You are on page 1of 6

Benefits


1. Permanent weathertight layer installed as soon as frames and roof trusses are stood up.

2. Provides absolute weather protection before cladding is installed allowing interior work to

continue without weather interruption.


3. Protects framing from top to bottom – roof and walls.

4. Cost effective – less expensive than rigid materials and doesn’t require secondary canopies

or covers. One-time installation.


®
5. Installed quickly and easily – lightweight but robust – instant weather protection and
BCS-172217-CMNZ

permanent performance for the life of the building


R

6. Tested to withstand extra high winds and wind uplift.


7. Tested for airtightness.

FPS® Weathertight™ for


8. Codemark certified “system” – assured performance.
K

Installers roofs
must and walls
ensure the
followingFrame Protection System Ltd, FPS® Weathertight™ system is a comprehensive roof and wall

underlay system for timber and steel frame, panel and prefab building elements, providing

both interim and permanent weather protection plus moisture control within the wall or roof
1. Never leave plain staples exposed to the weather
structure. FPS® Weathertight™ is certified to allow internal work to proceed to completion
a. This will result in staple pull and possible air or water ingress.
before the roof and wall claddings are installed.
2. Ensure all joins and overlaps are properly sealed
a. Use double sided tape for horizontal joins.

b. No horizontal tapes on top of membrane, this could

result in channels for air or water ingress.

3. Direct any water runoff from the roof away from walls and joinery.

4. Ventilate the interior to the outside as often as possible while


working indoors.

5. Repair any holes and tears immediately they occur or are found

6. Seal off edges at top and bottom plate to prevent water and air

getting behind underlay.


Installation Requirements.
The Four Essential
Requirements for

O
1. Begin with weatherproofing ROOF – always specify FPS® Eurotop;

Weathertightness
a. Commence laying FPS® Eurotop horizontally from bottom edge (gutter) of roof with a 100mm overhang into gutter and 150-200mm
overhand at each end.
b. If securing membrane with counter battens running along length of trusses or rafters – plain staples may be used provided they are
covered with tape or securely fixed counter battens. Ensure membrane is pulled taut in all directions before securing.
c. If purlins and spacers are being installed – cap and staples must be used along length of trusses or rafters where counter battens would

R
have normally been fitted.
To laying
d. Before allowsecond
work layer
to progress inside –before
of FPS® Eurotop the exterior
fix Euroband cladding
DS (Double is to upper edge of first layer. Do not remove backing paper!
sided tape)
e. Lay the second layer of FPS® Eurotop with a 60mm overlap – when pulled taut and secured, remove the backing paper on the Euroband DS
and applied,
firmly pressa to
membrane must meet four minimum requirements;
get good adhesion.
f. At the apex of the roof – have at least 300mm flap of FPS® Eurotop running over to other side. Fix down when other side is laid so the flap is
moisture
on top. Fix downcontrol, waterproofing,
with Euroband windproofing
DS. Alternatively and UV
– fix a 500-600mm strip over the apex (ridge line)
g. Valley’s - either have a 500mm strip of if FPS® Eurotop laid down valley floor or horizontal layers running through valley and taped to

K
exposure.
opposite side well clear of valley.
h. With mono-pitch or skillion roofs it is essential to vent the upper side/edge – refer to FPS® Manuals or contact FPS®.

2. WALLS:
a. Measure 150cm (1500mm) from 75-100mm below the bottom plate and mark upper edge across entire wall section.
O ®A
b. Unroll FPS® Eurotop from left side to right side of wall, ensuring top edge is on marks and plain staple inside top 60mm.
c. Make sure at least 300mm is wrapped around each corner, or continue along next wall section.
d. Vertical joins require 75-100mm overlap and sealed with Euroband S60 tape on a stud or solid backing
e. At openings wider than 1500mm – the layer can be cut leaving 300mm flap each side of the opening.
f. Fix Euroband DS to upper horizontal edge of each layer of FPS® Eurotop – do not remove backing paper.
g. Apply a recommended FPS® adhesive and staple (as close to the edge of the membrane as possible) to the foundation or bottom plate to
prevent water and air/wind entering the wall structure under and behind the membrane. Depending on the substrate, FPS® supplies, Butyl
Moisture Control
R F
tape or liquid adhesive.
h. From the middle of wall section on a stud – run hand down membrane to get a flat taut surface - secure with staples. From the middle work
An underlay system must be vapour open to the outside, so that
across wall toward each end or corner. NOTE:
(i) If horizontal boarding cladding is specified, vertical cavity battens must be installed over staples. If there is any delay installing
any moisture
battens that isS still
either Euroband within
or FPS® the construction
Fleece-Butyl tape must becan
usedpass freely
to cover staples.
(ii) If vertical boarding cladding is specified, horizontal cavity battens must be installed – cap and staple fixings must be used on studs
orto the ventilation
panels cavity.
between battens.

K
(iii) For brick veneer – cap and staple fixings are recommended.
i. Next layer of FPS® Eurotop is rolled out and fixed/ stapled at upper edge across entire wall section, taped and smoothed out from the centre
stud as before with first layer.
j. When upper Waterproofing
layer securely fixed, pull backing paper off Euroband DS progressively across wall pressing firmly to get good adhesion.
k. If second layer extends beyond the top of the wall, both continue across the eave or soffit and connect to the roof section.
Anwall
l. To finish the underlay system
installation must
– fix the be waterproof
bottom from the
edge to the foundation outside,
with both
FPS® Butyl tape or FPS® Liquid Adhesive and further secure the
membrane to the bottom plate with cap and staples.
m. All soffitsinandits eaves
ability to have
must holdFPS®
out Eurotop
a volume ofand
fitted water, and its
connected abilityroof
to either to membrane
hold or other wind tight element at roof edge.
FA
out water continuously for an extended period.
3. Install Euroband S 120 or 180 Sill-tape to all openings. Refer to Sealing Corner Sections leaflet.

4. Install Windproofing
doors and windows before commencing any work on the interior – if rain enters building after FPS®
Eurotop is installed – interior must be dried.
An underlay system must be wind tight, both in terms of wind

uplift durability as well as being airtight. Wind uplift is important


5. IMPORTANT:
O K®

because the roof of a structure acts like an aircraft wing.


(1) Do not leave plain staples exposed to the weather
(2) Ensure all joins and overlaps are properly sealed (water and air/wind proof) – NO horizontal tapes on top of membrane.
However, airtightness is also important because of airborne
(3) Direct any water runoff from the roof away from walls and joinery.
(4) Ventilate the interior as often as possible while working indoors.
moisture
(5) Repair any holes andvapour (humidity).
tears immediately they occur or are found
(6) Ensure proper sealing around cable and plumbing penetrations through exterior membrane.
RA

UV Exposure

An underlay must be able to withstand

exposure to the sun for an extended period,


F

without any degradation.


www.frameprotection.co.nz
Frame Protection System Ltd
PO Box 10286, Te Rapa, Hamilton 3241
Telephone: 0800723426 E-mail: info@frameprotection.co.nz
A

O
F
Benefits

R
Moisture Control
To be able to install insulation and linings on the
®
1. Permanent weathertight layer installed as soon as frames and roof trusses
inside of aare stood any
building, up. moisture that is still inside

K
2. Provides absolute weather protection before cladding is installedthe
allowing interior
structure, mustwork to to get out. Therefore,
be able
continue without weather interruption. the building enclosure must be vapour open to the
3. Protects framing from top to bottom – roof and walls.

Waterproof
outside.
O
FA
4. Cost effective – less expensive than rigid materials and doesn’t require
• All FPSsecondary
membranescanopies
are considered vapour open
or covers. One-time
To be able installation.
to line inside, the outside of the structure according to British Standard BS5250.
®
5. Installed
must bequickly and easily – lightweight but robust
waterproof. – instant weather
BCS-172217-CMNZ • To beprotection
consideredand“vapour open”, permeability must
permanent performanceare
forclass
the life of the building
R

• All FPS membranes 1 waterproof products, be less than 0.25MNs/g according to British
6. Tested tono
with withstand extra high winds and wind uplift.
tent effect. Standard BS5250.
7. Tested for airtightness.
• All FPS membranes have passed column of water

FPS® Weathertight™ for


8. Codemark
tests ofcertified
between“system”
1.5m & – assured performance.
5.5m.
K

K
• FPS membranes are the only underlay in New

Installers roofs
must and walls
ensure the
Zealand to have been tested and passed the 24-hour

Water Streaming Test.


FA
following Frame Protection System Ltd, FPS® Weathertight™ system is a comprehensive roof and wall

underlay system for timber and steel frame, panel and prefab building elements, providing

both interim and permanent weather protection plus moisture control within the wall or roof
1. Never leave plain staples exposed to the weather
structure. FPS® Weathertight™ is certified to allow internal work to proceed to completion
a. This will result in staple pull and possible air or water ingress.
before the roof and wall claddings are installed.
2. Ensure all joins and overlaps are properly sealed

a. Use double sided tape for horizontal joins.

b. No horizontal tapes on top of membrane, this could

result in channels for air or water ingress.

3. Direct any water runoff from the roof away from walls and joinery.

4. Ventilate the interior to the outside as often as possible while


working indoors.

5. Repair any holes and tears immediately they occur or are found
R

6. Seal off edges at top and bottom plate to prevent water and air

getting behind underlay.


Installation
The
WindFour Requirements.
Essential
Uplift
Requirements for

O
To be able to line inside, the outside of the structure must be windproof, both in terms of air ingress as well as
1. Begin with weatherproofing ROOF – always specify FPS® Eurotop;
wind uplift.

Weathertightness
a. Commence laying FPS® Eurotop horizontally from bottom edge (gutter) of roof with a 100mm overhang into gutter and 150-200mm
• All at
overhand FPS

covered with tape


membranes
each end.

or securely
have been tested for wind uplift.
b. If securing membrane with counter battens running along length of trusses or rafters – plain staples may be used provided they are
- Tested: Refer tocounter
fixed FPS® Technical Manual
battens. Ensure – Wind
membrane Loadings
is pulled taut inPage 17: BRE
all directions Testsecuring.
before Report 301-688
c. If purlins and spacers are being installed – cap and staples must be used along length of trusses or rafters where counter battens would

R
have normally been Issue 2, 9th Feb 2015.
fitted.
Tolaying
d. Before allowsecond
worklayerto progress inside–before
of FPS® Eurotop the exterior
fix Euroband cladding
DS (Double sided tape)is to upper edge of first layer. Do not remove backing paper!
• FPS Eurotop N65 is certified for use as an unsupported underlay
e. Lay the ®
second layer of FPS® Eurotop with a 60mm overlap – when pulled taut and in Extra
secured, High
remove theWind
backingZones
paper on the Euroband DS
applied,
and firmly pressa to
membrane must meet four minimum requirements;
get good adhesion.
instead
f. At the apex ofroof
of the rigid boarding.
– have at least 300mm flap of FPS® Eurotop running over to other side. Fix down when other side is laid so the flap is
moisture
on top. Fix downcontrol, waterproofing,
with Euroband DS. Alternativelywindproofing and UV
– fix a 500-600mm strip over the apex (ridge line)
®
g. Valley’s - either-have a 500mm strip of if FPS®
Recommendations for FPS product in NZ Eurotop
® laid down valley floorzones:
wind or horizontal layers running through valley and taped to

K
exposure.
opposite side well clear of valley.
h. With mono-pitch or skillion roofs it is essential to vent the upper side/edge – refer to FPS® Manuals or contact FPS®.

FPS® Eurotop Product Recommendations


2. WALLS:
NZ Wind Ratings Unsupported Supported
O
a. Measure 150cm (1500mm) from 75-100mm below the bottom plate and mark upper edge across entire wall section.
O ®A
b. Unroll FPS® Eurotop from left side to right side of Roofwall, ensuring top edgeWall
is on marks and plain staple
Roof inside top 60mm.Wall
c. Make sure at least 300mm is wrapped around each corner, or continue along next wall section.
d. Vertical
Low joins require 75-100mm overlap and sealed
[115kmh] N35with Euroband S60 tape N15 on a stud or solid backing
N35 N15
e. At openings wider than 1500mm – the layer can be cut leaving 300mm flap each side of the opening.
f. Fix Euroband DS to upper horizontal edge of each layer of FPS® Eurotop – do not remove backing paper.
Med [133kmh] N35 N15 N35 N15
g. Apply a recommended FPS® adhesive and staple (as close to the edge of the membrane as possible) to the foundation or bottom plate to
prevent water and air/wind entering the wall structure under and behind the membrane. Depending on the substrate, FPS® supplies, Butyl
Moisture Control
R F
High [158kmh] S65 N35 N35 N35
R

tape or liquid adhesive.


h. From the middle of wall section on a stud – run hand down membrane to get a flat taut surface - secure with staples. From the middle work
V wall
across
Antoward
High underlay
[180kmh] system must be vapour open to the outside,
each end or corner. NOTE: S65 N35 so that N35 N35
(i) If horizontal boarding cladding is specified, vertical cavity battens must be installed over staples. If there is any delay installing
E Highany moisture
battens [198kmh] that isS or
either Euroband still within
FPS® the S4
S65/ construction
Fleece-Butyl tape must becan
N35/
used pass
toS65freely
cover staples. S65 N35
(ii) If vertical boarding cladding is specified, horizontal cavity battens must be installed – cap and staple fixings must be used on studs
orto the ventilation
panels cavity.
between battens.
K

K
(iii) For brick veneer – cap and staple fixings are recommended.

UV Protection
i. Next layer of FPS® Eurotop is rolled out and fixed/ stapled at upper edge across entire wall section, taped and smoothed out from the centre
stud as before with first layer.
j. When upper Waterproofing
layer securely fixed, pull backing paper off Euroband DS progressively across wall pressing firmly to get good adhesion.
k. If second layer extends beyond the top of the wall, both continue across the eave or soffit and connect to the roof section.
Anythe
l. To finish An underlay
temporary
wall system
cladding
installation must
must
– fix the be
bottombewaterproof
abletoto
edge the from the
withstand
foundation UV outside,
withfor
FPS® both
anButyl
extended period.
tape or FPS® Liquid Adhesive and further secure the
membrane to the bottom plate with cap and staples.
• AllinFPS
m. All soffits itseaves
and ability
membranesto have
must holdareout
FPS® a volume
warrantied
Eurotop ofand
for
fitted water, anddays
upconnected
to 90 its ability
exposure
to either to membrane
roof hold
to UV. or other wind tight element at roof edge.
FA
out water continuously for an extended period.
3. Install Euroband S 120 or 180 Sill-tape to all openings. Refer to Sealing Corner Sections leaflet.

4. Install Windproofing
doors and windows before commencing any work on the interior – if rain enters building after FPS®
Eurotop is installed – interior must be dried.
An underlay system must be wind tight, both in terms of wind

uplift durability as well as being airtight. Wind uplift is important


5. IMPORTANT:
O K®

because the roof of a structure acts like an aircraft wing.


(1) Do not leave plain staples exposed to the weather
(2) Ensure all joins and overlaps are properly sealed (water and air/wind proof) – NO horizontal tapes on top of membrane.
However, airtightness is also important because of airborne
(3) Direct any water runoff from the roof away from walls and joinery.
(4) Ventilate the interior as often as possible while working indoors.
moisture
(5) Repair any holes andvapour (humidity).
tears immediately they occur or are found
(6) Ensure proper sealing around cable and plumbing penetrations through exterior membrane.
RA

UV Exposure
An underlay must be able to withstand

exposure to the sun for an extended period,


F

without any degradation.


www.frameprotection.co.nz
Frame Protection System Ltd
PO Box 10286, Te Rapa, Hamilton 3241
Telephone: 0800723426 E-mail: info@frameprotection.co.nz
A

O
F

R
Moisture Control
To be able to install insulation and linings on the
®
inside of a building, any moisture that is still inside

K
the structure, must be able to get out. Therefore,

the building enclosure must be vapour open to the

Waterproof
outside.
O
FA
• All FPS membranes are considered vapour open
To be able to line inside, the outside of the structure according to British Standard BS5250.
®
must be waterproof. BCS-172217-CMNZ • To be considered “vapour open”, permeability must
R

• All FPS membranes are class 1 waterproof products, be less than 0.25MNs/g according to British
with no tent effect. Standard BS5250.
• All FPS membranes have passed column of water

FPS® Weathertight™ for


tests of between 1.5m & 5.5m.

K
• FPS membranes are the only underlay in New

roofs and walls


Zealand to have been tested and passed the 24-hour

Water Streaming Test.


FA
Frame Protection System Ltd, FPS® Weathertight™ system is a comprehensive roof and wall

underlay system for timber and steel frame, panel and prefab building elements, providing

both interim and permanent weather protection plus moisture control within the wall or roof
structure. FPS® Weathertight™ is certified to allow internal work to proceed to completion

before the roof and wall claddings are installed.



R
Wind UpliftEssential
The Four
Requirements for
To be able to line inside, the outside of the structure must be windproof, both in terms of air ingress as well as

wind uplift.

Weathertightness

F
• All FPS membranes have been tested for wind uplift.

- Tested: Refer to FPS® Technical Manual – Wind Loadings Page 17: BRE Test Report 301-688

Issue 2, 9th Feb 2015.


To allow work to progress inside before the exterior cladding is
• FPS® Eurotop N65 is certified for use as an unsupported underlay in Extra High Wind Zones
applied, a membrane must meet four minimum requirements;
instead of rigid boarding.
moisture control, waterproofing, windproofing and UV

- Recommendations for FPS® product in NZ wind zones:
exposure.

FPS® Eurotop Product Recommendations

NZ Wind Ratings Unsupported Supported


Roof Wall Roof Wall

Low [115kmh] N35 N15 N35 N15

Med [133kmh] N35 N15 N35 N15


HighMoisture Control
[158kmh] S65 N35 N35 N35
R

An underlay
V High [180kmh]system must be vapour
S65 open to the outside,
N35 so that N35 N35

any[198kmh]
E High moisture that is still within theS4
S65/ construction N35/
can pass
S65 freely S65 N35
to the ventilation cavity.

UV Protection
Waterproofing

An underlaycladding
Any temporary system must be able
waterproof from the
to withstand UV outside, both
for an extended period.
• All in
FPSitsmembranes
ability to hold
areout a volumefor
warrantied ofup
water,
to 90and its exposure
days ability to hold
to UV.
out water continuously for an extended period.
R

Windproofing

An underlay system must be wind tight, both in terms of wind

uplift durability as well as being airtight. Wind uplift is important


K

because the roof of a structure acts like an aircraft wing.

However, airtightness is also important because of airborne

moisture vapour (humidity).


FA

UV Exposure

An underlay must be able to withstand

exposure to the sun for an extended period,

without any degradation.

You might also like