Plant or Equipment RISK ASSESSMENT Template
Plant or Equipment RISK ASSESSMENT Template
Consequences (C): How bad is the possible outcome? Likelihood (L): How likely is it to L Risk level (R)
occur, and how often? C Likely Possible Unlikely
High – Death, disability, extreme damage Likely At any time High H H M
Moderate – Time off work, severe damage Possible Could occur Mod. H M L
Low – No or first aid injury, slight damage Unlikely May occur Low M L L
Unauthorised entry to the Moderat Possibl Moderat Actioned: Implement security measures to prevent unauthorized entry to
site e e e the site.
Collisions High Possibl High Actioned: Implement traffic management measures to reduce the risk of
e collisions.
Unauthorised or unsafe High Possibl High Actioned: Develop and implement procedures for the safe operation of
operation e equipment.
Unsafe operation High Possibl High Actioned: Provide training to workers on the safe operation of equipment
e and procedures.
Moving parts Moderat Possibl Moderat Actioned: Guard moving parts to prevent injury.
e e e
Hazards and associated C L R Comments - How will the hazards and the risks be controlled?
risks
Hazardous exposure Moderat Possibl Moderat Actioned: Provide workers with personal protective equipment (PPE)
e e e and training on how to use it safely.
Spill or leak (on-site) High Possibl High Actioned: Implement spill prevention and response procedures.
e
Moving parts Moderat Possibl Moderat Actioned: Guard moving parts to prevent injury.
e e e
Fluid under pressure High Possibl High Actioned: Implement procedures for the safe handling of fluids under
e pressure.
Unsafe operation High Possibl High Actioned: Develop and implement procedures for the safe operation of
e equipment.
Risk of falls - operator’s High Possibl High Actioned: Provide fall protection measures for operators.
position e
Risk of falls – from heights High Possibl High Actioned: Provide fall protection measures for workers working at
e heights.
Operator safety High Possibl High Actioned: Provide training to operators on the safe operation of
e equipment and procedures.
Unsafe operation High Possibl High Actioned: Develop and implement procedures for the safe operation of
e equipment.
Lifting and placing of High Possibl High Actioned: Develop and implement procedures for the safe lifting and
loads e placing of loads.
Lifting and placing of High Possibl High Actioned: Provide training to workers on the safe lifting and placing of
loads e loads.
Hazards and associated C L R Comments - How will the hazards and the risks be controlled?
risks
Instability; overturning High Possibl High Actioned: Implement measures to prevent instability and overturning,
e such as using counterweights or outriggers.
Electrocution High Possibl High Actioned: Implement electrical safety measures, such as lockout/tagout
e and grounding.
Loss of control High Possibl High Actioned: Implement safety measures to prevent loss of control, such as
e emergency stop buttons and guards.
Overturning risk High Possibl High Actioned: Implement measures to prevent overturning, such as using
e counterweights or outriggers.
Falling objects High Possibl High Actioned: Implement measures to prevent falling objects, such as
e overhead guards and barricades.
Collision High Possibl High Actioned: Implement traffic management measures to reduce the risk of
e collisions.
Personal injury High Possibl High Actioned: Implement safety measures to reduce the risk of personal
e injury, such as PPE, training, and engineering controls.
Moving and falling parts Moderat Possibl Moderat Actioned: Guard moving and falling parts to prevent injury.
e e e
Hazardous manual tasks Moderat Possibl Moderat Actioned: Implement engineering and procedural controls to reduce the
e e e risk of hazardous manual tasks.
Safety and security of High Possibl High Actioned: Implement security measures to protect the plant from
plant e unauthorized access and vandalism.
Hazards and associated C L R Comments - How will the hazards and the risks be controlled?
risks
Legend: C = consequences; L = likelihood; R = risk level. Rate each as either H (=high), M (=moderate), L (=low).
Hierarchy of risk controls (in order of preference) How will risk controls be implemented? – Give an example for each hazard
ELIMINATION Can the risk be eliminated? E.g., redesign work
activity
PPE What PPE could be used to reduce the risks? E.g., gloves,
Legend: C = consequences; L = likelihood; R = risk level. Rate each as either H (=high), M (=moderate), L (=low)
SAFETY IN DESIGN RISK ASSESSMENT REGISTER – PLANT AND EQUIPMENT
Complete the risk assessment register below relating to the two hazards identified for plant and equipment from the assessment report above.
Hazard Category
Adjoining Areas Ergonomics and Space Noise Traffic and Pedestrian Management and
Loading
Amenities and Facilities Falling Objects Precast Concrete Underground Services
Crane Operation Heat Sources Slips, Trips and Falls Other Workplace Issues
2 Moderate Management input required. Manage with control measures and monitor.
M
1
Low Acceptable. Manage with control measures and monitor.
L
DESIGN CONTROLS
Control Effectiveness Description Effort
PLANT AND EQUIPMENT SAFETY RESIDUAL RISK REGISTER (action one hazard)
*Hazard Category Hazard *Risk Project Design Risk Residual Owner *Statu Comments
Description Level Control/Treatment Risk Level s assumptions/justifications/records
reference
Plant