Method Statement

StoPox KU 611 system,


High chemical and mechanical resistant epoxy coating, electrostatically
conductive

1. General
Approved specialist applicator shall execute the whole installation of the system and done in accordance to
manufacturer’s instruction. Materials shall be stored in a cool and dry environment, avoiding exposure to direct
sunlight. Ensure sufficient material, labour, equipment and accessories are available to maintain continuous
application process.

2. Scope
This method statement describes the installation process, type of materials, tools and equipment required and
safety in handling the material.

3. Work Procedure
3.1 Surface Preparation
a. Old floor with existing epoxy coating.
i. Tap with a hammer to check for hollowness.
ii. All hollow sections must be repaired with StoPox EPS GP epoxy mortar system. The edges
must be saw-cut and the loose materials remove with a breaker.
iii. Conduct random pull-off tests to determine the existing floor has bond strength of average
1.5 N/mm² and minimum value of 1.0 N/mm².
iv. Sand the floor with grit 60 or 80 sand paper using mechanical sander.
v. Surface temperature must be checked with an all-in-one dew point meter to ensure it is 3oC
above dew point.
b. On new concrete floor.
i. Concrete floor should be load bearing.
ii. Prepared the floor with either mechanical diamond grinding or ball blasting. Care must be
taken to remove all laitance that cannot be removed by diamond grinding. Corner where ball
blasting cannot reached are to be treated with hand-held diamond grinder.
iii. Conduct random pull-off tests to determine the existing floor has bond strength of average
1.5 N/mm² and minimum value of 1.0 N/mm². Weak area should be removed and repaired
with StoPox EPS GP epoxy mortar.
iv. All pot holes must be patched with Sto epoxy putty such as StoPox SK 41, StoPox EPA P or
StoPox EPA P3 Fast-set.
v. Check surface moisture content to be less than 4% measured with CM device (Carbide
Meter). The floor is checked with a suitable electronic moisture meter and the highest few
spots are then check with CM method.
vi. Surface temperature must be checked with an all-in-one dew point meter to ensure it is 3oC
above dew point.

Please note that all advice, recommendations, specifications or information are given in good faith. While efforts are made to ensure that they are accurate and correct, Sto SE
Pte Ltd has no continuous control over where or how the products are applied. As such, Sto SEA Pte Ltd cannot accept any liability either directly or indirectly arising from the
3.2 Priming
a. Old floor with existing epoxy coating.
i. Prime the prepared surfaces with one coat of StoPox WG 100, contact primer. The application
is by roller at coverage of approx. 0.15 to 0.20 kg/m².
ii. StoPox WG 100 comes in 2 components at a ratio of 5:1. Comp. A is 10 kg and comp. B is 2
kg.
iii. Mixing is first done by agitating the comp. A with a scraper to loosen up some settlement at
the base. This happened when the material was stored for sometimes. Next, mix comp. A
with a mechanical mixer fitted with stirrer until it is homogenous, pour in the whole content of
comp. B and mix again until homogenous. Add in 10% water to dilute the material and mix
again. Transfer to a new container, mix for few seconds and use the material from this
container.
b. On new concrete floor
i. Prime the prepared surface with one coat of StoPox GH 205. The application is by pouring
the primer onto the floor, spread and press into the concrete pores with suitable rubber
squeegee such as Sto-Rubber Squeegee (Art. Nr -17400-005) and cross-roll with a roller.
The coverage is approx.. 0.2 to 0.25 kg/m².
ii. Mixing is by adding comp. B into comp. A and stir with a mechanical mixer until it is
homogenous. Transfer to a new container, mix for few seconds and use the material from this
container.
c. Scratch leveller
i. If the subfloor is uneven, we recommend applying a layer of scratch coat consisting of 1 part
StoPox GH 205 and 1 part of fine quartz sand such as Sto Filler 60/100.
ii. The application is by pouring the material onto the floor and scratch sharply with flat blade
smoothing trowel.

3.3 Grounding point


a. We recommend for all our ESD floors, the ground points should be at every 100 m². The grounding
points should distribute as evenly as possible and no point on the surface should be further than 10 m
from grounding point. Larger distances can be bridged with the conductive ribbon StoDivers LB 100.
b. The grounding point is by installing StoDivers LS, grounding set. It should be at area with low
mechanical load of approx. 30 to 100 mm from wall or column.
c. The installation is by drilling a diameter 10 mm hole of 800 mm deep, clean surface of drilling dust,
adhere a strip of copper tape to the left and right side of hole, place the square board with hole align
to the drilled hole, insert high performance anchor with washer, tap with a hammer and tighten anchor.
Place the blue plastic tube on the protruded thread to protect it against epoxy contamination.
d. Ensure that the protruded thread is just enough for the M6 clip nut to be installed later.

Please note that all advice, recommendations, specifications or information are given in good faith. While efforts are made to ensure that they are accurate and correct, Sto SE
Pte Ltd has no continuous control over where or how the products are applied. As such, Sto SEA Pte Ltd cannot accept any liability either directly or indirectly arising from the
3.4 Intermediate conductive layer
a. This layer is the most important of the whole system; it bridges the finished layer and the grounding
point to earth.
b. The product is StoPox WL 118 (for human protection to meets VDE 0100-410). It comes with 10 kg
of comp. A (black) and 2 kg of comp. B at ratio of 5 : 1.
c. Mixing is first done by agitating the comp. A with a scraper to loosen up some settlement at the base.
This happened when the material was stored for sometimes. Next, mix comp. A with a mechanical
mixer fitted with stirrer until it is homogenous, pour in the whole content of comp. B and mix again
until homogenous. Add in 10% water to dilute the material and mix again. Transfer to a new container,
mix for few seconds and use the material from this container.
d. Dilute StoPox WL 118 with approximately 10% of water and apply it using a rubber squeegee or roller
at the coverage of approx. 0.15 to 0.20 kg/m².
e. Allow the coating to cure for one day and check the resistance to ground (Rg) before proceeding to
the finishing layer. Rg for StoPox WL 118 must be ≤ 1 x 106 Ω.

3.5 Finished layer


a. To avoid partial fiber accumulation, StoPox KU 611 must be applied uniformly with a rough toothed
rake (tooth shape 48) and immediately refinish it crosswise with a spiked roller.

b. StoPox KU 611 is supplied in 24.78 kg of comp. A and 5.22 kg of comp. B


c. Mixing is first done by agitating the comp. A with a scraper to loosen up some settlement at the base.
This happened when the material was stored for sometimes. Next, mix comp. A with a mechanical
mixer fitted with stirrer until it is homogenous, pour in the whole content of comp. B and mix again
until homogenous. Transfer to a new container, mix for few seconds and use the material from this
container.
d. The application is by spreading the material with toothed blade trowel and ventilate with spike roller.
Pour the material onto the floor, spread with toothed-trowel fitted with Tooth Shape 95 (Art. Nr -
08373-021) in reverse direction and ventilate the layer to release trapped air with Sto Spike Roller,
spike length 12mm, 250 mm ((Art. Nr -17406-001) or 500 mm (Art. Nr -17406-003). The coverage is
approx. at 1.3 kg/m²/mm.
e. Cure the finished layer before subjected to mechanical stress. Light traffic, 2 days and heavy traffic,
7 days.

3.6 Connection of grounding point to earth


a. Connection to earth must be carried out by an approved electrician.
b. Remove the blue plastic tube from the protruded thread and replace with cable foot M6 and tighten
with clip nut.
c. Connect by an electrician with a suitable earthing cable from the cable foot to the building earthing
point or strip.

Please note that all advice, recommendations, specifications or information are given in good faith. While efforts are made to ensure that they are accurate and correct, Sto SE
Pte Ltd has no continuous control over where or how the products are applied. As such, Sto SEA Pte Ltd cannot accept any liability either directly or indirectly arising from the
3.7 Conductivity measurement (min. 6 points)
a. TRBS 2153
i. RG < 108 Ω (method, EN 61340-4-1).
ii. RG < 106 Ω for storage of explosive material (method, EN 61340-4-1).

b. ANSI / ESD S20.20


i. RG < 109 Ω (method, ANSI / ESD S7.1)
ii. Person/shoe/floor resistance < 3.5 x 107 Ω (method, ANSI / ESD 97.1)
iii. or Walking test < 100 V (method, ANSI / ESD 97.2).

c. EN 61340-5-1
i. RG < 109 Ω (method, EN 61340-4-1)
ii. Person/shoe/floor resistance < 3.5 x 107 Ω (method, EN 61340-4-1)
iii. Walking test < 100 V (method, EN 61340-4-5).

d. VDE 0100-410
i. ≥ 10 x 104 Ω (method, VDE 0100-600)

4. Cleaning
4.1 Clean all tools and equipment with thinner immediately after use. Do not allow material to set.
4.2 Set material can only be cleaned using mechanical method.

5. Safety
5.1 All works shall comply with safety procedure or instruction as set out in our Technical Data Sheet and
Safety Data Sheet.
5.2 Proper PPE especially gloves are to be worn by workers at all time.

Please note that all advice, recommendations, specifications or information are given in good faith. While efforts are made to ensure that they are accurate and correct, Sto SE
Pte Ltd has no continuous control over where or how the products are applied. As such, Sto SEA Pte Ltd cannot accept any liability either directly or indirectly arising from the
Installation Instructions for the StoCretec Conductor Set
(StoDivers LS)
1. Contents:
10 pcs. Pre-drilled board 50 x 50 x 0.8 mm (pos. 1)
10 pcs. High performance anchor (pos. 2)
10 pcs. Washer 6.4 x 30 x 1.5 mm (pos. 3)
10 pcs. 6kt. nut M 6 (pos. 4)
10 pcs. Plastic tube (pos. 5)
10 pcs. Cable foot for M 6 (pos. 6)
10 pcs. 6kt. nut with clip part (pos. 7)
10 pcs. Washer A 6.4
20 pcs. Copper connector ribbon

1 2 3 4 5 6
7

2. Selection of connection points


Per earth connection, approx. 100 m² of jointless surface can be discharged.
The connection points should be as evenly distributed as possible, and selected such that
no point on the surface is further than 10 m from the connection point in question.
Larger distances should be bridged with the conductor ribbon StoDivers LB 100.

Please note that all advice, recommendations, specifications or information are given in good faith. While efforts are made to ensure that they are accurate and correct, Sto SE
Pte Ltd has no continuous control over where or how the products are applied. As such, Sto SEA Pte Ltd cannot accept any liability either directly or indirectly arising from the
3. Installation
• Arrange connection points in zones subject to low mechanical load (approx. 3 – 10 cm
from the wall or pillar).
• Drill a hole min. 8 cm deep (d = 10 mm) into the primed, equalised and hardened
surface. Clean surface of drilling dust.
• To the left and right of the drill hole, adhere a strip of copper ribbon.
• Lay the drilled board (pos. 1) on the drill hole. Take care that the perforation in the
board and the drill hole have identical coverage.
• Insert high performance anchor (pos. 2) together with underlay washer (pos. 3) and 6kt.
nut (pos. 4) (already pre-mounted) into the drill hole, and tap flush with upper edge of
board (pos. 1) if necessary with a hammer. Tighten anchor firmly by twisting the nut.
• Place plastic tube (pos. 5) on the projecting thread.
• Application of the conductor layer StoPox WL 110. The board (pos. 1) should be coated
as well.
• After hardening of the conductor film, apply conductive finish coat.
• Remove plastic tube (pos. 5).
• Place on cable foot M 6 (pos. 6) and tighten with 6kt. nut with clip part (pos. 7).
• The connection between the earthing point and the earth ring connection is created by
an electrical installer.

Conduit conduct by M&E NSC

Please note that all advice, recommendations, specifications or information are given in good faith. While efforts are made to ensure that they are accurate and correct, Sto SE
Pte Ltd has no continuous control over where or how the products are applied. As such, Sto SEA Pte Ltd cannot accept any liability either directly or indirectly arising from the
Conduit conduct by M&E NSC

Please note that all advice, recommendations, specifications or information are given in good faith. While efforts are made to ensure that they are accurate and correct, Sto SE
Pte Ltd has no continuous control over where or how the products are applied. As such, Sto SEA Pte Ltd cannot accept any liability either directly or indirectly arising from the
(by M&E NSC)