5 PREVENTIVE MAINTENANCE
5.2 RESPONSIBILTY
5.2.1 Master and Chief Engineer have primary responsibility for all vessel maintenance
5.2.2 It is responsibility of all crewmembers to promptly comply with requirements of
preventive maintenance system and report all mechanical, structural, electrical
and electronic deficiencies that vessel’s safety and performance are not
jeopardized.
5.2.3 It is the Master and Chief Engineer’s responsibility to plan & indent stores and
spares necessary for maintenance .It is the GM/DGM (Tech) responsibility to
arrange for timely supply of materials required for maintenance.
5.4.3 It is extremely critical that maintenance is carried out as per the planned
maintenance systems and accurate records of each equipment are maintained.
5.4.4 Job cards should state only reference or page number of the manual and not the
maintenance procedure. The idea behind this being that in case an incorrect
instruction has been fed into the PMS then wrong maintenance will be done.
Also it will ensure that the person concerned uses the manual directly for
maintenance and not a procedure written by someone else.
5.4.5 Work done changes for the month to be sent to at the end of every month.
5.4.6 Back up for changes (work done) to be kept on board also.
5.4.7 Vessel to endeavour to keep outstanding tasks below 2 % but in any case not
more than 6 %.
5.4.8 No changes (other than entry for work done) to be made in PMS without express
permission from head office.
5.4.9 PMS to be used for reporting of any defect to head office including dry dock
work list. This allows for better monitoring and overview.
5.4.10 PMS has been programmed for all spares inventory as well as to highlight or
warns user for any shortages in spares below minimum set level.
5.4.11 All critical equipments along with there spare are also identified in the P.M.S.
5.4.12 PMS also has been programmed defining competency for operation,
maintenance, and repair or for any changing of parameters.
5.6.1 Equipment on board, the sudden failure of which may result in a hazardous
situation, is identified as CRITICAL Equipment/system.
5.6.2 Such critical equipment, systems and alarms have been identified in the PMS and
due to the very nature should be treated as priority item
5.6.3 Regular testing of stand-by systems in order to ensure that one failure does not
result in the total loss of that critical function.
5.6.4 Maintenance routines should include the regular and systematic testing of the all
such critical and stand-by systems.
5.6.5 Critical equipment/systems listings as identified in PMS are as below:
Title: VSPM --05
VARUN SHIPBOARD PROCEDURES MANUAL Page : 3 OF 11
PREVENTIVE MAINTENANCE Rev.: 0
Date : 01.09.2005
Annually w/shop
O 2 Analyser , IG System Monthly ship
Prior USE ship
Loadicator Test 3 months Ship
Annually w/shop
Portable Analysers Monthly ship
Prior USE ship
Annually or as
Alcohol Sensor w/shop
per maker
Temp sensors & cut outs for cooling
Every DD w/shop
water system of main engines
Temp sensors & cut outs for cooling
Every DD w/shop
water system of aux engines
Pressure sensors for Main Eng. Lub oil
Every DD w/shop
systems & allied alarms and cut outs
Pressure sensors for Aux Eng. Lub oil
Every DD w/shop
systems & allied alarms and cut outs
MACHINERY Exhaust gas thermometer Every DD w/shop
5.12.6 Hot spots as per Fatigue analysis reports (where applicable) are to be checked
specially during conducting such tank inspections.
5.12.7 Reports to also include photographic records for all inspections.
5.14 DRY-DOCKING
5.14.1 During Dry Dock repairs, it is the Master’s responsibility to ensure that safety
arrangements are adequate, means of alarm fire-fighting and communication have
been properly established and understood, and that proper supervision is
maintained for fire safety at all times during vessel’s stay in Dry Docking.
5.14.2 Master to confirm, adequate security procedures implemented by yard.
5.14.3 All work carried out during dry-docking to be supervised by ship’s staff and in
accordance with the vessel’s repair specification.
5.14.4 The Dry Dock forms file must be started immediately after dry-docking and
continued up to next Dry dock. Repair specification forms to be sent to Head
Office on monthly basis. Repair specification form to contain maximum possible
data. Photographs, drawings, plans or sketches to be attached as applicable with
repair forms.
5.14.5 Complete specifications for dry-docking / repairs should be sent to the Company
3-4 months before the estimated dry docking date.
5.14.6 Additional Repair Specification items arising after sending of complete
specifications to be sent to Head Office immediately on discovery by E-Mail.
5.14.7 Unscheduled major repairs shall be carried out in accordance with this section.
5.16.20 The approved Fire Protection and appliances plans along with an updated muster
list and crew list shall be readily available in the W/T containers port and stbd on
the main deck. These should be checked prior arrival every port.
5.16.21 The Main Fire Line should be tried out and any leaks on the line should be
rectified .No doublers or patch up is allowed on fire and spray line.
5.16.22 All hydrants on deck, accommodation and machinery spaces must be maintained
in good condition i.e. easily operational; without any leaks when shut.
5.17.14 All lifebuoys should be stowed properly on their stands. They should be well
stencilled with the name and port of registry of the ship.
5.17.15 The grab lines should be attached firmly.
5.17.16 Attached SI Light floats should be tested regularly for operation and battery cells
renewed when they become weak.
5.17.17 Line Throwing Apparatus and distress signals are to be stowed on the bridge in a
marked position as indicated in the Safety/LSA Plan.
5.17.18 Immersion suits and thermal protective suits must be cleaned regularly when
taken out during boat drills and stowed properly.
5.17.19 The EPIRBs and SARTs are to be tested at intervals as per PMS and records of
the tests maintained.
CO 2 System , Piping
( HP , MP & LP)( above Pr.Testing 5 Years w/shop
15 years
SCBA Sets Service 1 year w/shop
6
SCBA Sets , Bottles Pr.Testing 5 Years w/shop