You are on page 1of 6

ID Task Task Name Duration Start Finish Predecessors

Mode 2023 2024 2025 2026 2027 2028


H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
1 G+1 REIDENTIAL BUILDING 351 days Fri 2/2/24 Fri 6/6/25
2 MOBILIZATION TIME 20 days Fri 2/2/24 Thu 2/29/24
3 A)SUB- STRUCTURE 95 days Fri 2/2/24 Thu 6/13/24
4 1.0) Excavation and Earthwork 26 days Fri 2/2/24 Fri 3/8/24
5 1.1) Site clearance 2 days Fri 2/2/24 Mon 2/5/24 Daily labor,Forman,Gang chief,Tools[1]
6 1.2) Bulk Excavation 2 days Tue 2/6/24 Wed 2/7/24 5 Daily labor,Forman,Gang chief,Tools[1]
7 1.3) Pit excavation 5 days Thu 2/8/24 Wed 2/14/24 6 Forman,Gang chief,drilling machine,Tools[1],Daily labor
8 1.4) Trench Excavation 4 days Thu 2/15/24 Tue 2/20/24 7 Daily labor,Forman,Gang chief,Tools[1]
9 1.5) Backfill Around footing 3 days Wed 2/21/24 Fri 2/23/24 8 Daily labor,Forman,Gang chief,Tools[1]
10 pads
1.5.1) Backfill around Trench 3 days Mon 2/26/24 Wed 2/28/24 9 Daily labor,Forman,Gang chief,Tools[1]
11 Excavation
1.5.2) Backfil Around Bulk 2 days Thu 2/29/24 Fri 3/1/24 10 Daily labor,Forman,Gang chief,Tools[1]
12 excavation of 25 cm Thick 3 days
1.6)Hardcore Mon 3/4/24 Wed 3/6/24 11 Daily labor,Forman,Gang chief,Tools[1]
13 1.7) Cart-away 2 days Thu 3/7/24 Fri 3/8/24 12 Daily labor,Forman,Gang chief,dump truck driver,Tools[1]
14 2.0) Concrete work 5 days Mon 3/11/24 Fri 3/15/24
15 2.1) C-5 Lean concrete 5 days Mon 3/11/24 Fri 3/15/24 13 Daily labor,Forman,Hand tools[1],Mason ,mixer,Mixer Ope
16 under footing pads and
3.0) Reinforcement Bars For under 6 days Mon 3/18/24 Mon 3/25/24
17 Sub-structures
3.1) Reinforcement Bars for 2 days Mon 3/18/24 Tue 3/19/24 15 Daily labor,Forman,Gang chief,Dia. 16 mm deformed bars[
18 Footing pads with stirups
3.2) Reinforcement Bars for 3 days Mon 3/18/24 Wed 3/20/24 15 Daily labor,Forman,Gang chief,Bar bender ,Dia. 16 mm def
19 footing column with
3.3) Reinforcement Barsstirups
For 6 days Mon 3/18/24 Mon 3/25/24 15 Daily labor,Forman,Gang chief,Bar bender ,Dia. 16 mm def
20 Grade Beams
4.0) Formwork for with stirups 35 days Tue 3/26/24 Mon 5/13/24 19
21 sub-structures
4.1) formwork for footing pad 6 days Tue 3/26/24 Tue 4/2/24 19 Carpenter,Daily labor,Gang chief,Euclyptus wood[1 ml],on
22 4.2) formwork for Grade Beams 4 days Tue 3/26/24 Fri 3/29/24 19 Carpenter,Daily labor,Gang chief,Euclyptus wood[1 ml],na
23 4.3) Form work for footing 31 days Mon 4/1/24 Mon 5/13/24 22 Carpenter,Daily labor,Gang chief,Euclyptus wood[1 ml],n
Column
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: bini mcn
Summary Manual Summary Rollup Progress
Date: Sun 2/4/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slack

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
Mode 2023 2024 2025 2026 2027 2028
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
24 5.0) C-25 concrete work 18 days Tue 5/14/24 Thu 6/6/24 23
25 5.1) C-25 Concrete work for 6 days Tue 5/14/24 Tue 5/21/24 23 Mason ,Daily labor,Gang chief,mixer,Mixer Operator,Cem
26 footing
5.2) C-25pads and Footing
Concrete work for 6 days Wed 5/22/24 Wed 5/29/24 25 Mason ,Daily labor,Gang chief,mixer,Mixer Operator,Cem
27 Grade
5.3) Beams
C-25 for ground floor slab 6 days Thu 5/30/24 Thu 6/6/24 26 Mason ,Daily labor,Gang chief,mixer,Mixer Operator,Ce
28 6.0) Masonary Work 5 days Fri 6/7/24 Thu 6/13/24 27
29 6.1) Stone masonary work 5 days Fri 6/7/24 Thu 6/13/24 27 Mason ,Daily labor,Gang chief,Alole stone[1 m2],Cemen
30 B) SUPER-STRUCTURES 251 days Fri 2/2/24 Fri 1/17/25
31 1.0) REINFORCEMENT BARSS 28 days Fri 6/14/24 Tue 7/23/24
32 FOR SUPER
1.1) STRUCTURES
Reinforcement bars for 5 days Fri 6/14/24 Thu 6/20/24 29 Bar bender ,cuter,Daily labor,Forman,Dia. 16 mm defor
33 Ground floor columns
1.2) Reinforcement bars with 4 days Fri 6/21/24 Wed 6/26/24 32 Bar bender ,cuter,Daily labor,Gang chief,Dia. 16 mm de
34 first floor
1.3) columns with
Reinforcement Bars for 5 days Thu 6/27/24 Wed 7/3/24 33 Bar bender ,Daily labor,Gang chief,Dia 8mm deformed
35 First floor
1.4) Beams with
Reinforcement stirups
Bars for 4 days Thu 7/4/24 Tue 7/9/24 34 Bar bender ,Daily labor,Gang chief,Dia 8mm deformed
36 Top tie
1.5) beams with stirups
Reinforcement Bars for 4 days Wed 7/10/24 Mon 7/15/24 35
37 stairReinforcement
1.6) case stirups Bars for 6 days Tue 7/16/24 Tue 7/23/24 36 Bar bender ,Daily labor,Gang chief,Dia 8mm deformed
38 first
2.0) floor slab with
FORMWORK FORstirups
FOR 19 days Wed 7/24/24 Mon 8/19/24 37
39 SUPER-STRUCTURES
2.1) formwork for ground 5 days Wed 7/24/24 Tue 7/30/24 37 Carpenter,Daily labor,Gang chief,Euclyptus wood[1 ml
40 floor elevation column
2.2) Formwork for first floor 3 days Wed 7/31/24 Fri 8/2/24 39 Carpenter,Daily labor,Gang chief,Euclyptus wood[1 m
41 elevation column
2.3) formwork for first floor 4 days Mon 8/5/24 Thu 8/8/24 40 Carpenter,Daily labor,Gang chief,Euclyptus wood[1 m
42 beams
2.4) formwork for Top ties 3 days Fri 8/9/24 Tue 8/13/24 41 Carpenter,Daily labor,Gang chief,Euclyptus wood[1 m
43 beams
2.5) Formwork for Stair case 4 days Wed 8/14/24 Mon 8/19/24 42 Carpenter,Daily labor,Gang chief,Euclyptus wood[1 m
44 3.0) CONCRETE WORK FOR 20 days Tue 8/20/24 Mon 9/16/24
45 SUPER-STRUCTURES
3.1) c-25 concrete for footing 4 days Tue 8/20/24 Fri 8/23/24 43 Mason ,Daily labor,Gang chief,mixer,Mixer Operator,
46 column,
3.2) C-25ground
concretefloor
workcolumn
for 3 days Mon 8/26/24 Wed 8/28/24 45 Mason ,Daily labor,Gang chief,mixer,Mixer Operator,
stair case
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: bini mcn
Summary Manual Summary Rollup Progress
Date: Sun 2/4/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slack

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors
Mode 2023 2024 2025 2026 2027 2028
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
47 3.3) C-25 concrete work for 4 days Thu 8/29/24 Tue 9/3/24 46 Mason ,Daily labor,Gang chief,mixer,Mixer Operator,
48 first C-25
3.4) floor concrete
slab work for 4 days Wed 9/4/24 Mon 9/9/24 47 Mason ,Daily labor,Gang chief,mixer,Mixer Operator
49 first floor
3.5) beams work for
c-25 concrete 5 days Tue 9/10/24 Mon 9/16/24 48 Mason ,Daily labor,Gang chief,mixer,Mixer Operator
50 Top tieBLOCK
4.0)HCB beamsWORK FOR 12 days Tue 9/17/24 Wed 10/2/24
51 WALLING
4.1) HCB block work for 6 days Tue 9/17/24 Tue 9/24/24 49 Mason ,Daily labor,mixer,Mixer Operator,Cement[1
52 ground
4.2) HCBfloor with
block partion
work for first 6 days Wed 9/25/24 Wed 10/2/24 51 Mason ,Daily labor,Cement[1 m3],Sand [1 m3],Tools
53 floor with
5.0) ROOF WORK partion walls 5 days Thu 10/3/24 Wed 10/9/24
54 5.1) Harvey Tile Roof work 5 days Thu 10/3/24 Wed 10/9/24 52 Carpenter,Daily labor,Roofing nails [1 kg]
55 6.0) CARPENTRY WORK 12 days Thu 10/10/24 Fri 10/25/24
56 6.1)fixing dia 10-12 Euclyptus 6 days Thu 10/10/24 Thu 10/17/24 54 Carpenter,Daily labor,Gang chief,Eucalyptus dia 8m
57 lower anddia
6.2)fixing upper
8-10trus
Euclyptus 6 days Fri 10/18/24 Fri 10/25/24 56 Carpenter,Daily labor,Gang chief,Eucalyptus dia 8m
58 vertical
7.0) CEILINGand and Diagonal
WORK 4 days Fri 2/2/24 Wed 2/7/24 Carpenter,Daily labor,Forman,Tools[1]
59 8.0) GLASSING WORK 32 days Fri 2/2/24 Mon 3/18/24
60 8.1)Glassing work for ground 4 days Fri 2/2/24 Wed 2/7/24 6 mm clear glass[1 m2],cuter,Daily labor,Forman,Glazer,Put
61 and first floor
8.1.1)6mm thick of size w1 2 days Thu 2/8/24 Fri 2/9/24 60 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
62 3.1*2.1
8.1.2)6mm thick of size w2 2 days Mon 2/12/24 Tue 2/13/24 61 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
63 2.8*1.36
8.1.3) 6mm thick of size w3 2 days Wed 2/14/24 Thu 2/15/24 62 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
64 2.7*2
8.1.4)6mm thick of size w4 2 days Fri 2/16/24 Mon 2/19/24 63 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
65 1.6*2
8.1.5) 6mm thick of size w5- 2 days Tue 2/20/24 Wed 2/21/24 64 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
66 0.65*0.96
8.1.6)6mm thick of size w6 2 days Thu 2/22/24 Fri 2/23/24 65 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
67 0.6*0.96 thick of size w7
8.1.7)6mm 2 days Mon 2/26/24 Tue 2/27/24 66 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
68 3.1*1.92 thick of size w8
8.1.8)6mm 2 days Wed 2/28/24 Thu 2/29/24 67 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
69 2.2*1.24 thick of size w9
8.1.9)6mm 2 days Fri 3/1/24 Mon 3/4/24 68 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
0.47*0.44
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: bini mcn
Summary Manual Summary Rollup Progress
Date: Sun 2/4/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slack

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Predecessors
Mode 2023 2024 2025 2026 2027 2028
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
70 8.2)6mm thick of size w10 2 days Tue 3/5/24 Wed 3/6/24 69 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
71 2.8*1.4
8.2.1)6mm thick of size w11 2 days Thu 3/7/24 Fri 3/8/24 70 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
72 0.65*0.9
8.2.3)6mm thick of size w12 2 days Mon 3/11/24 Tue 3/12/24 71 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
73 2.74*2.36
8.2.4) 6mm thick of size w13 2 days Wed 3/13/24 Thu 3/14/24 72 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
74 1.85*1.5
8.2.5) 6mm thick of size w13 2 days Fri 3/15/24 Mon 3/18/24 73 cuter,Daily labor,Forman,Glazer,Putty[1 kg],Tools[1]
75 0.65*1.9
9.0) FINISHING WORK 40 days Tue 3/19/24 Mon 5/13/24
76 MATERIAL
9.1)floor finishing material for 20 days Tue 3/19/24 Mon 4/15/24 74
77 ground
9.2)per floor
quatile 5 days Tue 4/16/24 Mon 4/22/24 76 Daily labor,Forman,perquatile[1 m2],Cement[1 m3],Tiller
78 9.3)marble tile 5 days Tue 4/23/24 Mon 4/29/24 77 Daily labor,Forman,Cement[1 m3],Hand tools[1],marble t
79 9.4)ceramic tile 5 days Tue 4/30/24 Mon 5/6/24 78 ceramic tile[1 m2],Daily labor,Cement[1 m3],Hand tools[
80 9.5)concrete tile 5 days Tue 5/7/24 Mon 5/13/24 79 concrete tile[1 m2],Daily labor,Cement[1 m3],Hand tools
81 10 .floor finishing material for 12 days Tue 5/14/24 Wed 5/29/24
82 first floor
10.1 perfloor
quatile 4 days Tue 5/14/24 Fri 5/17/24 80 perquatile[1 m2],Cement[1 m3],Daily labor,Hand tools[1
83 10.2 marble tile 4 days Mon 5/20/24 Thu 5/23/24 82 Cement[1 m3],Daily labor,marble tile[1 m2],Forman,Han
84 10.3 ceramic tile 4 days Fri 5/24/24 Wed 5/29/24 83 Cement[1 m3],Daily labor,ceramic tile[1 m2],Hand tools
85 11.0) PLASTERING WORK 36 days Thu 5/30/24 Thu 7/18/24
86 11.1) plastering for Ground 18 days Thu 5/30/24 Mon 6/24/24 84 Cement[1 m3],Daily labor,Forman,Hand tools[1],Plaste
87 floor HCBcoat
11.2)1st Walls and columns
plastering of 6 days Tue 6/25/24 Tue 7/2/24 86 Cement[1 m3],Daily labor,Forman,Hand tools[1],Plaste
88 20cm HCB thick
11.3)2nd coat plastering of 6 days Wed 7/3/24 Wed 7/10/24 87 Cement[1 m3],Daily labor,Forman,Plasterer,Sand [1 m3
89 20cm HCBcoat
11.4)3rd thick
plastering of 6 days Thu 7/11/24 Thu 7/18/24 88 Cement[1 m3],Daily labor,Forman,Hand tools[1],Plaste
90 20cmPlastering
12.1) HCB thickfor First floor 18 days Fri 7/19/24 Tue 8/13/24
91 HCB Walls coat plastering of
12.2)1st 6 days Fri 7/19/24 Fri 7/26/24 89 Cement[1 m3],Daily labor,Plasterer,Sand [1 m3],Tools
92 20cm HCBcoat
12.3)2nd thick
plastering of 6 days Mon 7/29/24 Mon 8/5/24 91 Cement[1 m3],Daily labor,Plasterer,Sand [1 m3],Wate
20cm HCB thick
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: bini mcn
Summary Manual Summary Rollup Progress
Date: Sun 2/4/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slack

Inactive Milestone Finish-only

Page 4
ID Task Task Name Duration Start Finish Predecessors
Mode 2023 2024 2025 2026 2027 2028
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
93 12.4)3rd coat plastering of 6 days Tue 8/6/24 Tue 8/13/24 92 Cement[1 m3],Sand [1 m3],Water[1 m3],Daily labor,P
94 20cm
13.0) HCB thick FOR BEAMS 4 days
PLASTERING Wed 8/14/24 Mon 8/19/24
95 13.1) Plastering for all beams 4 days Wed 8/14/24 Mon 8/19/24 93 Cement[1 m3],Sand [1 m3],Water[1 m3],Daily labor,P
96 14.0)PAINTING WORK 36 days Tue 8/20/24 Tue 10/8/24
97 14.1) painting for ground 18 days Tue 8/20/24 Thu 9/12/24 95 animal glue[1 kg],brush[1 pcs],Daily labor,Gypsum[1
98 floor walls
14.2)1st coat painting of 6 days Fri 9/13/24 Fri 9/20/24 97 animal glue[1 kg],brush[1 pcs],Daily labor,Forman,G
99 20cm HCB thick
14.3) 2nd coat painting of 6 days Mon 9/23/24 Mon 9/30/24 98 animal glue[1 kg],brush[1 pcs],Daily labor,Forman,G
100 20cm HCB thick
14.4) 3rd coat painting of 6 days Tue 10/1/24 Tue 10/8/24 99 animal glue[1 kg],brush[1 pcs],Daily labor,Forman,H
101 20cm HCB thick
15.0)painting for first floor walls26 days Wed 10/9/24 Wed 11/13/24
102 15.1) 1st coat painting of 4 days Wed 10/9/24 Mon 100 animal glue[1 kg],brush[1 pcs],Daily labor,Gypsum[
103 20cm HCBcoat
15.2)2nd thickpainting of 6 days 10/14/24
Tue 10/15/24 Tue 10/22/24 102 animal glue[1 kg],brush[1 pcs],Daily labor,Forman,H
104 20cm HCBcoat
15.3)3rd thick
painting of 5 days Wed Tue 10/29/24 103 animal glue[1 kg],brush[1 pcs],Daily labor,Forman,
105 20cm HCB thick
15.4)painting for stair case 5 days 10/23/24
Wed 10/30/24Tue 11/5/24 104 animal glue[1 kg],brush[1 pcs],Daily labor,Forman,
106 15.5)painting for Beams 6 days Wed 11/6/24 Wed 11/13/24105 animal glue[1 kg],brush[1 pcs],Daily labor,Forman
107 16.0) ELECTRICAL INSTALATION 12 days Thu 11/14/24 Fri 11/29/24
108 16.1) Electrical Installation for 6 days Thu 11/14/24 Thu 11/21/24 106
109 lamps of ground
16.2)ceiling and first
incadescent 3 days Fri 11/22/24 Tue 11/26/24 108 Incandescents type[1 pcs],Electrician,Daily labor,F
110 16.3)ceilling fluorescent philips3 days Wed 11/27/24Fri 11/29/24 109 fluorescents type[1 pcs],Electrician,Daily labor,For
111 17.0) SANITARY INSTALATION 18 days Mon 12/2/24 Wed 12/25/24
112 17.1)Water supply pipes 9 days Mon 12/2/24 Thu 12/12/24 110 driller,plumber,TVC ppes 20mm[1 "m],Daily labor
113 17.1.1)Total length of Dia 3 days Fri 12/13/24 Tue 12/17/24 112 driller,Daily labor,Forman,plumber,TVC ppes 20m
114 20mm
17.1.2)Total length Dia of 3 days Wed Fri 12/20/24 113 Daily labor,driller,Forman,plumber,TVC ppes 25m
115 25MM
17.1.3)Total length Dia of 3 days 12/18/24
Mon Wed 114 Daily labor,driller,Forman,plumber,TVC pipes 15m
15MM 12/23/24 12/25/24
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: bini mcn
Summary Manual Summary Rollup Progress
Date: Sun 2/4/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slack

Inactive Milestone Finish-only

Page 5
ID Task Task Name Duration Start Finish Predecessors
Mode 2023 2024 2025 2026 2027 2028
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
116 18.0)WASTE WATER PIPES 7 days Thu 12/26/24 Fri 1/3/25
117 18.1) Total length of 110. 3 days Thu 12/26/24 Mon 115 Daily labor,Forman,plumber,pvc pipes 110mm[1]
118 mm diameterlength
18.1.2)Total wasteofwater
65 2 days 12/30/24
Tue 12/31/24 Wed 1/1/25 117 Daily labor,Forman,plumber,pvc pipe 65mm[1],T
119 mm diameterlength
18.1.3)Total wasteof 50 2 days Thu 1/2/25 Fri 1/3/25 118 Daily labor,Forman,plumber,PVC pipes 50mm[1]
120 mm diameterFOR
19.0)FIXTURES waste
GROUND 10 days Mon 1/6/25 Fri 1/17/25
121 AND FIRST FLOOR
19.1)water clloset with 3 days Mon 1/6/25 Wed 1/8/25 119 Turkish WC[1 pcs],Asistant plumber,driller,Daily
122 15mm diameter
19.1.2)floor drainpipe 3 days Thu 1/9/25 Mon 1/13/25 121 driller,drilling machine,plumber,Daily labor,Form
123 19.1.3) one way valve 3 days Tue 1/14/25 Thu 1/16/25 122 one way valve[1],plumber,Asst.plumber,Daily lab
124 indirect cost 1 day Fri 1/17/25 Fri 1/17/25 123 indirect cost[1]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: bini mcn
Summary Manual Summary Rollup Progress
Date: Sun 2/4/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slack

Inactive Milestone Finish-only

Page 6

You might also like