Professional Documents
Culture Documents
net/publication/290441879
CITATIONS READS
0 44
1 author:
Günter Seidl
Fachhochschule Potsdam
61 PUBLICATIONS 401 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
HyConCast - Hybrid substructure of high strength concrete and ductile iron castings for offshore wind turbines View project
All content following this page was uploaded by Günter Seidl on 15 January 2016.
Abstract
To minimise cost and time consuming works on bridge construction sites, prefabricated construction elements are ever
more frequently taken into consideration in the development of new construction methods. Hence, there is the possibility to
transfer complex works into the prefabrication plant, to limit work time of bridges to only a few days and to simplify the
construction process. These advantages shall be put into use during new construction of a three lane road bridge with cycle
lane. Therefore a bridge has been developed with a transversal bearing system uncoupled from the longitudinal system and
consisting of deck elements. The deck elements are not connected with the longitudinal system afterwards but lie movably
in longitudinal direction on an elastic strip support. In the final stage, framing system and deck can be moved
independently for one another. The present report describes the particularities of the new construction method such as
bearing behaviour of the deck elements and construction details especially joint formation and support of the deck.
1 INTRODUCTION
When newly constructing a bridge, besides material and staff costs, construction time and thus the intervention in ongoing
traffic plays a decisive role in terms of costs. The development of new construction methods aims always at a level of
prefabrication as high as possible to minimise construction time on site. This was the aim of the new method herein
presented whose advantages are demonstrated on an exemplary project.
Main characteristic of the new construction method is a transversal bearing system uncoupled from the longitudinal system.
The longitudinal system consists of two prefabricated VFT-girders formed as framing structure with a clearance of
32.00 m; in transversal direction these girders are only connected on the abutments with retaining walls.
The deck consists of prefabricated deck elements of 16.00 m width and 2.50 m length that are laid with a crane onto the
framing bridge. As soon as the deck elements are laid, they are connected by longitudinal tendons without post-tension to
form a connected deck. This technique assures that the elements do not slip apart and that shear force is transmitted by the
shear-dowels. The deck elements are not connected later on with the longitudinal system. The elements lie in longitudinal
direction movably on an elastomeric strip that corresponds to a flexible support between the deck and the framing system.
It is thus assured that the framing system founded on bored piles and the deck move independently from one another in
case of traffic load and temperature.
Fig. 2 Schematic cross-section of the bridge
2 BRIDGE STRUCTURE
The construction can be divided in two bearing elements:
The frame forms the main structure of the bridge as, later on, the deck should not have a shear-resistant connection to the
bridge. Accordingly, the load bearing structure is build rigidly to sufficiently secure small deformations of the bridge even
without interaction of the deck.
The concrete is used directly for traffic which is made possible by the high quality of the prefabrication concrete. It can be
renounced to forming the bridge caps with cast-in-place concrete as this can already be taken into account in the formation
of the bridge deck.
The deck elements prefabricated at the plant are placed on the framing system consisting of the two main girders. No shear-
resistant connection of the elements with the longitudinal girders is provided but an independent shift of the two bearing
systems (longitudinal and transversal direction). This is in the context of prior experience showing that post-grouting is
sometimes not without inaccuracies. A great advantage of this variant is the very simple renewal of the deck in the course
of renovation works of the deck. In addition, constraint forces acting on the deck elements and on the longitudinal girders
can be reduced. A shear-resistant connection was furthermore examined. Decisive material savings were not achieved by
these measures because the high shear forces resulting from dead weight do not act on the later shear connection.
To permit an independent shift of the bearing systems, the deck elements are placed on an elastic intermediate layer of
about 2.5 cm. The elastic layer is lowered about 1.5 cm into a deepening planned in the longitudinal girders to prevent a
displacement of the strips. The bottom edge of the deck elements that runs parallel to the upper edge (one side inclination
of 2.5%) is formed horizontally near the longitudinal girders for support.
During construction stage, the deck elements are shifted to one another on the elastomeric strip that is to say, according to
the possible bearing situation, they have to be shifted several centimetres. Resulting from longitudinal pre-stressing, a
relatively large displacement between the longitudinal girder and the deck can be expected. A resting distortion of the
elastomeric strip due to these displacements should be prevented so as to guarantee the durability of the materials and to
permit the quasi-slide of the deck elements on the longitudinal girders. A PU-layer is applied to the elastomeric strip that
acts as sliding layer.
2.2.2 Joint formation in the connection area of the deck elements / sealing
The deck elements are joined to one another by concrete dowels with shear-connection. An external longitudinal pre-
stressing produces a high compression force that exceeds the shear force dowels in all load cases.
The deck is used for traffic without applying an asphalt layer. In the undisturbed areas of the deck elements, the high
concrete quality – guaranteed by fabrication at the plant – presents a sufficient sealing effect. In the area of the connection
of the deck elements, joints are build that have to be protected against infiltrating water. For that reason a continuous
sealing is assembled above the concrete dowel.
1) 2) 3) 4)
Fig. 3 Schematic demonstration of fabrication: 1) Fabrication of the frame corner, 2) Laying of the elastomeric strip,
3) Laying of deck elements, 4) Stressing together of deck elements
The dismounting of the overturning securing can now be done quickly and the drainage can be connected. Road works
proceed to the valance and the bridge is commissioned for traffic.