Professional Documents
Culture Documents
(3) The claims made by respondent No. 1 are beyond the terms and
conditions of the contract, more particularly, Clauses 17.2 and 18
of the General Conditions of Contract.
(4) The Arbitral Tribunal has no jurisdiction to award interest by
invoking the provisions of the MSMED Act and the claimant ought
to have approached the appropriate forum for the said relief, if so
advised, by raising a dispute before the Facilitation Council under
Sections 15 to 18 of the MSMED Act, 2006.
(5) The reasoning given by the Tribunal that the appellant
committed breach of contract is highly perverse as the claimant
himself breached the contract by not completing the work within
the extended period.
(6) The appellant herein did not commit any breach of contract, as
such, respondent No. 1 herein would not be entitled for any
compensation.
(7) The appellant herein terminated the contract as per the terms
and conditions of the contract, as such, the termination of the
contract cannot be faulted, and the Award, on the basis of the
findings arrived at, contra is neither sustainable nor tenable in the
eye of law.
(8) The Tribunal granted claims 5 and 8 in violation of the terms and
conditions of the contract and substantive law and the same are
not permissible in view of Clauses 23.1 and 18.5.1 of the General
Conditions of Contract read with Clause-15 of the Special
Conditions of Contract.
(9) As per Clause 15.3 of the Special Conditions of Contract, if the
delay is not attributable to the contractor, the contractor is
entitled for price variation only and not for damages as per
Clauses 23.1 and 18.5.1 of the General Conditions of Contract
read with Annexure-4.
(10) The Tribunal ought not to have awarded Claims 5 and 8 in view
of Section 28(3) of the Act, 1996 and the phrase compensation as
stipulated in Section 28(3) of the Act, 1996, is required to be
treated as liquidated damages.
(11) The judgment of the Hon'ble Supreme Court in Associate
Builders v. Delhi Development Authority1 cannot be made
applicable for claiming claims 5 and 8, since the clauses akin to
clause 18.5.1 of the General Conditions of Contract was not there
in the said reported case.
(12) All extensions were granted without liquidated damages, which
the contractor already claimed under Claim No. 1 in the form of
release of due payment of final bill (Rs. 75,26,745-91 ps), labour
escalation bill (Rs. 9,16,194-15 ps), POL escalation bill (Rs.
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 4 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
Court in Mitra Guha Builders (India) Company v. Oil and Natural Gas
Corporation Limited7 (Paras 16 to 29).
(17) On Claim No. 13, it is contended that as per Clause 9.3 of the
General Conditions of Contract, the contractor is not entitled for
the said claim and it would not be open for the contractor to claim
anything under this head.
(18) On Claim No. 14, it is contended by the learned Senior Counsel
that in view of Clause 28.4 of General Conditions of Contract, the
Arbitral Tribunal has no jurisdiction to award interest.
(19) Arbitral Tribunal is the creature of the statute, and while
exercising jurisdiction under the Act, 1996, the Arbitral Tribunal
erred in awarding interest as per the MSMED Act, 2006.
In support of his contentions on claim No. 14, learned Senior
Counsel places reliance on the following judgments:
(1) In Union of India v. Ambica Construction8 ;
(2) In Sri. Chittaranjan Maity v. Union of India9 ;
(20) The Arbitral Tribunal is prohibited under Section 31(7)(a) of the
Act, 1996 read with Clause 28.4 of the General Conditions of
Contract. Once the Arbitral Tribunal is barred under Section 31(7)
(a) of the Act, 1996, read with Clause 28.4 of the General
Conditions of Contract, the Arbitral Tribunal cannot fall back on
the provisions of the MSMED Act, 2006 and the said provision of
law will not confer jurisdiction on the Arbitral Tribunal to award
interest, and Sections 18 and 24 of the MSMED Act, 2006, would
not come to the aid of the appellant herein.
(21) Alternatively, it is the submission of Sri. V. Ravinder Rao,
learned Senior Counsel that the benefit of Section 15 of the
MSMED Act, 2006, is available only to the goods supplied by the
contractors and the services rendered to the buyer, but not for
contractual works.
(22) The violation of the orders of the Constitutional Courts are
required to be treated as the decisions taken against the public
policy (Referring Associate Builders v. Delhi Development
Authority's case reported in (2015) 3 SCC 49).
7. Submissions and contentions of S/Sri P.V. Krishnaiah and
M. Ramdas, learned counsel for respondents:
(1) The Award passed by the learned Arbitral Tribunal and the order
passed by the learned Special Judge under Section 34 of the Act,
1996, are strictly in accordance with the provisions of the said
legislation and that there are no errors, nor there exists any
infirmities, in the impugned order of the learned Special Judge, as
such, the same does not warrant any interference of this Court
under Section 37 of the Arbitration and Concilliation Act, 1996.
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 6 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
(2) The jurisdiction of the Courts is limited only to the extent of the
grounds set out in sub-section (2) of Section 34 of the Act, 1996
and in the instant case, there are no such grounds existing.
(3) Award of the Arbitral Tribunal cannot be impeached unless the
same is contrary to the provisions of the Act, 1996, and the terms
of the contract and the said contingencies are conspicuously
absent in the case on hand.
(4) At no point of time, respondent No. 1-contractor failed in
fulfilling the obligations and the delay in executing the contractual
work was due to the attitude of the appellant and not due to the
conduct of respondent No. 1-contractor.
(5) The grounds now sought to be pressed into service by the
learned counsel for the appellant were neither raised before the
Arbitral Tribunal nor before the Special Court nor before this Court
in the Memorandum of Grounds of Appeal, as such, the same do
not warrant any consideration by this Court.
(6) The findings of the team of Arbitrators, in the absence of any
person with judicial knowledge, are not fatal to the Award in view
of law laid down by the Hon'ble Supreme Court and in the instant
case, the First Arbitrator was appointed by the contractor and
second Arbitrator by the appellant, who in turn jointly elected the
third Arbitrator.
Learned counsel takes the support of the following judgments in
support of the submissions:
(1) Municipal Corporation of Delhi v. M/s. Jagan Nath Ashok
Kumar10
(2) P.R. Shah, Shares and Stock Brokers Private Limited v. B.H.H.
Securities Private Limited11
(7) In the absence of any fault on the part of any contractor, the
prohibition contained in Clause 19.1 cannot be applied for denying
the claims 5 and 8.
(8) The decision in Kailash Nath Associates v. Delhi Development
Authority (3 supra) is applicable only in the cases where there is
breach of contract and since there is no breach of contract
committed by the contractor, the said decision cannot be made
applicable.
(9) Learned counsel places reliance on a decision in Associate
Builders v. Delhi Development Authority case (1 supra), to sustain
the Award on claims 5 and 8.
(10) The contention as regards the liquidated damages was not
raised before all the lower fora nor raised in the Memorandum of
Grounds of Appeal in the present appeal, as such, the same
cannot be raised now orally for the first time during the course of
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 7 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
arguments.
(11) As per the appellant, claims 5 and 8 are also contrary to law,
but the same cannot be sustained and when there is a delay on
the part of the appellant, clause 18.4 of the General Conditions of
Contract would not come to the rescue of the appellant herein.
Learned counsel places reliance on the judgment in Central Bank
of India v. Virudhunagar Steel Rolling Mills Limited12 .
(12) In view of Clause 17.1 of the Special Conditions of Contract and
Clause 26.3 of the General Conditions of Contract, contentions of
the learned counsel for the appellant as regards claims 4 and 7
are not sustainable and he relies on a decision of the Hon'ble
Supreme Court in Kalpraj Dharamshi v. Kotak Investment
Advisors Ltd.13
(13) The contention of the learned counsel for the appellant as
regards the claim-14 cannot be sustained in view of the law laid
down by the Bombay in Steel Authority of India Ltd. v. Micro,
Small Enterprise Facilitation Council, through Joint Director of
Industries, Nagpur Region, Nagpur14 .
8. Both the learned counsel have filed written arguments also.
9. In the above background, now, the issues which this Court is
called upon to answer in the present Commercial Court Appeal are:—
(1) Whether the order of the learned Special Judge, confirming the
award passed by the Arbitral Tribunal is in accordance with the
provisions of the Arbitration and Concilliation Act, 1996, the
Indian Contract, 1872 and the Micro, Small and Medium
Enterprises Development Act, 2006 and whether the contentions
of the learned counsel for the appellant as regards claims 5 and 8
are sustainable and tenable?
(2) Whether the findings of the learned Arbitral Tribunal, as
confirmed by the learned Special Judge, on claims 4 and 7
warrant any interference of this Court under Section 37 of the
Arbitration and Concilliation Act, 1996?
(3) Whether the Arbitral Tribunal is justified in granting relief
covered by claim No. 13?
(4) Whether the Arbitral Tribunal and the Special Judge are justified
in granting interest to the respondent-contractor on claim No. 14
in view of the conditions of contract and Whether the Tribunal and
the Special Court are justified in invoking the provisions of the
Micro, Small and Medium Enterprises Development Act, 2006?
10. Anterior to the process of examining, analyzing and adjudicating
various issues that have cropped up in the present Commercial Court
Appeal, it may be highly essential and apposite to refer to the
provisions of Section 34 of the Arbitration and Concilliation Act, 1996,
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 8 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
labourers
3. Release of 34,90,000- 34,90,000- Not granted
Performance 00 00
guarantee
bond
submitted by
the Claimant
in lieu of
security
deposit under
provision of
SSI
4. Payment 1,19,30,185 79,27,943- Granted
towards -73 00
expenditure in
executing 12
Nos. of extra
items
5. Delay in issue 68,25,022- 40,95,013- Granted
of drawings, 00 00
materials and
nonavailability
of fronts
6. Change in 96,84,406- Rejected Not granted
specification 00 the claim
7. Fixing of 44,00,714- 23,30,236- Granted
higher BOQ 48 00
rates for the
additional
scope of work
for JH44A to
JH49A
8. Revision of bill 54,83,000- 36,49,047- Granted
of quantities 00 00
(BOQ) rates to
increase all
input costs for
the period
beyond
original
schedule date
of completion.
9. Semi 8,93,279- 6,14,457- Granted
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 11 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
Fabrication of 00 00
steel
structures
lying at the
site
10. Collection, 15,29,545- 13,33,247- Granted
transportation, 00 00
stocking, etc.,
of steel drawn
from VSP.
11. Additional 5,08,000- 4,16,000- Granted
expenditure 00 00
met by
engaging
higher
capacity
traitors 30
TON instead of
originally
engaged 20
Ton
12. Additional 25,62,500- Claim Not granted
expenditure 00 rejected by
for engaging Arbitral
heavy cranes Tribunal
13. Additional 4,15,000- 3,81,800- Granted
expenditure 00 00
for
development
of fabrication
site
14. Payment of As per @ 20.25% --
interest as per MSMED Act, at monthly
Government 2006 rates i.e., 3
norms from times of
time to time Banks rate
SSI (MSME) of 6.75% as
units as all the published
claims from by RBI on
the date of 09.12.2016
eligibility till vide
the actual Annexure 8
date of at Page 207
payment as in line with
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 12 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
“Clause 23.1: Prices or the Rates for the Work stipulated in the
Contract, shall remain firm and binding during the Contract Period
subject to the variations stipulated in the Special Conditions of the
Contract.”
21. Clause 15.0 of the General Conditions of Contract reads as
under:
“Clause 15.0 : Price Variation:
Clause 15.1: The price variation on accepted rates of the Bill of
Quantities will be permissible to the extent given in Annexure-4
enclosed. The rates quoted by the Tenderer shall be inclusive of all
taxes, levies, duties, etc., but exclusive of Service tax and Education
Cess thereon prevailing on the date of opening of Envelop-2.
Clause 15.2: During tenure of the Contract, if any new taxes,
duties/levies, etc., are imposed or tax rates undergo changes as
notified by the Govt. and become applicable to the subject works,
the same shall be reimbursed by the Employer on production of
documentary evidence in respect of payment of the same. Benefits
accruing to the Contractor on account of withdrawal/reduction in any
existing taxes and duties, the same shall be passed on to the
Employer.
Clause 15.3: The variations due to 15.1 and 15.2 above shall not
be permissible during the extended period of contract, if the delay is
attributable to the Contractor.”
22. Annexure-4 of the Special Conditions of Contract which deals
with Price Variation Formula reads as follows:
“ANNEXURE-4
(As per Clause No. 15.0 of Special Conditions of
Contract)
PRICE VARIATION FORMULA
The following clause relating to variation in wages shall be
applicable. No other claim on account of any other variation either
statutory or otherwise shall be applicable.
(CLARIFICATION : In case of revision of rates of materials, wages
& POL prices with effect from any date in a month say March, 2006.
The work done with effect from subsequent month (i.e., April, 2006)
only will qualify for price variation as per the above formula.)
1.0. PRICE VARIATION DUE TO LABOUR:
1.1 Price variation on account of wages for fabrication of steel
structures/pipe work:
For every rupee per month of 208 hours by which the wage
structure of minimum rates workers varied from the base month as a
result of Government action (direct or indirect), adjudication
(legislative or otherwise), the selling price, exclusive of escalation
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 16 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
claims shall be adjusted by Rs. 2.0 (Rupees two only) per tonne and
such adjustment shall be applied to such selling prices in respect of
structures inspected and accepted after the first day of the
subsequent month of such wage revision.
i) For the purpose of this order, the base date shall be the date of
opening of the Envelope-2.
For the purpose of this clause the wage structure of minimum
rated workers shall be defined as comprising:
1) Average of minimum rates of monthly wages of skilled, semi-
skilled & unskilled workers applicable for the area of work as
notified by the Commissioner of Labour, Andhra Pradesh,
Hyderabad published in the Andhra Pradesh Gazette.
2) Leave with pay. 3)Provident Fund
4) Employees State Insurance Contribution.
1.2 Escalation for erection in the composite rate of fabrication and
erection:
For the purpose of calculating the price variation for erection
work, the erection cost component in the awarded composite rates
of fabrication and erection shall be taken as 30% of the relevant
items. Against this 30% value, representing the erection cost, the
labour component in the erection cost shall be taken as 40%. On
this basis, the payable/deductible price variation towards erection
shall be computed as per the following formula:
V = W × 0.40 × 0.3 (X-X0)/XO
Where
V = Escalation or de-escalation payable or deductable.
W = Value of the work done based on the accepted composite
rates of the Bill of Quantities for the period for which variation is
applicable.
RASHTRIYA ISPAT NIGAM LIMITED
X = Average of revised minimum rates of wages of skilled, semi-
skilled and un-skilled workers applicable for the area of site of work
as per minimum rates of wages as notified by Commissioner of
Labour, Andhra Pradesh, Hyderabad, published in the Andhra
Pradesh Gazette for the period under consideration.
XO = Average of minimum rates of wages of skilled, semi-skilled
and unskilled workers on the base date (.e., the date of opening of
the Envelope-2) applicable for the area of site of work as per
minimum rates of wages as notified by Commissioner of Labour,
Andhra Pradesh, Hyderabad, published in the Andhra Pradesh
Gazette.
1.3 Labour escalation on Erection/Installation (without cost of
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 17 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
knew when they made the contract, to be likely to result from the
breach.” (At page 526, 527) Section 74 declares the law as to
liability upon breach of contract where compensation is by
agreement of the parties pre-determined, or where there is a
stipulation by way of penalty. But the application of the enactment is
not restricted to cases where the aggrieved party claims relief as a
plaintiff. The section does not confer a special benefit upon any
party; it merely declares the law that notwithstanding any term in
the contract predetermining damages or providing for forfeiture of
any property by way of penalty, the court will award to the party
aggrieved only reasonable compensation not exceeding the amount
named or penalty stipulated. The jurisdiction of the court is not
determined by the accidental circumstance of the party in default
being a plaintiff or a defendant in a suit. Use of the expression “to
receive from the party who has broken the contract” does not
predicate that the jurisdiction of the court to adjust amounts which
have been paid by the party in default cannot be exercised in dealing
with the claim of the party complaining of breach of contract. The
court has to adjudge in every case reasonable compensation to
which the plaintiff is entitled from the defendant on breach of the
contract. Such compensation has to be ascertained having regard to
the conditions existing on the date of the breach.” (At page 530)
35. Similarly, in Maula Bux v. Union of India (UOI), (1969) 2 SCC
554 : (1970) 1 SCR 928, it was held:
“Forfeiture of earnest money under a contract for sale of
property-movable or immovable-if the amount is reasonable, does
not fall within Section 74. That has been decided in several
cases : Kunwar Chiranjit Singh v. Har Swarup, AIR 1926 PC 1;
Roshan Lal v. The Delhi Cloth and General Mills Company Ltd.,
Delhi, I.L.R. All. 166; Muhammad Habibullah v. Muhammad Shafi,
I.L.R. All. 324; Bishan Chand v. Radha Kishan Das, I.D. 19 All.
49. These cases are easily explained, for forfeiture of a reasonable
amount paid as earnest money does not amount to imposing a
penalty. But if forfeiture is of the nature of penalty, Section 74
applies. Where under the terms of the contract the party in breach
has undertaken to pay a sum of money or to forfeit a sum of
money which he has already paid to the party complaining of a
breach of contract, the undertaking is of the nature of a penalty.
Counsel for the Union, however, urged that in the present case
Rs. 10,000/- in respect of the potato contract and Rs. 8,500 in
respect of the poultry contract were genuine pre-estimates of
damages which the Union was likely to suffer as a result of breach
of contract, and the plaintiff was not entitled to any relief against
forfeiture. Reliance in support of this contention was placed upon
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 25 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
of the Indian Contract Act and the ratio laid down in Fateh Chand
case [AIR 1963 SC 140 : (1964) 1 SCR 515 at p. 526] wherein it
is specifically held that jurisdiction of the court to award
compensation in case of breach of contract is unqualified except
as to the maximum stipulated; and compensation has to be
reasonable. Under Section 73, when a contract has been broken,
the party who suffers by such breach is entitled to receive
compensation for any loss caused to him which the parties knew
when they made the contract to be likely to result from the breach
of it. This section is to be read with Section 74, which deals with
penalty stipulated in the contract, inter alia (relevant for the
present case) provides that when a contract has been broken, if a
sum is named in the contract as the amount to be paid in case of
such breach, the party complaining of breach is entitled, whether
or not actual loss is proved to have been caused, thereby to
receive from the party who has broken the contract reasonable
compensation not exceeding the amount so named. Section 74
emphasizes that in case of breach of contract, the party
complaining of the breach is entitled to receive reasonable
compensation whether or not actual loss is proved to have been
caused by such breach. Therefore, the emphasis is on reasonable
compensation. If the compensation named in the contract is by
way of penalty, consideration would be different and the party is
only entitled to reasonable compensation for the loss suffered. But
if the compensation named in the contract for such breach is
genuine pre-estimate of loss which the parties knew when they
made the contract to be likely to result from the breach of it,
there is no question of proving such loss or such party is not
required to lead evidence to prove actual loss suffered by him.
67 …….. In our view, in such a contract, it would be difficult to
prove exact loss or damage which the parties suffer because of
the breach thereof. In such a situation, if the parties have pre-
estimated such loss after clear understanding, it would be totally
unjustified to arrive at the conclusion that the party who has
committed breach of the contract is not liable to pay
compensation. It would be against the specific provisions of
Sections 73 and 74 of the Indian Contract Act. There was nothing
on record that compensation contemplated by the parties was in
any way unreasonable. It has been specifically mentioned that it
was an agreed genuine pre-estimate of damages duly agreed by
the parties. It was also mentioned that the liquidated damages
are not by way of penalty. It was also provided in the contract
that such damages are to be recovered by the purchaser from the
bills for payment of the cost of material submitted by the
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 28 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
money and (2) that forfeiture of earnest money can be legal only if
the amount is considered reasonable. (at page 133). Both questions
were answered against the appellant. In deciding question two
against the appellant, this Court held:—
“But, as we have already mentioned, we do not propose to go
into those aspects in the case on hand. As mentioned earlier, the
appellants never raised any contention that the forfeiture of the
amount amounted to a penalty or that the amount forfeited is so
large that the forfeiture is bad in law. Nor have they raised any
contention that the amount of deposit is so unreasonable and
therefore forfeiture of the entire amount is not justified. The
decision in Maula Bux's, (1969) 2 SCC 554 : (1970) 1 SCR 928
had no occasion to consider the question of reasonableness or
otherwise of the earnest deposit being forfeited. Because, from
the said judgment it is clear that this Court did not agree with the
view of the High Court that the deposits made, and which were
under consideration, were paid as earnest money. It is under
those circumstances that this Court proceeded to consider the
applicability of Section 74 of the Contract Act. (At page 143)”
40. From the above, it is clear that this Court held that Maula
Bux's case was not, on facts, a case that related to earnest money.
Consequently, the observation in Maula Bux that forfeiture of earnest
money under a contract if reasonable does not fall within Section 74,
and would fall within Section 74 only if earnest money is considered
a penalty is not on a matter that directly arose for decision in that
case. The law laid down by a Bench of 5 Judges in Fateh Chand's
case is that all stipulations naming amounts to be paid in case of
breach would be covered by Section 74. This is because Section 74
cuts across the rules of the English Common Law by enacting a
uniform principle that would apply to all amounts to be paid in case
of breach, whether they are in the nature of penalty or otherwise. It
must not be forgotten that as has been stated above, forfeiture of
earnest money on the facts in Fateh Chand's case was conceded. In
the circumstances, it would therefore be correct to say that as
earnest money is an amount to be paid in case of breach of contract
and named in the contract as such, it would necessarily be covered
by Section 74.
41. It must, however, be pointed out that in cases where a public
auction is held, forfeiture of earnest money may take place even
before an agreement is reached, as DDA is to accept the bid only
after the earnest money is paid. In the present case, under the
terms and conditions of auction, the highest bid (along with which
earnest money has to be paid) may well have been rejected. In such
cases, Section 74 may not be attracted on its plain language
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 30 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
and shall certify what amount (if any) had at the time of such entry
and expulsion been reasonably earned by or would reasonably accrue
to the Contractor in respect of work then actually done by him under
the Contract and what was the value of any unused or partially used
materials, any Constructional plant and Temporary works which have
been deemed to become the property of the Employer Under Clause
No. 9.29 herein above upon the Site.”
37. In support of his contentions and submissions, learned Senior
Counsel appearing for the appellant seeks to place reliance on the
judgment of the Hon'ble Apex Court in the case of Mitra Guha Builders
(India) Company v. Oil and Natural Gas Corporation Limited (7 supra).
In the said judgment, paragraphs 16 to 29 read as under:
“16. In order to appreciate the claim of ONGC in levying the
damages in terms of Clause 2, it is necessary to refer to Clause 2 of
the agreement which reads as under:—
“Clause 2 : Compensation for Delay The time allowed for
carrying out the work as entered in the tender shall be strictly
observed by the contractor and shall be deemed to be the essence
of the contract on the part of the contractor and shall be reckoned
from the 15th day after the date on which the order to commence
the work is issued to the contractor. The work shall throughout
the stipulated period of the contract be proceeded with all due
diligence and the contractor shall pay compensation on amount
equal to½ % per week as the Superintending Engineer (whose
decision in writing shall be final) may decide on the amount of the
contract, value of the whole work as shown in the agreement, for
every week that the work remains uncommenced, or unfinished,
after the proper dates. After further to ensure good progress
during the execution of the work, the contractor shall be bound in
all cases in which the time allowed for any work exceeds, one
month (save the special jobs) to complete one-eighth of the work,
before one-fourth of the whole time allowed under the contract
has elapsed and three-eights of the work, before one-half of such
time has elapsed, and three-fourth of such time has elapsed.
However, for special jobs if a time schedule has been submitted
by the contractor and the same has been accepted by the
Engineer-in-Charge, the Contractor shall comply with the said
time schedule. In the event of the contractor failing to comply
with this condition, he shall be liable to pay as compensation an
amount equal to½ % per week as the Superintending Engineer
(whose decision in writing shall be final) may decide on the said
contract value if the whole work for every week that the due
quantity of works remains incomplete provided always that the
entire amount of compensation to be paid under the provisions of
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 42 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
the clause shall not exceed ten per cent (10%) of the tendered
cost of the work as shown in the tender.”
[Emphasis added]
17. A reading of Clause 2 makes it clear that the Superintending
Engineer has been conferred with not only a right to levy
compensation; but it also provides a mechanism for determination of
the liability/quantum of compensation. The very Clause 2 itself
would show that such a decision taken by the Superintending
Engineer shall be final. The finality clause in the contract in terms of
Clause 2 makes the intention of the parties very clear that there
cannot be any further dispute on the said issue between the parties;
much less before the arbitrator.
18. Clause 25 of the agreement - Settlement of disputes by
Arbitration, reads as under:—
“Clause 25 - Settlement of disputes by Arbitration If any
dispute, difference, question or disagreement shall, at any time,
hereafter arises between the parties hereto or the respective
representatives or assigns in connection with or arising out of the
contract, or in respect of meaning of specifications, design,
drawings, estimates, scheduled, annexures, orders, instructions,
the construction, interpretation of this agreement, application of
provisions thereof or anything hereunder containing or arising
hereunder or as to rights, liabilities or duties of the said parties
hereunder or arising hereunder any matter whatsoever incidental
to this contract or otherwise concerning the works of execution or
failure to execute the same whether during the progress of work
or stipulated/extended period or before or after the completion or
abandonment thereof shall be referred to the sole arbitration of
the person appointed by a Director of ONGC Ltd. at the time of
dispute. There will be no objection to any such appointment that
the arbitrator so appointed is an employee of ONGC Ltd. or that he
had to deal with the matters to which the contract relates and
that in the course of this duties as ONGC Ltd. employees, lie had
expressed views on all or any of the matters in dispute or
difference. If the arbitrator to whom the matter is originally
referred dies or refuses to act or resigns for any reason from the
position of arbitrator, it shall be lawful for the Director of ONGC
Ltd. to appoint another person to act as arbitrator in the manner
aforesaid. Such person shall be entitled to proceed with the
reference from the stage at which it was left by his predecessor if
both the parties consent to this effect, failing which the arbitrator
will be entitled to proceed de-novo. ………..
It is also a term of the contract that if the contractor(s)
do/does not make any demand for arbitration in respect of any
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 43 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
agreement.
………..
Quantification of liquidated damages may be an excepted
matter as argued by the appellants, under Clause 16.2, but for
the levy of liquidated damages, there has to be a delay in the first
place. In the present case, there is a clear dispute as to the fact
that whether there was any delay on the part of the respondent.
For this reason, it cannot be accepted that the appointment of the
arbitrator by the High Court was unwarranted in this case. Even if
the quantification was excepted as argued by the appellants
under Clause 16.2, this will only have effect when the dispute as
to the delay is ascertained. Clause 16.2 cannot be treated as an
excepted matter because of the fact that it does not provide for
any adjudicatory process for decision on a question, dispute or
difference, which is the condition precedent to lead to the stage of
quantification of damages.”
29. In BSNL's case, Clause 16 provided for entitlement of the
party to recover liquidated damages. In Clause 16(2), the phrases
used “value of delayed quantity” and “for each week of delay” clearly
show that it is necessary to find out whether there has been delay on
the part of the supplier in discharging his obligation. Thus, in BSNL's
case, in determining whether there is delay or not, a process of
adjudication is envisaged. Per contra, in the present case, Clause 2
of the agreement is a complete mechanism for determination of
liability. The right to levy damages for delay is exclusively conferred
upon the Superintending Engineer and Clause 2 of the present
agreement is a complete mechanism for determination of liability
and when such compensation is levied by the Superintending
Engineer, the same is final and binding. The parties have also
consciously agreed that for the delay caused, the Superintending
Engineer shall levy the compensation of the amount equal to half per
cent and the said amount shall not exceed from 10% of the cost of
the work and the determination by the Superintending Engineer is
final and cannot be the subject matter of arbitration. In claim No. 6,
the prayer sought for by the contractor to declare the compensation
levied by the Superintending Engineer as illegal is contradictory to
the agreed terms between the parties. So far as the liquidated
damages determined and levied, by virtue of Clause 2, is out of the
purview of the arbitration especially in view of the fact that under
the very same clause, the parties have agreed that the decision of
the Superintending Engineer shall be final.”
38. With due respect to the judgment of the Hon'ble Apex Court, in
the contract, which fell for consideration before the Hon'ble Supreme
Court in the above-referred judgment, there was a clause in the
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 49 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
contractor was not responsible for the delay and the delay occurred
only on account of the omissions and commissions on the part of the
respondents, it follows that provisions which make the decision of
the Superintending Engineer or the Engineer-in-Charge final and
conclusive, will be irrelevant. Therefore, the Arbitrator would have
jurisdiction to try and decide all the claims of the contractor as also
the claims of the respondents. Consequently, the award of the
Arbitrator on items 1, 3 and 11 has to be upheld and the conclusion
of the High Court that award in respect of those claims had to be set
aside as they related to excepted matters, cannot be sustained.
Re : Question (ii)
24. The arbitrator had considered and dealt with claims (1), (2,
4 and 5), (6), (7 and 8), (9) and (11) separately and distinctly.
The High Court found that the award in regard to items 1, 3, 5
and 11 were liable to be set aside. The High Court did not find any
error in regard to the awards on claims 2, 4, 6, 7, 8 and 9, but
nevertheless chose to set aside the award in regard to these six
items, only on the ground that in the event of counter claims 1 to
4 were to be allowed by the arbitrator on reconsideration, the
respondents would have been entitled to adjust the amounts
awarded in regard to claims 2, 4, 6, 7, 8 and 9 towards the
amounts that may be awarded in respect of counter claims 1 to 4;
and that as the award on counter claims 1 to 4 was set aside by it
and remanded for fresh decision, the award in regard to claim
Nos. 2, 4, 6, 7, 8 and 9 were also liable to be set aside.”
40. In Bharat Sanchar Nigam Limited v. Motorola India Private
Limited17 , it is held thus : (paragraphs 5, 9, 18, 23 and 32).
“It is the case of the appellants that the respondent had failed to
complete phase I and phase II of the project within the schedule as
provided in the tender document, and therefore, liquidated damages
were imposed by the Tamil Nadu Circle of the appellant on 21st of
May, 2004 under clause 16.2 of the tender document, quantification
of which was beyond the purview of the arbitration agreement.
…
The High Court, as noted herein earlier, by the impugned
judgment allowed the arbitration request of the respondents holding
that the imposition of liquidated damages by the appellant was not
an “excepted matter” and therefore, subject to arbitration. It is this
judgment of the High Court, which is impugned in this appeal, in
respect of which leave has already been granted.
…
We may keep on record that the appellants alleged that
respondents had not completed phase I and phase II of the project
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 52 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
fabrication site to the extent possible as the allotted fabricated site area
was slushy pond. Claim amount : Rs. 4,15,000/- (+) service tax and
interest.
44. Against the abovesaid claim, the Arbitral Tribunal granted Rs.
3,81,800/-. The essence of the stance of the learned Senior Counsel
appearing for the appellant as regards this claim is that in view of
Clause 9.3 of the General Conditions of Contract, respondent No. 1 is
not entitled for any amount under this head. In this connection, it
would be apposite to refer to the said clause No. 9.3 of the General
Conditions of Contract, which reads as follows:
“Clause No. 9.3 : Inspection of Site: The Contractor shall visit,
inspect and examine the Site and its surroundings and shall satisfy
himself before submitting the Tender as to the various facilities
available at the Site for the receipt storage and custody of the
materials, as to the nature of the ground and sub-soils (as far as it is
practicable) the form and nature of the Site, the conditions, the
quantities and nature of the work and materials, facilities necessary
for transportation, erection, testing and other works and the means
of access to the Site, the accommodation and other facilities that
may be required and, in general, shall himself obtain all necessary
information as to the working conditions, risk, contingencies and
other circumstances which may influence or affect his Tender. The
Tenderer shall note that no claim on this ground will be admissible.”
45. The learned Arbitral Tribunal, while dealing with this claim, took
into consideration the obligation on the part of the employer to make
available the land, free of charge, within and/or near the employer's
work site for the contractor to put up stores, site fabrication yard,
office, etc. as required for execution of the contract. The Tribunal also
took into consideration the photographs depicting the site conditions
and found that it was not possible to be used for keeping the raw
material, for carrying out fabrication and stacking fabricated structures,
and found further that movement of heavy cranes was impossible and it
was difficult event to walk. Having regard to the findings of the learned
Arbitral Tribunal, on factual situations, in the absence of any patent
illegality, this Court is not inclined to meddle with the Award rendered
by the learned Arbitral Tribunal, as confirmed by the learned Special
Judge.
46. Finding on claim No. 14 : The sum and substance of the case
of the appellant as regards this claim is that in view of Clause 28.4 of
the General Conditions of Contract read with Section 31(7)(a) of the
Arbitration and Concilliation Act, 1996, the Arbitral Tribunal has no
jurisdiction to award the interest. It is also the submission of the
learned counsel for the appellant that the Arbitral Tribunal grossly erred
in granting interest under the provisions of the MSMED Act, 2006 and
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 54 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
the said Act cannot be pressed into service and the Arbitral Tribunal
being creature of the statute i.e. the 1996 Act, it cannot usurp the
jurisdiction of the Facilitation Council as per the MSMED Act, 2006. In
this context, it may be appropriate to refer Clause 28.4 of the General
Conditions of Contract.
“Clause 28.4: No interest shall be awarded by the Arbitrator in
any Arbitration proceedings.”
47. In order to adjudicate claim No. 14, it would also be appropriate
to refer to the provisions of the Micro, Small and Medium Enterprises
Development Act, 2006. The said legislation, enacted by the
Parliament, came into force on 18.07.2006, and the Parliament brought
the said legislation to provide for facilitating the promotion and
development and enhancing the competitiveness of micro, small and
medium enterprises and the matters connected therewith or incidental
thereto. Section 2(d) and (n) of the Act, 2006 define the terms ‘buyer’
and ‘supplier’ and the said provisions of law read as follows:
“Section 2(d):“Buyer” means whoever buys any goods or receives
any services from a supplier for consideration.
Section 2(n):“Supplier” means a micro or small enterprise, which
has filed a memorandum with the authority referred to in sub-
section (1) of section 8, and includes,-
(i) the National Small Industries Corporation, being a company,
registered under the Companies Act, 1956 (1 of 1956);
(ii) the Small Industries Development Corporation of a State or a
Union territory, by whatever name called, being a company
registered under the Companies Act, 1956 (1 of 1956);
(iii) any company, co-operative society, trust or a body, by
whatever name called, registered or constituted under any law
for the time being in force and engaged in selling goods
produced by micro or small enterprises and rendering services
which are provided by such enterprises;”
48. Sections 15 to 18 of the said enactment read as under:
“Section 15 : Liability of buyer to make payment.- Where any
supplier supplies any goods or renders any services to any buyer, the
buyer shall make payment therefor on or before the date agreed
upon between him and the supplier in writing or, where there is no
agreement in this behalf, before the appointed day : Provided that in
no case the period agreed upon between the supplier and the buyer
in writing shall exceed forty-five days from the day of acceptance or
the day of deemed acceptance.
Section 16 : Date from which and rate at which interest is
payable.-Where any buyer fails to make payment of the amount to
the supplier, as required under section 15, the buyer shall,
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 55 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
Chandra (supra) this Court interpreted the clause 1.9 which provided
that no claim for interest or damages will be entertained by the
Government in respect to any moneys or balances which may be
lying with the Government. It was held that there was no provision
which could be culled out against the contractor not to claim interest
by way of damages before the arbitrator on the relevant items placed
for adjudication. In Ferro Concrete Construction (P) Ltd. (supra) this
Court considered clause 4 containing a stipulation that no interest
was payable on amount withheld under the agreement. It was held
that clause 4 dealt with rates, material and workmanship did not bar
award of interest by the arbitrator on claims of the contractor made
in the said case. In Sayeed Ahmed (supra) this Court has
emphasized that award of interest would depend upon nature of the
clause in the agreement. In Bright Power Projects (India) Pvt. Ltd.
(supra) this Court has considered the expression “unless otherwise
agreed by parties” employed in section 31(7)(a) of the Act of 1996
and laid down that in case contract bars claim of interest contractor
could not have claimed interest. The provision of section 31(7)(a) of
the Act of 1996 is binding upon the arbitrator. In Sree Kamatchi
Amman Constructions (supra) similar view has been taken.”
(b) In Sri. Chittaranjan Maity v. Union of India (9 supra), it is held as
follows : (paragraphs 14 to 20).
“14. The total interest awarded by the Arbitral Tribunal is Rs.
12,44,546/- which includes interest for the pre-reference period and
also pendente lite interest. Section 31(7)(a) of the 1996 Act
provides for payment of interest, as under:
“31(7)(a) - Unless otherwise agreed by the parties, where and
insofar as an arbitral award is for the payment of money, the
arbitral tribunal may include in the sum for which the award is
made interest, at such rate as it deems reasonable, on the whole
or any part of the money, for the whole or any part of the period
between the date on which the cause of action arose and the date
on which the award is made.” In this Section, a specific provision
has been created, whereby if the agreement prohibits award of
interest for the pre-award period (i.e. pre-reference and pendente
lite period), the Arbitrator cannot award interest for the said
period.
15. Admittedly, the GCC, governing the contract between the
parties, contains a clause which bars the payment of interest, which
is as under:
“16(2) - No interest will be payable upon the earnest money or
the security deposit or amounts payable to the contractor under
the contract, but government securities deposit in terms of sub-
clause (1) of this clause will be repayable (with) interest accrued
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 61 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
thereon.”
16. Relying on a decision of this Court in M/s. Ambica
Construction v. Union of India 2017 SCC OnLine SC 678, (C.A. No.
410 of 2008, disposed of on 26.04.2017) learned senior counsel for
the appellant submits that mere bar to award interest on the
amounts payable under the contract would not be sufficient to deny
payment on pendente lite interest. Therefore, the Arbitrator was
justified in awarding the pendente lite interest. However, it is not
clear from M/s. Ambica Construction (supra) as to whether it was
decided under The Arbitration Act, 1940 (for short ‘the 1940 Act’) or
under the 1996 Act. It has relied on a judgment of Constitution
Bench in Secretary, Irrigation Department, Government of Orissa v.
G.C. Roy (1992) 1 SCC 508. This judgment was with reference to the
1940 Act. In the 1940 Act, there was no provision which prohibited
the Arbitrator from awarding interest for the pre-reference, pendente
lite or post award period, whereas the 1996 Act contains a specific
provision which says that if the agreement prohibits award of
interest for the pre-award period, the Arbitrator cannot award
interest for the said period. Therefore, the decision in M/s. Ambica
Construction (supra) cannot be made applicable to the instant case.
17. Learned Additional Solicitor General appearing for the
respondent submits that the position of law for cases covered under
the 1996 Act, i.e. if agreement prohibits award of interest then the
grant of pre-award interest is impermissible for the Arbitrator, has
been reiterated by this Court in various judgments.
18. In Sayeed Ahmed and Company v. State of Uttar Pradesh
(2009) 12 SCC 26, this Court noted that the 1940 Act did not
contain any provision relating to the power of the Arbitrator to award
interest. However, now a specific provision has been created under
Section 31(7)(a) of the 1996 Act. As per this Section, if the
agreement bars payment of interest, the Arbitrator cannot award
interest from the date of cause of action till the date of award. The
Court has observed that in regard to the provision in the 1996 Act,
the difference between pre-reference period and the pendente lite
interest has disappeared insofar as award of interest by the
Arbitrator is concerned. Section 31(7)(a) recognizes only two
periods, i.e. pre-award and post-award period.
19. In Sree Kamatchi Amman Constructions v. Divisional Railway
Manager (Works), Palghat (2010) 8 SCC 767, this Court was dealing
with an identical case wherein Clause 16 of the GCC of Railways had
required interpretation. This is the same Clause 16(2) of the GCC
prohibiting grant of interest which is also applicable in the facts of
the present case. The Court held that where the parties had agreed
that the interest shall not be payable, the Arbitral Tribunal cannot
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 62 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
award interest between the date on which the cause of action arose
to the date of the award.
20.In Union of India v. Bright Power Projects (India) Private
Limited (2015) 9 SCC 695, a three-Judge Bench of this Court, after
referring to the provisions of Section 31(7)(a) of the 1996 Act, held
that when the terms of the agreement had prohibited award of
interest, the Arbitrator could not award interest for the pendente lite
period. It has been held thus:
“10. Thus, it had been specifically understood between the
parties that no interest was to be paid on the earnest money,
security deposit and the amount payable to the contractor under
the contract. So far as payment of interest on government
securities, which had been deposited by the respondent contractor
with the appellant is concerned, it was specifically stated that the
said amount was to be returned to the contractor along with
interest accrued thereon, but so far as payment of interest on the
amount payable to the contractor under the contract was
concerned, there was a specific term that no interest was to be
paid thereon.
11. When parties to the contract had agreed to the fact that
interest would not be awarded on the amount payable to the
contractor under the contract, in our opinion, they were bound by
their understanding. Having once agreed that the contractor
would not claim any interest on the amount to be paid under the
contract, he could not have claimed interest either before a civil
court or before an Arbitral Tribunal.” Therefore, it is clear that the
appellant is not entitled for any interest on the amount awarded
by the Arbitral Tribunal.”
53. Accordingly, this point as regards claim No. 14 is answered in
favour of the appellant and against respondent No. 1.
54. Yet another contention of the learned Senior Counsel appearing
for the appellant is that the Award stands vitiated as the Tribunal did
not have a person with judicial knowledge. In order to rebut the said
contention, learned counsel for respondent No. 1 places reliance on the
following judgments of the Hon'ble Apex Court:
(a) In Municipal Corporation of Delhi v. M/s. Jagannath Ashok Kumar
(10 supra), wherein it is held thus : (paragraphs 4 and 5).
“4. In this case, there was no violation of any principles of natural
justice. It is not a case where the arbitrator has refused cogent and
material factors to be taken into consideration. The award cannot be
said to be vitiated by non-reception of material or non-consideration
of the relevant aspects of the matter. Appraisement of evidence by
the arbitrator is ordinarily never a matter which the Court questions
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 63 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
and considers. The parties have selected their own forum and the
deciding forum must be conceded the power of appraisement of the
evidence. In the instant case, there was no evidence of violation of
any principle of natural justice. The Arbitrator in our opinion is the
sole judge of the quality as well as quantity of evidence and it will
not be for this Court to take upon itself the task of being a judge of
the evidence before the arbitrator. It may be possible that on the
same evidence the Court might have arrived at a different conclusion
than the one arrived at by the arbitrator but that by it self is no
ground in our view for setting aside the award of an arbitrator.
5. It is familiar learning but requires emphasis that section 1 of
the Evidence Act, 1872 in its rigour is not intended to apply to
proceedings before an arbitrator. P.B. Mukharji, J. as the learned
Chief Justice then was, expressed the above view in Haji Ebrahim
Kassam Cochinwall v. Nothern Indian oil Industries Ltd., AIR 1951
Cal 230 and we are of the opinion that this represents the correct
statement of law on this aspect. Lord Goddard, C.J. in Mediterranean
& Eastern Export Co. Ltd. v. Fortress Fabrics Ltd., (1948) 2 All ER
186 observed at pages 188/189 of the report as follows:
“A man in the trade who is selected for his experience would be
likely to know and indeed to be expected to know the fluctuations
of the market and would have plenty of means of informing
himself or refreshing his memory on any point on which he might
find it necessary so to do. In this case according to the affidavit of
sellers they did take the point before the Arbitrator that the
Southern African market has slumped. Whether the buyers
contested that statement does not appear but an experienced
Arbitrator would know or have the means of knowing whether that
was so or not and to what extent and I see no reason why in
principle he should be required to have evidence on this point any
more than on any other question relating to a particular trade. It
must be taken I think that in fixing the amount that he has, he
has acted on his own knowledge and experience. The day has long
gone by when the Courts looked with jealousy on the jurisdiction
of the Arbitrators. The modern tendency is in my opinion more
especially in commercial arbitrations, to endeavour to uphold
Awards of the skilled persons that the parties themselves have
selected to decide the questions at issue between them. If an
Arbitrator has acted within the terms of his submission and has
not violated any rules of what is so often. called natural justice
the Courts should be slow indeed to set aside his award.””
(b) In P.R. Shah, Shares and Stock Brokers Private Limited v. B.H.H.
Securities Private Limited (11 supra), wherein it is held thus :
(paras 22 and 23)
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 64 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
2
(2019) 5 SCC 341
4
(2011) 1 SCC 394
7
(2020) 3 SCC 222
SCC Online Web Edition, © 2023 EBC Publishing Pvt. Ltd.
Page 65 Sunday, August 13, 2023
Printed For: Mr Raghavan Kadaba
SCC Online Web Edition: http://www.scconline.com
© 2023 EBC Publishing Pvt. Ltd.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
8
(2016) 6 SCC 36
10
(1987) 4 SCC 497
13
2021 SCC OnLine SC 204
16
(2011) 5 SCC 758
Disclaimer: While every effort is made to avoid any mistake or omission, this casenote/ headnote/ judgment/ act/ rule/
regulation/ circular/ notification is being circulated on the condition and understanding that the publisher would not be
liable in any manner by reason of any mistake or omission or for any action taken or omitted to be taken or advice
rendered or accepted on the basis of this casenote/ headnote/ judgment/ act/ rule/ regulation/ circular/ notification. All
disputes will be subject exclusively to jurisdiction of courts, tribunals and forums at Lucknow only. The authenticity of
this text must be verified from the original source.