Professional Documents
Culture Documents
CHAPTER 3
Calculating unit costs
ABSORPTION
MATERIAL
COSTING
HOW TO ESTIMATE
INVENTORY
VALUATION?
WORK IN PROCESS
PRODUCT
MARGINAL
COSTING
GOODS, …
1
08/08/2023
Absorption costing
• Absorption costing – Inventory is valued at full production
cost i.e. including both variable and fixed elements of
production cost.
UNIT
Direct labour costs
COSTS
Overhead
Absorption costing
Absorption costing values a cost unit at prime cost plus
variable production overheads plus an estimate of the fair share
of fixed production overheads. This is the same as marginal
cost plus an estimate of the fair share of fixed production
overheads.
Absorption costing is also called full costing.
How can you determine the share of overhead need to be
attributed to a cost unit?
2
08/08/2023
Apportionment
• Whole cost items • All costs are
are charged added into unit
directly to a cost • Indirect costs are costs using
objects (centre). shared fairly calculated
• Service cost centre absorption rates.
costs are also
reapportioned
Allocation Absorption
• Allocation
Whole cost items are charged directly to a cost centres
3
08/08/2023
• Overhead Apportionment
Process by which Indirect Costs are shared fairly between
cost centres
Requires application of appropriate basis of apportionment to
ensure that the distribution between the cost centres is fair
• Floor area
E.g. Rent, Rates, Heating, Light, Repairs,
• Equipment cost
E.g. Depreciation, Equipment Insurance
• Number of employees /Labour hours worked etc
E.g. Personnel Office, Canteen, Wages Dept, Welfare
4
08/08/2023
10
5
08/08/2023
11
• Overhead Absorption
Process whereby overhead costs allocated and apportioned to
production cost centres are added to unit costs.
• Overhead absorption usually uses a predetermined absorption rate,
calculated from budgeted figures
12
6
08/08/2023
Paintbrush Easel
Direct labour 0.1 hrs @ £5ph = £0.50 1 hr @ £9 = £9
Direct materials 0.5 m @ £8 perm = £4 2 m @ £4 per m = £8
Direct expenses £0 £0
Variable production costs £0.10 £2
Natalia produces and sells 350 paintbrushes and 50 easels per month.
Budgeted fixed production overheads are: £4,000.
13
14
7
08/08/2023
15
Production Finishing
Allocated and apportioned fixed costs £55,000 £63,000
Direct labour hours per unit:
Product Alpha 1.5 hrs 2 hrs
Product Beta 1 hr 0.5 hrs
What is the budgeted fixed cost per unit for product Beta if company
applied blanket absorption rate?
A £4.116 B £4.00 C £9.75 D £10.425
16
8
08/08/2023
17
18
9
08/08/2023
• Standard vs Actual
A standard cost is the expected, or budgeted, cost per unit of output.
A standard cost card is drawn up in advance of a period and shows the
expected usage of resources and price of resources for each cost unit.
19
20
10
08/08/2023
Eg. Sunshie Ltd has Actual overhead £45,000. Absorbed say 0.50p
x 100,000 dlh = £50,000 Over absorbed = £5,000
21
22
11
08/08/2023
Cost of
Overhead is Adjustment will
sales is
23
24
12
08/08/2023
25
26
13
08/08/2023
A £14,840 B £15,960
C £17,320 D £18,680
27
1 2 3
28
14
08/08/2023
29
• Stage 1:
Allocation is the process by which whole cost items are charged
direct to a cost unit or a cost centre.
30
15
08/08/2023
• Stage 2:
Apportionment is a process whereby indirect costs are spread fairly
between cost centres.
Service cost centre costs may be reapportioned to production cost
centres by using one of the following methods:
• Direct method
• Step-down method
• Reciprocal method
Service Production
Center Center
(Canteen) (Machining)
Service Production
center Center
(Maintenance) (Assembly)
31
32
16
08/08/2023
Service Production
Center Center
Interactions
(Canteen) (Machining)
between service
centers are
ignored and all Ignore
costs are Interraction
apportioned
directly
to production Service Production
centers. Center Center
(Maintenance) (Assembly)
Direct Method
33
Service Production
Center Center
Once a service
(Canteen) (Machining)
center’s costs
are apportioned,
other service
center costs
are not
apportioned
back to it. Service Production
Center Center
(Maintenance) (Assembly)
Step-down Method
34
17
08/08/2023
Service Production
Center Center
Maintenance will
(Canteen) (Machining)
have a new
total to apportion
to production
centers; its
own costs plus
those costs
apportioned from Service Production
the Canteen. Center Center
(Maintenance) (Assembly)
Step-down Method
35
Service Production
Center Center
(Canteen) (Machining)
Interdepartmental
services are given
full recognition
rather than partial
recognition as with
the step method. Service Production
Center Center
(Maintenance) (Assembly)
Reciprocal Method
36
18
08/08/2023
37
38
19
08/08/2023
COST COST OF
CENTER ACTIVITY
39
- The Crystal Courier: 40,000 copies in one production run per week
- The Palace Bugle: 25,000 copies in two production runs per week
(b) What do you think about the basis which was used to absorb
production run set-up costs?
40
20
08/08/2023
41
The management accountant suggests that the overheads could be analysed into 'cost pools'
as follows:
42
21
08/08/2023
43
(2) (4)
(3)
Identify Calculate
Collect the
(1) the cost an activity
costs
Identify a drivers absorption
associated
business’ (the rate and
with each
major factors absorb
activity
activities causing overheads
into cost
activity into cost
pools
costs) units.
44
22
08/08/2023
- The Crystal Courier: 40,000 copies in one production run per week
- The Palace Bugle: 25,000 copies in two production runs per week
45
• Job costing
• Batch costing
• Contract costing
• Process costing
Costing methods
46
23
08/08/2023
Jobs costing
A job is a cost unit which consists of a single order or contract.
• Job costing has the following features:
• Work is undertaken to customers' special requirements.
• Each order is of short duration.
• Jobs are usually individual and separate records should be
maintained on an individual job costing sheet.
47
48
24
08/08/2023
49
Production overhead
costs
Absorbed
25
08/08/2023
Batch costing
A batch can be defined as a cost unit which consists of a separate,
readily identifiable group of product units which maintain their separate
identity throughout the production process.
• Example: Footwear, Baked goods and clothing manufacturing
industries.
• For costing purposes, each batch can be looked at as a separate job
where the selling price of a batch is calculated by adding a profit to the
cost of the batch.
Total batch costs
Cost per = -------------------------------------------------
unit Number of units made in the batch
51
Contract costing
Contract costing is appropriate for specific one-off jobs of relatively
long duration e.g. building a hospital.
Contract cost includes prime cost, allocated overheads and absorbed
overheads.
52
26
08/08/2023
53
Process costing
Process costing is used in businesses where identical items are
produced continuously and therefore costs cannot be traced to individual
units of production or batches.
Fearture of process costing:
All costs, direct or indirect, incurred during the period are charged to
each process so that a total process cost for each is obtained.
The total process cost of each process is then shared equally among all
cost units processed in that process
54
27
08/08/2023
Process Finished
Direct labour cost Process 1
N output
Overhead
Additional cost
(Material, Labour, Overhead)
55
56
28
08/08/2023
57
• Target costing
Market research is conducted to estimate the price customers would
be willing to pay to allow the business to achieve the required market share.
The required profit is deducted from this price to generate the target cost.
58
29
08/08/2023
59
30