of such a structure requires determination of the op-
bb bottom flange width
timum number of adjacent beams. Shape optimization
bw web thickness
requires the determination of the dimensions of the I
tt top flange thickness
section beam. In this study, the topological and shape
tb bottom flange thickness
optimization of the girder are performed at the same
pt top sloped thickness
time using a GA to reach an optimal solution.
pb bottom sloped thickness
A computer program coded in Visual Basic is used
nps number of the prestressing steel bars in each
to identify the optimum design, and the program is then
beam.
used for several design examples.
A typical cross-section of a prestressed concrete I-
beam section is illustrated in Fig. 1 to highlight several
of the design variables. In this study, adjacent I-beam
2 Optimum design of prestressed concrete girders are considered. Therefore, the slab thickness is
bridge girders not taken as a design variable. The design parameters
in this study are previously selected bridge cross-section
2.1 Objective function dimensions, material properties, unit costs of materials,
loads and the other relevant parameters.
In this study, the design criterion is the cost of pre-
cast beams. The objective is to minimize the cost 2.3 Constraints
without violating the constraints. The cost of precast
beams includes the cost of the precast concrete and the A total of 28 constraints are considered, consistent
cost of the prestressing steel. The cost of the precast with the AASHTO Standard Specifications (AASHTO
beams also includes the cost of the non-prestressed 2002). These constraints can be categorized into six
conventional reinforcing steel and the cost of suitable groups:
frameworks; however, these costs do not contribute
significantly to the total cost compared to the costs of 1. Flexural working stress constraints.
the precast concrete and the prestressing steel. The 2. Flexural ultimate strength constraints.
total cost of a prestressed concrete bridge girder is
formulated as
bt

CT = Cpc + Cps (1)

tt
where Cpc and Cps are the costs of the precast con-
pt
crete and the prestressing steel, respectively. The costs
of the precast concrete and the prestressing steel are
calculated as

hw
Cpc = uppc · nb · Apc · L (2) h bw

Cps = upps · nb · Apc · ρ · L (3)


prestressing steel
where uppc and upps are the unit prices of the precast pb
conventional reinforcing steel
concrete and the prestressing steel, respectively; Apc tb
and Aps are the cross-section areas of the precast con-
crete and the prestressing steel, respectively; nb is the bb
number of the precast beams; ρ is the density of the
prestressing steel; and L is the length of the girders. Fig. 1 Typical cross-section of prestressed concrete I-beam
Optimum topology and shape design of prestressed concrete bridge girders using a genetic algorithm

3. Shear constraints (working stress and ultimate where σ b , σ t and σ ts are the calculated stresses at the
strength). bottom edge of the precast section, at the top edge of
4. Ductility constraints. the precast section, and at the top edge of the composite
5. Deflection constraints. section, respectively; σ̄ci and σ̄ti are the initial allowable
6. Geometrical constraints. compression and tension stresses, respectively, of the
precast concrete; σ̄cf and σ̄tf are the associated final
These constraints are explained below. allowable compression and tension stresses; and σ̄cs is
the allowable compression stress of the traditional deck
2.3.1 Flexural working stress constraints concrete.

Working stresses are considered under four different


load conditions. The first load condition includes the 2.3.2 Ultimate flexural strength constraints
girder dead loads in addition to the prestress. The
second load condition includes a dead load of the deck The ultimate flexural strength constraints are consid-
superposed on the first load condition. The third load ered for the composite and the precast sections and can
condition includes all loads, except the vehicular load. be written, respectively, as
The fourth load condition includes all loads. For the
Md,c
third and fourth load conditions, it is assumed that the g11 = − 1, (14)
dead loads of the girders and the deck are carried by φ Mn
the precast section, and the other loads are carried by Md,p
g12 = − 1, (15)
the composite section. Under the first load condition, φ Mn
prestress losses are assumed to be minimal. For the
other load conditions, prestress losses are assumed to where Md,c and Md,p are the factored bending moments
be at a maximum. According to these load conditions, for the composite and the precast sections, respectively;
the working stress constraints in normalized form are φ Mn is the flexural strength of the related section; and
as follows: φ is the load factor that is assumed to be equal to 1.0 for
For the first load condition: factory-produced precast prestressed concrete mem-
σb1 bers. The flexural strength is determined according
g1 = − 1, (4) to the AASHTO Standard Specifications (AASHTO
σ̄ci
σt1 2002).
g2 = − 1. (5)
σ̄ti
For the second load condition: 2.3.3 Shear constraints (working stress and ultimate
strength)
σb2
g3 = − 1, (6)
σ̄tf The shear working stress constraints are considered at
σt2 the time of the initial prestress and for the long term
g4 = − 1. (7)
σ̄cf loading. The shear working stress constraints are:
For the third load condition:
τi
σb3 g13 = − 1, (16)
g5 = − 1, (8) τ̄i
σ̄tf τf
σt3 g14 = − 1, (17)
g6 = − 1, (9) τ̄f
σ̄cf
σts3 where τ i and τ f are the maximum shear stresses at the
g7 = − 1. (10)
σ̄cs time of the initial prestress and for the long term load-
ing, respectively; and τ̄i , and τ̄f are the initial and the
For the fourth load condition:
final allowable shear stresses, respectively. The details
σb4
g8 = − 1, (11) on τi , τf , τ̄i , and τ̄f can be found in AASHTO (2002).
σ̄tf The ultimate shear strength constraint is expressed
σt4 as
g9 = − 1, (12)
σ̄cf
σts4 Vu
g10 = − 1. (13) g15 = −1 (18)
σ̄cs φ (Vc + Vs )
Z. Aydın, Y. Ayvaz

where Vu is the factored shear force at the section; sections, respectively, and β 1 is a concrete strength fac-
and Vc and Vs are the shear strengths provided by the tor as defined in the AASHTO Standard Specifications
concrete and the web reinforcement, respectively. φ in (AASHTO 2002).
this equation is assumed to be equal to 0.90 for shear. The total amount of the prestressing steel must be
sufficient to develop an ultimate moment that is no
2.3.4 Deflection constraints less than 1.2 times the cracking moment at the critical
section. Therefore, the minimum prestressing steel con-
The deflection constraints are considered for four dif- straints can be given as
ferent load cases, as in the case of the flexural work- ∗
Mcr,c · 1.2
ing stress. The deflection constraints are listed below, g23 = − 1, (26)
φ Mn
consistent with these loads and final cases.

Mcr,p · 1.2
f1 g24 = − 1, (27)
g16 = − 1, (19) φ Mn
(L/500)
∗ ∗
where Mcr,c and Mcr,p are the cracking moments of the
f2 composite and the precast sections, respectively.
g17 = − 1, (20)
(L/500)
2.3.6 Geometrical constraints
f3
g18 = − 1, (21) The geometrical constraints in this study are given
(L/500)
below.
The thickness of the top flange must be adequate to
f4
g19 = − 1, and (22) transfer the latitudinal moment. Thus, the top flange
(L/1000) thickness of the optimal design section must be greater
than the constrained thickness. The related constraint
f can be given as
g20 = − 1, (23)
(L/500)
(tt + pt )min
g25 = −1 (28)
where f1 , f2 , f3 and f4 are deflections associated with (tt + pt )
the related number of load cases, and f is the deflection
of the final case. where (tt + pt )min is the minimum value of the top
It is considered that the deflection f1 is due to the flange thickness.
beam’s self weight; f2 is from the beam and deck self The width of the bottom flange must be smaller than
weights; f3 is due to all dead loads; f4 is due to the live the width of the top flange. The related constraint is
loads; and f is due to all live and dead loads.
bb
g26 = − 1. (29)
bt
2.3.5 Ductility constraints
The width of the web must be smaller than the width of
According to the AASHTO Standard Specifications the bottom flange. The related constraint is
(AASHTO 2002), the prestressed concrete members
must be designed so that the steel yields when the bw
g27 = − 1. (30)
ultimate capacity is reached. Therefore, the maximum bb
prestressing steel constraints for the composite and
The prestressing steels do not generally fit into one
precast sections are given below, respectively:
row. Thus, the thickness of the bottom flange must
ψc be adequate to fit the prestressing steels. The related
g21 = − 1, and (24) constraint can be written as
0.36β1
ψp tb,min
g22 = − 1, (25) g28 = −1 (31)
0.36β1 tb

where ψ c and ψ p are the prestressing steel reinforce- where tb,min is the minimum bottom flange thickness
ment indices for both the composite and the precast that is sufficiently thick to place prestressing steels.
Optimum topology and shape design of prestressed concrete bridge girders using a genetic algorithm

3 Optimum design with a genetic algorithm where n is the total number of constraints, and pi is the
violation factor of the ith constraint, calculated as
A GA is an optimization method from the artificial
intelligence family that uses the principles of natural pi = gi for gi > 0
selection. According to Darwin’s natural selection the-
pi = 0 for gi ≤ 0. (33)
ory, strong individuals of a population survive, while
weak individuals do not. The surviving individuals mate Given this penalty function, the penalized objective
to produce the next generation of individuals. It is function can be written
clear that individuals in the next generation will be
better than the individuals of the previous generations; (x) = C(x) · [1 + K · P] , (34)
individuals continue to get fitter as evolution continues.
Thus, individuals ultimately become perfect (Holland where K is a coefficient that depends on the type of the
1975; Goldberg 1989). problem. K determines the activity of the penalty func-
A GA is an evolutionary optimization method that tion when calculating the penalized objective function.
uses a group of initial solutions. These solutions are It is important to determine a suitable value of K to
represented by the design variables. The GA improves reach the best solution in a short time.
these solutions by using certain genetic rules. The initial
population is randomly determined. This generation 3.2 Coding of solutions and determining the initial
of solutions is taken to be the first generation of the population
design, and each individual is considered to be a solu-
tion within a given generation. The solutions for each There are several coding strategies for GAs, including
generation are coded using binary numbers in order binary, integer and real-valued representations. Binary
that genetic operators can be readily applied. coding is chosen in this study, since the purpose of
After determining the initial population, the genetic this study is to optimize the topology and the shape of
evolution begins. At first, the fitness of each individ- the prestressed concrete bridge girders, not to explore
ual is determined according to their closeness to the different coding types.
optimum solution, and individuals are categorized ac- The GA uses a set of design variables to generate an
cording to their fitness. After that, the reproduction, optimum design. Thus, the probable value set for each
the crossover and the mutation operators are applied design variable must be chosen before commencing.
to each generation to constitute a new generation. This This set is termed the design variable values set.
evolution continues until the majority of the solutions In the case of binary-coded GA, the solutions are
are identical (Ayvaz and Aydın 2000; Daloğlu and represented as strings that represent the values of de-
Aydın 1999), i.e. the convergence has occurred. sign variables. They are obtained by coding the row
GAs are widely used in engineering—for examples, numbers of the design variables into a binary represen-
see Rajaev and Krishnamoorthy (1992, 1998), Jenkins tation. Thus, the solution strings are constituted by the
(1992), Sarma and Adeli (2000), and Kameshki and numbers “0” and “1”.
Saka (2001). For example, suppose there are sixteen different
entries in a design variable values set for a given de-
3.1 Penalty function and penalized objective function sign variable. Then “0000” indicates the first possible
value, “0001” indicates the second possible value, and
GAs are suitable only for unconstrained optimum de- following this pattern, “1111” indicates the sixteenth
sign problems. Therefore, the objective function must possible value. All the design variables are coded in
be expressed as an unconstrained function. For this this manner and the solution strings are generated by
purpose, a penalty function is calculated consistent with joining these short strings. In this context, “0” and “1”
constraint violations. The unconstrained penalized ob- are termed genes, the small strings are chromosomes
jective function can be defined by adding this penalty and the solution strings are individuals who belong to a
function to the objective function. The penalty function certain generation.
is the fully normalized value of the violated constraints. The number of solution strings of a given generation
Thus, the penalty function can be expressed as depends on the length of the strings. If the string lengths
increase, more strings are required to increase the effi-

n ciency of the genetic operators. The solutions from the
P= pi , (32) initial population are determined by randomly coding a
i=1 certain number of “0”s and “1”s.
Z. Aydın, Y. Ayvaz

Parent strings New strings


3.3 Reproduction operator
101101100011 101010100011
The aim of the reproduction operation is to create
011010101000 011101101000
a subsequent generation that exhibits better solution
strings. The worst strings are removed and replaced
with copies of the best individuals. After the structural Crossover position ( 4, 7 )
analysis, the solution strings are categorized into three
groups according to their fitness values by applying the Fig. 3 Two-points crossover operation
reproduction operator. They are labeled the fittest, the
normal and the least fit solution strings. The weakest
strings are replaced by the fittest strings in the mating crossover, and the uniform crossover. All of these
pool. Thus, the fittest solution strings are placed twice, crossover methods are used in this study.
the normal strings are placed once, and none of the In the single-point crossover, a particular position
weakest strings are involved in the mating. The solution in the string character is chosen as the crossover po-
strings in the mating pool are known as parent strings. sition, and characters after this number are exchanged
The fitness value of each solution is determined ac- between randomly mated parent strings. An example
cording to its closeness to a problem related large value: of a single-point crossover is given in Fig. 2.
  In the two-point crossover, two positions are chosen
Fi = (x) max + (x) min − (x)i (35) as crossover positions and characters between these
two numbers are exchanged between randomly mated
where (x) max and (x) min are the largest and smallest parent strings. An example of a two-point crossover is
values of the penalized objective function among the given in Fig. 3.
solution strings in each generation. A fitness factor is Another crossover method used in this study is the
described, which is consistent with the fitness value. uniform crossover. Randomly determined new strings
The factor for each solution string is calculated as: (a crossover mask) are used for a uniform crossover.
The crossover masks have the same number of char-
Fc,i = Fi /Fort , (36)
acters as the solution strings. In order to perform a
uniform crossover, if the number in the crossover mask
where Fort is the average of the fitness values.
is “1”, then the related characters (based on its posi-
tion) will be exchanged between parent strings. If this
3.4 Crossover operator number is “0”, then the related number characters are
not exchanged. An example of a uniform crossover is
The reproduction operator works among existing so- given in Fig. 4.
lution strings and selects individuals from them, but it
does not create new individuals. In order to reach an 3.5 Mutation operator
optimum solution, the solution strings in the population
must be changed and generated. The crossover opera- Another operator that creates new solution strings is
tion is used to create new solution strings that depend the mutation operator: a few random characters from
on the existing solution strings in the mating pool. each generation are changed. The mutation rate in a
The crossover operation is applied by exchanging generation is generally chosen to be between 0.1%
characters of strings between the selected solution and 1%. In the event of a larger mutation rate, the
strings. In the literature, the most popular crossover fitter solution strings may be destroyed. In this study,
methods are the single-point crossover, the multi-point three kinds of the mutation operator—the standard

Parent strings New strings Crossover mask 1 0 1 0 0 1 1 1 1 0 1 0

101101100011 101101101000 1 0 1 1 0 1 1 0 0 0 1 1
Parent strings
0 1 1 0 1 0 1 0 1 0 0 0
011010101000 011010100011
0 0 1 1 0 0 1 0 1 0 0 1
New strings
Crossover position ( 7 ) 1 1 1 0 1 1 1 0 0 0 1 0

Fig. 2 Single-point crossover operation Fig. 4 Uniform crossover operation


Optimum topology and shape design of prestressed concrete bridge girders using a genetic algorithm

Table 1 Hybrid mutation String Generation before the Fitness Mutation Generation after the
operation
no mutation factor characters mutation
1 10100011100011100111 1.10 7–12 10100011100011100111
2 10100001110101001110 0.74 10100001110101001110
3 01010000111001110111 0.48 01010001111001110111
4 11000100100001111101 1.12 11000100100001111101
5 00110001010001110101 1.49 00110001010001110101
6 10101100101010011000 1.14 3–8 10101100101010011000
7 00111011111010111011 0.96 00111011111010111011
8 01101111011101110111 0.85 01101111011101110111
9 10011100000011010010 1.11 10011100000011010010
Mutation rate: 1% 10 00011100011111011011 1.01 00011100011111011011

mutation, the controlled mutation and the hybrid oped program. These examples have been previously
mutation—are used. designed by Emay International Eng. Cons. Co. (Emay
For the standard mutation, a fixed mutation rate is 1998, 2004) and by Haytek International Eng. Cons. Co.
determined at the beginning of the design. The mu- (Haytek 2004) and have been constructed in Turkey.
tation characters from each generation are randomly The discrete design variables are used in our software.
selected at this rate. The values of these characters are If continuous valued design variables had been selected
changed when the mutation operator is applied. instead, it would have been impossible to calculate the
In a controlled mutation, the mutation rate is re- dimensions of the beam cross-section as integer values.
duced stepwise as the generated solution becomes fit- In the industry, the dimensions of the beam cross-
ter. In this study, the mutation rate is reduced by 50% section are always integers—and often multiples of 5
when one-third of the solution strings in a generation or 10 cm. Also, the concrete strength is not chosen as a
are the same. The mutation stops when two-thirds of design variable in this study, because in reality concrete
the solution strings in a generation are the same. strength is normally pre-selected before the production
In a hybrid mutation, a fixed mutation rate is used, of prestressed concrete elements can begin.
as with the standard mutation. However, in the hybrid The thickness of the slab for all of the examples
mutation, instead of changing the value of the mutation given below is constant since the chosen bridge girders
character directly, it is made to match the character include pretensioned and prestressed concrete in adja-
expressed by the fittest string in the generation. In other cent, simply supported I section beams.
words, if the mutation character has the same value as
the fittest solution, then the value of the character is 4.1 Example 1
unchanged. Otherwise, it is changed. An example of a
hybrid mutation is given in Table 1. This example was optimised several times with differ-
ent optimal design parameters to demonstrate the capa-
bilities of our software. The design parameters used for
4 Numerical examples the first attempt are listed below. The design variable
set for this example is listed in Table 2.
A software package has been developed to perform
the optimization as explained above. Three examples Length of span (L) 32.00 m
are solved to demonstrate the efficiency of the devel- Width of deck (W) 10.00 m

Table 2 Design variable values sets for example 1


Design variable Number of value Values
Number of prestressed beam (nb ) 8 7, 8, 9, 10, 11, 12, 13, 14
Height of beam (hb ) 16 70, 75, 80, 85, 90, 95, 100, 105, 110, 115, 120, 125, 130, 135, 140, 150
Bottom flange width (b b ) 16 30, 35, 40, 45, 50, 55, 60, 65, 70, 75, 80, 85, 90, 95, 100, 105
Web thickness (b w ) 8 15, 17, 20, 22, 25, 30, 35, 40
Top flange thickness (tt ) 8 8, 10, 12, 15, 18, 20, 22, 25
Bottom flange thickness (tb ) 8 15, 18, 20, 22, 25, 28, 30, 35
Top sloped thickness ( pt ) 8 5, 8, 10, 12, 15, 17, 20, 25
Bottom sloped thickness ( pb ) 8 5, 8, 10, 12, 15, 17, 20, 25
Number of prestressing steel (nps ) 16 6, 8, 10, 12, 14, 16, 18, 20, 22, 24, 26, 28, 30, 32, 34, 36
Z. Aydın, Y. Ayvaz

Table 3 Optimal design parameters and penalized objective functions


Design Number of solution Length of solution Type of crossover Type of mutation Rate of Iteration number (x)
no in generation strings operator operator mutation
1 20 30 Uniform Controlled 0.5% 168 151,204
2 30 30 Uniform Controlled 0.5% 283 130,036
3 16 30 Uniform Controlled 0.5% 74 139,007
4 26 30 Uniform Controlled 0.5% 349 134,343
5 36 30 Uniform Controlled 0.5% 323 117,560
6 40 30 Uniform Controlled 0.5% No Convergence 132,713
7 46 30 Uniform Controlled 0.5% No Convergence 123,980
8 50 30 Uniform Controlled 0.5% No Convergence 119,975
9 36 36 Uniform Controlled 0.4% 796 124,637
10 36 36 Uniform Controlled 0.3% 281 118,186
11 36 36 Single-point Controlled 0.3% 300 120,663
12 36 36 Two-point Controlled 0.3% 456 119,390
13 36 36 Uniform Standard 0.3% No Convergence 118,186
14 36 36 Uniform Hybrid 0.3% 141 122,473
15 36 36 Uniform No Mutation – 134 133,794

Width of motorway 8.00 m Thickness of coating 10 cm


Number of traffic lanes (NL ) 2 Thickness of sidewalk 30 cm
Thickness of slab 0.20 m Weight of parapet and precast 3 kg/cm
Compressive strength of slab 250 kg/cm2 Load due to pedestrian 0.03 kg/cm2
concrete ( fcs ) Average annual relative 40%
Modulus of elasticity of slab 302,500 kg/cm2 humidity (RH)
concrete (Ecs ) Truck load category H30-S24
Compressive strength of 400 kg/cm2 Necessary spacing between 6 cm

prestressed concrete ( fc ) prestressing steels
Modulus of elasticity of 345,500 kg/cm2 Diameter of web reinforcement 10 mm
prestressed concrete (Ec ) steels
Ultimate strength of 18,983 kg/cm2 Spacing between web reinforcement 10 cm

prestressing steel ( fs ) steels
Modulus of elasticity of 2,073,000 kg/cm2
prestressing steel (Es )
Yield strength of non- 4,200 kg/cm2 In addition to the parameters given in Table 2, the
prestressed reinforcement ( fsy ) convergence criterion is taken as 60%, the maximum
Unit cost of prestressed 650 TL/m3 (TL: number of iterations is 1,000, and the violation factor
concrete (UCpc ) Turkish Lira) is 1.1. The effects of these design parameters on the
Unit cost of prestressing steel 7,000 TL/t optimum solution can be seen in Table 3.
(UCps ) As can be seen from Table 3, the best solution comes
Distance between top flanges 7.77 cm from design 5. The values of the design variables and
of girders (F) the cost function for this design are listed in Table 4.
Distance between slab and girder 0 Table 4 also shows the comparison of our results with
Diameter of reinforcing 15.24 mm the one of the real life project. The cross-sections of the
steel (dps ) bridge superstructure and of the prestressed beam are
Unit weight of concrete 2.5 t/m3 given in Fig. 5 for the application project and for the
Unit weight of coating 2.4 t/m3 best solution as provided by the GA.

Table 4 Values of design variables and cost function for the real life project and for the solution of this study
Design nb hb (cm) bb (cm) bw (cm) tt (cm) tb (cm) pt (cm) pb (cm) nps C
Real life project 10 125 75 20 10.7 16 7.3 8 25 158,215
This study 8 150 70 15 8 18 5 5 22 117,560
Optimum topology and shape design of prestressed concrete bridge girders using a genetic algorithm

Fig. 5 Cross-section of bridge


superstructure for a the real
life project and for b the best
solution obtained in this study

(a) The real life project

(b) The best solution obtained in this study

As can be seen from Table 4, the solution obtained of the prestressed beam is 75 cm. The design variable
in this study is 25% more economical than the one of value sets for this example are listed in Table 5.
the real life project. As can be seen from Fig. 5, the
number of beams at the bridge superstructure cross- Length of span (L) 14.725 m
section obtained in this study is less than the one for Width of deck (W) 9.00 m
the real life project. The variation of the penalized ob- Width of motorway 7.00 m
jective function average value according to the iteration Distance between top flanges of girders (F) 7.5 cm
number for the first design is illustrated in Fig. 6. Unit weight of coating 2.4 t/m3

The optimal design parameters for this example are:


4.2 Example 2
Number of solutions per generation 30
Length of solution strings 30
The design parameters that differ from those of the first
Type of crossover operator Uniform
example are listed below. All the other parameters are
Type of mutation operator Controlled
the same ones as those of the first example. This bridge
Rate of mutation 0.4%
is constructed in an urban area, so the maximum height
Convergence criterion 60%
Maximum number of iterations 1,000
Violation factor 1.5
2000000 The required convergence for the optimum design
1800000
is reached by the 342nd iteration. The design variable
values and the cost function of the optimum solution
1600000
are given in Table 6, which also compares our results
penalized objective function

1400000 with the ones of the real life project. The cross-section
of the bridge superstructure and of the prestressed
1200000
beam are given in Fig. 7 for the real life project and
1000000 for the solution obtained in this study.
As can be seen from Table 6, the solution obtained
800000
in this study is 28% more economical than the one of
600000 the real life project. As confirmed by Fig. 7, the number
400000 of beams at the bridge superstructure cross-section in
this study is fewer than the one for the real life project.
200000

0 4.3 Example 3
100

120
140

160
180

200

220

240

260

280
20

40

60

80
0

iteration number
In this example, the chosen bridge superstructure is
Fig. 6 Variation of the penalized objective function value for the optimized twice. First, the number of prestressed beams
first design at the bridge superstructure cross-section is maintained
Z. Aydın, Y. Ayvaz

Table 5 Design variable value sets for example 2


Design variable Number of value Values
Number of prestressed beam (nb ) 8 6, 7, 8, 9, 10, 11, 12, 13
Height of beam (hb ) 8 40, 45, 50, 55, 60, 65, 70, 75
Bottom flange width (b b ) 16 25, 30, 35, 40, 45, 50, 55, 60, 65, 70, 75, 80, 85, 90, 95, 100
Web thickness (b w ) 8 15, 16, 17, 18, 19, 20, 22.5, 25
Top flange thickness (tt ) 8 10, 11, 12, 13, 14, 15, 17.5, 20
Bottom flange thickness (tb ) 8 15, 17.5, 20, 22.5, 25, 27.5, 30, 35
Top sloped thickness ( pt ) 8 5, 6, 7, 8, 9, 10, 12.5, 15
Bottom sloped thickness ( pb ) 8 5, 6, 7, 8, 9, 10, 12.5, 15
Number of prestressing steel (nps ) 32 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20,
21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33

Table 6 Values of design variables and cost function for the real life project and for the solution of this study
Design nb hb (cm) bb (cm) bw (cm) tt (cm) tb (cm) pt (cm) pb (cm) nps C
Real life project 11 75 75 20 10 15 12.5 7.5 8 46,028
This study 8 75 65 15 10 15 5 5 10 33,080

Fig. 7 Cross-section of the


bridge superstructure for
a the real life project and
for b the solution obtained
in this study
(a) The real life project

(b) Solution obtained in this study

Table 7 Design variable value sets for example 3


Design variable Number of value Values
Height of beam (hb ) 16 80, 85, 90, 95, 100, 105, 110, 115, 120, 125, 130, 135, 140, 150, 155, 160
Bottom flange width (b b ) 16 25, 30, 35, 40, 45, 50, 55, 60, 65, 70, 75, 80, 85, 90, 95, 100
Web thickness (b w ) 8 15, 16, 17, 18, 19, 20, 22.5, 25
Top flange thickness (tt ) 8 10, 11, 12, 13, 14, 15, 17.5, 20
Bottom flange thickness (tb ) 8 15, 20, 25, 30, 35, 40, 45, 50
Top sloped thickness ( pt ) 8 5, 6, 7, 8, 9, 10, 12.5, 15
Bottom sloped thickness ( pb ) 8 5, 6, 7, 8, 9, 10, 12.5, 15
Number of prestressing steel (nps ) 32 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25,
26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36

Table 8 Values of design variables and cost functions for the real life project and for the solutions obtained in this study
Design nb hb (cm) bb (cm) bw (cm) tt (cm) tb (cm) pt (cm) pb (cm) nps C
Real life project 11 120 75 20 10 18 8 10 24 101,781
This study (number of beams is fixed) 11 125 40 15 10 35 5 5 21 82,907
This study (number of beams 7 140 65 18 10 25 5 5 29 75,941
is variable)
Optimum topology and shape design of prestressed concrete bridge girders using a genetic algorithm

Fig. 8 Cross-section of the


bridge superstructure for
a the real life project and
for b, c solutions obtained
in this study
(a) The real life project

(b) Solution obtained in this study


(The number of beams is fixed)

(c) Solution obtained in this study


(The number of beams is variable)

equal to the one of the real life project in order to in- tion for the optimum solution are listed in Table 8 by
vestigate the effects of the other design variables on the comparing our results with the ones of the real life
optimal design. Secondly, the number of prestressed project. The cross-sections of the bridge superstructure
beams at the bridge superstructure cross-section is and the prestressed beam are given in Fig. 8 for the
taken as the design variable. The design parameters real life project and for both solutions obtained in this
that differ from those of the first example are given be- study.
low. The other design parameters used are the same as As can be seen from Table 8, the solution reached
the ones of the first example. The design variable values by the GA is 19% more economical than the one of
for the eight design variables are listed in Table 7. the real life project if the number of prestressed beams
at the bridge superstructure cross-section is kept to
Length of span (L) 27.70 m be equal to the one of the real life project. As can
Width of deck (W) 12.00 m also be seen from Table 8, the solution reached by
Width of motorway 9.50 m the GA is 25% more economical than the one of the
Number of traffic lanes (N L ) 3 real life project if the number of prestressed beams at
Thickness of slab 0.21 m the bridge superstructure cross-section is taken as the
Distance between top flanges of girders (F) 4.5 cm design variable. This result suggests that it is important
Distance between slab and girder 1 cm to consider the number of beams a design variable,
Unit weight of coating 2.0 t/m3 in addition to the cross-sectional shape parameters, in
order to reach a more economical solution.
The optimal design parameters for this example are:
As can be seen from Fig. 8b, the number of beams at
Number of solutions in a single 30 the bridge superstructure cross-section obtained in this
generation study is fewer than the one of the real life project if the
Length of solution strings 28 number of prestressed beams at the bridge superstruc-
Type of crossover operator Uniform ture cross-section is taken as the design variable.
Type of mutation operator Controlled
Rate of mutation 0.4%
Convergence criterion 60%
Maximum number of iterations 1,000 5 Conclusions
Violation factor 1.5.
The aim of this study was to optimize the cost of a
The required convergence is obtained by the 356th prestressed concrete I-beam bridge superstructure by
iteration. The design variable values and the cost func- using a genetic algorithm. It is concluded that our
Z. Aydın, Y. Ayvaz

GA-driven software can be used to efficiently optimize Emay International Eng.Cons.Co. (2004) Edirnekapı kavþak
the shape and the topology of prestressed concrete köprüleri Köprü-4 uygulama projesi hesapları (in Turkish).
İstanbul, Turkey
bridge girders. In addition, the following conclusions Goldberg DE (1989) Genetic algorithms in search, optimization
can be drawn from this study: and machine learning. Addison-Wesley, New York
Haytek International Eng. Cons. Co. (2004) O-1 Otoyolu
• KM:17 + 088.000 üst geçit köprüsü üst yapı uygulama projesi
The solution obtained by the proposed GA is up to
hesapları, İstanbul, Turkey
28% more economical than the real life project. Holland JH (1975) Adaptation in natural and artificial systems.
• In this study, various crossover and mutation types University of Michigan Press, Ann Arbor
are used. The best solutions are obtained by using a Jenkins WM (1992) Plane frame optimum design environ-
ment based on genetic algorithm. J Struct Eng-ASCE
uniform crossover and a controlled mutation.
118(11):3103–3112
• In addition to the beam cross-section, it is impor- Jones HL (1985) Minimum cost prestressed concrete beam de-
tant to include the number of prestressed beams sign. J Struct Eng-ASCE 111(11):2464–2478
at the bridge superstructure cross-section as a de- Kameshki ES, Saka MP (2001) Optimal design of nonlinear steel
frames with semi-rigid connections using a genetic algo-
sign variable in order to obtain a more economical
rithm. Comput Struct 79:1593–1604
solution. Lewinski T, Rozvany GIN (2007a) Exact analytical solutions for
• Constraints can easily be adapted to the problem some popular benchmark problems in topology optimization
using a GA penalty function and design variable II: three-sided polygonal supports. Struct Multidiscipl Optim
33:337–349
value sets.
Lewinski T, Rozvany GIN (2007b) Exact analytical solutions for
• It is difficult to solve topological and shape opti- some popular benchmark problems in topology optimization
mization problems at the same time by using clas- III: L-shaped domains. Struct Multidiscipl Optim 35:165–174
sical optimization methods, but they can be easily Lounis Z, Cohn MZ (1993) Optimization of precast prestressed
concrete bridge girder systems. PCI J 38(4):60–78
solved with a GA.
Lounis Z, Mirza MS, Cohn MZ (1997) Segmental and conven-
• The solutions reached by the GA are realistic and tional precast prestressed concrete I-bridge girders. J Bridge
constructible without modification because of the Eng 2(3):73–82
use of discrete design variables and a probable Naaman AE (1982) Prestressed concrete analysis and design fun-
damentals. McGraw-Hill, New York
design variable value sets.
Rajaev S, Krishnamoorthy CS (1992) Discrete optimization of
structures using genetic algorithms. J Struct Eng-ASCE
118(5):1233–1250
Rajaev S, Krishnamoorthy CS (1998) Genetic algorithm-based
methodology for design of reinforced concrete frames.
Comput-Aided Civil Infrastruct Eng 13:63–74
References Rozvany GIN (2008) A critical review of established methods of
structural topology optimization. Struct Multidiscipl Optim.
AASHTO (2002) Standard specifications for highway bridges. doi:10.1007/s00158-007-0217-0
American Association of State Highway and Transportation Rozvany GIN, Querin OM, Lógó J, Pomezanski V (2006) Exact
Officials, Washington, DC analytical theory of topology optimization with some pre-
Ayvaz Y, Aydın Z (2000) Optimum design of trusses using a ge- existing members or elements. Struct Multidiscipl Optim
netic algorithm. In: Proceedings of the second international 31:373–377
conference on engineering using metaphors from nature. Sarma KC, Adeli H (2000) Fuzzy discrete multicriteria cost
Leuven, Belgium, pp 159–168 optimization of steel structures. J Struct Eng-ASCE
Chon MZ, Lounis Z (1994) Optimal design of structural concrete 126(11):1339–1347
bridge systems. J Struct Eng-ASCE 120(9):2653–2674 Sirca GF, Adeli H (2005) Cost optimization of prestressed con-
Daloğlu A, Aydın Z (1999) Kafes sistemlerin uygulamaya yöne- crete bridges. J Struct Eng-ASCE 131(3):380–388
lik optimum tasarımı (in Turkish). Mühend Bilim Der 5(1): Totres GGB, Brotchie JF, Cornell CA (1966) A program for
951–957 the optimum design of prestressed concrete highway bridges.
Emay International Eng.Cons.Co. (1998) Uzunçayır Barajı PCI J 11(3):63–71
Varyantı yolu Dinar Köprüsü uygulama projesi hesapları Yu CH, Das GNC, Paul H (1986) Optimization of prestressed
(in Turkish). İstanbul, Turkey concrete bridge girders. Eng Optim 10(1):13–24

You might also like