1 1 HBP R2 - SAP Project Schedule - All Solutions 111 days 18/04/2019 06/10/2019
3 3 Project Schedule 3 days 18/04/2019 22/04/2019 Project Manager[40%],SAP Procurement Process SME[40%],
4 4 Project Charter 5 days 21/04/2019 25/04/2019 Project Manager[40%],Sr Project Manager[40%],SAP Procure
7 7 SAP Ariba, Customer and FJ call to review Project Plan 0 days 28/04/2019 28/04/2019 SAP Procurement Process SME,Project Manager,Solution Ar
8 8 SAP Ariba and Customer confirm project schedule 2 days 29/04/2019 30/04/2019 HBP Core Team[50%],SAP Ariba[50%]
9 9 Review and sign off the Project Charter 2 days 29/04/2019 30/04/2019 HBP Core Team[50%]
10 10 SAP Ariba Overview Sessions 1 day 30/04/2019 30/04/2019 SAP Procurement Process SME,SAP Solution Architect,HBP
11 11 Customer registers as Designated Support Contact (DSC) 4 days 21/04/2019 24/04/2019 HBP Core Team
12 12 Project Kick Off 0 days 30/04/2019 30/04/2019 SAP Solution Architect,SAP Procurement Process SME,HBP
16 16 Present and Review the Solution Design Document 2 days 07/05/2019 08/05/2019 SAP Procurement Process SME[10%],HBP Core Team[40%]
17 17 Incorporate Feedback in Process Design 3 days 09/05/2019 13/05/2019 SAP Procurement Process SME[10%],eSourcing/eProcureme
18 18 Review and Signoff Solution Design Document 4 days 14/05/2019 19/05/2019 HBP Core Team[10%],Sr Project Manager,Solution Architect
19 19 Milestone: Process Design Sign off (Visios) 2 days 20/05/2019 21/05/2019 HBP Core Team[50%]
22 22 Hybris demo setup with and without SAP components 1 day 01/05/2019 01/05/2019 Lenin[10%]
26 26 Hybris Cloud Setup - Service and Sales 2 days 09/05/2019 12/05/2019 Surya[80%]
30 30 Filling with basic items (products, Items , etc.) 3 days 19/05/2019 21/05/2019 Lenin
31 31 Customizing Backoffice zk Framework 45 days 01/05/2019 09/07/2019 Java Developer for Hybris
Page 1
ID Task ID Task Name Duration Start Finish Resource Names
Mode
34 34 UI Design , HTML , CSS Styles 49 days 15/05/2019 29/07/2019 UI DESIGNER
35 35 Integrating Hybris Service and Hybris Commerce 2 days 11/06/2019 12/06/2019 Surya[50%]
43 43 Service Contract Mapping and SLAs creation 2 days 15/05/2019 16/05/2019 Surya
44 44 Test Development of Hybris and Trasnport Ready to QA 13 days 14/07/2019 30/07/2019 Surya[50%],Lenin,UIDesigner
45 45 Integration with S4 HANA with Hybris Cloud - Evaluate 39 days 14/07/2019 11/09/2019
48 48 Add Activities into Project for Integration 1 day 15/07/2019 15/07/2019 Surya[20%]
52 52 Create Users for the Integration Test 1 day 21/07/2019 21/07/2019 Basis
61 61 Configure and Deploy the iFlow Using SAP Web UI 3 days 19/08/2019 21/08/2019 Basis
Page 2
ID Task ID Task Name Duration Start Finish Resource Names
Mode
67 67 Maintain SSL Server Standard Trusted Certificate 1 day 25/08/2019 25/08/2019 Basis[10%]
68 68 Maintain SSL System Client Cert and Trusted Cert List1 day 25/08/2019 25/08/2019 Basis[10%]
75 75 iFlow Changes in SAP Cloud Platform Integration. 2 days 03/09/2019 04/09/2019 Basis
88 88 Create Authorization Role for Asynchronous Processing 1 day 30/07/2019 30/07/2019 Basis[5%]
89 89 Create Service User for Asynchronous Processing 1 day 30/07/2019 30/07/2019 Basis[5%]
98 98 Import the ImpEx File to SAP Hybris Commerce 1 day 05/08/2019 05/08/2019 Lenin[10%]
99 99 SAP Hybris Data Hub Base Configuration 1 day 05/08/2019 05/08/2019 Lenin[10%]
Page 3
ID Task ID Task Name Duration Start Finish Resource Names
Mode
100 100 SAP Hybris Commerce Backoffice settings 1 day 05/08/2019 05/08/2019 Lenin[10%]
102 102 Configure SAP Global Configuration 1 day 06/08/2019 06/08/2019 Basis[5%]
103 103 Upload SAP Configuration to SAP Hybris Data Hub 1 day 06/08/2019 06/08/2019 Lenin[10%]
107 107 Catalog Staging and Online Synch 1 day 19/08/2019 19/08/2019 Lenin[10%]
108 108 Update Customer Account Group in SAP Hybris Data Hub1 day 20/08/2019 20/08/2019 Lenin[10%]
111 111 Access to SAP HEC 1 day 01/05/2019 01/05/2019 Basis Consultant
112 112 Project Delivery Platform Setup 2 days 02/05/2019 05/05/2019 Basis Consultant,Solution Architect[30%]
113 113 Sandbox System Setup 3 days 06/05/2019 08/05/2019 Basis Consultant
114 114 Execute Technical Installation of SAP Products for DEV 2 days 09/05/2019 12/05/2019 Basis Consultant
environment
115 115 Execute Technical Upgrade of SAP Products for DEV 2 days 13/05/2019 14/05/2019 Basis Consultant
environment
116 116 Set up Role assignment / Authorizations / Test Users in DEV
1 day 15/05/2019 15/05/2019 Basis Consultant,Solution Architect[20%]
117 117 Perform Manual Configuration in DEV 3 days 16/05/2019 20/05/2019 Basis Consultant,FICO Consultant[30%],MM Consultant[30%]
119 119 Create Master Data in DEV Environment - Master Data #15-days
n 23/05/2019 29/05/2019 MM Consultant[40%],FICO Consultant[40%],SD Consultant[4
121 121 Setup Output Management 1 day 21/05/2019 21/05/2019 Basis Consultant
122 122 Setup User Interface (UI) Integration 2 days 23/05/2019 26/05/2019 Basis Consultant
123 123 Setup B2C Integration 3 days 27/05/2019 29/05/2019 CIG Consultant,MM Consultant[20%],SD Consultant[20%],FIC
124 124 Setup A2A Integration (On-Premise and Cloud) 3 days 30/05/2019 10/06/2019 CIG Consultant,FICO Consultant[30%],MM Consultant[30%],S
126 126 SAP Finance (FICO) 5 days 02/05/2019 08/05/2019 FICO Consultant[40%],Solution Architect[40%]
127 127 SAP Procurement (MM) 4 days 09/05/2019 14/05/2019 MM Consultant,Solution Architect
128 128 SAP Logistics (CPQ, SD, EWM and TM) 10 days 15/05/2019 28/05/2019 SD Consultant[40%],Solution Architect[20%]
129 129 SAP Projects (PPM, PS) 10 days 29/05/2019 18/06/2019 PPM-PS Consultant[60%],Solution Architect[20%]
131 131 Ensure Master Data Management Processes Ownership 2 days 19/06/2019 20/06/2019 CIG Consultant[50%],FICO Consultant[50%],MM Consultant[5
132 132 Conduct Data Mapping workshops (master data for pre-defined
2 dayssolutions)
19/06/2019 20/06/2019 CIG Consultant[50%],FICO Consultant[50%],MM Consultant[5
Page 4
ID Task ID Task Name Duration Start Finish Resource Names
Mode
133 133 Conduct Data Quality Assessment 2 days 23/06/2019 24/06/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
134 134 Define Automated Data Migration Approach 2 days 25/06/2019 26/06/2019 CIG Consultant[30%],FICO Consultant[30%],MM Consultant[3
135 135 Define Manual Data Migration Approach 2 days 25/06/2019 26/06/2019 CIG Consultant[30%],FICO Consultant[30%],MM Consultant[3
136 136 Prepare Data Quality Plan 2 days 27/06/2019 30/06/2019 CIG Consultant[30%],FICO Consultant[30%],MM Consultant[3
137 137 Prepare Data Security Design and plans 2 days 27/06/2019 30/06/2019 CIG Consultant[30%],FICO Consultant[30%],MM Consultant[3
139 139 REALIZE ARIBA ALL- General Data Collection 24 days 01/05/2019 10/06/2019
141 141 Review of Enablement Workbook - Draft 1 3 days 09/05/2019 13/05/2019 eSourcing/eProcurement Functional Consultant (SS) 2[10%],S
142 142 Fujitsu completes Enablement Workbook 16 days 01/05/2019 22/05/2019 eSourcing/eProcurement Functional Consultant (SS) 2[30%],e
143 143 Customer Validates the Enablement Workbook 2 days 23/05/2019 26/05/2019 Project Manager,Solution Architect Lead,HBP Core Team[50%
144 144 SAP Ariba loads Enablement Workbook data into Test site2 days 27/05/2019 28/05/2019 SAP Ariba
145 145 Solution Demo of Ariba Upstream Modules 2 days 09/06/2019 10/06/2019 SAP Procurement Process SME,eSourcing/eProcurement Fu
149 149 SAP Ariba reviews Custom Header Field Data Collection
2 days
Template 11/06/2019 12/06/2019 eSourcing/eProcurement Functional Consultant (SS) 2[50%],S
151 151 SAP Ariba configures custom header fields in Test site3 days 19/06/2019 23/06/2019 SAP Ariba[20%]
152 152 SAP Ariba reviews custom header field configuration with
1 day
FJ (including
24/06/2019
layout) 24/06/2019 eSourcing/eProcurement Functional Consultant (SS) 2[30%],e
153 153 Field configuration updated per feedback 3 days 25/06/2019 27/06/2019 SAP Ariba[10%]
155 155 Revisit/Finalize Design Matrix with customer 1 day 30/06/2019 30/06/2019 eSourcing/eProcurement Functional Consultant (SS) 2[80%],e
157 157 Review Process in Test site with customer 1 day 02/07/2019 02/07/2019 eSourcing/eProcurement Functional Consultant (SS) 2[20%],S
159 159 Process is updated per feedback 2 days 04/07/2019 07/07/2019 SAP Ariba[30%]
161 161 SAP Ariba reviews Savings Form Data Collection Template
1 day 08/07/2019 08/07/2019 SAP Ariba[20%],Solution Architect Lead[50%],SAP Procurem
162 162 FJ completes Savings Form Data Collection Template 2 days 09/07/2019 10/07/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
163 163 SAP Ariba configures Savings Form template in Test site
2 days 11/07/2019 14/07/2019 SAP Ariba[30%]
164 164 SAP Ariba reviews Savings Form Template 1 day 14/07/2019 15/07/2019 HBP Core Team[10%],SAP
configuration (including layout) Ariba[10%],eSourcing/eProcurement
165 165 Savings Form Template configuration updated per customer
1 day feedback
16/07/2019 16/07/2019 Functional
SAP Consultant
Ariba[20%]
Page 5
ID Task ID Task Name Duration Start Finish Resource Names
Mode
166 166 SOURCING - Configuration Freeze 2 days 17/07/2019 18/07/2019 SAP Ariba[20%],Project Manager[50%]
167 167 REALIZE - SOURCING - Training, Testing and Migration 19 days 03/07/2019 29/07/2019
to Production
168 168 Configuration Testing (Test Site) 5 days 03/07/2019 09/07/2019
169 169 Fujitsu will conducts Configuration Testing on the Test 2site
days 03/07/2019 04/07/2019 eSourcing/eProcurement Functional Consultant (SS) 2[30%],e
170 170 SAP Ariba makes changes based upon Configuration Testing
2 days 07/07/2019 08/07/2019 SAP Ariba[20%]
173 173 Training Documentation 5 days 03/07/2019 09/07/2019 eSourcing/eProcurement Functional Consultant (Supplier)[10%
174 174 Training schedule acceptance 1 day 10/07/2019 10/07/2019 Project Manager,HBP Core Team[50%]
175 175 Training Activities 3 days 11/07/2019 15/07/2019 HBP Bus-Ops [40%],HBP Core Team[30%],eSourcing/eProcu
176 176 Small Configuration Changes 2 days 16/07/2019 17/07/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
178 178 UAT Planning & Preparation - Logistics 3 days 03/07/2019 07/07/2019 Project Manager,SAP Procurement Process SME[50%],Soluti
179 179 Collect, review and approved the required data for Users
2 days
Testing 07/07/2019 08/07/2019 eSourcing/eProcurement Functional Consultant (Supplier)[20%
180 180 UAT Test Scripts - Preparation 3 days 07/07/2019 09/07/2019 eSourcing/eProcurement Functional Consultant (SS) 2[30%]
181 181 Review and approve the UAT Test Script 2 days 10/07/2019 11/07/2019 HBP Core Team[20%]
182 182 Conducting UAT Sessions 5 days 14/07/2019 18/07/2019 eSourcing/eProcurement Functional Consultant (SS)[30%],eS
183 183 Incorporate Feedback post UAT 3 days 21/07/2019 23/07/2019 SAP Ariba[40%],eSourcing/eProcurement Functional Consulta
186 186 REALIZE - SAP Ariba Supplier Lifecycle and Performance 37 days 11/06/2019 31/07/2019
187 187 REALIZE - Supplier Lifecycle & Performance and 25 days 11/06/2019 15/07/2019
Supplier Risk Site Configuration
188 188 Supplier Request Process 12 days 11/06/2019 26/06/2019
189 189 Review Supplier Request Design Matrix 1 day 11/06/2019 11/06/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
190 190 Customer Completes Supplier Request Design Matrix 2 days 12/06/2019 13/06/2019 HBP Bus-Ops [30%],HBP Core Team[30%]
191 191 SAP Ariba begins Test Site build of Supplier Request Process
4 days 16/06/2019 19/06/2019 SAP Ariba[10%]
192 192 SAP Ariba reviews configured items in Test site with customer
1 day 20/06/2019 20/06/2019 eSourcing/eProcurement Functional Consultant (Supplier)[30%
196 196 Review Supplier Registration Design Matrix 2 days 11/06/2019 12/06/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
197 197 Customer Completes Supplier Request Design Matrix 2 days 13/06/2019 16/06/2019 HBP Bus-Ops [20%],HBP Core Team[20%]
198 198 SAP Ariba begins Test Site build of Supplier Registration
4 days
Process 17/06/2019 20/06/2019 SAP Ariba[10%]
Page 6
ID Task ID Task Name Duration Start Finish Resource Names
Mode
199 199 SAP Ariba reviews configured items in Test site with customer
1 day 23/06/2019 23/06/2019 eSourcing/eProcurement Functional Consultant (Supplier)[50%
202 202 Supplier Qualification and Disqualification Process 12 days 30/06/2019 15/07/2019
205 205 SAP Ariba begins Test Site build of Supplier Qualification
4 days
and Disqualification
03/07/2019 Process08/07/2019 SAP Ariba[10%]
206 206 SAP Ariba reviews configured items in Test site with customer
1 day 09/07/2019 09/07/2019 SAP Ariba[20%],eSourcing/eProcurement Functional Consulta
210 210 Review Preferred Supplier Design Matrix 1 day 30/06/2019 30/06/2019 eSourcing/eProcurement Functional Consultant (SS)[10%],eS
211 211 Customer Completes Preferred Supplier Design Matrix1 day 01/07/2019 01/07/2019 HBP Bus-Ops [20%],HBP Core Team[20%]
212 212 SAP Ariba begins Test Site build of Preferred Supplier 3Process
days 02/07/2019 04/07/2019 SAP Ariba[10%]
213 213 SAP Ariba reviews configured items in Test site with customer
1 day 07/07/2019 07/07/2019 SAP Ariba[20%],eSourcing/eProcurement Functional Consulta
216 216 REALIZE - SLP - Testing and Migration to Production 14 days 14/07/2019 31/07/2019
217 217 Additional Configuration 4 days 14/07/2019 17/07/2019 eSourcing/eProcurement Functional Consultant (Supplier)[20%
219 219 Fujitsu will conducts Configuration Testing on the Test 1site
day 18/07/2019 18/07/2019 eSourcing/eProcurement Functional Consultant (SS) 2[30%],e
220 220 SAP Ariba makes changes based upon Configuration Testing
2 days 21/07/2019 22/07/2019 SAP Ariba[30%]
221 221 Customer validates changes and approves Test site configuration
1 day 23/07/2019 23/07/2019 HBP Bus-Ops [30%],HBP Core Team[30%]
224 224 UAT Planning & Preparation - Logistics 4 days 18/07/2019 23/07/2019 eSourcing/eProcurement Functional Consultant (SS)[30%],eS
225 225 Collect, review and approved the required data for Users
2 days
Testing 21/07/2019 22/07/2019 HBP Bus-Ops [30%],HBP Core Team[30%]
226 226 UAT Test Scripts - Preparation 1 day 21/07/2019 21/07/2019 eSourcing/eProcurement Functional Consultant (SS) 2[20%],e
227 227 Review and approve the UAT Test Script 2 days 22/07/2019 23/07/2019 HBP Core Team[20%]
228 228 Conducting UAT Sessions 3 days 24/07/2019 28/07/2019 eSourcing/eProcurement Functional Consultant (SS) 2[50%],e
229 229 Incorporate UAT Feedback 3 days 29/07/2019 31/07/2019 eSourcing/eProcurement Functional Consultant (Supplier)[30%
Page 7
ID Task ID Task Name Duration Start Finish Resource Names
Mode
232 232 REALIZE - CONTRACTS - Data Collection and Site Configuration
57 days 11/06/2019 04/09/2019
234 234 SAP Ariba & Fujitsu Reviews Custom Header Field Data
2 days
Collection Template
11/06/2019 12/06/2019 eSourcing/eProcurement Functional Consultant (SS) 2[20%]
236 236 SAP Ariba configures custom header fields in Test site3 days 17/06/2019 19/06/2019 SAP Ariba[20%]
237 237 SAP Ariba reviews custom header field configuration with
2 days
Fujitsu (including
20/06/2019
layout) 23/06/2019 eSourcing/eProcurement Functional Consultant (SS) 2[20%],e
238 238 Field configuration updated as per feedback 2 days 24/06/2019 25/06/2019 SAP Ariba[20%]
240 240 SAP Ariba reviews Contract Repository Data Collection2 Template
days with26/06/2019
Customer 27/06/2019 eSourcing/eProcurement Functional Consultant (SS) 2[20%],e
241 241 Customer provides SAP Ariba with a sample set of 7 days 11/06/2019 19/06/2019 HBP Core Team[20%]
Contract Repository Data (15-20 contracts)
242 242 Reviews sample contract repository data and provides 1feedback
day 20/06/2019 20/06/2019 SAP Ariba[20%],eSourcing/eProcurement Functional Consulta
243 243 Customer corrects any errors in sample data 3 days 23/06/2019 25/06/2019 HBP Core Team[20%]
244 244 SAP Ariba loads sample contracts into Test site 3 days 26/06/2019 30/06/2019 SAP Ariba[20%]
245 245 Customer collects and provides SAP Ariba with 13 days 01/07/2019 17/07/2019 eSourcing/eProcurement
Contract Repository Template and Documents for Functional Consultant (SS)
246 246 Full Load Process
Contracting 7 days 26/06/2019 04/07/2019 2[10%],HBP Core Team[20%]
247 247 Revisit/Finalize Design Matrix with customer 1 day 26/06/2019 26/06/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
248 248 Build Process Template in Test Site 2 days 27/06/2019 30/06/2019 SAP Ariba[20%]
249 249 Review Process in Test site with customer 1 day 01/07/2019 01/07/2019 eSourcing/eProcurement Functional Consultant (SS)[10%],eS
251 251 Process is updated per customer feedback 2 days 03/07/2019 04/07/2019 SAP Ariba[30%]
253 253 SAP Ariba reviews Form Data Collection Template with1 Customer
day 18/07/2019 18/07/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
254 254 Customer completes Form Data Collection Template 4 days 21/07/2019 24/07/2019 HBP Bus-Ops [20%],HBP Core Team[20%]
255 255 SAP Ariba configures Form template in Test site 3 days 25/07/2019 29/07/2019 SAP Ariba[20%]
256 256 SAP Ariba reviews Form Template configuration with customer
1 day (including
30/07/2019
layout) 30/07/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
259 259 Customer provides Main Agreement document 1 day 18/07/2019 18/07/2019 HBP Core Team[20%]
260 260 SAP Ariba reviews Main Agreement for formatting and 2provides
days feedback
21/07/2019 22/07/2019 SAP Ariba[20%]
263 263 SAP Ariba re views configured Main Agreement with the
2 days
customer 29/07/2019 30/07/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
Page 8
ID Task ID Task Name Duration Start Finish Resource Names
Mode
265 265 SAP Ariba Reviews Clause Library Data Collection Template
1 day with Customer
31/07/2019 31/07/2019 eSourcing/eProcurement Functional Consultant (SS)[20%],eS
266 266 Customer completes Clause Library Data Collection 15 days 01/08/2019 28/08/2019 HBP Bus-Ops [30%],HBP Core
Template and alternate clauses (in Word format) and Team[30%]
267 267 submits
SAP to SAP
Ariba loadsAriba
clauses into Test site 4 days 29/08/2019 03/09/2019 SAP Ariba[30%]
268 268 SAP Ariba reviews configured Clause Library with the customer
1 day 04/09/2019 04/09/2019 eSourcing/eProcurement Functional Consultant (SS),eSourcin
269 269 CONTRACTS - Configuration Freeze 3 days 31/07/2019 04/08/2019 eSourcing/eProcurement Functional Consultant (SS) 2[20%],S
271 271 Additional Configuration 3 days 05/08/2019 07/08/2019 eSourcing/eProcurement Functional Consultant (SS) 2[30%],e
273 273 Fujitsu will conducts Configuration Testing on the Test 1site
day 08/08/2019 08/08/2019 eSourcing/eProcurement Functional Consultant (SS) 2[30%],e
274 274 SAP Ariba makes changes based upon Configuration Testing
2 days 18/08/2019 19/08/2019 SAP Ariba[30%]
275 275 Customer validates changes and approves Test site configuration
1 day 20/08/2019 20/08/2019 HBP Core Team[20%]
278 278 UAT Planning & Preparation - Logistics 4 days 08/08/2019 20/08/2019 eSourcing/eProcurement Functional Consultant (SS)[30%],Pr
279 279 Collect, review and approved the required data for Users
2 days
Testing 18/08/2019 19/08/2019 eSourcing/eProcurement Functional Consultant (SS)[30%],eS
280 280 UAT Test Scripts - Preparation 3 days 18/08/2019 20/08/2019 eSourcing/eProcurement Functional Consultant (SS)[30%],eS
281 281 Review and approve the UAT Test Script 2 days 21/08/2019 22/08/2019 HBP Bus-Ops [30%],HBP Core Team[30%]
282 282 Conducting UAT Sessions 3 days 25/08/2019 27/08/2019 eSourcing/eProcurement Functional Consultant (SS)[30%],eS
283 283 Incorporate UAT Feedbacks 3 days 28/08/2019 01/09/2019 eSourcing/eProcurement Functional Consultant (SS)[30%],eS
288 288 Move all the Content from Dev to QA 5 days 01/08/2019 07/08/2019 Lenin[50%]
289 289 Hybris Service Cloud Transports for Business Roles 3 days 09/06/2019 11/06/2019 Surya[20%]
291 291 Hybris testing by HBP -UAT 15 days 22/08/2019 11/09/2019 Surya[40%]
293 293 SAP Hybris Service Cloud 5 days 08/09/2019 12/09/2019 Surya[20%]
296 296 Quality Assurance Environment (QAS): SW Setup 7 days 11/06/2019 19/06/2019
297 297 Execute Technical Installation of SAP Products for QAS environment
2 days 11/06/2019 12/06/2019 Basis Consultant
Page 9
ID Task ID Task Name Duration Start Finish Resource Names
Mode
298 298 Execute Technical Upgrade of SAP Products for QAS Environment
2 days 13/06/2019 16/06/2019 Basis Consultant
299 299 Check and Apply Latest HANA Revision and OS Patches 3 days 17/06/2019 19/06/2019 Basis Consultant
303 303 Import of System Fast-track Configuration into QAS 1 day 25/06/2019 25/06/2019 Basis Consultant[40%]
304 304 Perform Manual Configuration Settings in QAS 2 days 26/06/2019 27/06/2019 CIG Consultant[40%],FICO Consultant[40%],MM Consultant[4
305 305 Quality Assurance Environment (QAS): Data Load 4 days 30/06/2019 03/07/2019
306 306 Prepare and Load Master Data into QAS Environment for 2SCOPE
days OPTION
30/06/2019 01/07/2019 CIG Consultant[40%],FICO Consultant[20%],MM Consultant[4
307 307 Prepare and Load Transactional Data into QAS for SCOPE
2 days
OPTION 02/07/2019 03/07/2019 CIG Consultant[40%],FICO Consultant[20%],MM Consultant[4
309 309 Legacy Data Migration (New Implementation) 1 day 04/07/2019 04/07/2019 CIG Consultant[50%],FICO Consultant[30%],MM Consultant[3
310 310 Perform Load and Verification Runs (System Conversion)2 days 07/07/2019 08/07/2019 CIG Consultant[50%],FICO Consultant[30%],MM Consultant[3
311 311 Perform Client Transfer (LT Scenario- Client Transfer) 2 days 09/07/2019 10/07/2019 CIG Consultant[50%],FICO Consultant[30%],MM Consultant[3
313 313 Configuration - Development & Testing Environments 10 days 30/06/2019 11/07/2019
314 314 SAP Finance (FICO) 4 days 30/06/2019 03/07/2019 FICO Consultant[20%]
316 316 SAP Logistics (CPQ, SD, EWM and TM) 5 days 03/07/2019 09/07/2019 SD Consultant[40%]
317 317 SAP Projects (PPM, PS) 5 days 07/07/2019 11/07/2019 PPM-PS Consultant[30%]
319 319 SAP Finance (FICO) 3 days 07/07/2019 09/07/2019 FICO Consultant[40%]
321 321 SAP Logistics (CPQ, SD, EWM and TM) 3 days 09/07/2019 11/07/2019 SD Consultant[40%]
322 322 SAP Projects (PPM, PS) 3 days 09/07/2019 11/07/2019 PPM-PS Consultant[30%]
324 324 Request to Service 4 days 14/07/2019 17/07/2019 CIG Consultant[50%],FICO Consultant[50%],MM Consultant[5
325 325 Order to Cash 4 days 18/07/2019 23/07/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
326 326 Procure to Pay 4 days 24/07/2019 29/07/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
328 328 SAP Finance (FICO) 5 days 30/07/2019 05/08/2019 FICO Consultant
330 330 SAP Logistics (CPQ, SD, EWM and TM) 5 days 04/08/2019 08/08/2019 SD Consultant
Page 10
ID Task ID Task Name Duration Start Finish Resource Names
Mode
331 331 SAP Projects (PPM, PS) 5 days 06/08/2019 19/08/2019 PPM-PS Consultant
334 334 SAP Finance (FICO) 5 days 22/08/2019 28/08/2019 FICO Consultant
335 335 SAP Logistics (CPQ, SD, EWM and TM) 5 days 25/08/2019 29/08/2019 SD Consultant
336 336 SAP Projects (PPM, PS) 5 days 27/08/2019 02/09/2019 PPM-PS Consultant
339 339 SAP Ariba moves all configurations to Production site 5 days 30/07/2019 05/08/2019 SAP Ariba[10%]
342 342 SAP Ariba makes changes based upon Configuration Testing
1 day 18/08/2019 18/08/2019 SAP Ariba[40%]
343 343 Fujitsu & Customer validates changes and approves 3 days 19/08/2019 21/08/2019 eSourcing/eProcurement
Production site configuration Functional Consultant (SS)
344 344 DEPLOY - SAP Ariba Supplier Lifecycle and Performance 10 days 01/08/2019 21/08/2019 2[10%],eSourcing/eProcurement
347 347 Prepare End User Processes Manuals 3 days 01/08/2019 05/08/2019 eSourcing/eProcurement Functional Consultant (SS) 2[50%],e
348 348 Conduct the End User Training Session 3 days 06/08/2019 08/08/2019 eSourcing/eProcurement Functional Consultant (Supplier)[5%
349 349 SAP Ariba moves all configurations to Production site 5 days 01/08/2019 07/08/2019 eSourcing/eProcurement Functional Consultant (SS) 2[10%],S
352 352 SAP Ariba makes changes based upon Configuration Testing
2 days 19/08/2019 20/08/2019 SAP Ariba[40%]
353 353 Fujitsu & Customer validates changes and approves 1 day 21/08/2019 21/08/2019 eSourcing/eProcurement
Production site configuration Functional Consultant
354 354 DEPLOY - SAP Ariba Contracts 14 days 05/09/2019 25/09/2019 (Supplier)[20%],HBP Core
357 357 Prepare End User Processes Manuals 3 days 05/09/2019 09/09/2019 eSourcing/eProcurement Functional Consultant (SS) 2,eSourc
358 358 Conduct the End User Training Session 5 days 10/09/2019 16/09/2019 eSourcing/eProcurement Functional Consultant (SS) 2[50%],e
359 359 SAP Ariba moves all configurations to Production site 5 days 05/09/2019 11/09/2019 SAP Ariba
362 362 SAP Ariba makes changes based upon Configuration Testing
3 days 18/09/2019 22/09/2019 SAP Ariba
363 363 Fujitsu & Customer validates changes and approves Production
2 days site configuration
24/09/2019 25/09/2019 eSourcing/eProcurement Functional Consultant (SS) 2,eSourc
Page 11
ID Task ID Task Name Duration Start Finish Resource Names
Mode
364 364 DEPLOY - HYBRIS 11 days 18/09/2019 03/10/2019
365 365 Go/no go decision 1 day 18/09/2019 18/09/2019 Project Manager,Solution Architect Lead,Sr Project Manag
369 369 Service Cloud Prd Tarnsports 1 day 26/09/2019 26/09/2019 Surya
370 370 Conduct Data Quality Readiness Check 1 day 29/09/2019 29/09/2019 Surya
371 371 Finalize Cutover Plan 0.5 days 30/09/2019 30/09/2019 Surya
372 372 Perform Pre-Cutover Weekend Closing Activities 0.5 days 30/09/2019 30/09/2019 Surya
373 373 Final Check of Production Readiness and Sign-Off 0.5 days 01/10/2019 01/10/2019 Surya
375 375 Obtain Production Data Load Sign-off 1 day 02/10/2019 02/10/2019 Surya[50%]
380 380 SAP Finance (FICO) 5 days 03/09/2019 09/09/2019 FICO Consultant
382 382 SAP Logistics (CPQ, SD, EWM and TM) 5 days 08/09/2019 12/09/2019 SD Consultant[50%]
383 383 SAP Projects (PPM, PS) 5 days 10/09/2019 16/09/2019 PPM-PS Consultant[50%]
385 385 Execute Technical Installation of SAP Products for PRD 1 day 03/09/2019 03/09/2019 Basis Consultant
386 386 Execute Technical Upgrade of SAP Products for PRD 1 day 04/09/2019 04/09/2019 Basis Consultant
387 387 Import Configuration and Development Objects to PRD 1 day 05/09/2019 05/09/2019 Basis Consultant
389 389 Populate PRD with Test Master Data 2 days 10/09/2019 11/09/2019 Basis Consultant
390 390 Prepare and Load Master Data into PRD 3 days 12/09/2019 16/09/2019 Basis Consultant,CIG Consultant,FICO Consultant,MM Consu
391 391 Perform Manual Configuration Settings in PRD 2 days 17/09/2019 18/09/2019 Basis Consultant,CIG Consultant,FICO Consultant,MM Consu
392 392 Configuration Testing (Production) 1 day 19/09/2019 19/09/2019 Basis Consultant,CIG Consultant,FICO Consultant,MM Consu
393 393 System User Roles and Authorization Administration 3 days 22/09/2019 25/09/2019
396 396 Conduct Data Quality Readiness Check 1 day 26/09/2019 26/09/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
Page 12
ID Task ID Task Name Duration Start Finish Resource Names
Mode
397 397 Finalize Cutover Plan 1 day 29/09/2019 29/09/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
398 398 Perform Pre-Cutover Weekend Closing Activities 1 day 30/09/2019 30/09/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
399 399 Final Check of Production Readiness and Sign-Off 1 day 01/10/2019 01/10/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
401 401 Obtain Production Data Load Sign-off 1 day 03/10/2019 03/10/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
406 406 Milestone: Go Live Readiness and Sign off 0 days 27/08/2019 27/08/2019 eSourcing/eProcurement Functional Consultant (SS) 2[25%],H
409 409 Milestone: Go Live Readiness and Sign off 0 days 27/08/2019 27/08/2019 eSourcing/eProcurement Functional Consultant (SS) 2[50%],H
412 412 Milestone: Go Live Readiness and Sign off 0 days 03/10/2019 03/10/2019 BTSI
416 416 Go Live 0 days 06/10/2019 06/10/2019 CIG Consultant,FICO Consultant,MM Consultant,PPM-PS Co
417 417 HBP R3 - SAP Project Schedule - All Solutions 132 days 01/04/2019 16/10/2019
418 418 S4HANA Integration with Hybris 132 days 01/04/2019 16/10/2019
419 419 Integration between Hybris and S4 HANA -Must Have Scenarios
2 days 01/08/2019 04/08/2019 Muneer[10%],Surya[10%]
421 421 Integration with S4 HANA with Hybris Cloud - Must Have 23 days 05/09/2019 08/10/2019
422 422 Hyrbis Cloud Activities - As in Explore Phase 3 days 05/09/2019 09/09/2019 Basis[20%]
423 423 Cloud Platform Activities - Explore Phase 2 days 10/09/2019 11/09/2019 Basis[50%]
424 424 Connectivity Setup between S4 and Hybris Cloud - Explore Phase
4 days 12/09/2019 17/09/2019 Basis[20%]
425 425 Integration with Basic Authentication - Explore Phase 9 days 18/09/2019 01/10/2019 Basis[30%]
426 426 S4 HANA Activities - Explore phase and Must Have 5 days 02/10/2019 08/10/2019 Surya[10%],Muneer[20%]
427 427 Integration with S4 HANA with Hybris Commerce - Must 6 days 09/10/2019 16/10/2019
Have
428 428 S4 Hana and Hybris commerce - Explore Phase and Must Have
2 days 09/10/2019 16/10/2019 Surya[30%],Muneer[30%]
Page 13
ID Task ID Task Name Duration Start Finish Resource Names
Mode
429 429 Integration with S4 HANA with Hybris Cloud - Deploy 9 days 01/04/2019 11/04/2019
430 430 Hyrbis Cloud Activities - As in Explore Phase 3 days 01/04/2019 03/04/2019
431 431 Cloud Platform Activities - Explore Phase 2 days 04/04/2019 07/04/2019
433 433 Integration with Basic Authentication - Explore Phase 9 days 01/04/2019 11/04/2019
434 434 S4 HANA Activities - Explore phase and Must Have 5 days 01/04/2019 07/04/2019
435 435 Integration with S4 HANA with Hybris Commerce - Deploy 17 days 01/04/2019 23/04/2019
436 436 S4 Hana and Hybris commerce - Explore Phase and Must17 days
Have 01/04/2019 23/04/2019
Page 14
Predecessors Successors
14,20,21,109
6
6,11SS,23
6
4,3,5 9,7,142SS
6 8,10
7
6
7
4SS 12
11 15SS
2 139SS
25FS+2 days 29
28 30,34SS
29 32FS+2 days
22SS 44FS+2 days
30FS+2 days 33
32 35
Page 15
Predecessors Successors
29SS
33
22 37
36 38
37 39
38 40
39 41SS+1 day
40SS+1 day 42SS+2 days
41SS+2 days 43
42
31FS+2 days 288FS+1 day
313
300 58,59FS+7 days,86,87,88,85,89
300 48
47 49
48 50
49 51
50 52
51 53
52 54
53 55
54 56
55 57
56
46 72
46FS+7 days 60
59 61
60 62,64,65,63,66
61
61
61
61
61 67,68
Page 16
Predecessors Successors
66
66 69
68 70
69
76,77,78,79,80,81,82,83
58 73
72 74
73 75
74
71 422SS
71
71
71
71
71
71
71 84
83
46
46
46
46
46 90,91
89
89 92,93
91
91 94,95,96
93
93
93 97,98,99,100,101
96
96
96
Page 17
Predecessors Successors
96
96 102,103
101
101 104
103 105
104 106
105 107
106 108
107
2
112
111 113,126SS
112 114
113 115
114 116
115 117
116 118,121
117 119,122
118
296,297
117
118 123
122 124
123
130,131,132
112SS 127
126 128
127 129
128
125
125 133
125 133
Page 18
Predecessors Successors
131,132 134
133 135SS
134SS 136
135 137SS
136SS
14SS 146
16
6SS 143
142 144
143 145FS+2 days
144FS+2 days 149,189,196,234,241
139 338,339
166
145 150
149 151
150 152
151 153
152 155,154
153
153 156
155 157
156 158SS,173,169,178
157SS 159
158 161
159 162
161 163
162 164
163 165
164
Page 19
Predecessors Successors
147
157 170
169 171,179SS,180SS
170
157 174
173 175
174 176
175
157
170SS
170SS 181
180 182
181 183
182 184
183 185
184
344
145 190
189 191
190 192
191 193
192 194
193
145 197
196 198
197 199
Page 20
Predecessors Successors
198 200
199 201
200 203,210
201 204
203 205
204 206
205 207
206 208,217
207
201 211
210 212
211 213
212 214
213 215
214
207 218,219
217
217 220,224SS
219 221,225SS,226SS
220 222
221
219SS
220SS
220SS 227
226 228
227 229
228 230
229
354,355,356,357
Page 21
Predecessors Successors
145 235
234 236
235 237
236 238
237 240
238
145 242
241 243
242 244,247
243 245
244 253,259
243 248
247 249
248 250
249 251
250
245 254
253 255
254 256
255 257
256
245 260
259 261
260 262
261 263
262 265,269
Page 22
Predecessors Successors
263 266
265 267
266 268
267
263 271
269 272,273
271
271 274,278SS
273 275,279SS,280SS
274 276
275
273SS
274SS
274SS 281
280 282
281 283
282 284
283
364,365
21FS+11 days
44FS+1 day 290,419SS
21FS+11 days
288 291,420FS+6 days
290
Page 23
Predecessors Successors
297 299
298
296 305,306,47,46
296 302
301 303
302 304
303
300 308,309,314SS,315SS+2 days,316SS+3 days,317SS+5 days
300 307
306
305
305 310
309 311
310 312
311
318SS+5 days,45
305SS 319
305SS+2 days
305SS+3 days
305SS+5 days
313SS+5 days 323,324
314 320SS+2 days,321SS+2 days,322SS+2 days
319SS+2 days
319SS+2 days
319SS+2 days
318 327,328
318 325
324 326
325
323 332,333
323 329SS+2 days,330SS+3 days,331SS+5 days
328SS+2 days
328SS+3 days
Page 24
Predecessors Successors
328SS+5 days
327
327 334SS+2 days,335SS+3 days,336SS+5 days
333SS+2 days
333SS+3 days
333SS+5 days
146 404
146 340,341
339
339 342
341 343
342
186 407,408
348
347
351
349 352
351 353
352
231 410,411
231
231
231 358
357
361
359 362
361 363
362
Page 25
Predecessors Successors
285 413
285 366,367
365
365 368
367 369
368 370
369 371
370 372
371 373
372 374
373 375
374 376
375
295 415
295
295
295 381SS+2 days,382SS+3 days,383SS+5 days
380SS+2 days
380SS+3 days
380SS+5 days
295 393,394
295 386
385 387
386 388
387 389
388 390
389 391
390 392
391
384 395
384
393
397
Page 26
Predecessors Successors
396 398
397 399
398 400
399 401
400 402
401
338
406
405
344
344 409
408
354
354 412
411
364
377
288SS
290FS+6 days 293SS+5 days
76SS 423
422 424
423 425
424 426
425 428
426
Page 27
Predecessors Successors
431
430
Page 28