PROJECT SITE MASTER PLAN (SAGS & POWER PLANT)

Definition:

Site Master Plan is an overall plant layout shown as a top-down orientation (helicopter view) and has considered several aspects such as Safety In
Design (SID), Hazard Operation (HAZOP), Hazardous Area, Operability, Maintainability and Reliability so that the plant design can be reached 55 MW
(net) with reliability and availability is 99.xx %.

FEED Design Consideration FEED Design Coverage Design of Power Plant Design Control of fluid

1. Safety In Design refer to ISO & 1. Detail basic design follow with 1. Generation 55 MW (net) 1. Upstream and downstream
OHSASSS operational cycling as agreed pressure should linier control by
2. Air quality (ambient & H2S), control valve
2. Follow with Pilot Plant Dieng 2. Detail specification and estimate water quality (fresh water, rain
result cost major material/parts per water and ground water) and 2. Flow and opening control valve
items will use in EPC process waste handling manageable should linier
3. Meet to environmentally friendly
and conservation 3. Detail process flow refer to plant 3. SAGS and Power Plant emission 3. Low friction control valve
as required level 0 %
4. Encourage Dieng program as a 4. Resistant to erosion from friction
tourism and conservation area 4. Design control logic and 4. Reach 100% steam condensation of solid material
protection philosophy
5. Meet with aesthetic and 5. Reliability 99.xx% during the first 5. Cooling system PH range 4.5-5.5
instagrammable elements 5. System design description and 5 years of operating
control philosophy 6. Use steam purifying facilities from
6. Conduct seismic hazard study 6. SAGS system able control solid material and liquid
and demonstrate that power plant 6. Follow with simulation result of automatic to support well
structure design is safe for fluid characteristic of Dieng Pilot performance (pressure and 7. The equipment design is low
anticipated seismic risk. Plant temperature) noise

7. Conduct wind speed and storm 7. SAGS design must coverage 7. Have interconnection pipe 8. Able to prevent of back pressure
21

drainage analysis for building and brine management process and (existing and new well) to support
structures waste management both unit-1 and unit-2 9. Resistant to silica and acid

8. Transmission line (150kV) from 8. Cooling Tower design should 8. DCS Unit-1 and Unit-2 able 10. Actuator able operate with
Power Plant Unit-2 to GI consider routine maintainability communicate and operate with minimum power (oil&air)
substation will use underground without need shutdown same HMI
cable (no social impact / land 11. Able to operate in two phase
clearing). 9. Basin Cooling Tower Design able 9. Plant monitoring system should condition
to be cleaned of mud and integrate with Internet of Things
9. Max concentrate of pollutants sediments (IoT) can be accessed by mobile
concern at site boundary and devices
nearest receptor with ambient 10. Design filter of basin should able
H2S level (28µg/m3, 24-hr to prevent the entry of dirt into the 10. Design concept follow with
average time) and emission level cooling system Operability and Maintainability to
(30 mg/Nm3) get more reliable plant
11. Data Output DCS system able
10. Operational Noise sound edit and manipulate by office 11. MV/LV system should
pressure level max software interconnection of both unit-1 and
unit-2
 85db (1 meter from any point 12. Cooling system able to inspection
on any item of equipment) during unit online 12. Plant able to syncrone at GCB
and 150KV CB and can house
 70db (day time) & 60db (night 13. Detail of hazardous area load max 8 hours.
time) at site boundary classification area
13. Design storage tank and handling
 55db (day time) & 45db (night 14. FEED Design include direct will strictly comply with
time) at nearest sensitive utilization international industry standard
receptor and code
15. Calculate existing emergency
11. Operational Hazard Study generator and able to coverage 14. Final design integrate aesthetic
including fire and explosion essential load during both unit-1 and landscape architecture
hazard assessment and fire & unit-2 blackout and redesign if elements as in “design with
safety and H2S detector needed nature” to blend with the existing
proposal (fire detection and landscape
alarm system). This study 16. Conduct plant Life Cycle Analysis
(LCA) and electrical- HAZOP 15. Control room noise sound level

And
22

(HAZID and Risk Assessment) max 65db (refer to Ministry


conduct by independent 17. Conduct explosion risk Environment Decree No. 48
consulting assessment and demonstrate 1996)
compliance
12. Dust level due to mob/demob of 16. Acceptable for geothermal
construction vehicle, equipment 18. Conduct detail site investigation environmental (silica, sulphur,
and material for drilling. including flood and landslide risk H2S, acid, corrosive) and high
assessment 2,000 meter a.s.l
13. Design lifetime, high MTBF, low
MTTR and spare part availability 17. Have Condition Based Monitoring
(CBM) Online tools as following

 Electrical (Partial Discharge,


Disturbance Fault Recorder,
Intelligence Diagnostic Devices,
Battery Management System,
Flux Probe)

 Mechanical (Vibration including


spectrum analysis)