Professional Documents
Culture Documents
OVERVIEW
Objective
¾ Terminology
OVERHEADS ¾ Allocation, apportionment and
absorption
¾ Absorption bases
SERVICE ACCOUNTING
ABSORPTION
DEPARTMENTS FOR OVERHEADS
0501
SESSION 05 – OVERHEADS
1 OVERHEADS
1.1 Terminology
1.2.1 Allocation
¾ Charging to a cost centre those overheads that result solely from its existence, e.g.
1.2.2 Apportionment
¾ When an overhead is common to more than one cost centre it must be shared out or
split on an equitable basis, e.g.
1.2.3 Absorption
¾ Attributing the overheads accumulated by a cost centre to the cost units passing
through it, e.g.
0502
SESSION 05 – OVERHEADS
Illustration 1
¾ Appropriate where more than one type of unit is produced each taking a different
amount of time.
Illustration 2
Solution
Total overheads
Overhead absorption rate per hour =
Total planned hours worked
$15,000
= = $1/hour
( 3 ,000 × 1) + ( 2 ,000 × 6 )
¾ This is a fairer method of absorbing the overhead as it recognises the greater time taken
to produce a computer rather than a calculator.
0503
SESSION 05 – OVERHEADS
Example 1
Sofas Chairs
Volume (units) 100 400
$ $
Direct costs per unit:
Materials ($10.00 per kg) 80.00 30.00
Labour ($2.50 per hr) 105.00 42.50
Other information
Sofas and chairs pass through two production cost centres; the Assembly
department and the Trimming department. A sofa takes 24 hrs in the
Assembly department and 18 hrs in the Trimming department. A chair takes 9
hrs in the Assembly department and 8 hrs in the Trimming department.
The written down value of the equipment in the Assembly department and the
Trimming department is $104,500 and $115,500 respectively.
Materials storage costs should be apportioned two fifths to Assembly and three
fifths to Trimming.
0504
SESSION 05 – OVERHEADS
Required:
(a) Using appropriate bases apportion total overheads between the two cost
centres. Calculate an absorption rate per hour for each cost centre.
(b) Calculate the overhead cost per unit for each product.
Solution
(a) Overhead
Basis Ratio Assembly Trimming
$ $
Canteen
Machine depn &
machine repairs
Rent and rates
Prod man’s salary
Heat and light
Materials storage
______ ______
______ ______
WORKINGS
_____
Absorption rate =
_____
Absorption rate = (b) Overhead cost per unit
0505
SESSION 05 – OVERHEADS
WORKINGS $
Sofas: Assembly
Trimming
_____
_____
Chair: Assembly
Trimming
_____
_____
2 SERVICE DEPARTMENTS
2.1 Overview
Steps
Indirect Indirect Establish cost centres
Rent Electricity materials labour and
1 Allocate and
2(a) apportion
overheads to cost centres
Direct Direct
materials labour
2.2 Explanation
¾ Absorption is the process of charging overhead into a cost unit. The overhead is
absorbed while a product passes through a cost centre.
¾ Products do not pass through service cost centres and therefore an absorption rate will
not be calculated for the service cost centre. Absorption rates are only calculated for
production departments.
¾ This is why overhead in service cost centres must be reapportioned to production cost
centres.
0506
SESSION 05 – OVERHEADS
¾ This secondary apportionment should be done on a fair basis to reflect the benefit derived
from the service centre.
Example 2
$
Rent 20,000
Depreciation – machinery 10,000
– buildings 8,000
Electricity 5,000
Indirect materials 15,000
______
58,000
______
The following statistics are available.
Required:
STEPS 1 and 2(a) – Allocate (1) and primarily apportion (2(a)) overheads to cost centres.
0507
SESSION 05 – OVERHEADS
STEP 2(b) – Reapportion service department costs to production cost centres (secondary
apportionment)
A situation of reciprocal services is apparent i.e. the canteen does 20% of its work
for the maintenance department and the maintenance department does 5% of
its work for the canteen.
¾ Direct method
¾ Step-down method
¾ Reciprocal method – 2 methods
¾ Reciprocal services (if any) are ignored. The service department costs are reapportioned
to production departments only.
0508
SESSION 05 – OVERHEADS
¾ Services that do most work for other service departments are allocated first. Reciprocal
services (if any) are then ignored.
Maintenance (55:40)
______ ______ ______ ______
– –
______ ______ ______ ______
Maintenance (55:40:5)
______ ______
Canteen (50:30:20)
______ ______
Maintenance (55:40:5)
______ ______
Canteen (50:30)
______ ______ ______
______ ______
0509
SESSION 05 – OVERHEADS
Let c be
Let m be
c =
m =
There are numerous ways in which these equations can be solved either simultaneously
and/or by substitution – the suggested solution is only one way.
c = 8,535
m = 10,707
STEP 3
The firm’s two products have the following direct costs per unit.
Product A B
$ $
Direct Materials 7.00 5.00
Direct Labour
Pressing A: 3 hrs/unit 15.00
B: 2 hrs/unit 10.00
Assembly A: 2 hrs/unit 8.00
B: 1 hr/unit 4.00
______ ______
Prime cost 30.00 19.00
It has been decided to absorb overheads into products on the basis of labour
hours.
Required:
0510
SESSION 05 – OVERHEADS
Commentary
A reciprocal method must be used for reciprocal services unless told otherwise.
B
______ ______
______ ______
Assembly
_____ _____
Overhead cost per unit
_____ _____
3 ABSORPTION
3.1 Departmental rates
0511
SESSION 05 – OVERHEADS
¾ A single overhead rate computed for the entire factory by omitting the first of these two
stages.
Cost units passing through centres with high overhead costs (e.g. machine shops)
will be under-costed
Those passing through low overhead centres (e.g. an assembly department) will be
over-costed.
¾ May be used where they are an approximation to departmental rates as they simplify
product cost calculations.
¾ As management needs to know overhead costs per unit in advance e.g. to ensure sales
price covers all costs, they calculate predetermined overhead absorption rates, i.e.
¾ This standard absorption rate is then used during each period (e.g. month) to charge
production overheads through the management accounting Income Statement.
¾ For example every time labour works one hour a standard amount of overhead is
charged into cost of sales.
¾ Total overhead absorbed = standard rate x actual activity during the period .
¾ At the end of each period the cost accountant must check that the correct amount of
overhead has been charged through the income statement.
¾ If overhead absorbed > actual overhead incurred then this is described as over-absorption
and the difference is written off as a credit to cost of sales or to the profit figure (there is
no one rule about exactly where the adjustment is made).
¾ If overhead absorbed < actual overhead incurred then this is described as under-
absorption and the difference is written off as a debit to cost of sales or to the profit
figure.
¾ Activity in a specific month may be higher or lower than the long-run average level
used to calculate the standard rate.
0512
SESSION 05 – OVERHEADS
¾ If activity in a particular period is higher than normal levels then too much fixed cost
will be charged into cost of sales i.e. over-absorption. If activity is below normal levels
then under-absorption will occur.
¾ You may feel that the above system for accounting for overheads is rather complex –
rather than simply showing the actual overhead for a period (as in financial accounting)
we go through three steps when showing cost accounting i.e.
(2) during the period use the standard rate to charge overhead through the cost
accounts (standard rate x actual activity)
(3) at the end of the period reconcile overhead absorbed to actual overhead incurred by
making an adjustment for under/over-absorption.
¾ The next section works through the calculation of under/over-absorption and should
help to clarify the system. Furthermore you will see under/over-absorption again in
session 6 on absorption costing.
Illustration 3
Budgeted Actual
Overhead $32,844 $35,742
Direct labour hours 4,000 hrs 4,200 hrs
Solution
$32 ,844
Predetermined absorption rate = = $8.211 per direct labour hour
4 ,000
$
Actual overhead incurred 35,742
Overhead absorbed (recovered)
Actual hours × Predetermined absorption rate
(4,200 × $8.211) 34,486
_____
Under-absorption
1,256
_____
¾ Under/ (over) absorption is simply written off in total through the income statement i.e.
is not split between the income statement and balance sheet. .
0513
SESSION 05 – OVERHEADS
¾ This session is perhaps the most complex of the three concerning resource inputs.
However for decision making, overhead apportionment and absorption may be
considered as irrelevant due to the subjective nature of sharing overheads between
products.
¾ That does not mean that the analysis of overheads becomes redundant as for many
organisations they constitute a large proportion of totals costs.
¾ Overheads may therefore need to be analysed more accurately and ways of absorbing
overheads looked at more closely, to ensure appropriate costs per unit are calculated.
¾ The following section on Activity Based Costing (ABC) suggests a method of analysing
overheads more accurately. This is provided for background purposes; ABC is not
likely to be examined in paper F3 but is important for later ACCA papers.
0514
SESSION 05 – OVERHEADS
Key points
FOCUS
You should now be able to:
¾ allocate and apportion production overheads to cost centres using an appropriate basis;
¾ reapportion service cost centre costs to production cost centres (using the reciprocal
method where service cost centres work for each other);
0515
SESSION 05 – OVERHEADS
EXAMPLE SOLUTION
Solution 1 — Allocation, apportionment, absorption of overheads
(a) Overhead
Basis Ratio Assembly Trimming
$ $
Canteen No of employees 30:70 1,230 2,870
Machine depn &
machine repairs WDV 104.5:115.5 1,045 1,155
Rent and rates Area 3:1 4,725 1,575
Prod man’s salary Time spent 2:1 4,800 2,400
Heat and light Area 3:1 2,400 800
Materials storage Allocation 2:3 800 1,200
______ ______
15,000 10,000
______ ______
WORKINGS
Hours
Sofas 100 × 24 = 2,400
Chairs 400 × 9 = 3,600
_____
6,000
_____
15,000
Absorption rate = = $2.50 per direct labour hour.
6 ,000
Hours
Sofas 100 × 18 = 1,800
Chairs 400 × 8 = 3,200
_____
5,000
_____
10 ,000
Absorption rate = = $2.00 per direct labour hour.
5 ,000
0516
SESSION 05 – OVERHEADS
Direct method
Pressing Assembly Canteen Maintenance
$ $ $ $
15,000 26,000 8,000 9,000
Canteen (50:30) 5,000 3,000 (8,000)
Maintenance (55:40) 5,211 3,789 (9,000)
______ ______ ______ ______
25,211 32,789 – –
______ ______ ______ ______
0517
SESSION 05 – OVERHEADS
Reciprocal methods
Continuous re-apportionment
0518
SESSION 05 – OVERHEADS
c = 8,000 + 0.05m
m = 9,000 + 0.20c
__________________
Rearranging
c – 0.05m = 8,000 (1)
– 0.20c + m = 9,000 (2)
c – 535 = 8,000
c = $8,535
__________________
“Step 3” – Absorption
Pressing Assembly
Overhead $25,156 $32,844
Direct Labour hours A 1,000 units × 3 hrs 3,000
1,000 units × 2 hrs 2,000
B 2,000 units × 2 hrs 4,000
2,000 units × 1 hr 2,000
______ ______
7,000 4,000
______ ______
0519
SESSION 05 – OVERHEADS
0520