Professional Documents
Culture Documents
Inspection and Testing
Inspection and Testing
1. INTRODUCTION
The primary aim of the Regulation is to protect persons, property and livestock against
hazards arising from an electrical installation.
There is little point in setting up Regulations to control the way in which electrical installations
are designed and installed, if it is not verified that they have been followed.
For example, the protection of installation users against the danger of fatal electric shock due
to indirect contact is usually by the low impedance of the earth fault loop; unless this
impedance is correctly measured, this aspect of safety cannot be confirmed.
The Wiring Regulations stipulate test requirements but do not specify test procedures.
Suitable test methods are given in IET Guidance Note 3 which is a separate publication.
The installation tester, as well as the user, must be provided with clear indications as to how
the installation will carry out its intended purpose. To this end, the person carrying out the
inspection and testing must be provided with the following data:
Without such information the tester cannot verify whether the installation is in
Contd…/2
: 2 :
3. INSPECTION
Prior to testing it is necessary and important that a thorough inspection of the complete
The main purpose of the inspection is to confirm that the equipment and materials installed;
a) Are not obviously damaged or defective which could affect the safety of the installation.
b) Have been correctly selected and properly erected.
c) Are suitable for the prevailing environmental conditions.
6) Checking of design calculations to ensure that correct live and protective conductors have
been selected in terms of their current-carrying capacity and volt drop
7) Presence of fire barriers, suitable seals and protection against fire
Contd…../3
:3:
8) Protection of live parts by insulation to prevent direct contact with live conductors
9) Protection against fault contact by the use of:
a) Protective conductors
b) Earthing conductors
c) Main and supplementary equipotential bonding conductors
d) Earthing for combined protective and functional purposes
e) Use of Class II equipment or equivalent insulation
f) Non-conducting location and the absence of protective conductors
g) Earth-free local equipotential bonding
h) Electrical separation
i) SELV
j) Double insulation
k) Obstacles and placing out of reach
l) Barriers and enclosures
These should be considered as being the minimum requirements. It must be emphasized that
inspection (and testing) of an installation need not await the latter’s completion but where
necessary the exercise should be carried out even during erection. This is particularly applicable
to major projects where clearly; an effective inspection cannot be carried out unless it is made
an ongoing process from the commencement of the project.
Contd……/4
:4:
3. TESTING
Testing can be hazardous, both to the tester and to others who are within the installation
during the test. Electronic equipment such as dimmer switches, power controls, electronic
fluorescent starter switches, touch switches, delay timers etc. which could be damaged by
the application of high-test voltage should be disconnected for testing purposes. Further,
capacitors and indicator or pilot lamps must be disconnected or an inaccurate test reading
will result.
(b) Insulation resistance (between live conductors and between each live conductor and
earth). Where appropriate during this measurement, line and neutral conductors may be
connected together, for example, where many lighting transformers are installed on a
lighting circuit
(c) Polarity: this includes checks that single-pole control and protective devices, for example,
switches, circuit-breakers and fuses, are connected in the line conductor only,
(d) that bayonet and Edison screw lamp-holders have their outer contacts connected to the
neutral conductor and that wiring has been correctly connected to socket-outlets and
other accessories
(e) Protection by separation
(f) Protection by barriers and enclosures
(g) Earth electrode resistance (TT systems).
If at any point in the sequence there is a failure in the test being carried out then, not only does
that the test have to be repeated after the fault is corrected, but all the previous tests that may
have been affected by the fault must be repeated. It is important to use reputable and reliable
test equipment to carry out the tests. They should be checked and recalibrated regularly to
ensure accuracy.
The importance of regular inspection and testing of electrical installations cannot be overstated,
but unfortunately it is an aspect of electrical safety which is very often overlooked.
It is now a requirement of the Regulations that the installer of an installation must tell the user
of the need for periodic test and inspection and when such attention is necessary.
The following table gives suggested intervals between periodic tests and inspection.
Contd/…….6
:6:
APPENDIX A
BASIC FEATURES
Contd/….…III
: III :
Contd/……..IV
: IV :
Contd/………V
:V: