Professional Documents
Culture Documents
Draft Report 1
Draft Report 1
NOVEMBER 2023
TABLE OF CONTENTS
Table of Contents
LIST OF TABLES.......................................................................................................3
1.1. Brief Background.....................................................................................................5
1.3. Objectives of the Verification...................................................................................6
2.0. ASSESSMENT FOR ADDITIONAL QUANTITIES...........................................................6
2.1. Bill Item 21.01 (a); Excavation of Open Drains................................................................6
2.2. Bill Item 31.01 (a); Bush Clearing and Grubbing.............................................................8
2.3. Bill Item 31.01 (b); Top Soil Removal............................................................................8
2.4. Bill Items 36.01 (a); Common Excavation to Spoil..........................................................8
2.5. Bill Item 36.01(c); Rock Excavations..............................................................................9
2.6. Bill Item 36.02 (c); Minimum G15 Quality Material.........................................................9
2.7. Bill Item 36.03 (c); Roadbed Preparation.....................................................................10
2.8. Series 6000: Structures...............................................................................................10
3.0. FINANCIAL ANALYSIS FOR LOT 2 ROADS......................................................13
3.1 Variation Option-1..................................................................................................13
3.2. Variation Option-2.................................................................................................13
3.3. Variation Option-3.................................................................................................14
4.0 RECOMMENDATIONS......................................................................................15
5.0 CONCLUSION...............................................................................................15
LIST OF TABLES
Table 1:Change in quantities and cost of open drains for executed works................................8
Table 2:Additional cost due to increase in quantity of bush clearing & grubbing.......................9
Table 3:Additional cost due to increase in quantity due to top soil removal..............................9
Table 4:Indicates additional cost due to increase in quantity due to extra common excavation.
....................................................................................................................................... 10
Table 5:Indicates additional cost due to increase in quantity due to rock excavations.............10
Table 6:Indicates additional cost due to increase in quantity of fill materials..........................10
Table 7:Indicates additional cost due to increase in quantity due to roadbed preparation........11
Table 8: Showing the propopsed medium term drainage structures.......................................12
Table 9:Summary of the estimated cost verses the original contract amount..........................12
Table 10: Showing estimated cost for proposed drainage structures by Drainage’s team(MoWT)
....................................................................................................................................... 13
1.0. INTRODUCTION
The Ministry of Works and Transport (MOWT) and Uganda Martyrs Housing and Construction
Company Ltd (UMHCC) signed a contract on 2 nd Dec 2022 for the Emergency Opening and
Improvement of Security Roads totaling to 112 km in Karamoja Sub-Region under Lot 2;
Karisarik-Magos-Naput (80Km) and Kobebe-Kalongolemuge-Nakapelimoru (32Km). The
Contract Price VAT inclusive, is UGX 23,690,925,719 (Twenty-Three Billion Six Hundred
Ninety Million Nine Hundred Twenty-Five Thousand Seven Hundred Nineteen Uganda Shillings
Only). Works commenced on 10 th January 2023 with an expected completion date of 11 th July
2024.
The physical progress of the project to date stands at 75.9% against the scheduled time
progress of 55.5% while the financial progress including general preliminaries is at 62.45%.
For details, refer to October 2023 Progress Report i.e. Annex A1.
In order to enable the completion of the project, we (PMT) raised a detailed verification of
works on 6th Sept 2023 for your adoption and onward management. Refer to the Site
Inspection Report (Annex A3).
a) To bring to the CMT’s attention quantities overruns affecting the project implementation.
b) Critical drainage structures that were omitted and their cost implications.
c) The cost implications if the project omitted structures were to be erected and overrun
quantities executed.
Refer to bill item 21.01 (a), the BOQ quantity is 10,080m³. However, from the survey data
(refer to Appendix 1), the additional quantity required is 150,307.36m3 as shown in table 1
below. The raise in quantities is due to a need for open drains, mitre drains, catch water drains
in order to minimize on the souring of the roads given the low laying terrain. Also, the
increment in the quantities is due to the need for river training on major and minor river
crossing as many are wandering rivers. The additional cost is UGX 2,254,610,400/= against
the BOQ cost of UGX 151,200,000/=. Refer to Annex A4.
Table 1:Change in quantities and cost of open drains for executed works.
Bill Rate Addition BoQ
BoQ Qty Additional
item Description (UGX) al Qty Amount
(m3) Amount (UGX)
no. (m3) (UGX)
Excavation
for open
21.01(a) drains on 15,000 10,080 150307.36 151,200,000 2,254,610,400
both road
section.
2.2. Bill Item 31.01 (a); Bush Clearing and Grubbing.
From the bill item 31.01 (a), the specified road clearing and grubbing is 9m wide. However,
in the typical road drawings it’s 12m. However, given that it’s common practice that drawin
gs take precedence over the Bill of Quantities (BOQ), the CMT instructed that typical
drawings be used. This resulted in an additional quantity of 29.9ha against the BOQ quantit
y of 100.8ha hence a financial increment of UGX 291,936,000 against the BOQ cost of U
GX 1,008,000,000/=. Refer to table 2 and attached Annex A2 1st CMT Management
meeting minutes.
Table 2:Additional cost due to increase in quantity of bush clearing & grubbing
Bill item Descriptio Rate BoQ Qty Additional BoQ Amount Additional
no. n (UGX) (m3) Qty(m3) (UGX) Amount (UGX)
Table 4:Indicates additional cost due to increase in quantity due to extra common
excavation.
Technical advice was sought from the MoWT Bridges’ team on the suitable drainage
structures given the terrain. They visited the roads and their costings are as shown in table
10 below whereas the report is shown in appendix 2.
Kobebe-Kalongolemuge-Naput (Road2)
Table 9:Summary of the estimated cost verses the original contract amount
Additional
Series Description BoQ Amount (UGX)
Amount (UGX)
Table 10: Showing estimated cost for proposed drainage structures by Drainage’s
team(MoWT)
Given that some quantities were either lower in the BoQ than the ones required or
construction and safeguarding of the roads or critical structures not considered for
continued continuity, a financial overrun would not be avoided. Below is the analysis of
different options that bring about overruns.
Given that all the additional works proposed are critical, then Variation Options 2 and 3 are
the most suitable for the project. However, comparing the costs for the two options and
their suitability given the terrain, Option 3 is more suited for the task.
4.0 RECOMMENDATIONS
b. There is a need for the CMT to recommend to Top management to approve the
recommended financial appraisal variation option 3 to enable continued continuity.
5.0 CONCLUSION
b. The funds provided for in the BoQ are not adequate to cater for the additional in order
to make the road motorable. The additional are due to the absence of design data during
the billing phase since the reconnaissance survey was aerially conducted.
c. Given that all the additional works proposed are critical, then Variation Options 2 and 3
are the most suitable for the project. However, comparing the costs for the two options
and their suitability given the terrain, Option 3 is more suited for the task.
ATTACHMENTS: