Professional Documents
Culture Documents
BSBPMG533
Manage project cost
Table of Contents
INTRODUCTION....................................................................................................................4
I. DETERMINE PROJECT COSTS .....................................................................................5
1.1 ............ Identify Resource Requirements for Individual Tasks Identified in the Work Breakdown
Structure in Consultation with Relevant Stakeholders ....................................................................... 6
1.1.1 What is a Work Breakdown Structure? ............................................................................. 6
1.1.2 Determining the Resource Requirements ........................................................................... 8
1.1.3 Input from Stakeholders and Guidance from Others ..................................................... 19
1.2 .................... Estimate Project Costs for Project Budget to be Prepared within Agreed Tolerances
.......................................................................................................................................................... 22
1.2.1 Types of Costs Included in a Project’s Budget................................................................. 22
1.2.2 Tools and Methods Used to Estimate and Analyse Costs................................................ 23
1.2.3 Estimating Costs within Agreed Tolerances .................... Error! Bookmark not defined.
1.3 ................................................................................................................ Develop a Project Budget
.......................................................................................................................................................... 28
1.3.1 Process of Developing a Project Budget ........................................................................... 29
1.3.2 Options for Project Management Software...................................................................... 29
1.3.3 Appropriate Budgeting Techniques .................................. Error! Bookmark not defined.
1.3.4 Formats for Presenting Budget Estimates ........................................................................ 30
1.3.5 Putting the Budget Together.............................................. Error! Bookmark not defined.
1.4 .... Develop a Cost-Management Plan for Project Finances According to Scope of Responsibility
.......................................................................................................................................................... 38
BSBPMG533 2
II. MONITOR AND CONTROL PROJECT COSTS ........................................................41
2.1 .......Implement Agreed Financial-Management Processes and Procedures for Monitoring Actual
Expenditure Against Budget ............................................................................................................. 42
2.1.1 Implement Agreed Financial-Management Processes .................................................... 42
2.1.2 Monitor Actual Expenditure Against Budget .................................................................. 43
2.2 ............................................................ Identify Cost Variations and Evaluate Alternative Actions
.......................................................................................................................................................... 48
2.2.1 Alternative Actions for Variances ..................................................................................... 51
2.3 ............................. Implement and Monitor Agreed Actions for Maintaining Financial Objectives
.......................................................................................................................................................... 55
2.4 ............................................................................. Provide Accurate and Timely Financial Reports
.......................................................................................................................................................... 55
III. COMPLETE COST-MANAGEMENT PROCESSES ................................................59
3.1 .........Conduct Activities to Signify Financial Completion According to Task and Organisational
Requirements .................................................................................................................................... 60
3.2 ...................................................................... Review Project Outcomes Using Available Records
.......................................................................................................................................................... 62
3.3 ................................................... Review Cost-Management Issues and Document Improvements
.......................................................................................................................................................... 65
REFERENCES .......................................................................................................................71
BSBOPS501 3
Introduction
The ability to manage project costs is vital for the project manager. The skills that you learn in this
unit will prepare you for project management cost processes and documentation and be accountable
for the cost performance of your project. Please take part in all activities in this Learner Guide as they
will activate your learning.
The process of managing costs will vary according to the phase of the project. For example, managing
costs in the planning stages involves a detailed analysis of the labour needed to accomplish the
project. By breaking this down into components, it can be costed. You will also learn the five most
commonly used estimation techniques so that you can forecast costs accurately. Next, you will learn
how to create a budget that includes contingencies for the ‘unknown unknowns’ and ‘known
unknowns’.
Once a project has commenced, you will need to track and report on the cost performance of the
project using Earned Value Management techniques and formulae. You will find out how to
determine if your cost blowout is significant and needs attention, and some common causes and
corrective actions. Finally, you will learn how to plan and execute your project’s closure and review
the project’s success.
BSBPMG533 4
I. Determine Project Costs
In this chapter, you will learn about the first step of managing project costs, which is determining
project costs at the start of the project. This step is vital as the costs that you estimate and include in
the budget at the start of the project will determine the performance and success of the project as a
whole.
There are four steps or elements in determining project costs. Firstly, this chapter will introduce you
to the Work Breakdown Structure (WBS) and how to create or use this document, along with input
from stakeholders and others, to determine the resource requirements for specific tasks.
Next, you will determine how to estimate project costs, develop a budget, and develop a plan that will
show how finances will be managed during the project.
In later units, you will learn more about monitoring and controlling costs as the project deliverables
are created, and how to finalise financial activities and review project cost management at the
completion of the project.
BSBOPS501 5
1.1 Identify Resource Requirements for Individual Tasks
Identified in the Work Breakdown Structure in
Consultation with Relevant Stakeholders
The first step in determining resource requirements for your project is creating or understanding your
project’s Work Breakdown Structure.
Note that the words ‘task’ and ‘work package’ are used interchangeably and refer to the
smallest unit of work which you will include.
Once the deliverables are known, the tasks or units of work are added to the branches of the tree.
There may be several levels showing the sub-components needed to create the end products.
BSBPMG533 6
The purpose of determining resource requirements for individual tasks is to determine the total
amount of work and cost of work. This is done by summing up the cost of individual tasks. The total
labour costs will be needed to prepare the overall project budget.
Using a WBS, you can check that all tasks are covered and that there are no gaps or overlaps in the
tasks for the project
Figure 2: Work Breakdown Structure of developing a new toy, adapted from projectinsight.com.
BSBOPS501 7
1.1.2 Determining the Resource Requirements
Resource requirements refer to the means used to perform specific tasks to achieve the objectives.
These include human resources, equipment, work conditions, funds, and information.
It is important to determine the resource requirements yourself as a project manager, rather than using
the WBS from a client or another source without checking the information. Whether you are using
Jira, Confluence, GanttPRO, Slack, Project or another project management software, the process you
follow in determining resource requirements is the same.
When determining resource requirements, you will need the following resources:
Work Breakdown Structure, detailing the units of work that are needed for each
deliverable. A list of all activities can be generated from the WBS.
Human Resource Management Plan or similar, detailing the project staffing attributes
and personnel rates, including those for external contractors. Knowledge about staff
attributes will help you to determine which staff member can be allocated to which
unit of work. A Resource Calendar, if available, will provide information on which
days and shifts each resource is available during a work activity period, which will
assist in estimating resource availability.
You may need expert help input such as stakeholder input in allocating units of work
to job roles. Stakeholders are people who are not directly working on a project but who
have something to gain or lose by the success of the project. They may include
managers and senior management, vendors, clients and more. Input can vary from
meetings and briefings, mentoring, informal conversations to formal training.
Schedule Management Plan. The Schedule Management Plan is created during the
project’s Planning Process Phase and is considered a component of the Project
Management Plan (PMP). It defines how the project schedule is managed throughout
the project lifecycle. Additionally, it provides guidance and sets expectations for
project schedule policies and procedures for planning, developing, managing,
executing, and controlling the project schedule.
This document also contains the level of accuracy, which you will use in determining
resource requirements.
BSBPMG533 8
The Process for Determining Resource Requirements
8. Document
2. Estimate the assumptions and
5. Add up costs of
duration of each constraints and
contractors.
activity or task. include in project
documents.
3. Determine the
4. Allocate each task
daily rate of
to a staff member or
contractors and
contractor.
current staff rates.
Figure 3: Process for determining resource allocation using the bottom-up method (from units of
work upwards) Further information about each step of the process is following.
BSBOPS501 9
5. Add up costs of contractors.
When doing this, refer to the section below on constraints. Constraints are items which
limit the project’s options. One major constraint you may face is the length of the term
of contractors. The contracts may need to have a minimum length or be a fixed term.
6. Determine total cost of resources, within an agreed margin of error.
This is done by adding all cost of resources. The agreed margin of error is agreed upon
by stakeholders and senior management before the project commences.
7. Provide resource cost documents in an agreed format, such as for each work
period or for each work package.
8. Document assumptions and constraints and include in project documents.
Write down the assumptions under which you operate and the constraints that limit the
options available to you in the project. For the virtual stylist app, the assumptions may
include assumptions of which devices, operating systems, or mobile platforms will be
supported and which are not.
BSBPMG533 10
Case Study
Thread, a long-established European clothing company, entered the Australian market in 2018.
Thread opened five flagship stores in Sydney, Melbourne, Brisbane, Adelaide, and Perth the
same year. Thread’s aim is to be one of the top five clothing retailers in Australia within three
years.
Thread is unique in offering stylists in their stores who offer free half-hour consultations with
job seekers. Thread’s website also offers a 24-hour stylist. However, the stylist is often booked
up weeks in advance. To provide further styling service to customers, Thread has decided to
offer a virtual stylist on its website. Customers upload a photo of themselves to the site, along
with key dimensions, and the virtual stylist will display Thread clothing on your photo, as well
as recommend sizes and items which will go with the customer photo.
BSBOPS501 11
Virtual Stylist
Online Tool
Evaluate Website
Function Design AI definition Internal testing
Requirements integration
BSBPMG533 12
STEP 1: Allocate each task or activity in the WBS or Activity List to a job role
First, you identify one or more job roles for each of the 14 work packages.
BSBOPS501 13
STEP 2: Estimate the duration of each activity or task
Secondly, you identify the duration of work needed for each task (this may involve a further
breakdown of the work packages into work tasks).
BSBPMG533 14
Work package Job role Number
of
days
needed
Training Trainer 20
Communications 10
Specialist
BSBOPS501 15
STEP 3: Determine daily rate of contractors and current staff rates
Website $400
Administrator
Communications $500
Specialist
Trainer $500
BSBPMG533 16
STEP 4: Allocate current staff to job roles
STEP 5: Add up costs of contractors for job roles not filled by current staff
Take limitations into account (e.g. contract length).
BSBOPS501 17
STEP 7: Provide resource cost documents in an agreed format, such as for each work
period or for each work package
Virtual stylist project: Work Breakdown Structure (outline format)
1. Analysis
1.1 Evaluate requirements 4/738 workdays = 0.5%
1.2 Produce detailed evaluation 20/738 workdays = 2.7%
1.3 Program Management 100/738 workdays = 13.6%
2. Design
2.1 Function design 42/738 workdays = 5.7%
2.2 System design 42/738 workdays = 5.7%
3. Development
1.1 AI definition 44/738 workdays = 6.0%
1.2 UI definition 16/738 workdays = 2.0%
1.3 Programming 360/738 workdays = 49.0%
2. Testing
2.1 Internal testing 10/738 workdays = 1.4%
2.2 Integration testing 10/738 workdays = 1.4%
2.3 User testing 10/738 workdays = 1.4%
3. Implementation
3.1 Website integration 30/738 workdays = 4.0%
3.2 Training 30/738 workdays = 4.0%
3.3 Early adopter feedback 40/738 workdays = 5.4%
249/738 of workdays to be filled by staff currently on payroll = 34%
BSBPMG533 18
STEP 8: Document assumptions and constraints and include in project documents
BSBOPS501 19
Some examples of stakeholder inputs are as follows:
Project Sponsor – Since the project sponsor keeps track of the project funding, you
can obtain information such as the intended budget for the project. Additionally,
project sponsors develop the initial scope of the project; thus, they can provide you
with information regarding the expected work tasks and deliverables to be produced.
Contractors – Contractors can provide you with information such as the capacity of
their labour force, specific details of the work they can provide, and the procedures for
doing such.
Human resource managers – Human resource managers hold information regarding
your organisation’s labour force, the corresponding roles or tasks of the members of
the labour force, and salaries. You can use this information in deciding the division of
tasks and the costs that will be incurred for the tasks done.
Project team members – Project team members perform technical work to complete
the project deliverables. Thus, you can obtain information such as specific tasks
corresponding to a role and elicit information such as additional equipment needed to
perform a specific task.
With the information at hand, you can determine the appropriate resource requirements for
the project to operate. However, it would be best if you elicited feedback after you have
drafted a list of the necessary resource requirements. This is to confirm that everything is clear
and ensure that no resource requirement is left out from the discussion.
BSBPMG533 20
Generally, the guidance that these qualified individuals offer may be in the form of reviews,
suggestions, clarifications, and expert advice. This is to ensure that facts and details are
accurate, identify flaws or discrepancies in the processes, and point out problem areas which
may potentially pose challenges in the future as the project progresses. Additionally, qualified
individuals provide valuable insights into the project environment and can assist you in
determining the most suitable methods.
Guidance may be obtained through various methods and channels such as face-to-face
meetings, email correspondence, phone calls, and peer review sessions.
Further Reading
For further information on creating a Work Breakdown Structure,
read this article on Matchware.
WBS Software
BSBOPS501 21
1.2 Estimate Project Costs for Project Budget to be
Prepared within Agreed Tolerances
According to the Project Management Institute, ‘Cost estimates are a prediction that is based on the
information known at a given point in time. Cost estimates include the identification and
consideration of costing alternatives to initiate and complete the project.’
Once the number of workdays for the project is known, and the Work Breakdown Structure has been
created or checked, the next step is to estimate the total costs of the project.
There are five ways that estimates can be made (refer to below). You can use more than one of these
methods within your budget.
Project costs are estimated in preparation for the actual project budget development process. This will
be discussed in the next element.
BSBPMG533 22
4. Indirect costs
These are costs that may be shared over several projects. For example, a Project Manager or
Consultant may be working on several projects at once, and therefore this cost is an indirect
cost.
5. Other
According to BrightHubPM, other factors can include costs which have already occurred and
are considered to be ‘sunk’, or not directly related to the deliverables of the project. For
example, pre-planning costs and licenses already purchased are sunk costs. There may also be
contingency/risk plans showing possible risks to cost.
1. Parametric estimating
2. Bottom-up estimating
3. Three-point estimating
BSBOPS501 23
1. Parametric estimating
This form of estimating uses a relationship between variables and historical data to calculate
the cost. For example, if you know the unit cost or duration and number of units required, you
can estimate the total cost so long as the variables are scalable.
Parametric estimating is widely used in construction. For example, Budget Direct has found
that the average cost of building a house in 2017–2018 was $313, 800 with an average square
meterage of 220.5. This amounts to $1,423 per square metre.
Using parametric estimating, the cost of a housing project can be determined from a square
meterage. However, use with caution as many other factors can also affect the price per
square metre, such as the location of the house, complexity, and luxury factors. The estimate
will be less accurate if the quantity is extremely large or small.
2. Bottom-up estimating
Bottom-up estimating is the process of estimating the value of small components and then
adding them up to estimate a total cost. It is typically used in calculating the cost of labour by
identifying the cost of each work package in the Work Breakdown Structure.
The main disadvantage of this method of estimating is that it is time-consuming to complete.
Accordingly, it has a high level of accuracy.
3. Three-point estimating
Three-point estimating is the method of estimating from optimistic, pessimistic and most-
likely values.
Two commonly used methods for three-point estimates are beta and triangular.
PERT (Program Evaluation and Review Technique) is based on the beta distribution. The
PERT estimate formula is, according to PM Study Circle:
𝑪𝒐 + 𝟒𝑪𝒎 + 𝑪𝒑
𝑪𝒆 =
𝟔
BSBPMG533 24
Where:
Ce
• Expected Cost
Cm
• Most Likely Cost
• This considers a typical case where everything goes as usual
Cp
• Pessimistic Cost, where many things go wrong during the project
Co
• Optimistic Cost, where everything goes better than expected.
𝑪𝒐 + 𝑪𝒎 + 𝑪𝒑
𝑪𝒆 =
𝟑
BSBOPS501 25
In estimating project costs, you can use the three tools mentioned below. These are:
1. Estimating software
2. Bottom-up estimating
In the bottom-up cost analysis, personnel who are involved in the project are interviewed, and
project processes are observed as they happen. This approach allows you to get a firsthand
idea of the different factors that go into driving up the project’s costs.
BSBPMG533 26
1. Analogous Estimating
In analogous estimating, values related to finances such as cost, and budget are used from
previous, similar projects as the basis to determine cost variations. Using this method, actual
values are used from previous, similar projects against estimated values in the current project.
2. Computation
In this method, the cost variations are determined by calculating the difference between the
Earned Value (EV) and the Actual Cost (AC). The resulting cost variation may be positive or
negative.
Three tools you can use to analyse project costs are the following:
5. Spreadsheets
BSBOPS501 27
3 Estimating Costs within Agreed Tolerances
When you set an estimate, you must include information about the level of tolerance that is included.
Tolerance refers to the amount of variance that will be tolerated, and who has permission to do this.
For example, a budget tolerance of 5 per cent within the project budget means the project manager
can deliver the project 5 per cent above or below cost without needing special permission from higher
managers or the Finance Department to do so.
The purpose of tolerance is so that stakeholders agree at the start of the project the number of budget
increases they will accept without taking up their time and effort in change requests and approvals for
minor budget increases. The project manager should get stakeholders to agree on an appropriate
tolerance and include it in the project documents.
During the project, if you believe your costs for a work package will be outside tolerance levels, you
will need to raise a formal change request to make your stakeholder aware of the issue and follow
the processes outlined in the next chapter. A change request is a formal proposal from the project
manager to senior management to alter a deliverable of a project.
The levels of tolerance should be set up before the project commences. The process of getting
agreement on tolerance is outside the scope of this unit.
Further Reading
To see an example of a budget for building a house, click on the link
below.
The cost to build a house in 2019
For examples of different variables in project cost management, click
the link below.
Types of Project Costs - Examples of the Different Variables in
Project Cost Management
Click the link below for more information regarding cost tolerances.
Project financial management: Tolerance
BSBPMG533 28
In developing a budget, you should be aware of the budgeting processes that should be standardised in
a workplace budgeting procedure. These are:
How to estimate the costs of a project
How to identify and mitigate project budget risks
How to record expenses (and income, if any) incurred
How to adjust project budget
How to monitor project budget
How to finalise the project budget at the end of the project
How to report on project budget
Cost estimates should be revised during the project and will become more accurate as the project
progresses.
Alternatively, project managers can simply use spreadsheets, which is good enough for itemising
expenses and other costs for the project. This helps the project manager identify all the expenses
needed to complete the project, including wages for labour, equipment, materials, and more. This data
is then used in determining the budget to be allocated for the project.
BSBOPS501 29
1.3.4 Formats for Presenting Budget Estimates
The estimate formats (i.e. outputs) stated below are covered in this chapter.
Project Funding
Cost-Management Plan
Requirements
Basis of Estimate
The purpose of the Basis of Estimate is to show how the project’s cost estimate was determined and
provide data which demonstrates the estimate ranges and confidence levels. All known assumptions
and constraints in regards to the project’s cost are included in the Basis of Estimate.
BSBPMG533 30
The Basis of Estimate contains the same line items as in the Activity Cost Estimate. However, it needs
to include more detail about each line item in order to show how each estimate was decided. Review
the example on the following page.
This Type of Costs Costs Amount Estim Method Any Informa Rang The
should resour direct not of ated used assumpt tion on e of degree
be the ce ly directly funding cost for this ions cost of estim of
WBS (labou relate attribut held in estimat used in quality, ate confide
number r, d to able to reserves e such develop interest nce in
from materi proje the for as ing the rate, or the
the al, ct project continge parame estimate other estimat
Work equipm work (utilitie ncies tric, such as e based
Breakd ent, (staff s, rent, analog labour on
own service salari security ous, cost per availab
Structu , etc.) es, , etc.) bottom- hour/da le
re suppl up, etc. y informa
ies, tion
Any
traini
constrai
ng,
nts such
etc.)
as
minimu
m
contract
terms
or
BSBOPS501 31
Basis of Estimate
Project: Date:
WBS Element:
Indicates The cost The An The total Includes The Explains Describes
which of work indirect of the any sum the which method
stage of materials cost for cost that material, reserve of all source was used to
the for this this line relates work cost costs of arrive at the
project line item. item. to this and designated for funding cost estimate.
the line line indirect for the the for this
item item. costs. line item. line section
belongs item. of the
to. project.
WBS Description: This description captures the scope of this line item. It can appear in the
WBS.
Cost Description: This section should provide details on how costs were calculated. If costs
were derived from vendor quotes, wage rates or other means, this information must be included in
this section.
BSBPMG533 32
Cost Baseline
Determining a project’s budget is a process of adding up the estimated costs of all activities, including
both direct and indirect costs, to create a Cost Baseline that can be approved. The Cost Baseline
provides a tool for monitoring and controlling the costs and performance of the project.
The cost (or budget) baseline is an essential and basic component of the budget. It states not only what
is to be spent but when it is to be spent. It can only be prepared once the project’s schedule has been
finalised. According to A Guide to Project Management Body of Knowledge (PMBOK), ‘the cost
baseline is the approved version of the time-phased project budget but excludes Management
Reserves’.
Developing a Cost Baseline requires all cost documents to date, which are the Activity Cost
Template, Basis of Estimate, Cost-Management Plan as well as the Resource Calendar or Work
Breakdown Structure, showing which resources will be spent and when, and the Project Schedule,
indicating the start and finish dates of all project milestones. The Cost Baseline also includes the
Contingency Reserve (refer to Section 1.3.4).
Project: Date:
BSBOPS501 33
Pre- Labour $30,00
planning 0
Equipme $5,000
nt /
Material
s
Equipme $20,000
nt /
Material
s
Equipme $20,00
nt / 0
Material
s
Equipme $25,00
nt / 0
Material
s
Equipme $10,00
nt / 0
Material
s
BSBPMG533 34
Completio Labour $30,0
n 00
Equipme $5,00
nt / 0
Material
s
Cost-Management Plan
The Cost-Management Plan is an important part of the project management plan that describes how
project costs will be managed. It is described further in Section 1.4.
The purpose of the Cost-Management Plan is to show who is responsible for managing the costs of
the project (the project manager), who has the authority to approve changes to the project or its
budget, and how the cost performance will be measured and reported on. It documents how costs will
be reported.
Putting the Budget Together
Total Management
Project Reserve
Budget
Cost Contingency
Baseline reserves
Work Activity
package Contingency
cost Reserve
estimates
including Activity Cost
all direct Estimates
and
indirect
costs
Figure 4 shows the components of a project budget. As in the diagram, the total project budget is
composed of components which are further broken down into sub-components.
BSBOPS501 35
According to the PMBOK, Management Reserve is ‘an amount of the project budget withheld for
management control purposes.’ Additionally, they are budgets reserved to fund any ‘unknown-
unknowns’ or unforeseen works within the project scope and which can affect a project’s budget. The
Management Reserve is set by management rather than the project manager and established according
to the organisation’s policies. Usually, it is a percentage of the overall budget, between 5 per cent and
15 per cent. The Management Reserve added to the Cost Baseline makes up the total project budget.
As in the figure, the Cost Baseline is composed of the work package cost estimates, including all
direct and indirect costs, and the Contingency Reserves. The PMBOK formally defines Contingency
Reserve as a ‘budget within the cost baseline or performance measurement baseline that is allocated
for identified risks that are accepted and for which contingent or mitigating responses are developed.’
In other words, Contingency Reserve covers the ‘known-unknowns’ that can affect a project into
account and are generally 5 per cent to 10 per cent, according to PMBOK. However, they can also be
a fixed number. Contingency reserves can be developed in conjunction with stakeholders. One of the
various formulae for calculating contingency reserve is:
𝑬𝑴𝑽 = 𝒑𝒓𝒐𝒃𝒂𝒃𝒊𝒍𝒊𝒕𝒚 (𝒑𝒆𝒓𝒄𝒆𝒏𝒕𝒂𝒈𝒆) 𝒙 𝒊𝒎𝒑𝒂𝒄𝒕 (𝒅𝒐𝒍𝒍𝒂𝒓 𝒂𝒎𝒐𝒖𝒏𝒕)
For example, if you know that a key staff member is likely to be required to work on another project
prior to completion of this project, the impact might be costed at a specific rate of $10,000. Say this
is 70 per cent likely to happen. The Contingency Reserve is then:
𝑬𝑴𝑽 = 𝟎. 𝟕 𝒙 $𝟏𝟎𝟎, 𝟎𝟎𝟎 = $𝟕, 𝟎𝟎𝟎
As the project progresses and there are fewer unknowns, it may be possible to reduce or even get rid
of the Contingency Reserve.
Referring again to Figure 4, the work package cost estimates are composed of The Activity Cost
Estimates and the Activity Contingency Reserve. The Activity Contingency Reserve refers to a
reserve (usually 5 per cent to 10 per cent) that accounts specifically for the risk within each activity
stated in the WBS.
To summarise, the Activity Contingency Reserve, when added to the Activity Cost Estimates, equals
the work package cost estimates. The work package cost estimates also include all direct and indirect
costs. When the work package cost estimates are added to the contingency reserve, they make up the
cost baseline. Then, when the cost baseline is added to the management reserve, the value represents
the Total Project Budget.
BSBPMG533 36
Checkpoint! Let’s Review
1. What is the difference between Management Reserve and
the Contingency Reserve?
2. What components make up the cost baseline?
3. What makes up the project’s total budget?
Further Reading
Click the link below to read an article about how to create a project
budget.
Creating a Project Budget – A Complete Guide for 2020
For more information on creating a budget or cost baseline, click the link
below.
Creating Budget Or Cost Baseline For Projects
Read more information on project management software by clicking the
link below.
Project Cost Management Software
BSBOPS501 37
1.4 Develop a Cost-Management Plan for Project Finances
According to Scope of Responsibility
Once the total budget amount and Cost Baseline and Project Funding Requirements documents have
been prepared, the next step is to develop the Cost-Management Plan. The Cost-Management Plan is a
component of the project management plan and describes how project costs will be planned,
structured, and controlled.
BSBPMG533 38
Scope of Responsibility
The scope of responsibility refers to the breadth and depth of a person’s role within an organisation.
For example, what duties a manager undertakes, the resources they are responsible for, and the areas
within an organisation they are assigned to. Within a Cost-Management Plan, the scope of
responsibility refers to who is accountable for each part of the project’s costs and what is involved
with upholding this responsibility. It is paramount that all stakeholders are aware of the role they play
around finances, resourcing and authorisation within the Cost-Management Plan.
Therefore, the Cost-Management Plan states who is responsible for managing the costs of the project
(the Project Manager), who has the authority to approve changes to the project or its budget, and how
the cost performance will be measured and reported on.
The cost-management plan documents the cost management reporting formats, tools, and techniques.
Additionally, the Cost-Management Plan states the following for the project:
1. Units of measure: For example, staff hours, days or weeks for time, metres, litres or tonnes
for quantity, currency.
2. Level of precision: How the cost estimates will be rounded up or down, for example, $99.95
to $100.
3. Level of accuracy: An acceptable range (such as plus or minus 10 per cent) for resource costs.
4. Links to organisational procedures: Utilisation of unique codes or account numbers in the
work breakdown system that link to the organisation’s accounting system.
5. Control thresholds: Generally expressed as a percentage, these are the amount that the cost
performance can differ from the budget before action is to be taken.
6. Units of performance measurement: Earned value management (EVM) rules of
performance measurement are an example. These indicate how the success of the project will
be measured as it goes along. Within Earned Value, there are four measures: Schedule
Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI), and Cost
Performance Index (CPI). If the SV is 0 and the Cost Variance is 0, the project is perfectly on
time and on budget. If the SPI and CPI are both 1, the project is perfectly on time and on
budget.
BSBOPS501 39
7. Reporting formats: Defines the formats cost reports are in, and how frequently they are to
be delivered.
8. Process descriptions: Descriptions of other cost management processes.
9. Additional details: Information about additional cost management activities, which could
include descriptions of funding choices, procedures to cater to currency rate fluctuations, and
procedures to record project costs.
Further Reading
Click the link below for a sample Cost-Management Plan.
Cost Management Plan
BSBPMG533 40
II. Monitor and Control Project Costs
In the previous chapter, you learned about determining project costs, including determining resource
requirements, estimating project costs, developing a project budget, and developing a cost-
management plan.
Now, the project enters into the implementation and monitoring stage. It is in this phase when the
plans previously set are put into action. Additionally, during this phase, you must establish processes
to ensure that the project goes as planned, tasks are performed as specified in the schedule, and costs
are spent within budget. However, no matter how carefully a project is planned, changes are
inevitable. As a project manager, it is your job to control the changes incorporated in the project, and
analyse and document the impacts that come with the changes.
This chapter will thoroughly discuss monitoring and controlling project costs, including:
Implementing agreed financial-management processes and procedures for monitoring actual
expenditure against budget
Identifying cost variations and evaluating alternative actions
Implementing and monitoring agreed actions for maintaining financial objectives
Providing accurate and timely financial reports
BSBOPS501 41
2.1 Implement Agreed Financial-Management Processes and
Procedures for Monitoring Actual Expenditure Against
Budget
In order to track actual expenditure against the budget, the following inputs are needed:
Project Funding
Cost Baseline Cost-Management Plan
Requirements
BSBPMG533 42
To do this, you may set a meeting with the stakeholders to review and agree on the financial-
management processes, as well as the procedures for monitoring actual expenditures, as reflected in
the cost-management plan. Aside from reviewing and agreeing, this meeting will serve to clarify any
questions that stakeholders may have.
BSBOPS501 43
Strategies for managing project costs
Listed below are some strategies which you can use in managing project costs. These are:
2. Performance Review
3. Forecasting
Earned Value Management (EVM): This integrates schedule, costs, and scope to determine
the project performance and measures the actual project performance in terms of being on
track with the budget. In this strategy, when managing project costs, comparisons are made
between actual values and planned values which can then help them predict the project’s
performance and adjust accordingly.
This strategy is often used in situations where there are variances in project costs, (e.g., higher
than expected, lower than expected) or where proper resources and personnel can be allocated
for monitoring and reporting
BSBPMG533 44
Forecasting: Forecasting predicts the costs and resources involved in completing a project. It
involves a formula (EV) that allows you to forecast future project performance, calculate delay
in the project and also establish why the delay may have occurred. In this strategy, project
managers are able to use historical and current project data to anticipate project costs and plan
resources accordingly.
This strategy is often used in situations where there is data available, that is useful for the
forecast or where it is necessary to plan the use of project finances due to limited resources.
Variance Analysis: The Project Management Institute, Inc. (2013) defines variance analysis
as ‘a technique for determining the cause and degree of difference between the baseline and
actual performance.’ Variance analysis can be done by using spreadsheets.
Project Management Software: A project’s success relies heavily on your ability to manage
the budget. There are a variety of programs available to support you in this. A Google search
will support you in identifying one that is suitable for your needs.
BSBOPS501 45
Process for Monitoring Expenditure
In monitoring expenditures, take note of the following information you need, such as:
Total budget for the tasks included within the scheduled time
Actual expenditure to date and future expenditure commitments. Both are compared with the
total budget within the scheduled time to obtain the balance of budget remaining.
Forecast Outturn, which describes the expected position of the project in terms of budget
Positive or negative variance analysis, including explanations, during the comparison of
expenditures and forecast outturn to budget. Additionally, you need a documented action plan
to address unfavourable variances.
To monitor project expenditure, you must manage the receipts properly. This can be done with the aid
of a cost-management software application previously discussed in this Learner Guide. In addition to
that, you must record expenses promptly. This means documenting these expenses as soon as possible
so as to avoid the likelihood of forgetting such expenses. A cost-management software application can
also be used to document expenses conveniently and promptly.
One important process to perform in monitoring expenditures is to conduct regular reviews. Weekly
reviews, for example, can mean the difference between fixing a budget about to run 15 per cent over
and a budget that has run 30 per cent over after a month. Using one of the tools mentioned can ensure
that measures can be put in place early to get back on track.
A situation wherein monitoring expenditures are necessary is when you decide to change the
allocation of funds from one area to another. Monitoring expenditures in one area or task of the
project allows you to see if there are extra financial resources that can be transferred to other areas or
tasks which are expected to go over the task budget. Another example would be when the organisation
decides to increase savings from the project.
Make it clear to stakeholders and team members that you are on top of the budget, and it is being
tracked at regular intervals. This will help avoid unwarranted costs and hours being charged for
services that may never have occurred or did not take as long as expected.
BSBPMG533 46
Carefully assess all ‘extras’ requested by stakeholders for impact and make it clear to the team that
this is occurring prior to them being added on. Small requests can unintentionally add thousands of
dollars to a project.
Further Reading
To learn more about Earned Value Management Systems, read the
conference paper written by Chance Reichel. You can access this
document by going to PMI's official website and typing 'Earned
value management systems (EVMS)' in the website search bar.
BSBOPS501 47
2.2 Identify Cost Variations and Evaluate Alternative
Actions
PMI’s PMBOK® Guide defines a variance as ‘a quantifiable deviation, departure, or divergence away
from a known baseline or expected value’ (PMI, 2004, p. 379). Two key measures of cost variations
are the Cost Variance (CV) and Cost Performance Index (CPI). These need to be included in any
Cost Performance Reports.
Before proceeding, it is important to define first the terms that are going to be used for the
calculations in the following paragraphs. These terms are:
Cost Variation: Also known as Cost Variance (CV), cost variation describes whether the cost
incurred from performing project activities cost more or less than the budget. In other words,
it indicates whether the project is financially performing well or not.
Cost Performance Index (CPI): This measures a project’s financial effectiveness and
efficiency by considering the ratio between Earned Value and Actual Costs.
In considering cost variations, it is equally significant to consider variations in the project schedule
since any delays in the project can result in cost overruns. To further understand this, take, for
example, renting heavy equipment for a week. If the task to be done using the equipment is not
completed within the specified week, you will have to rent the equipment again. This means
additional costs for the project. The relevant terms include:
Schedule Variance (SV): This quantitatively describes how much the project is ahead or
behind schedule
Schedule Performance Index (SPI): This is a measure of the project’s progress by
considering how close the project is to being completed based on the schedule.
Mathematically, this is the ratio between the Earned Value and Planned Value.
As mentioned, the Cost Variance is the difference between work performance (Earned Value) and
Actual Costs. It is expressed by the sum:
𝑪𝑽 = 𝑬𝑽 − 𝑨𝑪
For example, in the project above, EV = $100,000. However, if the actual costs of the project to date
have been $120,000, then:
𝑪𝑽 = $𝟏𝟎𝟎, 𝟎𝟎𝟎 − $𝟏𝟐𝟎, 𝟎𝟎𝟎
𝑪𝑽 = − $𝟐𝟎, 𝟎𝟎𝟎 (project running over budget)
BSBPMG533 48
To determine how much the project is under or over budget, use the Cost Performance Index. The
Cost Performance Index (CPI) is the measure of the efficiency of a project, the Earned Value divided
by the Actual Costs.
𝑬𝑽 𝟏𝟎𝟎,𝟎𝟎𝟎
𝑪𝑷𝑰 = 𝑨𝑪 = 𝟏𝟐𝟎,𝟎𝟎𝟎 = 𝟎. 𝟖𝟑
From Figure 5, A CPI of less than 1.0 indicates a cost overrun. Since the CPI calculated is 0.83, the
project is over the budget.
BSBOPS501 49
The Cost Performance Index is typically presented in a table which uses colour coding to indicate
how much the costs have overrun, as shown already in Figure 5. In the case of the CPI = 0.83, this
would be shown in yellow.
Schedule Performance Index (SPI) Between 0.9 and 0.8 or Less Than 0.8 or Greater
Between 1.1 and 1.2 than 1.2
Cost Performance Index (CPI) Between 0.9 and 0.8 or Less Than 0.8 or Greater
Between 1.1 and 1.2 than 1.2
Schedule Variance (SV) is the difference between the cost of work performed and the cost of work
scheduled; the Earned Value (EV) minus the Planned Value (PV). In the example above, the Earned
Value is $100,000. However, if the Planned Value of work to be completed within the same
timeframe is $76,000, then the calculation is as below.
𝑺𝑽 = 𝑬𝑽 − 𝑷𝑽 = $𝟏𝟎𝟎, 𝟎𝟎𝟎 − $𝟕𝟔, 𝟎𝟎𝟎 = $𝟐𝟒, 𝟎𝟎𝟎
This project has a positive Schedule Variance and is ahead of schedule. To work out how much the
project is ahead of schedule, use the Schedule Performance Index (SPI). It measures how close the
project is to being completed on schedule. This is very important as delays will cost money.
To calculate the SPI, divide the Earned Value by the Planned Value. For example, let us say that a
project is halfway through. The Planned Value, or work that was planned to be completed, is 50 per
cent of the total budget cost of $1 million ($500,000). However, the actual amount of work completed
is only $430,000. Therefore,
𝑬𝑽 𝟒𝟑𝟎,𝟎𝟎𝟎
𝑺𝑷𝑰 = 𝑷𝑽 = 𝟓𝟎𝟎,𝟎𝟎𝟎 = 𝟎. 𝟖𝟔 this case, the SPI is 0.86, indicating a schedule overrun that would be
shown in yellow.
BSBPMG533 50
2.2.1 Alternative Actions for Variances
According to actiTIME, there are five major reasons for cost overruns.
2. Estimation errors
3. Scope creep
4. Performance failures
According to consultants McKinsey & Co. and the University of Oxford (refer to Further Reading),
project cost overruns are common due to an overly optimistic estimation. Half of all large IT projects
massively blow their budgets, running on average 45 per cent over budget and seven per cent over
time.
BSBOPS501 51
1. Identify if variance needs to be acted upon – is it more than 0.2?
2. WHAT. Identify where the variance is in the Cost Baseline.
3. WHEN. When did the variance occur? Review the WBS components and schedule.
4. Identify WHY it happened. Was it labour overrun, materials overrun, indirect costs overrun?
Were materials defective? Keep asking why until you understand exactly why this occurred
without finger-pointing. Some people may be unwilling to give bad news, so make sure all
project team members know that you would like this information now rather than later. Take
time to fully understand the reasons why this occurred.
5. Take action. First of all, revisit the original documentation of the project to identify any
estimation errors, scope changes and to verify the validity of your business case. Ask the
question: What do I need to do next? This may include informing appropriate stakeholders of
all approved changes and associated cost; and bringing expected cost overruns within
acceptable limits. Review your resources and make sure that the right people are assigned to
the right tasks that they are competent for. You may need to move resources from non-critical
to critical tasks. Review the planned deliverables and strip out non-essential tasks without
sacrificing quality. Make sure review stages are managed efficiently, such as by scheduling a
meeting-based review.
Cost Performance Reports indicate the performance of the project using the performance measures
mentioned earlier, including Schedule Variance (SV), Cost Variance (CV), Schedule Performance
Index (SPI) and Cost Performance Index (CPI). These will provide stakeholders with a clear picture
of how the project is performing against expectations.
Regardless of whether your project is over budget or not, it is important to provide stakeholders with
regular and frequent (such as weekly) Cost Performance Reports. The process of producing Cost
Performance Reports will be discussed further in Section 2.3.
BSBPMG533 52
Below are the outputs in controlling Cost Variance.
Cost Performance
Report/Project
Performance Report Cost Baseline Cost-Management Plan
includes Cost Variance
Corrective Action Plan
BSBOPS501 53
Review your current plan as you won’t be able to solve the schedule issues unless you reorganise or
rearrange your current schedule, according to MyClientSpot. This may involve cutting down on
unnecessary items or working overtime. Be aware that cost, scope and time are closely linked, and
you cannot change one item without affecting another. Changes to time may affect quality, so make
sure you think through all the implications of schedule changes.
Further Reading
You can learn more about the causes of cost overruns from this article
by actiTIME.
5 Primary Causes of Cost Overruns
Click the link below to learn more about delivering a project from the
article by McKinsey and Co., (2012).
Delivering large-scale IT projects on time, on budget, and on value
MyClientSpot.com also provides information on dealing with a
project that is behind schedule. Click the link below.
A Step-by-Step Process of Dealing with a Project that is falling behind
Schedule
Additionally, you can read more information by reading an article
about over-budget projects. Click the link below.
What to do if your project runs over-budget, and how to prevent it
BSBPMG533 54
2.3 Implement and Monitor Agreed Actions for Maintaining
Financial Objectives
During the project, the project manager should monitor costs and deliverables on an agreed schedule
(such as weekly) and report on performance in a Cost Performance Report as already mentioned. It is
important that stakeholders are informed of and agree to this schedule.
The Cost Performance Report is provided for the following purposes.
1. As well as monitoring cost performance and identifying and understanding variances from the
Cost Baseline, it should monitor work performance (Earned Value) against the funds paid out
(Actual Costs).
2. The Cost Performance Report allows the project manager to check that the total costs of all
WBS components and activities do not exceed the authorised budget.
3. It shows whether change requests are documented, approved, and acted on promptly.
4. It prevents unapproved changes from being included in the reported costs or resource usage
5. It informs stakeholders of all approved changes and their associated cost.
6. It brings cost overruns within acceptable limits, such as by using a less expensive human
resource/contractor.
You should document all activities relating to costs so that stakeholders are not surprised at the end
of the project by the cost of each WBS component, each change request, or each minor cost overrun.
Added together, these can bring a project significantly over budget.
Include in your documentation the agreed actions to bring costs back under control, such as
maintaining a tight project schedule, using a less expensive human resource, increasing the budget to
fit a more accurate estimate, finding a less expensive vendor or material supplier, or limiting the
number of change requests.
BSBOPS501 55
such as the Activity Cost Template and the documents included in this manual. The report should
include all relevant details.
1. Although there are many different reports, the main purpose is to provide an account of the
project status at a specific point in time or after completion. As well as indicating the results or
performance of the project, a financial report provides a detailed analysis.
2. These reports may be communicated widely, and there are many templates available if necessary.
You may be asked to use project management applications or more specific accounting software,
or even Excel.
3. The format and style of reports will vary with your organisation, as will the policies you will
need to follow in reporting.
4. Whatever format is followed, the status report should:
Be logically structured
Be clear and easy to read
Be well-organised with short and concise paragraphs
Include terms of reference, summaries, and alternatives
Include results, conclusions, and recommendations
Be accurate.
5. In style, the status report can be either formal (long and including complex information) or
informal (less content and in a shorter format such as an email).
BSBPMG533 56
6. Essential components of a status report include:
High-level overview of the project status, divided into project identifiers, progress
summary, and overall project health and percentage completed
Project identifiers: These include the name of project, ID/identifiers, project manager’s
name and date
Progress summary: Includes high-level review of all project goals and progress made
towards them to date.
Overall project health and per cent complete: This is divided into the categories of
Scope, Budget, Timeline, Risks, Quality, Per cent Complete. Colour coding can be used
(green, on target; amber, less than 10 per cent behind target; red, more than 10 per cent
behind target). Refer to Further Reading for more information.
Project Milestones: After the high-level overview, the second section should include
information about progress towards each deliverable or milestone.
Risk Management and change requests: The third section draws attention to all project
issues, states new issues/risks, provides updates on the Risk Management Plan to mitigate
existing risks, and draws stakeholders attention to any change requests or issues that need
their attention.
The financial reports will bring together a wide range of existing records and information, including:
Banking information
Cash flow
Cost Baseline and Cost-Management Plan
Reports on variances, such as a Cost Performance Report and Cost Variance Corrective Action
Plan.
Typically, a financial report includes a written summary.
This summary provides stakeholders with information regarding a project’s financial goals and
financial progress.
The summary can then be used within discussions about project problems and the financial status
of the project.
Your financial report will provide details on the Earned Value of a project during a specified
period of time within a project. It can also be used to influence financial decisions, such as
whether to inject more funds into the project.
BSBOPS501 57
Checkpoint! Let’s Review
1. What are the essential components of a Project Status
Report?
2. What qualifies data as accurate?
3. What information do financial reports provide?
Further Reading
To see a template of a project status report, click on the link below.
Project Status Report Template
To learn more about Project Status Report Checklists, read this article
on Software Advice.
Your Project Status Report Checklist: Where to Include When
You Report to Stakeholders
BSBPMG533 58
III. Complete Cost-Management Processes
In the previous chapter, you learned about monitoring and controlling project costs, including
implementing agreed financial-management processes and procedures, identifying cost variations and
evaluating alternative actions, implementing and monitoring agreed on actions, and providing
accurate and timely financial reports. Now, the project approaches the closure stage.
In the closure stage, you must finalise cost-management processes, which includes completing
documents such as the Project Closure report. This is necessary in order to successfully deliver the
project and authorise the handoff of the project. Additionally, it is in this stage wherein you review all
project cost-management documentation to identify cost-management issues and supply
recommendations to improve actions. After which, these must be documented to be used as a
reference for future projects.
This chapter will thoroughly discuss completing cost management processes, including:
Conducting activities to signify financial completion according to task and organisational
requirements
Reviewing project outcomes using available records
Reviewing cost-management issues and documenting improvements
BSBOPS501 59
1.1 Conduct Activities to Signify Financial Completion
According to Task and Organisational Requirements
Project completion should be planned and commenced when the project has just started. It includes a
process of financial reconciliation, as well as finalising the project deliverables, closing contracts, a
Project Closure report or similar, and review of the project and its performance.
Project completion includes checking that the project has met all its objectives, including objectives
that were added along the way in change requests. All project documentation should be updated and
finalised. This phase can include meetings and review meetings or documentation.
Most companies have their own Project Management Policy that provides an outline to ensure
projects are completed timely and efficiently. They also include what to do and who to report to when
the project is complete. You can consult with senior management to locate this should it not be made
available to you. As the project manager, you are responsible for obtaining approval for the completed
work from the senior manager and/or the project sponsor or customer. Both organisational and task
requirements must be considered.
Organisational requirements are formalised, general requirements that apply to all project managers in
an organisation. Some examples are quality assurance, legal requirements, standards, and protocol.
Task requirements are specific to each individual project manager and may vary depending on the
nature of the project. For example, coordinating with team members, finalising contracts, and project
reviews/deadlines.
BSBPMG533 60
Performance Analysis: This contains the comparison between actual data and the baseline to
further support project accomplishments. In addition to that, project milestones summary and
financial summary may be provided to simplify the analysis.
Lessons Learned: This contains information regarding challenges and issues faced throughout
the project, including the actions taken to address these issues. Additionally, recommendations
may be provided to be used as a reference so as to avoid the same issues and challenges in future
projects.
Financial completion
Financial completion means that all the expenditure for a project grant has been financed. This
includes:
Final payments are made to vendors, with bonuses if necessary, so that the final work is
completed on time. The supplier is notified that this is the final payment.
All costs associated with the project should be charged to the project.
Reconcile monies spent and outstanding invoices against the original project budget in
addition to expected incoming invoices and the balance remaining after all invoices are paid.
The process and documentation must follow processes approved by the finance department;
the financial records are not reconciled until the finance department agrees.
Further Reading
Click the link below to access a template for a project closure report.
BSBOPS501 61
1.2 Review Project Outcomes Using Available Records
Project Reviews or post-project reviews are commonly completed both in meetings, discussions and
through formal documentation.
A Project Review has a number of purposes:
Summarises the project, its scope and staffing.
States the project deliverables (both planned and actual)
Provides a transition plan
Outlines the budgeted and actual costs for each phase of the project. Includes comments about
why costs were under or over budget where this occurred.
In line with those purposes, the processes followed on a project stated below will enable you to
review costs against actual outcomes:
Sending invoices on a regular basis (e.g. monthly)
Paying invoices received promptly
Checking for consistency across relevant financial paperwork
Regularly updating financial paperwork (e.g. daily or weekly)
BSBPMG533 62
Project review processes and procedures can vary between organisations, but they are essential to
future project success. Developing a review team ensures the process captures valuable data from a
variety of stakeholders. As a project manager, reviewing the key collection of reports, notes and
completion dates, for example, can support you in the review process. During review meetings, the
inclusion of interview questions can facilitate active participation and focus responses on specific
areas. After evaluating the findings, your role will involve producing a report. Findings support future
projects and help define best practice in performance.
The following processes will support the project completion report:
Exploring the overall costs and benefits of the project
Determining if goals were met
Considering customer satisfaction with the final product
Documenting the successes and recommendations
Exploring the positive and negative lessons
Gathering objective and honest data
Reviewing through a future-focused lens
Recording any corrective actions
Procedures that can support the processes above include:
A Gap Analysis: This helps companies assess their current performance in line with the
desired performance. It answers questions such as: Did the project deliver a quality product in
line with original objectives? Were there gaps in the project and if so, how will they be
addressed next time?
Data collection tools: Interviews, feedback forms and surveys, for example, help gather
valuable information from all stakeholders.
Independent reviewers: Enlisting the support of an external company to review the project
can gather objective data.
Present the report: Industry-specific templates can be used by organisations; however, word
publishing programs can be just as efficient when compiling the data.
BSBOPS501 63
Documents required to review project outcomes may include:
The Work Breakdown Structure (WBS).
Project Budget
Financial Report
Status Report
Cost Performance Report
Cost Management Plan
Project Funding Document
Project Schedule
BSBPMG533 64
1.3 Review Cost-Management Issues and Document
Improvements
Review Cost-Management Issues
In reviewing cost-management issues, you have to examine the details established during the
application of control processes in cost management. One of the control processes involved is the
iterative reviews of actual performance against cost-management plans. Iterative reviews give you an
idea of the issues which frequently arise and at what particular point/s in the project duration they
occur. For example, in reviewing delays in the creation of an output, information from the regular
iterative reviews conducted may tell you that it was not the pace of the project team members, but the
delivery delays from the suppliers end that led to the delay of the entire project.
Another process that you could examine is the performance analysis in the form of graphs and charts
to demonstrate progress against the budget. For example, through bar graphs, you could analyse the
actual expenses juxtaposed with the baseline budget for the month. You can point out issues as to why
the project went over the budget for this month but stayed within budget during the previous month.
Document Improvements
Costs may be impacted by scope creep, poor planning, schedule delays, optimistic estimates, or other
factors. In Section 2.2.1, five major reasons for cost overruns were discussed. Here, some possible
actions to overcome theme are listed. The appropriate action to take will depend on the exact
circumstances.
BSBOPS501 65
Major Reasons for Cost Improvement Actions
Overruns
Scope creep This can occur with poor estimation so follow the
actions above
Time tracking software allows managers to view
time on multiple projects
Develop and approve project documentation and
communication that allows stakeholders to smoothly
review and approve change requests
BSBPMG533 66
It is important to hold a Lessons Learned meeting to reflect on what further can be done to make
improvements for the next project. This should include a section of the Project Review that
documents and analyses of any cost management issues.
BSBOPS501 67
Project Phase Budgete Actual Cost Reason for
d Cos Varianc Varianc
Cost t e e
Analysis
Design
Development
Testing
Implement-
ation
HR
Man
age
ment
Procure
ment
Man
age
ment
BSBPMG533 68
Scope
Man
age
ment
Quality
Man
age
ment
Risk
Man
age
ment
BSBOPS501 69
Although the lessons learned and review documentation will include documentation of cost
management errors, a more thorough process of analysing and documenting cost management
improvements should be followed.
Begin by reviewing all project cost documentation, in particular the Cost-Management Plan,
performance measures, Project Status Reports or Cost Management Report, and Cost Variance Action
Plans to identify where costs overran and how effective your corrective actions were in controlling
costs. If any corrective measures were not effective, analyse why and how you could have improved
these. Summarise and document all cost improvements that can be made in the future to more
effectively control costs.
In your report, consider the five largest causes of cost overruns – weak risk management, estimation
errors, scope creep, performance failures, and weak project design. Make suggestions or
recommendations across each of these areas.
BSBPMG533 70
References
5 Primary Causes of Cost Overruns. (n.d.). ActiTIME. Retrieved November 2, 2020, from
https://www.actitime.com/project-cost-management/causes-of-cost-overruns/
Blackburn, M. (2020, February 24). How to Make a Cost Management Plan. ProjectManager.
https://www.projectmanager.com/blog/cost-management-plan
Closure – Project Closure Report. (n.d.). University of Washington Academic and Student Affairs.
Retrieved November 2, 2020, from https://www.washington.edu/asa/project-management-
draft/project-management-resources/templates/closure-project-closure-report/
Cost Management Plan. (2019, December 11). Project Management Docs.
https://www.projectmanagementdocs.com/template/project-planning/cost-management-
plan/#ixzz6Yd1iOSFD
Cost Management Plan: What, Why and How? (2020, September 10). BIT.AI Blog.
https://blog.bit.ai/cost-management-plan-what-why-and-how/
Definition of Agreed Financial Completion Date. (n.d.). Law Insider. Retrieved November 2, 2020,
from https://www.lawinsider.com/dictionary/agreed-financial-completion-date
Financial and Budget Management Good Practice Guidanced. (2019, April 18). University of
Sheffield. https://www.sheffield.ac.uk/finance/staff-
information/howfinanceworks/allocating_budgets
Ghioca, T. (2019, August 7). Creating Budget Or Cost Baseline For Projects. RationalPlan.
https://www.rationalplan.com/projectmanagementblog/creating-budget-cost-baseline-
projects/
Managing Costs on Your Project. (2018, August 25). Project Management Docs.
https://www.projectmanagementdocs.com/blog/managing-costs-on-your-
project/#axzz6cbNFzRfG
Project Budget Management. (2015). In PM4DEV. https://www.pm4dev.com/resources/free-e-
books/2-project-budget-management/file.html
Project Cost Management and Monitoring Techniques. (2009, November 26). Bright Hub PM.
https://www.brighthubpm.com/monitoring-projects/57317-tools-used-to-monitor-and-control-
costs-in-projects/
Project Cost Management Software. (n.d.). Software Connect. Retrieved November 2, 2020, from
https://softwareconnect.com/project-cost-management/
BSBOPS501 71
Project financial management: Tolerance. (2010, April 2). PM Tips.
https://pmtips.net/article/tolerance
Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) (6th ed.). Project Management Institute, Inc.
Quinn, J. (2012, June 20). What to do if your project runs over-budget, and how to prevent it. Project-
Management.Com. https://project-management.com/what-to-do-if-your-project-runs-over-
budget-and-how-to-prevent-it/
Reichel, C. W. (2006). Earned value management systems (EVMS) “you too can do earned value
management.” Project Management Institute.
Stempfley, T. (2013). Project Cost Management. Embry-Riddle Aeronautical University.
https://erau.instructure.com/eportfolios/8804/Monitoring_and_Controlling_Process_Group/7_
Project_Cost_Management
The cost to build a house in 2019. (n.d.). Budget Direct. Retrieved November 2, 2020, from
https://www.budgetdirect.com.au/home-contents-insurance/guides/buying-house/cost-to-
build-a-house.html
Types of Project Costs - Examples of the Different Variables in Project Cost Managementment.
(2009, November 3). Bright Hub PM. https://www.brighthubpm.com/project-planning/54894-
example-of-costs-in-project-management/
University of California. (n.d.). Schedule Management Plan Template. University of California Office
of the President. Retrieved October 29, 2020, from https://www.ucop.edu/information-
technology-services/_files/itlc/3.1-supporting-schedule-management-plan-template-with-
instructions.docx#:~:text=The%20Schedule%20Management%20Plan%20defines
Usmani, F. (2020, July 26). 4 Tools to Estimate Costs in the Project Management. PM Study Circle.
https://pmstudycircle.com/2012/06/4-tools-to-estimate-costs-in-the-project-management/
Viter, I. (n.d.). Creating a Project Budget – A Complete Guide for 2020. Forecast. Retrieved
November 2, 2020, from https://blog.forecast.it/how-to-create-a-project-budget
WBS Software. (n.d.). Matchware. Retrieved November 2, 2020, from
https://www.matchware.com/wbs-software
End of Document
BSBPMG533 72