Professional Documents
Culture Documents
Scope
This Global Practice (GP) covers basic requirements for the installation, inspection, and testing of
submarine pipelines and risers. Pipeline and riser design, materials, weight coating, corrosion protection
coating, and cathodic protection are covered in other Company documents.
Upstream, Pipelines and Terminals For ExxonMobil Use Only Version 1.0.0
Table of Contents
1. Required References ............................................................................................ 5
1.1. Global Practices–ExxonMobil Engineering Practices ................................... 5
1.2. ExxonMobil Data Sheets .............................................................................. 5
1.3. ExxonMobil Practice Tutorials ...................................................................... 6
1.4. API–American Petroleum Institute ................................................................ 6
1.5. ASME–American Society of Mechanical Engineers ..................................... 6
1.6. ASNT–American Society for Nondestructive Testing ................................... 6
1.7. AWS–American Welding Society.................................................................. 7
1.8. BSI–British Standards Institute ..................................................................... 7
1.9. CFR–U.S. Code of Federal Regulations....................................................... 7
1.10. ISO–International Organization for Standardization ..................................... 7
2. General ................................................................................................................... 7
1. Required References
This Section lists Practices and Standards that are generically referenced and assumed to be a part of this
document. Unless otherwise specified herein, use the latest edition.
2. General
The installation, inspection and testing of submarine pipelines and risers shall be in accordance with
requirements of this GP, unless superceded by more stringent local regulations.
The requirements of this GP apply to all methods of submarine pipeline installation, including reel, S-
type, J-type lay, and bottom pull and tow.
3. Design Data
Pipeline design data are given on the ExxonMobil Data Sheets for this GP. Environmental data are given
to the Contractor for information only. The Contractor shall obtain any verification or additional data
necessary to perform installation engineering and install the pipeline(s).
4. Installation Equipment
The Contractor shall provide the number, type, and capacity of equipment sufficient to install the
pipeline(s) in a safe and expedient manner.
1) A list of equipment shall be supplied in accordance with the ExxonMobil Data Sheets for this GP at
the time of bidding.
2) The Contractor shall demonstrate in the bid the adequacy of the equipment based on the preliminary
engineering analysis. Engineering shall take into account physical conditions, including water depth,
bottom soil properties and maximum environmental conditions anticipated during installation. (Refer
to the ExxonMobil Data Sheets for this GP.) Pipeline stresses during installation and testing shall not
exceed those given in Section 5.1.3 of this GP.
3) The Contractor shall clearly state all environmental criteria and stresses used in the engineering. This
shall include safety factors for equipment capacity and pipeline stresses.
4) Following completion of detailed installation engineering, the Contractor shall review all these safety
factors and demonstrate their adequacy. Should any safety factor(s) prove to be inadequate, the
Contractor shall upgrade equipment as necessary.
5) The Contractor shall ensure that all equipment proposed in the project is adequate for the use intended
and will meet or exceed any and all applicable governmental, industry, environmental, safety and
health standards and regulations. It is the Contractor's responsibility to determine existing regulatory
requirements and ensure compliance.
6) The Company reserves the right to audit all marine vessels and other construction equipment
proposed for use by the Contractor. Any equipment failing to comply with either the job
specifications or environmental or safety requirements, as determined by the Company, shall be
replaced or modified by the Contractor prior to use.
2) Seabed preparation
3) Pipeline crossing preparation and completion
4) Storage, handling and transportation of materials supplied by the Company and the Contractor
5) Pipe tracking
6) Pipe lay (including startup, laydown, temporary protection of existing pipelines/cables, and temporary
installation aids)
7) Pipe lay over crossings
8) Pipe lay abandonment/recovery
9) Pipe welding (automatic and/or manual), including weld repair
10) Welder/welding machine operator qualification
11) Radiography
12) Radiographer qualification
13) Ultrasonic examination
14) Field joint coating and protection (FBE)
15) FBE coating repair
16) Concrete coating repair
17) Span correction
18) Trenching
19) Rock dumping
20) Flooding, cleaning and gauging
21) Hydrostatic testing
22) Anchor handling and anchor patterns (including layaway pipeline/crossings and laydown)
23) Anchoring-up at any location (e.g., commencement of operations)
24) Dynamic positioning
25) Installation of mechanical subsea connection tools
26) Hyperbaric welding (including welder qualification)
27) Hyperbaric NDT (including tester qualification)
28) Spool-piece installation
29) Diving operations
30) ROV operations
31) Contingency operations
a) Wet/dry pipeline buckle
b) Incorrect positioning of line
UPST, PL For ExxonMobil Use Only Version 1.0.0
5.2. Procedures
The Contractor shall develop all procedures required for the installation, inspection and testing of the
pipeline system.
The Contractor shall ensure that no damage is done to existing pipelines and cables by submitting and
following fully developed installation procedures and installing temporary protection where necessary.
Specific anchor patterns and placement procedures shall be developed.
6. Pre-lay Survey
6.1. Pre-lay Activities
The following pre-lay survey activities shall be undertaken:
1) A bathymetric and side-scan sonar survey shall be performed prior to commencing pipe lay.
2) Contour plans and longitudinal sections shall be prepared (at scales to be approved by the Company)
displaying all pertinent details of the survey and submitted for Company review. They shall include
the obstructions, pipelines, cables or other seabed features within the pipe lay corridor.
3) The extent of trenching and rock dumping shall be determined, including the design of trenching
profiles, and submitted for Company approval.
4) Seabed preparation requirements shall be analyzed and determined at locations where pipeline
spanning may cause excessive stresses or critical spans.
5) The final pipeline route within the specified corridor shall be determined, including preparation of
route drawings and submitted for Company approval.
4) Government regulations
5) Lay techniques
6) Anchor patterns
7. Crossings
The following activities shall be undertaken:
1) A detailed survey of the crossing location shall be performed comprised of a bathymetric and side-
scan sonar survey, a sub-bottom profiling video survey and the procurement of soil samples.
2) Contour plans and longitudinal sections shall be prepared, at scales to be approved by the Company,
displaying all pertinent data. These shall include the location of pipelines to be crossed, depth of
burial/degree of exposure, the condition of exposed pipeline and any obstructions in the vicinity of
the proposed crossing location.
3) Details of crossing design shall be finalized, based on detailed survey results and calculated bearing
pressure (including design of gravel and rock layers in rock dump) and submitted for Company
approval.
4) Obstacles shall be removed from the vicinity of crossings and the line to be crossed shall be lowered
if required.
5) After their installation, a survey of the installed mattresses shall be performed and "as-installed"
drawings submitted for Company approval. The separation between pipelines shall be a minimum of
0.5 m (1.6 ft).
8. Pipe Lay
8.1. Transportation
1) Company-furnished line pipe and materials shall be released to the Contractor at designated locations
in accordance with the schedules given in the job specifications.
2) Unless otherwise specified by the Company, the installation Contractor shall receive, load out and
transport coated line pipe and all other Company-furnished material to the Contractors fabrication and
installation site in accordance with GP 86-01-02, GP 59-01-14, and the job specifications.
3) The Contractor shall assume responsibility and custody for all Company-furnished materials, and
shall develop and maintain an inventory and tracking system for these items.
4) Upon job completion, the Contractor shall load out and transport remaining line pipe and other
Company-furnished material to a site specified in writing by the Company.
8.2. Alignment
1) The final on-bottom position of the pipeline shall be located within 10 m (33 ft) of the approved
route centerline.
2) The pipeline shall be laid along the predetermined route (in accordance with the ExxonMobil Data
Sheets for this GP) except in the vicinity of the platform approaches and crossings. There, the on-
bottom placement of the pipeline shall have a nominal spacing of 90 m (300 ft) from other objects
and shall not be closer than 30 m (100 ft) to any adjacent pipeline. Separation between a pipeline and
a platform to which the pipeline does not have a connection is 90 m (300 ft) minimum.
3) The minimum on-bottom radius shall be determined from the requirements in Section 5.1.3 of this
GP.
4) If the sea floor is too congested to adhere to these requirements, the Company shall be advised in
writing and a proposed pipeline alignment shall be presented to the Company for approval.
1) The Contractor shall demonstrate the accuracy of tensioner and constant tension winch load cells
prior to lay. The tension control systems shall be shown to be accurate, efficient, and reliable.
2) Prior to start of pipe laying, the Contractor shall check the height, location and condition of each
roller support on the pipe lay vessel for adherence to drawings and installation procedures.
3) Rollers shall be soft-faced with molded polypropylene or similar material. Worn rollers and tensioner
shoes shall be replaced.
4) The rollers on the stinger shall be inspected prior to the start of the pipe lay and at regular intervals
thereafter. No additional inspections may be required if the job is short in duration (e.g., one week).
The inspection may be conducted by ROV (Remote Operated Vehicle) or by air divers.
5) Deepwater stingers, which tend to be exposed to high environmental loadings, shall be inspected
regularly.
6) Prior to the start of pipe lay, the Contractor shall check and demonstrate that the tensioners and roller
supports are precisely aligned on the centerline of the pipe ramp.
7) The Contractor shall demonstrate the operability of the pipe lay stinger prior to the commencement of
pipe lay. This shall include testing loadcells, cameras, and other monitoring equipment.
9) The pipe lay operation shall be monitored by ROV a minimum of twice per day, depending on
prevailing weather conditions. At critical locations, continuous monitoring by ROV may be required.
8.8.2. Calculations
1) The Contractor shall prepare abandonment/recovery calculations that determine stress levels in the
pipe on the barge, stinger and sagbend; the reactions on the barge and stinger rollers; and the forces in
the abandonment/recovery cable.
2) Abandonment/recovery calculations shall be performed for the most critical water depth for each
different pipe diameter/wall thickness/concrete combination.
3) The calculations shall indicate barge and stinger configuration, roller heights, pipe profiles, and the
expected pipe tension for all stages of the abandonment/recovery operations.
UPST, PL For ExxonMobil Use Only Version 1.0.0
4) All results shall be tabulated and presented in graphic form for ease of use by field personnel and
their subsequent usage shall become an integral part of the approved procedures.
5) Stresses during abandonment and recovery shall comply with the requirements of Section 5.1.3 of this
GP.
8.8.3. Heads
1) Any pipe end lowered in the water shall have abandonment/recovery heads.
2) The installation and removal of abandonment/recovery heads shall be performed by the Contractor as
part of the normal pipe laying operation. Abandonment/recovery heads shall always be on board the
pipe lay barge and kept in ready status.
3) Abandonment/recovery heads shall be designed and fabricated by the Contractor and be subject to the
Company approval.
4) The heads shall have all necessary contingency facilities required to flood and de-water the pipeline.
These facilities shall be protected from damage by a protective cage or equivalent.
5) In addition, the heads shall be equipped with suitable Company-approved marker systems to facilitate
their relocation.
8.10. Diving
It shall be the sole responsibility of the Contractor to ensure that all diving activities are performed in
accordance with statutory diving regulations.
4) The holding power of the deadman anchor or pile startup system shall be proved by load testing to 1.5
times the maximum predicted load, holding for 30 minutes. The Contractor shall be responsible for
clearing the seabed of deadman anchor or pile startup system.
Company at all times. Work not welded in accordance with the approved WPS and/or by qualified
welders shall be rejected.
9.2. Equipment
1) All welding shall be performed using reliable equipment suitable for the work being done.
2) The Contractor shall establish a procedure to check and demonstrate to the Company that all welding
machines are properly grounded to avoid the occurrence of stray arcing.
3) The Contractor shall provide ground clamps of an approved design and employ only insulated
electrode holders and/or leads.
4) All welding equipment shall be of the same type used in the welding procedure qualification.
9.3.2. Electrodes
All coated welding electrodes for manual welding shall be kept in hermetically sealed containers and
stored in accordance with the manufacturer's recommendation. They shall be handled in a manner that
ensures no mechanical or physical damage is caused to the coatings.
Once the sealed containers are opened:
1) Electrodes with low hydrogen covering conforming to AWS A5.1 classification E60XX and E70XX
shall be dried in an electrode drier for at least two hours at temperatures between 232C and 260C
(450F and 500F).
2) Low hydrogen electrodes conforming to AWS A5.5 classification E70XX- X and above shall be dried
in an electrode drier for at least one hour at temperatures between 370C and 426C (700F and
800F).
3) The electrodes shall be stored in an electrode holding oven at a minimum temperature of 149C
(300F) immediately after their removal from the drying ovens.
4) The welder shall remove no more electrodes from the holding oven than can be used in two hours.
5) Once removed from the holding ovens, the electrodes shall be immediately placed into a portable
heated quiver or hot box maintained at 102C (215F).
6) Electrodes remaining unused three hours after their removal from the holding oven shall be discarded
unless returned to the drying oven, reheated for two hours and then replaced in the holding oven.
7) Electrodes shall not be re-dried more than three times and shall be discarded if not consumed after the
third redry.
8) Electrodes that have become wet shall not be used and shall be removed from the work site.
9.4.1.2. Diagrams
1) Diagram showing bevel, dimensions, and tolerances.
2) Diagram showing bead sequencing with each bead numbered.
9.4.1.3. Lineup Clamp
1) Type of lineup clamp.
2) When permissible to remove lineup clamp.
9.4.1.4. SAW Welding
Electrode offset and angle for SAW welding.
9.4.1.5. Gas Metal Arc Welding
For WPSs Gas Metal Arc Welding (GMAW), oscillation width and frequency, wire feed, sidewall dwell
time, pulsing frequency and parameters.
9.4.1.6. Other
1) Minimum number of welders/operators for each pass.
2) Maximum permitted time lapse between root pass and second pass and between second pass and third
pass.
3) Welding consumable size, specification, and brand name for each pass. Only one choice is
permissible.
4) For each pass, ranges for heat input, amperage, voltage, speed of travel, electrode wire speed, gas
flow rate, gas content, etc. (The instrumentation requirements for recording welding parameters by
the Contractor shall be clearly stated.)
2) Failures due to lack of fusion or due to cracking shall be investigated and explained to the satisfaction
of the Company. The WPS shall then be changed to eliminate the problems before a new
qualification test weld is made.
9.5.4. Consumables
Welding consumables used for the procedure qualifications and production welds shall be from the same
batch. The Contractor shall ensure that sufficient welding consumables from a single batch are available
for both the welding procedure qualification and for production welding.
9.6.2. Requalification
Requalification of welders and welding operators is required if any change is made to the welding
procedure that necessitates its requalification.
After qualification for the project work, approval is valid if the following condition is obtained and
documented: the welding operator or the welder has carried out qualified work with acceptable welding
performance and with no interruption longer than three months.
9.7.5. Alignment
1) The alignment of the abutting ends shall minimize the radial offset. The internal offset between pipe
ends shall not exceed 1.6 mm (1/16 in.).
2) Hammering or heating for correction of alignment is not permitted.
3) Internal lineup clamps shall be used when possible and shall not be removed until 100 percent of the
root and hot pass is completed.
4) When external lineup clamps are used, the Company shall approve the equipment prior to welding.
5) If external lineup clamps are approved, 50 percent of the root pass shall be complete before removing
the clamp.
6) In some situations, the Company may also require the hot pass to be deposited on the root pass before
removal of the external lineup clamp.
7) Spacer tools shall be used to check final fit-up. The longitudinal welds shall be located in the top 180
degrees of the pipe and have an offset of 152 mm (6 in.) minimum.
9.7.6. Preheat
1) The welding procedure shall specify the necessary preheat and interpass temperature, taking materials
and welding conditions into consideration. The necessary preheat temperature selection shall be
based on welding procedure qualification tests.
2) The specific use of preheat shall be approved by the Company when proper documentation has been
submitted. The documentation shall indicate the necessity of preheat, with regard to hardness control
and/or prevention of hydrogen-induced, delayed cracking (cold cracking).
3) Preheating shall be applied by methods approved by the Company that are capable of heating the
entire circumference of a joint in a uniform manner while avoiding overheating and damage to the
pipe's protective coating.
4) Measurement of preheat and interpass temperature shall be performed using thermocouples,
temperature indicating crayons or other suitable methods approved by the Company.
5) Temperature measurements shall be made on the same locations for qualifications and production
welds at least 50 mm (2 in.) away from bevel on pipe surface.
9.8.4. Recapping
1) External defects, such as undercut and pinholes, may be recapped provided the procedure
qualification has been approved.
2) The recapping shall extend past both ends of the defect.
3) All repair welds made during production shall be subject to full non-destruction inspection, in
accordance with the requirements of Section 9.9 of this GP.
4) When defect interpretation from radiographic film is insufficient, ultrasonic inspection shall be
carried out in addition to visual and radiographic inspection.
9.9.2. Permits
The Contractor shall be responsible for securing all necessary operational permits needed to comply with
the requirements of governing authorities related to the performance of radiographic services.
9.9.3. Radiography
9.9.3.1. Sources
In the event X-ray equipment is used, the Contractor shall ensure that the pipe laying barge has sufficient
regulated electrical power and adequate space to accommodate the use of such equipment.
If gamma-radiography is employed, the Contractor shall use an Iridium 192 radioactive source. The
source strength shall be maintained to ensure a maximum exposure duration of 30 seconds per exposure.
9.9.3.2. Film Type
1) Outdated or expired film emulsions shall not be permitted.
2) All film shall be fresh stock.
3) Only Kodak or a Company-approved alternate Class II fine grain and high contrast film shall be used
for X-ray radiography.
4) Class I extra fine grain and high contrast film shall be used for gamma-radiography.
9.9.3.3. Penetrameters
Wire penetrameters shall be used. Their thickness, identifying number and placement shall be in
accordance with API STD 1104.
9.9.3.4. Illuminators
Only viewing illuminators that can produce light intensity (110 volt-high intensity) sufficient to provide
the following result shall be used. All portions of the radiography of the weld and base metal shall
transmit sufficient light to reveal the pertinent details of the radiographs having H&D densities up to 4.0.
Such equipment shall also be equipped with a variable intensity regulator.
3) Personnel qualification certificates shall be available on site. Personnel without this documentation
of qualification shall not be accepted.
4) Level II technicians shall be used for interpretation.
9.9.5.2. Film Orientation/Identification
For pipe welded in the fixed horizontal position, the zero datum shall be the top of the pipe. The
orientation of the film shall be defined and be the same for all films.
As a minimum, the film identification shall include the following:
1) Client
2) Project Number
3) Weld Number/Joint Number
4) Date
5) Radiography Position
9.9.5.3. Interpretation of Radiographs
All interpretations of radiographs shall be made in accordance with the appropriate sections in this GP
governing acceptability of welds.
1) The Contractor shall provide Level II radiographers who shall be responsible for the interpretation of
all radiographs.
2) The Company shall provide independent interpreters who shall review some or all radiographs and
provide the final decision on the acceptance, rejection or repair of the radiographs in question.
9.9.5.4. Personnel
The Company shall have the right to require removal of any employee of the Contractor who, in the
opinion of the Company, is incompetent, careless or otherwise not qualified to perform the work
assigned; or who may be insubordinate or guilty of improper conduct. The Contractor shall immediately
replace the employee with another Company-approved employee, at no cost to the Company.
9.9.5.5. Safety Precautions and Protection
1) The Contractor shall be responsible for the protection and monitoring of radiographic personnel and
shall ensure that all work is carried out in accordance with the relevant health and safety regulations.
2) The area exposed to radiation shall be posted.
3) The Contractor's radiographer shall be responsible for the protection and monitoring of all personnel
working near X-ray or Gamma-radiation equipment.
4) An adequate supply of NRC (Nuclear Regulatory Commission) approved "Danger" or "Caution"
signs shall be displayed during any radiographic work on the pipeline.
5) It is the Contractor's responsibility to protect the general public and the construction Contractor's
personnel from harm.
9.9.5.6. Film Processing
1) The Contractor shall prepare a procedure for film processing and submit it to the Company for
approval prior to job commencement.
UPST, PL For ExxonMobil Use Only Version 1.0.0
2) Film shall be exposed so that the average H&D density shall not be less than 2.0 and the density
through the thickest part of the sound weld metal shall not be less than 1.5.
3) Radiographs shall be free from all defects caused by bending, dirt, faulty screens, static marks, light
leakage, and handling. Any film containing defects interfering with the interpretation of the
radiograph shall be discarded and the weld shall be re-radiographed.
4) Radiographs shall be processed in accordance with API standards to allow storage of film without
discoloration for at least three years. The processing chemical shall be changed regularly and care
shall be exercised during processing to prevent scratches on the film.
3) The epoxy powder used for field joint coating shall comply with the requirements stated in GP 86-01-
02 and GP 59-01-14.
4) Epoxy powder shall be handled, stored, and tested throughout the duration of the job in accordance
with the requirements of GP 86-01-02 and GP 59-01-14.
FBE field joint coating may not always be practical due to lack of space on the lay vessel or for a project
with a short design life. Shrink sleeves are commonly used in the industry for coating field joints and are
probably the next practical alternative to FBE coating.
5) A surface finish to ISO 8505-1 shall be obtained with a peak to trough profile height between 50
and 75 (2 mil and 3 mil) for the exposed steel area. All areas to be field coated shall, at the
Company's discretion, be salt tested after blast cleaning to check for removal of all salts.
6) The working abrasive shall be maintained free of water, oil, salt, and other contaminants. Water/oil
traps and filters shall be incorporated in all blast cleaning apparatus.
7) No blast cleaning shall be allowed when the pipe surface temperature is less than 3C (5F) above
dew point.
8) After blast cleaning, the area to be field coated shall be vacuum cleaned of all deleterious matter. A
clean, dry brush may be used to aid cleaning.
9) If jagged or rough edges are left along the edge of the yard-applied coating or if any of the coating is
disbonded, then the loose coatings shall be removed until sound coating has been obtained. The area
shall then be recleaned.
9.10.5. Testing
This Section outlines the minimum test procedure that shall be employed.
1) The Contractor shall submit a detailed description of the proposed coating test procedure for
Company approval.
2) The first 10 welds to be coated under full production conditions shall undergo the following tests:
a) Coating thickness
b) Holiday detection
c) Adhesion
d) Cure
3) Tests shall be conducted and evaluated in accordance with GP 86-01-02 and GP 59-01-14.
4) After the first 10 welds are tested as outlined above, additional tests shall be conducted throughout
production at the following frequencies:
a) The mastic shall be poured from a heated kettle at a temperature approved by the manufacturer.
It shall fill the joint without damage to or disbondment of, the fusion bonded epoxy.
b) The exterior of the form may be vibrated to consolidate the mix, which shall be topped up as
required, without causing segregation of the constituents of the mastic.
c) On completion of pouring and subsequent topping up operations, the mastic filling-flap opening
shall be closed and banded in place. Then the whole assembly shall be sprayed with cold water to
assist cooling of the mastic to an acceptable level before immersion in the sea. The Contractor
shall ensure that the filling flap does not protrude from the mold.
3) For other filler materials, application of the material shall be in accordance with procedures
established by the manufacturer and submitted by the Contractor to the Company for approval.
4) On completion of field joint coating, the form shall be checked to ensure that the mold is full and that
no swelling, distortion or undue leakage has occurred.
9.10.7. Reports
The Contractor shall submit inspection reports, in an approved format, for all inspection and testing
undertaken.
A record shall be kept of all repairs made by the Contractor to the yard-applied coating with relevant pipe
length numbers noted.
10. Anodes
The Contractor shall install anodes manufactured in accordance with GP 86-01-02 and GP 59-01-14 at
intervals specified by the Company.
Anode installation shall involve installing prefabricated anode pipe joints furnished by the Company or
installing semi-cylindrical pipeline anodes in accordance with the job specifications.
10.1.1. Insulation
1) Fire retardant cloth or other suitable material approved by the Company, with a minimum thickness
of 3 mm (1/8 in.), shall be wrapped around the pipe in the area under the anode.
2) Insulation shall overlap the steel core plates that are to be welded.
3) During anode installation the insulating cloth shall be held in place with a suitable tape.
10.1.4. Cleaning
1) After the anode has been installed, the weld area shall be thoroughly cleaned with a wire brush.
2) All exposed steel surfaces of the pipe and anode core plates, plus the thermite weld areas, shall be
coated with epoxy patching compound (or the Company approved equivalent).
3) Care shall be exercised to prevent corrosion coating from touching the outer face of the anode.
Repeated weight coating damage shall be immediately investigated so that the cause can be identified and
remedial action taken to the Company's satisfaction.
12. Risers
The Contractor shall fabricate risers in accordance with this GP and the job specifications. All riser bends
shall have a minimum radius of five pipe diameters. Girth welds shall be no closer than 1.5 m (5 ft) from
the centerline of any riser clamp.
12.1. Installation
1) The Contractor shall provide sufficient bracing at installation to prevent the cathodic protection
insulating flange from supporting the riser weight.
2) Riser clamps shall be installed in accordance with this GP and the job specifications. If the clamps
are to be installed on an existing structure, all marine growth on the structure shall be removed from
the structure surface where the clamp is to be located immediately before installation.
3) If the riser is installed offshore, it shall be installed in accordance with procedures approved by the
Company.
12.2. Testing
1) Each riser shall be hydrostatically tested as a single unit after fabrication and before installation.
2) The test pressure shall be in accordance with the strength test pressure indicated on the ExxonMobil
Data Sheets for this GP.
3) The test duration shall be at least four hours with less than 0.2 percent pressure decrease after
temperature corrections.
4) The final pressure after four hours shall be equal to or greater than the test pressure on the
ExxonMobil Data Sheets for this GP.
5) There shall be no visible leakage.
6) The hydrostatic test shall be witnessed by the Company.
7) If the riser is hydrostatically tested separately, the Contractor shall produce a separate test report
whose format and general requirements shall be the same as for the overall pipeline test report.
13.3. Documentation
1) The Contractor shall provide details of proposed equipment for pulling the shore approach section of
line in accordance with Section 4 of this GP. Refer to Section 8.11, Item 4 of this GP for capacity of
deadman anchors.
2) In addition to the procedures, installation manuals, etc., required by Section 5, the Contractor shall
provide similar documentation for the shore approach as applicable to the specific project and as
required by the job specifications.
3) Any obstructions encountered shall be immediately brought to the Company's attention for resolution.
The Contractor shall take every precaution not to damage existing obstructions, but in the event of
their damage, shall replace or repair them at Contractor's cost to the Company's satisfaction.
14.1. Accuracy
1) Accuracy of the survey shall be 3 m (10 ft) in the horizontal planes.
2) The Contractor shall resurvey any areas where post lay conditions such as spanning or insufficient
burial depth were previously identified to verify repairs.
16.1. Procedures
1) The Contractor shall include detailed procedures, design drawings and calculations relating to
pipeline trenching, jetting, sandbagging or rock dumping operations in the appropriate Installation
Manual.
2) Design and procedures for jetting and trenching operations shall ensure that excessive stresses are not
imposed on the pipeline due to the formation of unsupported spans or contact between the pipeline
and trenching/jetting equipment.
16.3. Inspection/Testing
1) Post-lay trenching and jetting operations shall be continuously monitored by ROV, fixed video
cameras, or divers.
2) Inspection using ROV or other approved methods shall be made following burial/stabilization
activities to verify that the design requirements have been met.
3) Hydrostatic testing shall be accomplished after stabilization/burial is complete. Verification of
pipeline integrity after laying but before stabilization/burial shall be performed as required by the
Company.
17.1. General
17.1.1. Procedure/Schedule
The Contractor shall submit for approval a detailed step by step procedure and testing operations schedule
a minimum of six weeks prior to the start of the test.
The procedure shall state the required equipment type and size, number and type of pipeline pigs,
inhibitor type and quantity and a description of the test monitoring equipment.
2) Any work by the Contractor or test conditions deemed by the Company to be unsafe shall be
corrected.
3) The testing operations shall not continue until the unsafe conditions have been corrected to the
satisfaction of the Company.
4) The Contractor shall not receive additional compensation for time lost due to unsafe conditions.
17.1.4. Supervision
If testing is subcontracted, the Contractor shall be responsible for supervising the testing operations. The
Company shall witness and approve all tests.
17.2.3. Lighting
The Contractor shall furnish sufficient lighting in the compressor-pump enclosure and test header areas
during periods of darkness when testing operations are in progress.
1) A meter of sufficient size and accuracy shall be used to measure the quantity of water injected into
the test section.
2) Before water is injected into the pipeline, suspended matter in the water shall be extracted by a filter
capable of removing 99 percent of all particles 92 (3.6 mil) in diameter and larger or equivalent to
using a 100 x 100 (4 x 4 mil) wire-mesh screen.
3) If foreign material is pumped into the line because of faulty equipment or careless work, the
Contractor shall flush the line with clean water at no cost to the Company.
4) The test water may be analyzed by the Company to determine its suitability for use in the testing
operations and to determine the water treatment requirements.
a) Corrosion inhibitor, oxygen scavenger, and biocide treatment may be used except where
environmental discharge problems of hydrotest water prevent their use.
b) Chemical treatments shall be reviewed and approved by a Company Corrosion Engineer early in
the project to facilitate timely injection of the chemicals into the system.
c) The required chemical additives shall be injected with the water by the Contractor (immediately
behind the gauging scraper pig) in concentrations sufficient to protect the pipeline for a minimum
of 12 months. Any nearby offshore installations involved in water-making operations shall also
be notified.
after compensating for temperature. None of this or the foregoing shall be included in the test
duration.
4) Water shall be injected or withdrawn from the test section to maintain pressure within the specified
limits. The volume of these injections and/or withdrawals shall be measured and recorded.
5) Pressure-volume-temperature (PVT) calculations shall be performed to show any observed pressure
loss due to a temperature change or a leak.
6) A pressure recorder and temperature recorder shall be used to continuously record the test pressure,
fluid temperature and ambient temperature. In addition, pressures shall be read and recorded to the
nearest 7 kPa (1 psi), using a deadweight tester furnished by the Contractor. The pressure shall be
recorded every 15 minutes until it has stabilized; then it can be recorded every 30 minutes.
17.6.2. Calibration
1) All recorders and dead weight testers shall be calibrated immediately prior to use.
2) Calibration certification shall be provided for each recorder and dead weight tester used.
3) Recorders shall have calibration verified following the hydrotest.
4) Post-test calibration failure for any recorder shall be grounds for the hydrotest to be rejected by the
Company.
Record of Change
Version 1.0.0 Date: 07/01
Location Action Description
Initial Publish