Professional Documents
Culture Documents
FPMAPPH Building Siting Assessments
FPMAPPH Building Siting Assessments
Abstract
This appendix gives supplemental guidelines for API RP 752 - Management of
Hazards Associated with Process Plant Buildings. It was developed by CRTC’s
Process Risk Team.
Contents Page
Stage 1
Hazard Identification
Occupancy/Function
Screen
Stage 2
Building Evaluation
Consequence
Modeling
Stage 3
Risk Assessment
Qualitative and/or
Quantitative
hazard criteria are evaluated for occupancy and function. Other buildings are
exempt from further evaluation.
Occupancy data is gathered for each building to determine the peak occupancy load
and the average occupancy level (hrs/wk). Building function is evaluated to deter-
mine if a building must be occupied during an incident for safe shutdown of the
facility or if a building is designated as an emergency response shelter. The occu-
pancy data is then compared against the occupancy/function screening criteria (See
Section H2.3). Buildings that exceed the criteria proceed to Stage 2 - Building Eval-
uation. Buildings that do not meet the criteria are exempt from further evaluation.
Is
building
routinely No
occupied?
See Section H2.1
Yes
Is
there a toxic, No further
fire, or explosion No
evaluation
hazard?
See Section H2.2
Yes
Is occupancy
Yes
> 400 hrs/wk?
See Section H2.3
No
Is peak
Yes occupancy
> 40/one hr?
See Section H2.3
No
Must the
building be
Yes
occupied during
an incident?
See Section H2.3
No
H2.4 Recommendations
Buildings that meet the hazard and occupancy/function criteria proceed to Stage 2
to be evaluated with consequence modeling (for explosion & toxic hazards) or eval-
uated against a checklist of Company design standards (for fire hazards).
Buildings that do not meet the criteria are exempt from further evaluation in the
study. These buildings should be reviewed to ensure that the emergency response
plan addresses the identified hazard, including appropriate notification and evacua-
tion. For example, if a chlorine hazard is identified for a small maintenance
building with one occupant, there is an identified hazard, but low occupancy. This
building would not be subject to Stage 2 consequence modeling, but there should
be an emergency response plan that details how the building occupant would be
alerted in the event of a chlorine leak and the appropriate response. Typical docu-
mentation of Stage 1 findings are shown in Figure H-2.
building is calculated. For fire hazards, the building is evaluated using a checklist of
Company design standards.
Release Scenarios
The release scenarios to be modeled should include a 2 inch hole in any piping
system or equipment identified as having a toxic hazard potential.
Note Exception: the maximum piping size should be used if it is less than 2 inch
Although small flange and seal leaks and small piping breaks (<3/4 inch) are more
likely scenarios, 2 inch releases have occurred within the Company on a yearly
basis. Larger releases from line breaks are extremely rare events and as such, are
not credible scenarios for building design. Potential leak sources should include
underground piping. Atmospheric vents and atmospheric relief valve discharges
should be modeled as well. A range of weather stability and wind speeds should be
modeled for each release point. Often, the most severe scenario involves “F” atmo-
spheric stability and 5 mph winds, conditions that might be found during a calm,
cool night or early morning. Inputs to the dispersion modeling program include:
Recommendations
Results of the dispersion modeling are used to determine the potential maximum
concentration at the buildings studied and the time to reach this concentration,
assuming that the cloud is blowing toward the building. Concentrations are
predicted as 60 minute average values at the building location. If the concentration
is less than the ERPG-1 level, then no mitigation is required. This is the level at
which it is believed that nearly all individuals could be exposed for up to 1 hr
without experiencing other than mild transient adverse health effects or perceiving a
clearly defined objectionable odor. Also included is the time to reach the ERPG-2
level. This is the level at which nearly all individuals could be exposed for up to 1
hr without experiencing or developing irreversible or other serious health effects or
symptoms that could impair their abilities to take protective action. If a building
evacuation will take longer than the time to reach ERPG-2 then, personal protective
equipment will be necessary in order to safely evacuate, or if it will be necessary to
shelter in place. A list of some ERPG levels is included in Figure H-3. A complete
list is available from the American Industrial Hygiene Association. (See Refer-
ences, Section H6.0.)
Physical Explosion
In processes that have the potential for a “runaway reaction,” a vessel rupture
scenario should be modeled to determine potential blast overpressures at affected
buildings. This overpressure due to a vessel rupture (physical explosion) should be
estimated using the calculations described in Section 1200 of the Fire Protection
Manual. The method is very similar to that described above for vapor cloud explo-
sions, except that the energy term is calculated differently.
Recommendations
The response of the affected buildings to an explosion is dependent upon both the
overpressure and the duration of the blast. These values should be compared with
the data from the 1995 WBE Industry Tech Coop reports to determine the predicted
building response. (Software is available from the Process Risk team). Damage
levels are described in Figure H-5 and Figure H-6. Where building damage is
predicted above the 2B level, mitigation measures should be taken to reduce the
risk to occupants. Mitigation measures may also be appropriate for buildings within
the vapor cloud itself (within 100% LFL). Potential mitigation includes:
• Change of function (e.g. designating a different building as the emergency
response center)
• Prevent scenario (e.g. remove walls that produce confinement in the process
areas)
• Upgrade building (e.g. reinforce roof-to-wall connections, strengthen walls -
Contact the Process Risk team for information on cost effective building
upgrade options)
• Relocate the building
• Change the process to eliminate/reduce the risk. (e.g., shutdown the process)
Windows can be expected to fail with high fragment velocities between .15 and .6
psig, depending upon the size of the window and the blast duration. Where the
predicted overpressure falls within this range, the SAFEVUE software can be used
to determine if the window will break. (Contact the CRTC Process Risk team for
information on SAFEVUE.) Windows that are expected to break can be removed or
upgraded to meet the predicted overpressure. The Process Risk team can provide
design details on the application of polyethylene film to the window, which
removes the fragment hazard for blast overpressures of up to 5 psig. New buildings
should use laminated glass designed for the predicted overpressures.
Documentation of typical Stage 2 explosion modeling results are shown in
Figure H-7. Where the mitigation measures are impractical or extremely costly, a
risk assessment is recommended to be completed per Section H4.0.
2. Is there a hydrocarbon detector in the inlet air duct for the building that alarms at 20% LFL and
shuts down the ventilation system at 60% LFL?
3. Is the air intake for the ventilation system located 30 feet above grade?
5. Is there a personnel egress door located on the opposite side of the building from the process
area?
6. Is there a fire water monitor located within 40 -70 ft from the building that can protect the
building from a fire in the process area.
7. Are the roof and wall(s) facing the process area rated for 2 hour fire?
8. Is the surface drainage sloped away from the building toward the process area?
9. Are the drains within the building sealed to prevent vapors from entering the building from the
underground drainage system?
10. Is there an emergency response plan for building occupants that details their response in the
event of a fire?
11. Are annual hypothetical drills held to practice the emergency response plan?
4. Review industry history of incidents in similar systems. (Contact the Fire &
Process Safety Team for information)
5. List the consequences predicted during Stage 2 of the scenario. For damage
level >2B, the consequence is major. For damage level >1, the consequence is
serious.
6. List and critically evaluate the safeguards in place at the facility that could
prevent the scenario from occurring. (e.g. shutdown systems, inspection
programs, safe work practices, control of ignition sources, etc.) Do not list a
program or procedure unless it has been confirmed during the most recent
PSM or Safe Operations audit. Do not list automatic shutdowns unless quar-
terly testing is performed and documented.
7. Use the risk ranking matrix shown in Figure H-9 to assign an overall risk for
the scenario.
8. If the assigned risk is a 1 or 2, then prevention or mitigation is required. If the
assigned risk is a 3, then the team should evaluate whether additional safe-
guards can be added to reduce the risk to a 4 or 5. (e.g. increasing inspection,
improving safe work practices) If the assigned risk is a 4 or 5 then no addi-
tional mitigation is required.
H6.0 References
American Industrial Hygiene Association Emergency Planning Committee, “Emer-
gency Response Planning Guidelines (ERPG),” September 1995.
American Petroleum Institute, Recommended Practice 752, “Management of
Hazards Associated with Location of Process Plant Buildings,” 1995.
Wilfred Baker Engineering, Inc., “Upgrade of Windows to Mitigate the Glass Frag-
mentation Hazard from Vapor Cloud Explosions,” prepared for the 1993-1994
Petroleum and Chemical Processing Industry Technology Cooperatives.
Wilfred Baker Engineering, Inc., “Conventional Building Blast Performance Capa-
bility,” prepared for the 1995 Industry Technology Cooperative.