Professional Documents
Culture Documents
CIRED2005
Session No 5
CIRED 18th International Conference on Electricity Distribution Turin, 6-9 June 2005
"RISKS"
Damage
Example
Hazards Consequential limitation
preventive
damage measures
potential measures
causes:
- not knowing training, PPE, escapes,
Human error, health &
- not able procedures, fire fighting eq't,
Normal Operation
Normal Operation
normal
failure
operation
1. REPORTING
Figure 2: Risk Management Principles 2. EVALUATING
"CONTROL MEASURES" 3. DIRECTING
Information requirements To obtain this data, each risk ‘block’ in figure 2 was treated
as a separate entity and discussed in detail with the relevant
groups.
All risks in relation to the MV grid are related to the As the study commenced in the year 2003, the only complete
performance of the separate components in the grid and their outage figures and statistics that were available, were from
functionality. To quantify the risks, information is required 2002. Although some improvements had already been made,
from all levels of the grid: from component-level up to these were the figures that were used throughout the study.
system-level. To obtain this information, several workshops The entire QRA process, as executed, is depicted in figure 3.
were organised in which Eneco staff were interviewed for
their perception of the problems.
Costs of failure
Different sessions were held with representatives from the
management teams, planning, design and operations
departments. The representatives were selected on the basis From statistics and verbal information from Eneco, the
of their knowledge of the particular issues. The sessions average cost of an outage failure was calculated as follows:
resulted in a list of most-feared risks, supplemented with Average cost = the total costs paid to recover from the
potential mitigating measures and their rough cost estimates. failures, divided by the total number of failures. In the Eneco
2002 case: (€ 2.2 Million) / (201 failures) = € 11.000 per
failure. This € 2.2 Million comprised € 1.4 Million of time-
BASIC DATA AND ESTIMATES depending costs and € 0.8 Million of fixed costs (e.g.
component costs). Obviously, if recovery times could be
reduced, a cost saving could be obtained. Saving one percent
To verify cost savings from implementing risk-mitigating in total time for recovery from the problems would yield a
(control) measures, a limited amount of numerical data is cost saving of: € 1.4 Million / 100 = € 14.000. The 201
required. failures accounted for approximately 9 million customer
minutes lost.
Risk-reduction
Failure (mitigation) measures Recommended
Database Risk Assessment Convergence Cost-benefit analyses actions
Failures
Ranking on C/B ratio
SAIDI reduction
Information A (short term) 1
on all failures B 2
Costs &
and outages C ….
Benefits
Criteria & D SAIFI reduction
Risk
Evaluation E (short term)
Analyses
F
Interviews Information G
Discussions from the … SAIFI reduction To the Planning
Workshops organisation
(long term) Department; new
(staff)
construction items
Session No 5
CIRED 18th International Conference on Electricity Distribution Turin, 6-9 June 2005
Estimates of mitigating measure quality and costs efficiency of this action mainly determines the time the
outage persists. Improving the related business processes
therefore can reduce the average outage times. Some
To assess the improvement potential of mitigating measures, (random) examples are:
estimates are required of their costs, benefits and anticipated
service life duration. To facilitate providing these estimates, x Hazard: Increased traffic delays repair crews
four categories were developed, each with a different rating - Potential mitigating measure: Spread out home
of severity: L (Low), M (Medium), H (High) and VH (Very bases of crews so travel distance becomes shorter
High). x Hazard: Small stations are difficult to find in the
cities due to new buildings covering or hiding them
For outage duration reduction, the following categories were - Potential mitigating measure: Equip all vehicles
used: L = 0-2%, M = 2-6%, H = 6-14% and VH = in excess with GPS location finders
of 14%. x Hazard: Equipment expertise and area knowledge is
Analogues categories for costs [units: € x 1000]: disappearing through retiring of staff
0-150, 150-750, 750-1500 and in excess of 1.5 Million. - Potential mitigating measure: Hire and train new
Analogues categories for anticipated minimum service life staff prior to old staff leaving the company
[years]: 0-2, 2-6, 6-14 and in excess of 14 years.
The above are just a few examples of the many proces-related
To estimate the service life of mitigating measures, the risks and mitigating actions that were identified. At this stage,
following assumptions were made: i.e. prior to the cost/benefit analyses, it was by no means
certain that any of the above mitigating measures would
- New equipment lasts at least 20 years actually be implemented.
- Modifications and upgrades last at least 10 years After the cost-benefit analyses were carried out, the following
- IT and organisational upgrades last 4 years four mitigating measures appeared to be economically viable:
- Inspections, plans, etc. are only valid for one year
- Install GPS equipment in each repair crew vehicle
To compare investments, all costs and benefits are expressed - Review protection philosophy and procedures
on a ‘per year’ basis. The approximation was made that new - Readjust protection relay settings
investments were written off linearly over the anticipated - Earth the isolated neutral system (i.e. earthing the
service lives of the particular investments. This is not as ‘floating neutral’ across the grid)
accurate as working with Net Present Values (NPV’s), but the
difference lies well within the uncertainty of the other input Further investigation with more accurate data would have to
parameters and therefore has not much added value (at this prove whether these four projects indeed are economically as
stage). good as they appear. Some of these studies have been, and
others are currently being carried out.
RESULTS
Outage frequency (SAIFI) reduction
CIRED2005
Session No 5
CIRED 18th International Conference on Electricity Distribution Turin, 6-9 June 2005
The above are just a few examples of the many component- After the cost/benefit analysis, (only) the following two
related risks and mitigating actions that were identified. At mitigating measures appeared to be economically viable:
this stage, i.e. prior to the cost/benefit analyses, it was by no
means certain that any of the above mitigating actions would - Develop and implement a pro-active cable joint
actually be implemented. replacement strategy, relating replacement priority
to joint type and soil conditions
To obtain an estimate of the costs of each particular failing - Develop and implement procedures for handling of
component type, the failure database was analysed. After cables and joints at excavation sites
correcting for some obvious input-errors, the failure statistics
were divided in surface equipment (i.e. substation component) Again, further investigation with more accurate data would
failures and subsurface component failures (cables and have to prove whether these projects indeed are economically
joints). Note: It should be borne in mind that there are no as good as they appear. Some of these studies have been, and
overhead lines in The Netherlands at MV distribution level; others are currently being carried out.
only underground cables.
33 action possible
164 20% 23 cables
subsurface cables
70% (19,688 cust.hrs.)
equipment
failures
201 Outages 3 3 terminations
terminations (2,568 cust.hrs.)
(from failure
batabase) 37 7 7 circ. break.
surface equipment circ. breakers (5,992 cust.hrs.)
failures
(includes cable
4 4disconnects
terminations)
Disconnects (3,424 cust.hrs.)
CIRED2005
Session No 5
CIRED 18th International Conference on Electricity Distribution Turin, 6-9 June 2005
top items on the list yield 6-14% 12 8 Other ‘hidden extras’ are available because of the simplified
much more benefit than 2 - 6% 4,8 3,2 accounting method (linear depreciation and Money of the Day
improving the ones at the Kosten 22 72 [MOD]). When calculations are repeated with Net Present
bottom of the list. Each Kosten 26 1.440 Values (NPV) and realistic depreciation times, the projects
item in the list represents Baten 46 17,51265455
with a longer service life tend to become even more
an input parameter like Kosten 46 24.579
Downside economical.
costs, times, improvement Upside
assumptions etc.
Figure 6: Tornado Diagram
In summary, the QRA has proven to be a valuable tool in
achieving cost-effective SAIFI and SAIDI reduction. To
obtain more accurate budget figures for the proposed (and
CONCLUSIONS selected) mitigating measures, the process can be repeated for
each measure in more detail. In this manner, obtaining
detailed information is only required for the selected
Upon completion of the above exercises, the following solutions, not for all solutions as identified in the beginning
conlusions could be drawn with respect to the QRA process: of the QRA process.
CIRED2005
Session No 5