Placing FR style door flush in an existing condition

Minimum 6" combined


frame & concrete width
Frame Width 3"
Overall Frame Size

FR Cover

Frame Depth 31/2"

Frame Opening

Support under frame & 6" depth including


concrete required by others in the field Minimum 6" combined
(angle shown for detail) frame & concrete depth

Surface must be covered by ALBI coating


after installation

Masonary Opening
Box out to size shown for FR
Set door and fill this area at time of
delivery.
Apply ALBI coating to inside frame
opening per customer drawing and
installation instructions

Box Out Opening


12" larger than frame opening
6" minimum either side

Box Out Depth 6"

Frame Opening
Slab Depth ? Note : FR unit has springs
and mounting hardware that project
down into this area and may interfere
with poured slab upon drop in.

Box out for existing condition


Frame of unit must be surrounded by concrete (not wood, steel, etc.)
for a total of 6" minimum in each direction
Collar for FR must meet 6" in all directions.
Apply ALBI coating to inside frame opening
per customer drawing and installation
instructions

Minimum Collar Width


Taper section
Frame Opening + 12"
as desired to
6" minimum either side
prevent
tripping

Frame Opening
Slab Width Note : FR unit has springs
must be and mounting hardware that project
at least 6" down into this area and may interfere
with poured slab upon drop in.

Sitting on top of existing condition


Frame of unit must be surrounded by concrete (not wood, steel, etc.)
for a total of 6" minimum in each direction

You might also like