A Marble
Labour charges for Marble flooring rates inclusive of Cutting,
laying, Polishing of 8 coats, Adhesive all Chemicals, Man
1 power, lead lift, Machineries, Tools and Tackles and all SqFt 4549.17 130 5,91,392
consumable material to complete the entire scope of work as
per drawing BOQ and instruction of EIC.
Tiles
Labour charges for Floor tile (upto to 1200mm) laying work
rates inclusive of cutting, laying, man power, lead, lift,
5 machineries, tools, tackles, grouting with chemicals all SqFt 1032.57 30 30,977
consumable material as per drawing BOQ and instruction of
EIC.
Labour charges for Floor tile skirting laying work rates
inclusive of cutting, laying, man power, lead, lift, machineries,
6 Rft 276.61 20 5,532
tools, tackles, grouting with chemicals all consumable material
as per drawing BOQ and instruction of EIC.
B Granite
Labour charges for Kitchen granite top including cutting, laying
adhesive all chemicals, man power, lift, lead, machineries,
9 tools and tackles, cutting, chamfering, facia, top skirting and all SqFt 251.88 250 62,969
consumable material to complete the entire scope of work as
per the drawing specification and instruction of EIC.
0
Labour charges for Toilet ledge top laying work, rate including
cutting, laying, chamfering, polishing, adhesive material, man
10 Rft 27.56 75 2,067
power, lead lift, machineries, tools, tackles, all consumable
materials as per drawing specification and instruction of EIC.
Labour charges for Balcony/ Uitlity ledge top laying work, rate
including cutting, laying, chamfering, polishing, adhesive
11 material, man power, lead lift, machineries, tools, tackles, all Rft 121.46 75 9,110
consumable materials as per drawing specification and
instruction of EIC.
SPR
S.No Description Unit Quantity
Rate Amount
C Staircase - Granite
Labour charges for Granite Laying in Staircase tread rates
including Cutting, laying, adhesive Chemicals, man power, lead
12 SqFt 250.33 45 11,265
lift, Machineries, Tools and Tackles and all consumable
material as per drawing specification and instruction of EIC.