CURVA "S"

"RECUPERACIÓN DE LA INFRAESTRUCTURA DE LA UGEL RIO TAMBO, UNIDAD EJECUTORA DE EDUCACIÓN N 312, DISTRITO DE RÍO TAMBO –
PROYECTO:
PROVINCIA DE SATIPO - DEPARTAMENTO DE JUNÍN"
PLAZO: 240 dias calendario
FECHA: 9/30/2021

Plazo estimado Cronograma de inversión (Soles)


N° para ejecución MONTO TOTAL ITEM
(meses) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08

1 8 S/ 6,761,004.43 INVERSION S/ 399,006.59 S/ 444,274.54 S/ 1,181,947.02 S/ 1,619,031.67 S/ 1,337,596.15 S/ 753,255.94 S/ 571,553.54 S/ 454,338.98
%ACUMULADO 6.27 % 14.76 % 30.23 % 51.89 % 71.86 % 84.57 % 92.71 % 100.00 %

CURVA "S"
S/ 1,800,000.00 120.00 %

S/ 1,600,000.00
100.00 %
S/ 1,400,000.00

S/ 1,200,000.00 80.00 %

S/ 1,000,000.00
60.00 %
S/ 800,000.00

S/ 600,000.00 40.00 %

S/ 400,000.00
20.00 %
S/ 200,000.00

S/ - 0.00 %
1 2 3 4 5 6 7 8

INVERSION % A C U MU LA D O