Information Flow Control Valve

Purchase Order Received from


Customer
Application Team
Internal Sales Order Entry (ERP)
Customer Related
Order Accepactance Entry - ERP
Work Order Preperation
Prepared & Uploaded in
Updtes on Updates on common folder.
Optisize & Email ERP & Email to Sales Job Order - ERP
to Customer ERP update Excel Entry
CBOM Customer Relation Team
Generaton
(ERP) Quality Plan, Technical Data sheet
prepared as per std. for each work
order (Optisize)
Work Order & SJO When ever required by customer,
Material Flow Generel Assembly Drawing is
prepared/shared. Work Order
& SJO Packingslip /
'Technical Documents Approval'
Invoice / LR /
(Only if Specified by Customer)
EWayBill

Raw Material Source Production Planning


Material Vendor PO
Material Dispatch
Daily Planning Report

Delivery
Challen &
Invoice

1G
8G 8G 21G 15G 23 G 4G 20 G 20 G 2G
Inventory Store / Purchase QC for Incomng Material Sub - Contracting Random QC In House Machining Product Assembly Seat Leakage Test Painting & Finishing Accessories Mounting Final Calibration & Testing Packaging & Despatch
Incoming Semi-finished Drilling & Hydro Test - Body
Valve (Body + Bonnet + Trim) (Valve Assembly+Actuator) Daily Despatch Plan
Inventory Stock Verifications material. Bonnet. Seat Leakage Test Ready Valves (14G)
Invoice / GRN - Verification & Machining are assembled together. Painted Product Labeling each product Credit / Proforma Invoice
Control Valve - 3" Indent Generation Generate Inspection Report - Hard Facing (Welding M/c) (Valve Assembly+Actuator)
Clearence - (ERP) & Sign on Tuming / Drilling / Milling / Actualtor + Accessories (Paint paremeters updated in a Accessories Mounting Approval.
Body Bonnet Flow Material Vendor PO Body&Bonnet only. CNC - Critical Dimensions
hard copy. Welding Assembly. Register) Packing slip.
Material Inward (ERP) - GRN SC GRN Verification clearence Final Processesed Material -
Processed Material Prepare LR / Eway Bill
(ERP) (Trim).

After QC or
Subcontracting

15 G 23 G 4G 20 G 20 G 14 G 2G

Product Assembly Seat Leakage Test Painting & Finishing Accessories Mounting Final Calibration & Testing Ready Valve Area Packaging & Despatch
Valve Assembly Daily Despatch Plan
Seat Leakage Test
(V10CJNAB 4F2 & Valve (Body + Bonnet + Trim) (Valve Assembly+Actuator) Labeling each product All part mounting & make Credit / Proforma Invoice
(Valve Assembly+Actuator)
1 TACA 20C1F0220) Assembly. Painted Product Accessories Mounting Valve Ready Stoarage Approval.
Processed Material Packing slip.
Prepare LR / Eway Bill

1G 8G 7G 16G 4G 15 G 23 G
Inventory / Purchase QC for Incomng Material Drilling Hydro Manual Painting & Finishing Product Assembly
Q Plan.
Body & Bonnet in Inventory Stock Verifications Valve (Body + Bonnet + Trim)
Invoice / GRN - Verification & (Valve Assembly+Actuator)
Indent Generation Actualtor + Accessories Moved for seat leakage
2 Machine condition Material Vendor PO
Clearence - Sign. Drilling & Tapping Hydro Testing Table Painted Product
Assembly. along with trim.
Generate Inspection Report
Material Inward (ERP) - GRN Processed Material
(ERP)

1G 8G 21 G 9G 15 G
Inventory / Purchase QC for Incomng Material Welding M/c Lathe M/c Product Assembly
Q Plan.
Plug & Seat in Inventory Stock Verifications Valve (Body + Bonnet + Trim)
Invoice / GRN - Verification & Hard Facing (Welding M/c)
Indent Generation Actualtor + Accessories Moved for seat leakage
3 Machined condition Material Vendor PO
Clearence - Sign. 2 M/cs's with different capaity
Assembly. along with Body & Bonet.
Generate Inspection Report
Material Inward (ERP) - GRN Processed Material
(ERP)

1G 8G 3F 11 G
Inventory / Purchase QC for Incomng Material Main Store (1st Floor) CNC
Q Plan.
Locking Ring & Cage Inventory Stock Verifications
Invoice / GRN - Verification & Inward Qty Confirmation (ERP)
Indent Generation Casting code changes. Then
4 Casting Material Vendor PO
Clearence - Sign. Material Requisition Machining.
fixed inside parent part.
Generate Inspection Report (Body+Bonnet+Trim)
Material Inward (ERP) - GRN
(ERP)

1G 8G 3F 15 G
Body Join / Glant / Inventory / Purchase QC for Incomng Material Main Store (1st Floor) Product Assembly
Glant Packing / Glant Q Plan.
Inventory Stock Verifications Valve (Body + Bonnet + Trim)
Invoice / GRN - Verification & Inward Qty Confirmation (ERP)
Flange / Glant Studs Indent Generation Actualtor + Accessories
5 Clearence - Sign. Material Requisition
and Nuts / Packing Material Vendor PO Assembly.
Generate Inspection Report (Body+Bonnet+Trim)
Material Inward (ERP) - GRN Processed Material
Spacer / Locking Ring / (ERP)

1G 8G 3F 20 G

Inventory / Purchase QC for Incomng Material Main Store (1st Floor) Final Calibration & Testing
Air Filter Regulator Q Plan.
Inventory Stock Verifications
(FPR) Invoice / GRN - Verification & Inward Qty Confirmation (ERP) All part mounting & make
Indent Generation Mounted to the valve & then
6 Bought out Clearence - Sign. Material Requisition Valve Ready
Material Vendor PO moved to 14 G.
Generate Inspection Report (Body+Bonnet+Trim)
Material Inward (ERP) - GRN
(ERP)
Directly Bought Material
1G 8G 3F 2S 7G
Inventory / Purchase QC for Incomng Material Main Store (1st Floor) Lathe M/c Drilling M/C
Pilot Relay Investment Q Plan.
Casting Inventory Stock Verifications
Invoice / GRN - Verification & Inward Qty Confirmation (ERP)
Indent Generation
7 (part of an accessory - Material Vendor PO
Clearence - Sign. Material Requisition Changs to Parent
valve position) Generate Inspection Report (Body+Bonnet+Trim)
Material Inward (ERP) - GRN
(ERP)
Directly Bought Material

1G 8G 3F 6F
Hex Nut 5/8" / Lower Inventory / Purchase QC for Incomng Material Main Store (1st Floor) Actuator Assembly
Travel stop / Adjusting Q Plan. Part of Actuators assembled in
Inventory Stock Verifications
Invoice / GRN - Verification & Inward Qty Confirmation (ERP) to actuator.
sleeve / Actuator stem Indent Generation
8 Clearence - Sign. Material Requisition Moved to Seat Leakage.
/ Spring cover plate / Material Vendor PO
Generate Inspection Report (Body+Bonnet+Trim)
Material Inward (ERP) - GRN
Diaform collar / Collar (ERP)
Directly Bought Material

1G 8G 3F 7S

Inventory / Purchase QC for Incomng Material Main Store (1st Floor) Valve Positioner Assembly
Bought out items used Q Plan.
Inventory Stock Verifications
for Valve Positioner Invoice / GRN - Verification & Inward Qty Confirmation (ERP) Valve Positioner Assembled
Indent Generation Items Moved to 3F - issue to
9 Assembly Clearence - Sign. Material Requisition and tested accuracy and
Material Vendor PO production
Generate Inspection Report (Body+Bonnet+Trim) performance.
Material Inward (ERP) - GRN
(ERP)
Directly Bought Material

1G 8G 3F
Inventory / Purchase QC for Incomng Material Main Store (1st Floor) Sub - Contracting
Bell Crank Lever / Q Plan.
Stroke Lever / Inventory Stock Verifications
Invoice / GRN - Verification & Inward Qty Confirmation (ERP) Machining
Indent Generation
10 Manifold for VP Material Vendor PO
Clearence - Sign. Material Requisition Tuming / Drilling / Milling /
Casting Generate Inspection Report (Body+Bonnet+Trim) Welding
Material Inward (ERP) - GRN
(ERP)
Directly Bought Material

1G 8G 3F 3S
Inventory / Purchase QC for Incomng Material Main Store (1st Floor) Drilling M/c
Q Plan.
Bell Crank Lever / Inventory Stock Verifications
Invoice / GRN - Verification & Inward Qty Confirmation (ERP)
Indent Generation
11 Stroke Lever Material Vendor PO
Clearence - Sign. Material Requisition Drilling & Tapping
Generate Inspection Report (Body+Bonnet+Trim)
Material Inward (ERP) - GRN
(ERP)

1G 8G 4G 6F 8F
Yoke M/C, Spring Inventory / Purchase QC for Incomng Material Painting & Finishing Actuator Assembly Ready Actuators
Tube Assembly, DIAP Q Plan. Part of Actuators assembled in
Inventory Stock Verifications
Invoice / GRN - Verification & (Valve Assembly+Actuator) to actuator.
Case Asmbly, Indent Generation
12 Clearence - Sign. Painted Product Store Ready Actuators
Adjusting NUT, Material Vendor PO
Generate Inspection Report
Material Inward (ERP) - GRN
Covering Plate (ERP)

1G 8G 7G 9G 15 G
Inventory / Purchase QC for Incomng Material Drilling Lathe M/c Product Assembly
Q Plan.
Inventory Stock Verifications Valve (Body + Bonnet + Trim)
Invoice / GRN - Verification &
Cage Indent Generation Actualtor + Accessories
13 Clearence - Sign. Drilling & Tapping 2 M/cs's with different capaity
Material Vendor PO Assembly.
Generate Inspection Report
Material Inward (ERP) - GRN Processed Material
(ERP)

1G 8G 7S

Inventory / Purchase QC for Incomng Material Valve Positioner Assembly

Right & Left Hand Turn Q Plan.


Inventory Stock Verifications
Invoice / GRN - Verification & Valve Positioner Assembled
14
Buckle Acc Indent Generation
Clearence - Sign. and tested accuracy and
Material Vendor PO
Generate Inspection Report performance.
Material Inward (ERP) - GRN
(ERP)

1G 8G 7S 1G 8G 7S

Inventory / Purchase QC for Incomng Material Valve Positioner Assembly Sub - Contracting Inventory / Purchase QC for Incomng Material Valve Positioner Assembly

Manifold for VP Q Plan. Q Plan.


Inventory Stock Verifications Inventory Stock Verifications
Invoice / GRN - Verification & Valve Positioner Assembled Machining Invoice / GRN - Verification & Valve Positioner Assembled
15
without Byepass Indent Generation
Clearence - Sign. and tested accuracy and Tuming / Drilling / Milling /
Indent Generation
Clearence - Sign. and tested accuracy and
Material Vendor PO Material Vendor PO
Generate Inspection Report performance. Welding Generate Inspection Report performance.
Material Inward (ERP) - GRN Material Inward (ERP) - GRN
(ERP) (ERP)

1G 8G
Body Cast, Norm Bont Inventory / Purchase QC for Incomng Material Sub - Contracting
Cast, Gland INV Q Plan.
Inventory Stock Verifications
Invoice / GRN - Verification & Machining
Casting, Packing Indent Generation
16 Clearence - Sign. Tuming / Drilling / Milling /
Spacer, Round Bar, Material Vendor PO
Generate Inspection Report Welding
Material Inward (ERP) - GRN
Yoke Casting, Spring (ERP)

1G 8G 1G 8G 3S 7S

Inventory / Purchase QC for Incomng Material Sub - Contracting Inventory / Purchase QC for Incomng Material Drilling M/c Valve Positioner Assembly
Q Plan. Q Plan.
Inventory Stock Verifications Inventory Stock Verifications
Cover for VP Invoice / GRN - Verification & Machining Invoice / GRN - Verification & Valve Positioner Assembled
Indent Generation Indent Generation
17 Clearence - Sign. Tuming / Drilling / Milling / Clearence - Sign. Drilling & Tapping and tested accuracy and
Material Vendor PO Material Vendor PO
Generate Inspection Report Welding Generate Inspection Report performance.
Material Inward (ERP) - GRN Material Inward (ERP) - GRN
(ERP) (ERP)
1G 8G 1G 8G 1G 8G 7S

Inventory / Purchase QC for Incomng Material Sub - Contracting Inventory / Purchase QC for Incomng Material Sub - Contracting Inventory / Purchase QC for Incomng Material Valve Positioner Assembly
Q Plan. Q Plan. Q Plan.
Inventory Stock Verifications Inventory Stock Verifications Inventory Stock Verifications
Base Plate for VP Invoice / GRN - Verification & Machining Invoice / GRN - Verification & Machining Invoice / GRN - Verification & Valve Positioner Assembled
Indent Generation Indent Generation Indent Generation
18 Clearence - Sign. Tuming / Drilling / Milling / Clearence - Sign. Tuming / Drilling / Milling / Clearence - Sign. and tested accuracy and
Material Vendor PO Material Vendor PO Material Vendor PO
Generate Inspection Report Welding Generate Inspection Report Welding Generate Inspection Report performance.
Material Inward (ERP) - GRN Material Inward (ERP) - GRN Material Inward (ERP) - GRN
(ERP) (ERP) (ERP)

20G 14G 2G

Accessories Mounting Final Calibration & Testing Packaging & Despatch


Daily Despatch Plan
PV 2821 Labeling each product Ready Valves Credit / Proforma Invoice
19 Accessories Mounting Approval.
Packing slip.
Prepare LR / Eway Bill

7S

Valve Positioner Assembly

Pilot Relay for VP Valve Positioner Assembled


20 and tested accuracy and
performance.

7S 3F 20G 14G 2G

Valve Positioner Assembly Main Store (1st Floor) Accessories Mounting Final Calibration & Testing Packaging & Despatch
Daily Despatch Plan
Allumenium Bracket Valve Positioner Assembled Inward Qty Confirmation (ERP) Labeling each product Ready Valves Credit / Proforma Invoice
21 and tested accuracy and Material Requisition Accessories Mounting Approval.
performance. (Body+Bonnet+Trim) Packing slip.
Prepare LR / Eway Bill

8F 23 G 4G 20G 14G 2G

Ready Actuators Seat Leakage Test Painting & Finishing Accessories Mounting Final Calibration & Testing Packaging & Despatch
Daily Despatch Plan
Seat Leakage Test
ACT A2 (Valve Assembly+Actuator) Labeling each product Ready Valves Credit / Proforma Invoice
(Valve Assembly+Actuator)
22 Store Ready Actuators Painted Product Accessories Mounting Approval.
Packing slip.
Prepare LR / Eway Bill