Arbitration Agreement
BETWEEN
M/s. SAI SIDDHANT DEVELOPERS, A partnership firm duly registered under the
provisions of Indian Partnership Act, 1934, having its office at 1, Ramkrupa Building,
Devji Bhimji Lane, Mathuradas Road, Kandivali (West), Mumbai – 400 067, hereinafter
referred to as “THE SAID SAI” (which expression shall unless it be repugnant to the
contextor meaning hereof include the partners or partner for the time being of the said
firm, survivors or survivor of them, the heirs, executors, administrators of the last
AND
AND
2|Page
D. N. NAGAR SHIVNERI CO-OPERATIVEHOUSING SOCIETY LIMITED, A Society,
having its registered office at Building No. 5, D. N. Nagar,Andheri (West), Mumbai – 400
repugnant to the contextor meaning thereof include their Directors and assigns)OF THE
THIRD PART;
WHEREAS:
the said Sai. The said Sai was appointed Developer in respect of the property viz.
Bombay 400 053, hereinafter referred to as "the said property", upon the terms
(b) By and under letter dated 6th January 2018, the said society terminated the said
(c) The said Sai has disputed termination and the matter is referred to the sole
(d) By and under Order dated 21 st July 2020, the said Arbitrator has directed the said
Sai to hand over possession of the said property to the said D. N. Nagar Niwara
3|Page
Co-op. Housing society, to enable the said society to complete the balance
construction work;
(e) The said Sai has disputed the rights of the New Developer and therefore, there is
a dispute between the parties hereto with regard to respective rights of the
parties.
(f) The said Westin has agreed to refer the said disputes to arbitration and join as a
NOW, THEREFORE, the parties agree to the terms and conditions as follows
1. In event of dispute of every nature and kind arising between the above-mentioned parties, in
respect of the [TYPE OF GENERAL AGREEMENT] agreement, executed on [DATE] between
the same parties including but not limited to the existence, validity, meaning and interpretation,
enforcement, operations, performance, nonperformance, breach, continuance, or termination of
the agreement shall be referred to arbitration as per the terms laid infurther in theagreement.
2. After a dispute has arisen, either party may demand the arbitration proceedings to commence
as the agreement, in writing within [NUMBER] days, with details of the dispute and the details
of the arbitrator named by the party demanding arbitration.
a. After such a demand has been raised, the other party within [NUMBER] days shall supply
details of the arbitrator being named on their behalf. The two arbitrators so appointed shall
further select the third arbitrator within [NUMBER] days who shall act as the Presiding
Arbitrator. In the event where the name of the third arbitrator is not agreed upon, the third
arbitrator shall be appointed by theArbitration Committee,
4|Page
b. The rules and procedures of [PARTICULAR TRADE, INDUSTRY, OR ASSOCIATION]
shall govern the arbitration hearing. The law of evidence shall govern the presentation of
evidence at such hearing. The provisions of the [Arbitration and Conciliation Act, 2013] so far as
applicable shall apply to this reference to arbitration.
4. The proceedings shall be held at [CITY], wherein the venue may be mutually decidedupon by
either the parties themselves or the appointed arbitrators.
5. Nothing contained in this agreement shall be deemed to give the arbitrators any power, right or
authority to change, amend, modify, add, alter any provisions as provided in the primary
agreement between the parties.
6. This Arbitration Agreement shall serve as a complete defense to any suit, action, or
proceeding instituted in any court or administrative tribunal with respect to any dispute arising
during the period of this agreement and which shall have been being referred to the arbitral
tribunal.
8. The terms of this agreement serve as a bar to any suit, action, or proceeding instituted in any
other court in respect to the disputes which require being referred to arbitration as per this
agreement.
9. The arbitration provisions of this agreement, with respect to controversy or dispute which
requires being arbitrated, shall survive the termination/ expiration of the [TYPE OF GENERAL
AGREEMENT agreement, executedon[DATE]
10. The award rendered by a majority of the arbitrators shall be final and binding on the parties
5|Page
Having agreed to the above provisions, this Agreement is signed on [DATE] at [PLACE], copy
delivered to both the parties
6|Page
WITHOUT PREJUDICE DRAFT
22.12.2020
THIS AGREEMENT made and entered into at Mumbai this day of ______
2020
BETWEEN
M/s. SAI SIDDHANT DEVELOPERS, A partnership firm duly registered under the
provisions of Indian Partnership Act, 1934, having its office at 1, Ramkrupa Building,
Devji Bhimji Lane, Mathuradas Road, Kandivali (West), Mumbai – 400 067, hereinafter
referred to as “THE SAID SAI” (which expression shall unless it be repugnant to the
contextor meaning hereof include the partners or partner for the time being of the said
firm, survivors or survivor of them, the heirs, executors, administrators of the last
AND
7|Page
_________________________________, hereinafter referred to as “THE SAID
AND
having its registered office at Building No. 5, D. N. Nagar,Andheri (West), Mumbai – 400
repugnant to the contextor meaning thereof include their Directors and assigns)OF THE
THIRD PART;
WHEREAS:
the said Sai. The said Sai was appointed Developer in respect of the property viz.
Bombay 400 053, hereinafter referred to as "the said property", upon the terms
8|Page
(h) By and under letter dated 6th January 2018, the said society terminated the said
(i) The said Sai has disputed termination and the matter is referred to the sole
(j) By and under Order dated 21 st July 2020, the said Arbitrator has directed the said
Sai to hand over possession of the said property to the said D. N. Nagar Niwara
Co-op. Housing society, to enable the said society to complete the balance
construction work;
(k) The said Sai has disputed the rights of the New Developer and therefore, there is
a dispute between the parties hereto with regard to respective rights of the
parties.
(l) The said Westin has agreed to refer the said disputes to arbitration and join as a
1. The said Westin hereby agrees to refer all its dispute with the said Sai with regard
to rival claim of development rights in respect of the said property and all other
Agreement dated 08th December 2010 and Agreement dated _________ and join
9|Page
2. The said Westin and both the parties hereby agree that Arbitration shall be
1996 and the decision given by the Learned Arbitrator shall be final and binding
on the parties.
IN WITNESS WHEREOF the parties hereto have hereunto set and subscribed their
respective hands at Mumbai the day and the year first hereinabove written.
in the presence of … …. … … … … }
1) }
2)
10 | P a g e
THE WITHINNAMED “THE WESTIN” }
in the presence of … …. … … … … … }
1.
2.
in the presence of … …. … … … … … }