num desicna unite qte pu

8 couche roulement en bb t 22,656.00 12,000.00


11 glissiere de securite ml 20,000.00 9,000.00
6 couche de base gc m3 40,000.00 3,200.00
12 accottements ml 40,000.00 2,500.00
15 talutatage m2 120,000.00 800.00
5 couche fond tvc m3 48,000.00 1,600.00
4 deblai mise en remblai m3 40,000.00 900.00
7 couche impregnation m2 160,000.00 170.00
1 decapage m3 56,000.00 400.00
2 remblai m3 20,000.00 800.00
3 deblai m3 25,000.00 600.00
13 fosse betonnee ml 2,000.00 7,000.00
14 ouvrage de protection rn gc u 10.00 800,000.00
16 beton armé pour ouvrage m3 100.00 80,000.00
9 signalisation hor m2 9,000.00 700.00
10 signa verticale u 20.00 100,000.00
mt ht % part % total
271,872,000.00 27% 27% 54,374,400.00 13,593,600.00
180,000,000.00 18% 45% 36,000,000.00 9,000,000.00
128,000,000.00 13% 58% 25,600,000.00 6,400,000.00
100,000,000.00 10% 67% 20,000,000.00 5,000,000.00
96,000,000.00 10% 77% 19,200,000.00 4,800,000.00
76,800,000.00 8% 85% 15,360,000.00 3,840,000.00
36,000,000.00 4% 88% 7,200,000.00 1,800,000.00
27,200,000.00 3% 91% 5,440,000.00 1,360,000.00
22,400,000.00 2% 93% 4,480,000.00 1,120,000.00
16,000,000.00 2% 95% 3,200,000.00 800,000.00
15,000,000.00 1% 96% 3,000,000.00 750,000.00
14,000,000.00 1% 98% 2,800,000.00 700,000.00
8,000,000.00 1% 98% 1,600,000.00 400,000.00
8,000,000.00 1% 99% 1,600,000.00 400,000.00
6,300,000.00 1% 100% 1,260,000.00 315,000.00
2,000,000.00 0% 100% 400,000.00 100,000.00
-
-
1,007,572,000.00
201,514,400.00