Professional Documents
Culture Documents
Final Report On Assessment Concept Design and Layout For Proposed Rainwater Harvesting Infrastructure in Southwestern Bangladesh - 2
Final Report On Assessment Concept Design and Layout For Proposed Rainwater Harvesting Infrastructure in Southwestern Bangladesh - 2
Prepared by
Syed Azizul Haq, PEng
Architect Md. Ashraful Alum
Prepared by
1|P ag e
2|P ag e
Table of Contents
Executive Summary ........................................................................................................................... 1
1. Introduction .............................................................................................................................. 2
11.3.2. Model Site name: Munsiganj Degree College (building 1 and 2) ............................... 14
11.3.3. Major site Observation from Munshiganj Degree College site ................................... 29
11.4. Drinking water demand & Rainwater harvesting storage calculation ............................ 29
12. The details design of rainwater harvesting system for Mushiganj Degree College................. 37
13. Costing/BOQ of rainwater harvesting system at Munshuganj Degree College for four options
39
13.1. Option 1: According to ToR guidelines catchment area and storage tank ...................... 39
13.2. Option 2: Consultant recommended catchment area and According to ToR guidelines
storage tank ................................................................................................................................ 41
13.3. Option 3: According to ToR guidelines catchment area and consultant recommended
storage 43
13.4. Option 4: Consultant proposed catchment area and storage tank ................................ 45
iv | P a g e
Executive Summary
Due to climate change, saltwater intrusion is increasing in low-lying coastal areas of the
Bangladesh. Moreover, climate change will increase the frequency and intensity of disasters
like cyclone for example SIDR (2007) and AILA (2009) have caused massive havoc in the
coastal region of Bangladesh and destroyed most of the fresh water sources in this region.
Recent World Bank findings indicate that Climate change will cause significant changes in
salinity in the southwest coastal area of Bangladesh by 2050. These changes are likely to lead
to significant shortages of drinking water in the coastal urban areas, scarcity of water for
irrigation for dry-season agriculture, and significant changes in the coastal aquatic
ecosystems.
This report presents a study on potentiality of rainwater harvesting in institutional level which
conducted in five unions in Sathkira of Southern Bangladesh, quantifies the prospective
relationship between drinking water supply and demand, assessment of location specific
details survey, identification of suitable adaptation alternatives, and costing of adaptation.
This study also investigated institutional -scale rainwater harvesting (RWH) systems as a
water supply strategy to meet drinking water demands. It envisions collecting rainwater from
building roofs and routing it to a tank. Each building or building cluster would incorporate a
self-contained water supply system, including all facilities required to filter/treat/disinfect the
water to meet drinking water demands within and around the building(s).
These large-scale rainwater harvesting systems are as dependent on rainfall, and the proper
sizing of the storage tank. Examining an institutional-scale RWH system entails
considerations of the required facilities, the costs, the sustainability, the governance
requirements the conditions required to ensure a RWH strategy.
The study also has analyzed the appropriateness of RWH system components considering the
local context of Southern part of Bangladesh. Detail site information and site specific RWH
system design has been drawn for clear understanding the exact establishment of solving
water demand to particular area. Climate resilience modern materials versus local engineered
structural viability and the implementation consequences are deeply dig down to assess the
executional path way of RWH system in the institutional buildings. The detail costing of a
moderate size RWH system in Munshigonj Degree College has been developed to understand
per unit cost of infrastructure. Institutional arrangement is very much imperative and the
modality of management is covered in the study.
1. Introduction
Water scarcity is an abstract concept to many but a stark reality for every citizen of
Bangladesh like others. While we have ample sources of fresh water, people in the
southwest coastal region of Bangladesh experiences extreme shortage of fresh drinkable
water due to salinity. The struggle for the water in this part of the country is immense.
Scarcity of water is hampering in every sphere of life of the people living in the southwest
coastal part of Bangladesh. In spite of several interventions of government for bringing
out a positive change, little progress was made because of poor efficiency and
sustainability of the mitigating measures taken. Moreover, at times, the salinity issue was
even overlooked by the government. For example, according to BBS-2013, 98.5%
populations within the country have access to fresh water but this study did not
incorporate the issues of salinity, which would have significantly reduced the above
statistical data. Bangladesh is mostly a low lying flood plain with southern and south
western region is at sea level or only a meter or two above the sea level. The coastal
region of Bangladesh, especially the southwest region is being affected by the major
consequences of climate change, e.g. sea level rise, salinity intrusion, frequent natural
hazards and so on. Sea level rise would cause saline water to enter into the flood plains
and new areas, in each year, thereby increasing salinity marching with time. To draw
examples we might not have to look in near future. Over the last few decades, salinity is
engulfing new areas almost every year, which will have a huge impact on the accessibility
to potable water in the near future.
It is evident that fresh water crisis is rising and there is no other way out other than taking
immediate actions. We need strong devotion and collaborative work to mitigate this crisis
and bring stability in the lives of the people of the Southwest coastal regions. Against this
backdrop, RAiN Forum has initiated an in-depth pilot study for Satkhira district in order
to locate the effective, efficient and sustainable water solution for the people of the
southwest coastal region
2|P ag e
2.1. Catchment
Catchment is the area where rain water is collected. This can be the roofs in a rooftop
RWH system and the driveway, landscape or any other surface in a runoff system.
Catchment
3|P ag e
2.3. Filters
Filters are used to filter out the debris that comes with the rooftop water and prevent
them being added to the storage tank. There are various filter devices, which must be
chosen according to the purpose of using harvested rainwater.
Mesh filters – a wire mesh fixed at the mouth of or on the down pipe to
prevent leaves and debris from entering the system in water.
First-flushing devices – first flush device is a valve that ensures the runoff
from the earliest rains are flushed out and does not enter the system. (The
first rains carries relatively larger amount of pollutants and dust from the
air and catchment surface)
Filtration Chamber :
The chamber can be any size and can be placed anywhere. However it is
very effective to consider the water volume and flow rate to determine the
size of Filtration chamber. The chamber needs to maintain periodically and
for that the device should have easy access to maintain.
4|P ag e
Fig 2.4:Filtration Chamber
Material of construction
Position of tank
5|P ag e
Fig.2.5: A schematic diagram of a rainwater harvesting system (storage tank, below
ground)
6|P ag e
3. Rainwater harvesting efficiency
The efficiency of rainwater harvesting depends on the materials used, design and
construction, maintenance and the total amount of rainfall. A commonly used
efficiency figure, runoff coefficient, which is the percentage of precipitation that
appears as runoff, is 0.8. For comparison, if cement tiles are used as a roofing
material, the year-round roof runoff coefficient is about 75%, whereas clay tiles
collect usually less than 50% depending on the harvesting technology. Plastic and
metal sheets are best with an efficiency of 80-90%. For effective operation of a
rainwater harvesting system, a well-designed and carefully constructed gutter system
is also crucial. 90% or more of the rainwater collected on the roof will be drained to
the storage tank if the gutter and down-pipe system is properly fitted and maintained.
The main disadvantages of rainwater harvesting technologies are the limited supply
and uncertainty of rainfall. Rainwater is not a reliable water source in times of dry
periods or prolonged drought. Other disadvantages include:
Low storage capacity which will limit rainwater harvesting, whereas,
increasing the storage capacity will add to the construction and operating costs
making the technology less economically feasible
7|P ag e
Possible contamination of the rainwater with animal wastes and organic matter
which may result in health risks if rainwater is not treated prior to
consumption as a drinking water source
Leakage from tanks can cause the deterioration of load-bearing slopes
Storage tanks can be unsafe for small children if proper access protection is
not provided.
8|P ag e
It would appear that the potential for slight contamination of roof runoff from
occasional bird droppings does not represent a major health risk. Nevertheless,
placing taps at about 10 cm above the base of the rainwater storage allows any debris
entering the tank to settle on the bottom, where it will not affect the quality of the
stored water, provided it remains undisturbed. Finally, effective rainwater harvesting
schemes require community participation which is enhanced by:
Sensitivity to people’s needs
Indigenous knowledge and local expertise
Full participation and consideration of gender issues, and
Taking consideration of prevailing farming systems as well as national policies and
community by-laws.
Catchment types
Meteorological data
Design consideration
9|P ag e
11.1. Catchment Data
Tiled
CATCHMENTS RCC
Paved
Unpaved
Total catchment area of all exiting building of Munshuganj Degree College is 790 sq. meter
where according to ToR guidelines catchment area is 315 sq. meter.
Annual Rainfall
METEOROLOGICAL DATA
Rainfall Distribution
Peak Rainfall
Intensity
10 | P a g e
Table 11.2.1: Decadal average rainfalls for BMD stations in Bangladesh (Islam
and Morshed-2014)
Table 11.2.1 shows Decadal average rainfalls for in Satkhira and average yearly rainfall in
Satkhira is 1700 mm.
11 | P a g e
Fig: 11.2.1: Average Monthly rainfall data (mm) in Satkhira (2001-2013)
The following issues were taken into consideration before finalizing the sites:
Site Condition
Infrastructure survey including roof area, roof slope, and roof type.
Downpipe and gutters of exiting building.
Available space for installing reservoir, roof and filter medium.
Availability of locally manufactured material
Availability of local expertise for drilling, installation and maintenance.
Socioeconomic condition and affordability of the local people.
After we were satisfied with our mentioned prerequisites, we select 33 sites for further
analysis.
12 | P a g e
11.3.1. Key Social Findings of 33 sites
13 | P a g e
11.3.2. Model Site Profile: Munsiganj Degree College (building 1 and 2)
14 | P a g e
Land elevation (Mean Sea 6 ft. (Google earth)
Level)
Highest Flooding Depth During Cyclone Aila, 4 ft.
Groundwater level (ft.) 200 ft. (Apporx) local opinion
Drinking water tube well No
Total perimeter 450 meter
Site boundary available 160 meter
Nearby surface water Yes, 50ft
(ponds) source and distance
15 | P a g e
Road network condition Moderate
from site to Upazilla Sadar
Building Information
Number of floor Two, Single
Roof dimension (m) Two storied building (16.5X8)
Single storied building 1 (28X6.5)
Single storied building 2 (11X7.7)
Semi Pacca Building 1 (16.4 X 7.7)
Semi Pacca Building 2 (16.6 X5.6)
Semi Pacca Building 3 (22 X 8)
Under construction building (32 X 10)
Two storied building
16 | P a g e
Single storied building 2
17 | P a g e
Semi Pacca building 3
18 | P a g e
Roof Condition and Two storied building (Good)
treatment Single storied building 1 (Roof treatment needed)
Single storied building 2 (Roof treatment needed)
Semi Pacca Building 1 (Need replacement of exiting tin shade)
Semi Pacca Building 2 (Need replacement of exiting tin shade)
Semi Pacca Building 3 (Need replacement of exiting tin shade)
Under construction building
Roof type: two storied RCC
building
19 | P a g e
Roof type: Single storied RCC
building 2
20 | P a g e
Roof type: Semi pacca Tin shade
building 3
21 | P a g e
Construction completions 2002 and 2005
Evidence of leakage on N/A
existing pipe network
Number of toilets in building 4
22 | P a g e
Wet section of the top ceiling Yes
Broken PSF
23 | P a g e
Existing rainwater harvesting
storage for drinking purpose
of building occupants
Site boundary
24 | P a g e
25 | P a g e
Site boundary
26 | P a g e
Site boundary
27 | P a g e
Soil test
28 | P a g e
11.3.3. Major site Observation from Munshiganj Degree College site
Concrete Structure
There are three RCC building structures in Munshiganj Degree College site.
One is two-storied and the other two are single-storied. The condition of two-
storied building is better compared to both of the single-storied buildings.
Total land area of the Munshuganj Degree College is nearly 3 acres, where
0.8acre area is occupied by building structure, pond and monument. The rest
of the area is used for playground and waking way. Total perimeter of land
area is 450 meter, where the site boundary occupies only 160 meter.
29 | P a g e
The reservoir size calculation is based on below formula:
Size ( )=I A C
Where,
C=0.85, Coefficient
Volume, V (m³) = I × A × C
Where,
C=0.85, Coefficient
Type Catchment Annual volume Tank volume Tank type Tank location Length(m) Width(m) Depth/H Dia(m)
area(m²) of rainwater(m³) (m³) eight(m)
30 | P a g e
Table 11.4.2: Drinking water demand calculation of Munshiganj Degree College and nearby
village
Table 11.4.3: Monthly rainwater collection and distribution to the college students/staffs and
villagers
31 | P a g e
Table 11.4.3 shows the monthly volume of rainwater that can be collect from
Munshiganj Degree College catchment area. The consultant to provide drinking
water to the students/staff and nearby villagers from October to May and from June to
September the consultant to provide drinking water only to the students/staff of
Munshiganj Degree College.
32 | P a g e
11.5. The design consideration of rainwater harvesting system at
Munshiganj Degree College
33 | P a g e
34 | P a g e
11.5.2. Site location and risk factor
During cyclone AILA, Satkhira receives the highest amount of impacts in its
infrastructures including educational institutions, religious institutions, roads,
bridges, embankments etc. Among the unions of the Shyamnagar upazila
Munshigaj and Gabura were mostly affected. Local people and school
authority said that during the cyclone AILA the peak of the flooding was
about 4-feet at Mushiganj Degree College. The site is 1 km away from the
nearby canal, which is connected by a sluice gate of Malancho River.
As the site is near to coastal belt, it is vulnerable to tidal surge during cyclone.
In this regard all structure should be constructed with climate resilient
consideration. In order to improve the durability of concrete in moist saline
environments consider:
35 | P a g e
Consideration for brick works in moist saline environments: Using best quality
brick. The characteristics of best quality brick are
Size: Commonly used 9.5 x 4.5 x 2.75 inch size of bricks. Brick size
should be regular and uniform. Good quality bricks shouldn't exceed
the following tolerances in size -
In length they shouldn't exceed 3mm and in width and height 1.5 mm.
Color of bricks: Well burnt brick i.e. good quality bricks always have
uniform color. Over burnt or less burnt bricks loose its uniformity of
color on its surface as well as its strength. So, a good quality brick
having uniform color throughout can be red, cherry or copper-colored.
Well burnt bricks give metallic ringing sound when struck with one
another.
Surface finish: The surface of good quality brick should be free from
cracks, flaws, air holes and any defect or impurities. Broken surface of
good quality bricks should show uniform, compact and fine structure.
Water absorption: Good quality bricks don’t absorb water more than
20% of its dry weight when soaked 24 hours in cold fresh water.
36 | P a g e
12. The details design of rainwater harvesting system
for Mushiganj Degree College
Option 1: According to ToR guidelines catchment area and Steel storage tank above
ground
Pond
Under
Construction
Building Semi
Pacca
Road
Garden Single
Storied
Road
BH=1 Building
Catchment Area
Road
Double storied
Road
130.61 sqm
5000
Liter
tank
Shahid
Minar
Semi
Pacca
RAIN WATER
COLLECTION
TANK
340 cum
Ghat Toilet
Catchment Area
Single storied
184.38 sqm
Pond
Water
Tank
57.412 m
[188'-4"]
Tin Shed
Catchment Area-88.09 sqm
Catchment Area-123.75 sqm
Pond
Under Construction 3 storied bldg
Tin Shed
Road
Catchment Area
Double storied
Garden
130.61 sqm
Road
BH=1
Road
Catchment Area
Garden
Double storied
Road
Open
130.61 sqm
5000
Liter
tank
Open
Shahid
Minar
RAIN WATER
COLLECTION
TANK
800 cum
Ghat Toilet
Garden
Open
Catchment Area
Single storied
184.38 sqm
Pond
Water
Tank
57.412 m
[188'-4"]
37 | P a g e
Option 3: According to ToR guidelines catchment area and consultant recommended
storage tank below ground
Pond
Under
Construction
Building Semi
Pacca
Road
Garden Single
Storied
Road
BH=1 Building
Catchment Area
Road
Double storied
Road
130.61 sqm
5000
Liter
tank
Shahid
Minar
Semi
RAIN WATER Pacca
COLLECTION
TANK
340 cum
Ghat Toilet
Catchment Area
Single storied
184.38 sqm
Pond
Water
Tank
57.412 m
[188'-4"]
Option 4: Consultant proposed catchment area and recommended storage tank below
ground
Tin Shed
Catchment Area-88.09 sqm
Catchment Area-123.75 sqm
Pond
Under Construction 3 storied bldg
Tin Shed
Road
Catchment Area
Double storied
Garden
130.61 sqm
Road
BH=1
Road
Catchment Area
Garden
Double storied
Road
Open
130.61 sqm
5000
Liter
tank
Open
Shahid
Minar
RAIN WATER
COLLECTION
TANK
800 cum
Ghat Toilet
Garden
Open
Catchment Area
Single storied
184.38 sqm
Pond
Water
Tank
57.412 m
[188'-4"]
38 | P a g e
13. Costing/BOQ of rainwater harvesting system at
Munshuganj Degree College for four options
All options approximate cost is given below. The amount of the cost is
based on Public Works Department (PWD) price schedule.
39 | P a g e
3 Rain water harvesting tank (Diameter = 10.5 m, Height = 4m) Sedimentation Tank
Size: 3mx2mx2m
a) Supply and installation of Rain water harvesting tank made of galvanized steel frame
with an internal bladder including supply of hardware, consumables, fittings etc. all
complete approved and accepted by the Engineer.
liter 340,000.00 15.00 5,100,000.00
b) Earthwork in excavation for concrete base and sedimentaion tank of any dimension
in all kinds of soil including cutting up to required depth including bailing out water
and throwing on the embankment, breaking clods, ramming and leveling, dressing in
225 mm layer with maintaining the side slopes and level of both tank and the
embankment as per design and accepted by the Engineer.
cum 50.00 147.30 7,365.00
c) One layer of brick flat soling in concrete base with first class or picked jhama bricks
including preparation of bed and filling the interstices with local sand, leveling etc.
complete and accepted by the Engineer.
sqm 120.00 355.00 42,600.00
d) Reinforcement cement concrete works using steel shutter with minimum cement
content relates to mix ratio 1:1.5:3 having minimum fcr=26mpa,and satisfying a
specified compressive strength f'c=21mpa at 28 days on cyliders as per standard
practice of code ACI/BNBC/ASTM& Cement conforming to BDS EN-197-1-
CEM1,52.5N(52.5MPa)/ASTM-C 150 Type -i,best quality sylhet sand or coarse sand of
equivalent F.M 2.2 and 20 mm down well graded stone chip conforming to ASTM C-33
making, shutter, placing shutter in position and maintaining .making shutter water
tight properly,placing reinforcement in position,mixing with standard mixer machine
with hooper.All complete approved and accepted by the Engineer
cum 75.00 10,970.00 822,750.00
e) Supplying,fabrication and fixing to detail as per design:Ribbed or deformed bar
reinforcement for reinforced cement concrete(M.S Fabrication work,Fy=400MPa.)
kg 4,700.00 85.00 399,500.00
f) Formwork/shuttering, prop and necessary supports etc. sqm 15.00 391.00 5,865.00
g) Waterproffing & Desalt Chemical Admixture LS 1.00 250,000.00 250,000.00
4 Pit
a) Construction of masonry pit with 250 mm thick brick work in cement mortar (1:4)
including necessary earth work, side filling and one layer brick flat soling, 75 mm
thick (1:3:6) base concrete for making invert channel and 12 mm thick (1:2) cement
plaster with neat finishing etc. all complete up to a depth of 700 mm approved and
accepted by the Engineer.( Size: Clear 600 x 600 mm) each 4.00 6,882.00 27,528.00
b) Construction and placing of R.C.C. inspection pit cover (slab) in (1:2:4) with 1%
reinforcement excluding M.H. cover with locking/unlocking arrangement including
necessary earth work, side filling shuttering, curing, cement plaster (1:4) with neat
finishing on edges and top etc. all complete approved and accepted by the
Engineer.( Size: 900 x 900 x 75 mm )
each 4.00 1,309.00 5,236.00
5 Supply and installation Solar panel in position all complete approved and accepted
by the Engineer. LS 1.00 300,000.00 300,000.00
6 Filter Gravels materials cum 4.00 6,355.00 25,420.00
7 UV Filter LS 1.00 400,000.00 400,000.00
8 Pump each 1.00 25,000.00 25,000.00
TOTAL 7,880,897.00
IN WORD: TK. Seventy eight lac eighty thousand eight hundred and ninty seven only.
40 | P a g e
13.2. Option 2: Consultant recommended catchment area and
according to ToR guidelines storage tank
Bill of Quantity (BOQ) DATE: 26.01.17
Project: Cost Estimate for Rain Water Harvesting System of Munshigonj Degree LOCATION: SHYAMNAGAR,
College (Option 2) SATKHIRA, BANGLADESH.
Sl. No Item Unit Quantity Rate(TK) Amount (TK)
1 Catchment Treatment
a) 75 mm Damp proof course (DPC) (1:1.5:3) in cement concrete with cement, sylhet
sand (F.M. 1.2) and stone chips including breaking chips, screening, centering,
shuttering, casting, curing and finished with a coat of bitumen including the supply
of water, electricity and other charges and costs of tools and plants etc. all complete
and accepted by the Engineer. sqm 405 1,174.00 475,470.00
b) 125 mm brick works with first class bricks in cement sand (F.M. 1.2) mortar (1:4) and
making bond with connected walls including necessary scaffolding, raking out joints,
cleaning and soaking the bricks for at least 24 hours before use and washing of sand
curing at least for 7 days in all floors including cost of water, electricity and other
charges etc. all complete and accepted by the Engineer. sqm 22 837.00 18,414.00
2 Semi Paca Building Treatment(Tin Shed)
a) Labour & Material cost of MS Frame For Shed all complete and accepted by the
Engineer. sqm 400 2,700.00 1,080,000.00
b) Labour & Material cost of Cement Sheet all complete and accepted by the Engineer. sqm 400 1,075.00 430,000.00
3 Rain water collection and Supply
a) Supplying 100 mm inside diameter best quality uPVC rain water down pipe and
supply pipe fitting, fixed in position with head and shoes, bends, min.20 mm width
F.I. Bar clamp and nails, and including all accessories such as round grating/domed
roof grating bands, sockets approved and accepted by the Engineer. rm 210.00 642.00 134,820.00
b) Supplying 12mm inside dia wall thickness 2.8mm-3.3mm best quality ABS pressure
pipe for water supply having specific gravity 1.35 - 1.45, and other physical, chemical,
thermal, fire resistivity properties etc. as per BSTI approved manufacturer standards
or ASTM, BS/ISO/IS standards fitted and fixed in position with sockets, bends, with
all accessories approved and accepted by the Engineer. (length: 6000 mm each)
rm 20.00 439.00 8,780.00
c) Supply, fitting and fixing gutters in position with all accessories approved and
accepted by the Engineer. rm 140.00 425.00 59,500.00
d) Supplying, fitting and fixing best quality 12mm CP bib cock etc. complete approved
and accepted by the Engineer each 5.00 682.00 3,410.00
e) Supply and installation First flush diverter all complete approved and accepted by
the Engineer. each 12.00 10,000.00 120,000.00
41 | P a g e
4 Rain water harvesting tank ( Diameter = 14m, Height = 5.25 m) Sedimentation Tank
Size: 3mx2mx2m
a) Supply and installation of Rain water harvesting tank made of galvanized steel frame
with an internal bladder including supply of hardware, consumables, fittings etc. all
complete approved and accepted by the Engineer.
liter 800,000.00 15.00 12,000,000.00
b) Earthwork in excavation for concrete base and sedimentation tank of any dimension
in all kinds of soil including cutting up to required depth including bailing out water
and throwing on the embankment, breaking clods, ramming and leveling, dressing in
225 mm layer with maintaining the side slopes and level of both tank and the
embankment as per design and accepted by the Engineer.
cum 65.00 147.00 9,555.00
c) One layer of brick flat soling in concrete base with first class or picked jhama bricks
including preparation of bed and filling the interstices with local sand, leveling etc.
complete and accepted by the Engineer.
sqm 185.00 355.00 65,675.00
d) Reinforcement cement concrete works using steel shutter with minimum cement
content relates to mix ratio 1:1.5:3 having minimum fcr=26mpa,and satisfying a
specified compressive strength f'c=21mpa at 28 days on cyliders as per standard
practice of code ACI/BNBC/ASTM& Cement conforming to BDS EN-197-1-
CEM1,52.5N(52.5MPa)/ASTM-C 150 Type -i,best quality sylhet sand or coarse sand of
equivalent F.M 2.2 and 20 mm down well graded stone chip conforming to ASTM C-33
making, shutter, placing shutter in position and maintaining .making shutter water
tight properly,placing reinforcement in position,mixing with standard mixer machine
with hooper.All complete approved and accepted by the Engineer
cum 115.00 10,970.00 1,261,550.00
e) Supplying,fabrication and fixing to detail as per design:Ribbed or deformed bar
reinforcement for reinforced cement concrete(M.S Fabrication work,Fy=400MPa.)
kg 7,200.00 85.00 612,000.00
f) Formwork/shuttering, prop and necessary supports etc. sqm 20.00 391.00 7,820.00
g) Waterproffing & Desalt Chemical Admixture LS 1.00 400,000.00 400,000.00
5 Pit
a) Construction of masonry pit with 250 mm thick brick work in cement mortar (1:4)
including necessary earth work, side filling and one layer brick flat soling, 75 mm
thick (1:3:6) base concrete for making invert channel and 12 mm thick (1:2) cement
plaster with neat finishing etc. all complete up to a depth of 700 mm approved and
accepted by the Engineer.( Size: Clear 600 x 600 mm) each 14.00 6,882.00 96,348.00
b) Construction and placing of R.C.C. inspection pit cover (slab) in (1:2:4) with 1%
reinforcement excluding M.H. cover with locking/unlocking arrangement including
necessary earth work, side filling shuttering, curing, cement plaster (1:4) with neat
finishing on edges and top etc. all complete approved and accepted by the
Engineer.( Size: 900 x 900 x 75 mm )
each 14.00 1,309.00 18,326.00
6 Supply and installation Solar panel in position all complete approved and accepted
by the Engineer. LS 1.00 300,000.00 300,000.00
7 Filter Gravels materials cum 4.00 6,355.00 25,420.00
8 UV Filter LS 1.00 400,000.00 400,000.00
9 Pump each 1.00 25,000.00 25,000.00
TOTAL 17,552,088.00
IN WORD: TK. One crore seventy five lac fifty two thousand and eighty eight only.
42 | P a g e
13.3. Option 3: According to ToR guidelines catchment area and
consultant recommended storage
43 | P a g e
3 Under Ground Water Reservoir(UGWR) Size:17mX10mX2m Sedimentation Tank
Size: 3mx2mx2m
a) Earthwork in excavation of tank of any dimension in all kinds of soil including cutting
up to required depth including bailing out water and throwing on the embankment,
breaking clods, ramming and leveling, dressing in 225 mm layer with maintaining the
side slopes and level of both tank and the embankment as per design and accepted
by the Engineer.
cum 480.00 147.30 70,704.00
b) One layer of brick flat soling in concrete base with first class or picked jhama bricks
including preparation of bed and filling the interstices with local sand, leveling etc.
complete and accepted by the Engineer.
sqm 190.00 355.00 67,450.00
c) Reinforcement cement concrete works using steel shutter with minimum cement
content relates to mix ratio 1:1.5:3 having minimum fcr=26mpa,and satisfying a
specified compressive strength f'c=21mpa at 28 days on cyliders as per standard
practice of code ACI/BNBC/ASTM& Cement conforming to BDS EN-197-1-
CEM1,52.5N(52.5MPa)/ASTM-C 150 Type -i,best quality sylhet sand or coarse sand of
equivalent F.M 2.2 and 20 mm down well graded stone chip conforming to ASTM C-33
making, shutter, placing shutter in position and maintaining .making shutter water
tight properly,placing reinforcement in position,mixing with standard mixer machine
with hooper.All complete approved and accepted by the Engineer
cum 125.00 10,970.00 1,371,250.00
d) Supplying,fabrication and fixing to detail as per design:Ribbed or deformed bar
reinforcement for reinforced cement concrete(M.S Fabrication work,Fy=400MPa.)
kg 12,115.00 85.00 1,029,775.00
e) Formwork/shuttering, prop and necessary supports etc. sqm 750.00 391.00 293,250.00
f) Waterproffing & Desalt Chemical Admixture LS 1.00 500,000.00 500,000.00
4 Pit
a) Construction of masonry pit with 250 mm thick brick work in cement mortar (1:4)
including necessary earth work, side filling and one layer brick flat soling, 75 mm
thick (1:3:6) base concrete for making invert channel and 12 mm thick (1:2) cement
plaster with neat finishing etc. all complete up to a depth of 700 mm approved and
accepted by the Engineer.( Size: Clear 600 x 600 mm) each 4.00 6,882.00 27,528.00
b) Construction and placing of R.C.C. inspection pit cover (slab) in (1:2:4) with 1%
reinforcement excluding M.H. cover with locking/unlocking arrangement including
necessary earth work, side filling shuttering, curing, cement plaster (1:4) with neat
finishing on edges and top etc. all complete approved and accepted by the
Engineer.( Size: 900 x 900 x 75 mm )
each 4.00 1,309.00 5,236.00
5 Supply and installation Solar panel in position all complete approved and accepted
by the Engineer. LS 1.00 300,000.00 300,000.00
6 Filter Gravels materials cum 4.00 6,355.00 25,420.00
7 UV Filter LS 1.00 400,000.00 400,000.00
8 Pump each 1.00 25,000.00 25,000.00
9 Supply and installation of foreign made food grade stainless steel water tank (6000
liter capacity) including supply of hardware, consumables, fittings etc. all complete
approved and accepted by the Engineer. each 1.00 68,740.00 68,740.00
TOTAL 4,653,986.00
IN WORD: TK. Fourty six lac fifty three thousand nine hundred and eighty six only.
44 | P a g e
13.4. Option 4: Consultant proposed catchment area and storage
tank
45 | P a g e
4 Under Ground Water Reservoir(UGWR) Size:40mX10mX2m Sedimentation Tank
Size: 3mx2mx2m
a) Earthwork in excavation of tank of any dimension in all kinds of soil including cutting
up to required depth including bailing out water and throwing on the embankment,
breaking clods, ramming and leveling, dressing in 225 mm layer with maintaining the
side slopes and level of both tank and the embankment as per design and accepted
by the Engineer.
cum 1,150.00 147.30 169,395.00
b) One layer of brick flat soling in concrete base with first class or picked jhama bricks
including preparation of bed and filling the interstices with local sand, leveling etc.
complete and accepted by the Engineer.
sqm 450.00 355.00 159,750.00
c) Reinforcement cement concrete works using steel shutter with minimum cement
content relates to mix ratio 1:1.5:3 having minimum fcr=26mpa,and satisfying a
specified compressive strength f'c=21mpa at 28 days on cyliders as per standard
practice of code ACI/BNBC/ASTM& Cement conforming to BDS EN-197-1-
CEM1,52.5N(52.5MPa)/ASTM-C 150 Type -i,best quality sylhet sand or coarse sand of
equivalent F.M 2.2 and 20 mm down well graded stone chip conforming to ASTM C-33
making, shutter, placing shutter in position and maintaining .making shutter water
tight properly,placing reinforcement in position,mixing with standard mixer machine
with hooper.All complete approved and accepted by the Engineer
cum 290.00 10,970.00 3,181,300.00
d) Supplying,fabrication and fixing to detail as per design:Ribbed or deformed bar
reinforcement for reinforced cement concrete(M.S Fabrication work,Fy=400MPa.)
kg 28,500.00 85.00 2,422,500.00
e) Formwork/shuttering, prop and necessary supports etc. sqm 1,150.00 391.00 449,650.00
f) Waterproffing & Desalt Chemical Admixture LS 1.00 1,000,000.00 1,000,000.00
5 Pit
a) Construction of masonry pit with 250 mm thick brick work in cement mortar (1:4)
including necessary earth work, side filling and one layer brick flat soling, 75 mm
thick (1:3:6) base concrete for making invert channel and 12 mm thick (1:2) cement
plaster with neat finishing etc. all complete up to a depth of 700 mm approved and
accepted by the Engineer.( Size: Clear 600 x 600 mm) each 14.00 6,882.00 96,348.00
b) Construction and placing of R.C.C. inspection pit cover (slab) in (1:2:4) with 1%
reinforcement excluding M.H. cover with locking/unlocking arrangement including
necessary earth work, side filling shuttering, curing, cement plaster (1:4) with neat
finishing on edges and top etc. all complete approved and accepted by the
Engineer.( Size: 900 x 900 x 75 mm )
each 14.00 1,309.00 18,326.00
6 Supply and installation Solar panel in position all complete approved and accepted
by the Engineer. LS 1.00 300,000.00 300,000.00
7 Filter Gravels materials cum 4.00 6,355.00 25,420.00
8 UV Filter LS 1.00 400,000.00 400,000.00
9 Pump each 1.00 25,000.00 25,000.00
10 Supply and installation of foreign made food grade stainless steel water tank (6000
liter capacity) including supply of hardware, consumables, fittings etc. all complete
approved and accepted by the Engineer. each 1.00 68,740.00 68,740.00
TOTAL 10,646,823.00
IN WORD: TK. One crore six lac fourty six thousand eight hundred and twenty three only.
46 | P a g e
13.5. Cost Summary of four (4) RHS options
Option Types Amount in Storage Liter /BDT
BDT capacity(m ) (Storage )
Option 1 According to ToR guidelines catchment 7,880,897 455 17.32
area and storage
Option 2 Consultant recommended catchment area 17,552,088 1142 15.37
and according to ToR guidelines
Option 3 According to ToR guidelines catchment 4,653,986 455 10.22
area and consultant recommended storage
Option 4 Consultant proposed catchment area and 10,646,823 1142 9.32
storage
Option1:According to - Steel tank is easy to install at the - As the tank will be placed above
ToR guidelines site ground it will be required
catchment area and significant space in the campus.
storage tank
- Steel tank can be assemble
within a short time - Allocation of space for the tank
would not be possible in some
schools/colleges due to shortage
- Less periodical maintenance is of land.
required
- For single stored building the
roof height will be bellow of tank
- More protective from height. In that case the tank will
contamination be submerged in the ground.
- Sedimentation chamber/tank,
filtration chamber will be
difficult to arrange above ground.
47 | P a g e
- The proposed catchment area
will not be sufficient for meet up
the students demand round the
year.
-
Option 3: According to - As the tank will be constructed - Underground RCC water
ToR guidelines below the ground, no open space reservoir will required intense
catchment area and will be hampered. Moreover, It is construction care and expert
very convenient to collect supervision to ensure quality and
consultant recommended
rainwater from rooftop durability.
storage tank catchment area
48 | P a g e
- The RCC water reservoir will be - If the water level is shallow then
constructed with the local de-watering facilities should be
technician ensure to maintain proper
construction
- Concrete joint need additional
- The underground water reservoir care during construction
can be shaped as per site.
- The volume can be enhanced as
per demand - Cleaning the underground water
reservoir will be difficult and
need huge fresh water
- Repairing the reservoir will not
be difficult part
Option4:Consultant
proposed catchment area
Same as Option-2 and Option-3 Same as Option-3
and recommended
storage tank
49 | P a g e
13.7. Life Cycle Assessment of RWH System:
Components Catchment, Leaf First Flush Pipe, valves, Filter Storage tank
catcher and gutters Diverter all opening Materials &
in storage Sedimentation
tank Tank
Maintenance Minimum once per After each Before Annually Before starting
month or after significant starting or two rainy season
each significant rainfall. rainy season times (annually).
rainfall for (annually). during the
hanging vegetation rainy
site. season.
100% Leaf catcher and Can sustain Can sustain Can sustain Can sustain
Change gutters should be every 5 every 7 to 10 every 3 every 30 to 50
changed in every 3 years cycle years cycle years years cycle
to 5 years cycle
14. Recommendation
Government of Bangladesh, in its strategic paper, also highlighted the
importance of Rainwater Harvesting for mitigating the water crisis of this
region. The government realized that Rainwater Harvesting system would help
to ensure a sustainable water solution for this part of the country. Such system
can also contribute to bring about immediate positive impact on the water
crisis scenario of Satkhira region. The government has also proposed
desalination plant based on modern technology, as a solution to the prevailing
scenario. But such solution involves high cost and requires cost intensive
maintenance on a regular basis. On the other hand, RWHS is based on simple
technology, which involves bare minimum maintenance cost.
RAiN Forum believes that if rainwater harvesting system is installed in these
proposed 33 sites, then water crisis at Shyamnagar upazila would be reduce to
a considerable level. The plan of the project and the sites selected will ensure
that the mass people:
Via this plan, 100% fresh water will be ensured for the local community. On
the other hand, maintenance of the rainwater harvesting systems will also be
ensured.
50 | P a g e
14.1. Management and Institutional Arrangements
Institute Supporting Organization Support Activities
Trustee Board Monitoring Involved in a Network
Teacher and Guardian Maintenance Regular Training
Association Repairing Performance Monitoring
Upozila Education Office Management Reporting
Local Government Renovation Critical State
Councilor Management
Female Councilor
Chairman
DC/ADC
DPHE
Red Crescent
Rover Scout
Girls Guide
Water Stewardship
Students will enjoy the educational activities as well as the institution by performing the
leadership of the society.
51 | P a g e
Thus there would be developed so many new successful stories. Forming Water Stewardship
program, RAiN Forum suggest
1) Training
2) Execution
3) Networking
4) Self-sustaining development program.
RAiN Forum has devised this plan with a firm belief that the maximum sustainability and
efficiency of the rainwater harvesting system can be ensured by following the aforementioned
three phases, which are
Each of the phases has its own importance and thus be followed accordingly. All the
mentioned tasks in each of these three phases need to be conducted effectively thereby
ensuring the sustainability and maximum efficiency of the installed RWHS.
The amount of Rainwater that might be harvested may be insignificant but it is enough to
meet the demand of drinking water of the locality. At some places, the installed rainwater
harvesters had failed to ensure its sustainability. But such failure occurred only because of
lack of maintenance. In most of the cases, the installed rainwater fulfilled its promise of
ensuring the supply of potable water.
52 | P a g e
DRAWINGS of
Rainwater Harvesting System
For
Munshigonj Degree College, Shamnagar, Shatkhira, Bangladesh
Prepared By
23.467 m
[77']
Pond
Under
12.414 m
[40'-9"] Construction
16.400 m
Building 10.053 m
[33'] Semi [53'-10"]
Pacca
Road
Garden Single
Ro ad Storied 11.250 m
[36'-11"]
BH=1 Building
Road
Double
16.349 m
Storied [53'-8"]
5000
Liter
Building
tank
105.971 m
Shahid
[347'-8"]
Minar 100.990 m
[331'-4"]
Semi 22.257 m
Pacca [73']
BH=2
8.104 m
[26'-7"] 4.413 m
Toilet [14'-6"]
Ghat
0.727 m
[2'-5"]
Garden
Open
Single
26.594 m Storied
Building
Pond
[87'-3"] 28.249 m
[92'-8"]
Water
Tank
57.412 m
[188'-4"]
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title:
Site Plan of Munshigong Degree College Prepared By:
Name of the Building: Munshiganj Degree College
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj,
Shyamnagar, Sathkhira, Bangladesh. Page No: D-01 Date:26.1.2017 Scale: Not In Scale
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E
Semi
Pond Pacca
Under 2
Construction
Building Semi
Pacca
Road 1
Garden Single
Ro ad Storied
BH=1 Building
2
Road
Garden
Road
Open
Double
Storied
5000
Liter
Building
tank
Open
Shahid
33.317 m Open
Minar
[109'-4"]
Semi
Pacca
3
BH=2
Toilet
Ghat
Garden
Open
Single
Storied
Building
1
Pond
Water
Tank
57.412 m
[188'-4"]
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title:
Building Structure Layout Plan Prepared By:
Name of the Building: Munshiganj Degree College
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj,
Shyamnagar, Sathkhira, Bangladesh. Page No: D-02 Date:26.1.2017 Scale: Not In Scale
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E
Pond
Under
Construction
Building Semi
Pacca
Road
aer At ne mhct a C
dei r ot s el b uo D
Garden Single
Ro ad
BH=1 Building
Road
Road
5000
Liter
tank
Shahid
Minar Semi
Pacca
RAIN WATER
COLLECTION
TANK
340 cum
Toilet
Ghat
aer At ne mhct a C
dei r ot s el g ni S
mqs 83. 48 1
Pond
Water
Tank
57.412 m
[188'-4"]
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title:
Prepared By:
Name of the Building: Munshiganj Degree College Section (Moderate Catchment and Proposed Tank)
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj,
Shyamnagar, Sathkhira, Bangladesh. Page No: D-03 Date:26.1.2017 Scale: Not In Scale
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E
P P P P P P
P.L
G.L
Sedimentation
Tank
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title: Section: Moderate Catchment and
Prepared By:
Name of the Building: Munshiganj Degree College Above Ground Storage Tank
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj,
Shyamnagar, Sathkhira, Bangladesh. Page No: D-04 Date:26.1.2017 Scale: Not In Scale
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E
321- a er A t ne mhct a C
dehS ni T
Tin Shed
Catchment Area-88.09 sqm
Pond
Under Construction 3 storied bldg
Catchment Area-368.32 sqm
aer A t ne mhct a C
dei r ot s el buo D
mqs 16. 031
Road
Garden
aer At ne mhct a C
dei r ot s el b uo D
mqs 16. 031
Ro ad
BH=1
Road
Garden
Road
Open
dehS ni T
Liter
tank
Shahid
Open
Minar
RAIN WATER
COLLECTION
TANK
800 cum
aer At ne mhct a C
Toilet
Ghat
dei r ot s el g ni S
mqs 83. 481
Garden
Open
Pond
Water
Tank
57.412 m
[188'-4"]
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title:
Prepared By:
Name of the Building: Munshiganj Degree College Layout Plan (Maximum Catchment and Proposed Tank)
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj,
Shyamnagar, Sathkhira, Bangladesh. Page No: D-05 Date:26.1.2017 Scale: Not In Scale
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E
P P P P P P P P P P P
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title:
Prepared By: Flat- F3, RAZA Villa, 113 Lake Circus, Kolabagan,
Name of the Building: Munshiganj Degree College Section : Maximum Catchment and Proposed Tank Dhanmondi, Dhaka-1205, Bangladesh.
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj, Phone : +88 02 9121248, +8801713044077
Shyamnagar, Sathkhira, Bangladesh. Page No: D-06 Date:26.1.2017 Scale: Not In Scale
email : idyllicdesign11@gmail.com
aer At ne mhct a C
dei r ot s el b uo D
Garden Single
Ro ad
BH=1 Building
Road
Road
5000
Liter
tank
Shahid
Minar Semi
RAIN WATER Pacca
COLLECTION
TANK
340 cum
Toilet
Ghat
aer At ne mhct a C
dei r ot s el g ni S
mqs 83. 48 1
Pond
Water
Tank
57.412 m
[188'-4"]
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title: Layout Plan: Moderate Catchment and Prepared By:
Name of the Building: Munshiganj Degree College Under Ground Storage
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj,
Shyamnagar, Sathkhira, Bangladesh. Page No: D-07 Date:26.1.2017 Scale: Not In Scale
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E
P P P P P P
Sedimentation
Tank
Option 3: UNDP Proposed Catchment Area and Consultant Recommendation Storage Tank
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title: Section : Moderate Catchment and
Prepared By:
Name of the Building: Munshiganj Degree College Underground Storage Tank
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj,
Shyamnagar, Sathkhira, Bangladesh. Page No: Date:26.1.2017 Scale: Not In Scale
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E D-08
mqs 57. 321- a er A t ne mhct a C
dehS ni T
Tin Shed
Catchment Area-88.09 sqm
Pond
Under Construction 3 storied bldg
Catchment Area-368.32 sqm
aer A t ne mhct a C
dei r ot s el buo D
mqs 16. 031
Road
Garden
aer At ne mhct a C
dei r ot s el b uo D
mqs 16. 031
Ro ad
BH=1
Road
Garden
Road
Open
dehS ni T
Liter
tank
Shahid
Open
Minar
RAIN WATER
COLLECTION
TANK
800 cum
aer At ne mhct a C
Toilet
Ghat
dei r ot s el g ni S
mqs 83. 4 8 1
Garden
Open
Pond
Water
Tank
57.412 m
[188'-4"]
Sedimentation
Tank
UNDP Serial Number: 78,79 ,RF Serial Number :33 Drawing Title: Section: Maximum Catchment and
Prepared By: Flat- F3, RAZA Villa, 113 Lake Circus, Kolabagan,
Name of the Building: Munshiganj Degree College Underground Storage Tank Dhanmondi, Dhaka-1205, Bangladesh.
Location: Ward No - 01, Sardar Munsur Garaz, Munshiganj, Phone : +88 02 9121248, +8801713044077
Shyamnagar, Sathkhira, Bangladesh. Page No: Date:26.1.2017 Scale: Not In Scale
email : idyllicdesign11@gmail.com
35'-0"
C1 C1 C1 C1 C1 C1 C1
(12"X18")
(12"X18")
(12"X18")
(12"X18")
(12"X18")
(12"X18")
(12"X18")
SB-1
SB-1
SB-1
SB-1
SB-1
SB-1
SB-1
A' B' A' C' 129'-0"
A' C' A' B'
UNDP Serial Number:78,79RF Serial Number:33 Design By Drawing by: Review by: Drawing Title Page No:D 11 Consultant:
Name of the Building:Munshiganj Degree College Ar.Tanvir Chowdhury Date:
Syed Azizul Haq,PEng Dr.Afzal Ahmed Storage Tank Plan Flat- F3, RAZA Villa, 113 Lake Circus, Kolabagan,
Location:Ward No - 01, Sardar Munsur Garaz, Munshiganj, Eng.Md. Sohorab Hossain
Dhanmondi, Dhaka-1205.Bangladesh.
Ar.Md. Ashraful Alum Eng. Md. Moshiur Rahman
26.1.17
Shyamnagar, Sathkhira. Eng. Fuad Mollah
Phone : +88 02 9121248, +8801713044077
email : idyllicdesign11@gmail.com
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E Eng. Nowsad Akram
Naveed Ferdous
Details Section
UNDP Serial Number:78,79RF Serial Number:33 Design By Drawing by: Review by: Drawing Title Page No:D-12 Consultant:
Name of the Building:Munshiganj Degree College Ar.Tanvir Chowdhury Date:
Syed Azizul Haq,PEng Flat- F3, RAZA Villa, 113 Lake Circus, Kolabagan,
Location:Ward No - 01, Sardar Munsur Garaz, Munshiganj, Eng.Md. Sohorab Hossain
Dr.Afzal Ahmed Details Section 26.1.17 Dhanmondi, Dhaka-1205.Bangladesh.
Ar.Md. Ashraful Alum Eng. Md. Moshiur Rahman
Shyamnagar, Sathkhira. Eng. Fuad Mollah
Phone : +88 02 9121248, +8801713044077
email : idyllicdesign11@gmail.com
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E Eng. Nowsad Akram
Naveed Ferdous
5' 5' 5' 5'
16' 16'
SLAB
TIE DETAILS
COLUMN NOS.OF COLUMN
"3
ID REINFORCEMENT SIZE
12''
12''
C1 4-20mmØ
10mmØ@ 6"c/c
7'-0"
1) fy= 60,000 psi 1) fc'= 3,000 psi
2) Mix ratio 1 : 1.5 : 3
3) Use 100% sylhet sand (Minimum F.M.=2.5) fine aggregate
4) Use stone chips as coarse aggregate.
Cross Section
Existing Condition of Tin Shade Roof
Cross Section
Repairing Process of Tin Shade Roof
UNDP Serial Number:78,79RF Serial Number:33 Design By Drawing by: Review by: Drawing Title Page No:D 16 Consultant:
Name of the Building:Munshiganj Degree College Ar.Tanvir Chowdhury Date:
Syed Azizul Haq,PEng Flat- F3, RAZA Villa, 113 Lake Circus, Kolabagan,
Location:Ward No - 01, Sardar Munsur Garaz, Munshiganj, Eng.Md. Sohorab Hossain
26.1.17 Dhanmondi, Dhaka-1205.Bangladesh.
Ar.Md. Ashraful Alum Eng. Md. Moshiur Rahman Dr.Afzal Ahmed Repairing Process of Tin
Shyamnagar, Sathkhira. Eng. Fuad Mollah Shade Roof
Phone : +88 02 9121248, +8801713044077
email : idyllicdesign11@gmail.com
GPS Co-Ordinates: 22°15'59.1"N 89°09'07.6"E Eng. Nowsad Akram
Naveed Ferdous
Existing Debris
Chipping & Cleaning the Surface Apply one coat grouting with admixture
STEP-01 STEP-02
Avg. 3" thick C.C casting(1:2:4) with admixture Wire mesh in the casting
Apply two coat cement grouting with admixture
STEP-03 STEP-04
Fig 7.1: 3D view storage tank (above ground) of Munshiganj Degree College A
235 | P a g e
Fig 7.2: 3D view storage tank (above ground) of Munshiganj Degree College B
236 | P a g e
Fig 7.3: 3D view storage tank (partially above ground) of Munshiganj Degree College C
237 | P a g e
Fig 7.4: 3D view storage tank (partially above ground) of Munshiganj Degree College D
238 | P a g e
Fig 7.5: 3D view storage tank (below ground, Minimum potential) of Munshiganj Degree College E
239 | P a g e
Fig 7.6: 3D view storage tank (below ground, Minimum potential) of Munshiganj Degree College F
240 | P a g e
Fig 7.7: 3D view storage tank (below ground, maximum potential) of Munshiganj Degree College G
241 | P a g e