Professional Documents
Culture Documents
Page 1
ID Task Name Duration Start Finish Predecessors Qtr 3, 2019 Qtr 4, 2019
May Jun Jul Aug Sep Oct Nov Dec
41 3.1.2.8.2 Review of alternate technologies 0.25 wks 05/08/2019 06/08/2019 40
42 3.1.2.8.3 Recommendation with suggested PFD & FDS 0.25 wks 06/08/2019 07/08/2019 41
Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone
Page 2
ID Task Name Duration Start Finish Predecessors Qtr 3, 2019 Qtr 4, 2019
May Jun Jul Aug Sep Oct Nov Dec
82 3.3.1 LOBP & VII solubalization 6 wks 09/09/2019 23/10/2019
83 3.3.1.1 RFQ document for Core Blending & VII 3 wks 09/09/2019 01/10/2019 67SS-1 wk
Dissolution
84 3.3.1.2 RFQ for Core Filling Equipments 3 wks 01/10/2019 23/10/2019 83
85 3.3.2 Grease plant 5 wks 09/09/2019 16/10/2019
86 3.3.2.1 RFQ for CGU 2 wks 09/09/2019 23/09/2019 82SS
87 3.3.2.2 RFQ for Contactors 2 wks 24/09/2019 08/10/2019 86
88 3.3.2.3 RFQ for Grease filling equipments 1 wk 09/10/2019 16/10/2019 87
89 3.3.3 Used Oil reprocessing unit 12 wks 07/08/2019 06/11/2019
90 3.3.3.1 RFQ for used oil reprocessing plant 12 wks 07/08/2019 06/11/2019 59
91 3.3.4 LOBS loading facility (Automation system) 5 wks 09/10/2019 15/11/2019
92 3.3.4.1 RFQ for LOBS loading terminals 5 wks 09/10/2019 15/11/2019 82SS+4 wks
93 3.3.5 Warehouse Management system 3 wks 24/10/2019 15/11/2019
94 3.3.5.1 RFQ for warehouse mangement system 3 wks 24/10/2019 15/11/2019 91SS+2 wks
95 3.3.6 Product Receipt & Loading pipelines 8 wks 16/09/2019 15/11/2019 82SS+1 wk
96 3.3.7 Core EPC Package 8 wks 16/09/2019 15/11/2019
97 3.3.7.1 Grease process equipments 6 wks 16/09/2019 31/10/2019
98 3.3.7.1.1 Process Datasheet 2 wks 16/09/2019 01/10/2019 82SS+1 wk
99 3.3.7.1.2 Process Specifications for RFQs 2 wks 01/10/2019 16/10/2019 98
100 3.3.7.1.3 Process datasheet for Instruments 2 wks 16/10/2019 31/10/2019 99
101 3.3.7.2 Grease filling equipments 6 wks 16/09/2019 31/10/2019
102 3.3.7.2.1 Process Datasheet 2 wks 16/09/2019 01/10/2019 97SS
103 3.3.7.2.2 Process Specifications for RFQs 2 wks 01/10/2019 16/10/2019 102
104 3.3.7.2.3 Process datasheet for Instruments 2 wks 16/10/2019 31/10/2019 103
105 3.3.7.3 Brake fluid equpiments 6 wks 24/09/2019 07/11/2019
106 3.3.7.3.1 Process Datasheet 2 wks 24/09/2019 08/10/2019 101SS+1 wk
107 3.3.7.3.2 Process Specifications for RFQs 2 wks 09/10/2019 23/10/2019 106
108 3.3.7.3.3 Process datasheet for Instruments 2 wks 24/10/2019 07/11/2019 107
109 3.3.7.4 Coolant 6 wks 24/09/2019 07/11/2019
110 3.3.7.4.1 Process Datasheet 2 wks 24/09/2019 08/10/2019 105SS
111 3.3.7.4.2 Process Specifications for RFQs 2 wks 09/10/2019 23/10/2019 110
112 3.3.7.4.3 Process datasheet for Instruments 2 wks 24/10/2019 07/11/2019 111
113 3.3.7.5 Bitumen plant 6 wks 24/09/2019 07/11/2019
114 3.3.7.5.1 Process Datasheet 2 wks 24/09/2019 08/10/2019 109SS
115 3.3.7.5.2 Process Specifications for RFQs 2 wks 09/10/2019 23/10/2019 114
116 3.3.7.5.3 Process datasheet for Instruments 2 wks 24/10/2019 07/11/2019 115
117 3.3.7.6 Transformer oil & White oils 4 wks 01/10/2019 31/10/2019
118 3.3.7.6.1 Process Datasheet 2 wks 01/10/2019 16/10/2019 113SS+1 wk
119 3.3.7.6.2 Process Specifications for RFQs 2 wks 16/10/2019 31/10/2019 118
120 3.3.7.6.3 Process datasheet for Instruments 2 wks 16/10/2019 31/10/2019 118
121 3.3.7.7 RPO and BN Extract 4 wks 01/10/2019 31/10/2019
122 3.3.7.7.1 Process Datasheet 2 wks 01/10/2019 16/10/2019 118SS
123 3.3.7.7.2 Process Specifications for RFQs 2 wks 16/10/2019 31/10/2019 122
124 3.3.7.7.3 Process datasheet for Instruments 2 wks 16/10/2019 31/10/2019 122
125 3.3.7.8 DEF 4 wks 09/10/2019 07/11/2019
126 3.3.7.8.1 Process Datasheet 2 wks 09/10/2019 23/10/2019 121SS+1 wk
127 3.3.7.8.2 Process Specifications for RFQs 2 wks 24/10/2019 07/11/2019 126
Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone
Page 3
ID Task Name Duration Start Finish Predecessors Qtr 3, 2019 Qtr 4, 2019
May Jun Jul Aug Sep Oct Nov Dec
128 3.3.7.8.3 Process datasheet for Instruments 2 wks 24/10/2019 07/11/2019 126
129 3.3.7.9 Base oil Tankfarms 4 wks 09/10/2019 07/11/2019
130 3.3.7.9.1 Process Datasheet 2 wks 09/10/2019 23/10/2019 125SS
131 3.3.7.9.2 Process Specifications for RFQs 2 wks 24/10/2019 07/11/2019 130
132 3.3.7.9.3 Process datasheet for Instruments 2 wks 24/10/2019 07/11/2019 130
133 3.3.7.10 Additive Tankfarms 4 wks 09/10/2019 07/11/2019
134 3.3.7.10.1 Process Datasheet 2 wks 09/10/2019 23/10/2019 125SS
135 3.3.7.10.2 Process Specifications for RFQs 2 wks 24/10/2019 07/11/2019 134
136 3.3.7.10.3 Process datasheet for Instruments 1 wk 24/10/2019 31/10/2019 134
137 3.3.7.11 FP tankfarms 4 wks 09/10/2019 07/11/2019
138 3.3.7.11.1 Process Datasheet 2 wks 09/10/2019 23/10/2019 125SS
139 3.3.7.11.2 Process Specifications for RFQs 2 wks 24/10/2019 07/11/2019 138
140 3.3.7.11.3 Process datasheet for Instruments 1 wk 24/10/2019 31/10/2019 138
141 3.3.7.12 Base oil Dehydration facility 4 wks 09/10/2019 07/11/2019
142 3.3.7.12.1 Process Datasheet 2 wks 09/10/2019 23/10/2019 125SS
143 3.3.7.12.2 Process Specifications for RFQs 2 wks 24/10/2019 07/11/2019 142
144 3.3.7.12.3 Process datasheet for Instruments 1 wk 24/10/2019 31/10/2019 142
145 3.3.7.13 Utility equipments 3 wks 24/10/2019 15/11/2019
146 3.3.7.13.1 Process Datasheet 1 wk 24/10/2019 31/10/2019 141SS+2 wks
147 3.3.7.13.2 Process Specifications for RFQs 2 wks 31/10/2019 15/11/2019 146
148 3.3.7.13.3 Process datasheet for Instruments 1 wk 31/10/2019 07/11/2019 146
149 3.3.7.14 Scrubber, Knock out pot 2 wks 24/10/2019 07/11/2019
150 3.3.7.14.1 Process Datasheet 1 wk 24/10/2019 31/10/2019 145SS
151 3.3.7.14.2 Process Specifications for RFQs 1 wk 31/10/2019 07/11/2019 150
152 3.3.7.14.3 Process datasheet for Instruments 1 wk 31/10/2019 07/11/2019 150
153 3.3.7.15 OWS & ETP facility 2 wks 24/10/2019 07/11/2019
154 3.3.7.15.1 Process Datasheet 1 wk 24/10/2019 31/10/2019 145SS
155 3.3.7.15.2 Process Specifications for RFQs 1 wk 31/10/2019 07/11/2019 154
156 3.3.7.15.3 Process datasheet for Instruments 1 wk 31/10/2019 07/11/2019 154
157 3.3.7.16 Clay incineration unit 2 wks 24/10/2019 07/11/2019
158 3.3.7.16.1 Process Datasheet 1 wk 24/10/2019 31/10/2019 145SS
159 3.3.7.16.2 Process Specifications for RFQs 1 wk 31/10/2019 07/11/2019 158
160 3.3.7.16.3 Process datasheet for Instruments 1 wk 31/10/2019 07/11/2019 158
161
162 4 Detail Engineering 15.45 wks 28/08/2019 24/12/2019
163 4.1 Piping System with Heat tracing works 8.36 wks 19/09/2019 22/11/2019
164 4.1.1 Plant Layout preparation 4 wks 14/10/2019 12/11/2019
165 4.1.1.1 Plot plan 1 wk 14/10/2019 21/10/2019 60
166 4.1.1.2 Equipment layout 1 wk 14/10/2019 21/10/2019 60
167 4.1.1.3 Piping General arrangement drawings 1 wk 21/10/2019 28/10/2019 166
168 4.1.1.4 Piperack drawings 1 wk 29/10/2019 05/11/2019 167
169 4.1.1.5 Piping BOQ 1 wk 05/11/2019 12/11/2019 168
170 4.1.1.6 Prepare Insulation & Painting BOQ 3 wks 14/10/2019 05/11/2019 168SS-2 wks
171 4.1.2 3D Model (MS-5) 5 wks 19/09/2019 28/10/2019 60FS-3 wks 28/10
172 4.1.3 Prepare dynamic simulation model for one year 4 wks 27/09/2019 28/10/2019 171SS+1 wk 28/10
production (lubricant and grease) based on PFD (MS-6)
Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone
Page 4
ID Task Name Duration Start Finish Predecessors Qtr 3, 2019 Qtr 4, 2019
May Jun Jul Aug Sep Oct Nov Dec
173 4.1.4 Submission of Draft document , 3D model & Audio 1 wk 15/11/2019 22/11/2019 169FS+2
Visual model in entirety in line with the tender days
174
175 4.2 Instrument System 5 wks 19/09/2019 28/10/2019
176 4.2.1 Instrument Datasheet 1 wk 14/10/2019 21/10/2019 60
177 4.2.2 Control system specifiction 1 wk 14/10/2019 21/10/2019 60
178 4.2.3 Finalization of control system architecture 1 wk 21/10/2019 28/10/2019 177
179 4.2.4 Control room specification 1 wk 21/10/2019 28/10/2019 177
180 4.2.5 Communication, CCTV, PAGA, Fire alrm system, acess 3 wks 19/09/2019 11/10/2019 60FS-3 wks
control system, etc
181 4.2.6 BOQ 1 wk 14/10/2019 21/10/2019 180
182
183 4.3 Electrical HT & LT system 7 wks 16/09/2019 07/11/2019
184 4.3.1 Electrical Load List 2 wks 16/09/2019 01/10/2019 73FS-1 wk
185 4.3.2 HT Sub station design 3 wks 01/10/2019 23/10/2019 184
186 4.3.3 Electrical SLD 2 wks 01/10/2019 16/10/2019 184
187 4.3.4 SLD for power dist system & individual system 1 wk 16/10/2019 23/10/2019 186
188 4.3.5 Power control centre 1 wk 24/10/2019 31/10/2019 187
189 4.3.6 MDB & LDB 1 wk 24/10/2019 31/10/2019 187
190 4.3.7 Generator functional Spec 1 wk 24/10/2019 31/10/2019 187
191 4.3.8 BOQ 1 wk 31/10/2019 07/11/2019 190
192
193 4.4 Architectural System 9.75 wks 28/08/2019 11/11/2019
194 4.4.1 Overall Plot plan with Roadworks, SW drainage, 5 wks 12/09/2019 21/10/2019 60FS-4 wks
Parking areas, Admn bldg, Security, HT room (substn)
BoundAry wall, Site grading, Freshwater, UG tanks &
services
195 4.4.2 UG services 1 wk 28/08/2019 04/09/2019 60FS-6 wks
196 4.4.3 Building layouts 1 wk 14/10/2019 21/10/2019 60
197 4.4.4 Utility layouts 1 wk 14/10/2019 21/10/2019 60
198 4.4.5 Lube oil & Grease plant, VI solubilization 3 wks 28/08/2019 19/09/2019
199 4.4.5.1 Section & elevation drawings 3 wks 28/08/2019 19/09/2019 60FS-6 wks
200 4.4.6 Brake fluid & Coolant 3 wks 19/09/2019 11/10/2019
201 4.4.6.1 Section & elevation drawings 3 wks 19/09/2019 11/10/2019 198
202 4.4.7 Bitumen plant 3 wks 14/10/2019 05/11/2019
203 4.4.7.1 Section & elevation drawings 3 wks 14/10/2019 05/11/2019 60
204 4.4.8 Transformer oil & White oils 2 wks 25/10/2019 11/11/2019
205 4.4.8.1 Section & elevation drawings 2 wks 25/10/2019 11/11/2019 202FS-1.25 wks
206 4.4.9 RPO and BN Extract 2 wks 25/10/2019 11/11/2019
207 4.4.9.1 Section & elevation drawings 2 wks 25/10/2019 11/11/2019 204SS
208 4.4.10 LOBS loading facility 2 wks 25/10/2019 11/11/2019
209 4.4.10.1 Section & elevation drawings 2 wks 25/10/2019 11/11/2019 204SS
210 4.4.11 DEF 2 wks 25/10/2019 11/11/2019
211 4.4.11.1 Section & elevation drawings 2 wks 25/10/2019 11/11/2019 204SS
212 4.4.12 Base oil Tankfarms 2 wks 25/10/2019 11/11/2019
213 4.4.12.1 Section & elevation drawings 2 wks 25/10/2019 11/11/2019 204SS
214 4.4.13 Additive Tankfarms 2 wks 25/10/2019 11/11/2019
215 4.4.13.1 Section & elevation drawings 2 wks 25/10/2019 11/11/2019 212SS
Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone
Page 5
ID Task Name Duration Start Finish Predecessors Qtr 3, 2019 Qtr 4, 2019
May Jun Jul Aug Sep Oct Nov Dec
216 4.4.14 FP tankfarms 2 wks 25/10/2019 11/11/2019
217 4.4.14.1 Section & elevation drawings 2 wks 25/10/2019 11/11/2019 214SS
218 4.4.15 Utility Building (follow concept of Green Building) 2 wks 25/10/2019 11/11/2019
219 4.4.15.1 Section & elevation drawings 2 wks 25/10/2019 11/11/2019 214SS
220
221 4.5 Civil System 5 wks 14/10/2019 20/11/2019
222 4.5.1 Piling layout 1 wk 14/10/2019 21/10/2019 60
223 4.5.2 Earth works 1 wk 14/10/2019 21/10/2019 222SS
224 4.5.3 Substructure plan 1 wk 21/10/2019 28/10/2019 223
225 4.5.4 Superstructure layouts 1 wk 29/10/2019 05/11/2019 224
226 4.5.5 Civil BOQs for the builing, TF and offsite facilities 2 wks 05/11/2019 20/11/2019 225
227 4.5.6 Plot plan, Equipment layouts with Sections 1 wk 13/11/2019 20/11/2019 226FS-1 wk
228
229 4.6 Prepare BOQ and Tender specs for C & S works 3 wks 05/11/2019 27/11/2019 221FS-2 wks
230
231 4.7 Obtain approx. unit rates for the works 3 wks 31/10/2019 22/11/2019 81FS-2 wks
232
233 4.8 Cost Estimation & Tender Package Compilation 4 wks 31/10/2019 02/12/2019
(MS-7/9/10)
234 4.8.1 For Special Packages 2 wks 08/11/2019 22/11/2019 95FS-1 wk
235 4.8.2 Core EPC Packages 2 wks 31/10/2019 15/11/2019
236 4.8.2.1 Fire fighting, Fire hydrants, sprinklers 1 wk 31/10/2019 07/11/2019 81FS-2 wks
237 4.8.2.2 Lab facilities 1 wk 08/11/2019 15/11/2019 236
238 4.8.2.3 Admin/ Canteen/ IT services 1 wk 08/11/2019 15/11/2019 237SS
239 4.8.3 Civil & Structural Works 3 wks 08/11/2019 02/12/2019
240 4.8.3.1 Interior Works 3 wks 08/11/2019 02/12/2019 238SS
241
242 4.9 Develop approximate Phase II - EPC project schedule 1 wk 15/11/2019 22/11/2019 233FS-2 wks
(MS-8)
243
244 4.10 Comments by IOCL on Draft Report & discussion on 1 wk 02/12/2019 09/12/2019 239
Comments.
245
246 4.11 Submission of Final document with hardcopies, 2 wks 10/12/2019 24/12/2019 244
softcopies, 3D model & Audio Visual model after
incorporating IOCL comments on Draft DFR.(MS-11)
Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone
Page 6