PROJ. No. Q3510XX - DAP 107DEF Project ITEM No.

P.O. No.
GRADE DATE CHK APPD

HSE: A. APPROVED WITHOUT COMMENTS.

- The risk assessment is not appropriate (risks are B.


REVISE AND RESUBMIT, WORK MAY PROCEED, SUBJECT TO

not evaluated separately – list of risk with a list of


INCORPORATION OF CHANGES INDICATED.

M.A / B.B
REJECTED, TO BE REVISED AND RESUBMITED, WORK MAY
control measures) C. NOT PROCEED. 03/02/2022 S.S / I.R /
N. F
O.M

INFORMATION ONLY, REVIEW NOT REQUIRED, WORK MAY


I. PROCEED.

Construction: ASB. VENDOR CERTIFIED FINAL/ AS BUILT/ ACCEPTED AS FINAL.


- All lifting lug welded used for lifting should be "PERMISSION TO PROCEED DOES NOT CONSTITUTE ACCEPTANCE OF DESIGN DETAILS, CALCULATIONS, ANALYSIS, TEST METHODS
inspected prior to use OR MATERIALS DEVELOPED OR SELECTED BY THE VENDOR/ CONTRACTOR, DOES NOT RELIEVE THE VENDOR/ CONTRACTOR FROM
FULL COMPLIANCE WITH CONTRACTUAL OBLIGATIONS"

- FSK to be approved for all critical lifting duct

DAP units 107 D, 107 E & 107F

Quality:
- Check comments on below pages: 7, 8 & 10 of 21
DOCUMENT HISTORY & REVISION

10

Work Method Statement for DUCTS AND CHUTES S. FAJRI


29/12/2021 Y. IDLAASRI E. LAHFID 0
Y. SENNAD
Description - Revision Subject Prepared by Checked by Approved by Rev

DOCUMENT DESCRIPTION & REFERENCES

CLIENT NAME: OCP

PROJECT LOCATION : JORF LASFAR MAROC

PROJECT DESCRIPTION : DAP 107DEF

JE PROJECT NUMBER Q3510

PURCHASE ORDER REFERENCE : 4500001316/1317

REQUISITION REFERENCE :

OTHER REFERENCE (tag, unit) :

DISCIPLINE DOCUMENT TITLE

CONSTRUCTION Work Method Statement for DUCTS AND CHUTES

VENDOR Document Number

00092-JCM-JESA-CON-WMS-0006

JESA Document Number


Imm. 5 - Zénith Millenium - Lot. Attaoufik Route Nouaceur - Sidi Mâarouf Casablanca -
20270 Tél: +212 (0)5 22 87 70 00 / +212 (0)5 22 87 71 50 Fax: +212 (0)5 22 87 72
34
Q3510-00-SCIFCMI-4500001316/1317-Z-Z01-0019

CLIENT Document Number ( if applicable)


JESA
Imm. 5 - Zénith Millenium - Lot. Attaoufik Route Nouaceur - Sidi Mâarouf Casablanca - 20270 Morocco Tél: +212 (0)5 22 87 70 00 / +212 (0)5 22 87
71 50 Fax: +212 (0)5 22 87 72 34

HELP
JESA DOCUMENT NUMBERING SYSTEM Project Nbre Code of Sub-Project Sender Code PO Discipline Code Doc Type Number Order / Rev
Please Refer to Annex Q, L & DC
Procedure . Shall you need help to fill-in
this cover page, please contact JESA
Example (Trigram is unique to each contractor) Q3510 00 SCIFCMI 4500001316/1317 Z Z01 19 00
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

PROJECT DAP 107-D. E &F

WMS DUCTS AND CHUTES

S. FAJRI
Y. IDLAASRI E. LAHFID
00 Y. SENNAD Issued for approval
06/12/2021 08/12/2021 29/12/2021
Revision Prepared Reviewed Approved Description

johncockerill.com 1/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

Revision History

Revision Date Concerned Description of changes


00 29/12/2021 - First edition

johncockerill.com 2/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

TABLE OF CONTENTS

1. PURPOSE: ........................................................................................................................................ 4
2. SCOPE : ............................................................................................................................................ 4
3. Reference Document: ...................................................................................................................... 4
4. SITE ORGANIZATION CHART ......................................................................................................... 5
5. CONCERNED PARTIES: .................................................................................................................. 5
6. RESPONSIBILITIES .......................................................................................................................... 6
7. Resources: ....................................................................................................................................... 8
8. Procedures ....................................................................................................................................... 9
9. Material Receiving ......................................................................................................................... 10
10. Work Preparation ........................................................................................................................... 10
11. Safe Work Procedure ..................................................................................................................... 11
12. Sequence of Assembly .................................................................................................................. 11
13. Sequence of Erection .................................................................................................................... 12
14. Health, safety & Environment ....................................................................................................... 18

johncockerill.com 3/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

1. PURPOSE:

The present procedure describes ways, tools and manners that will be applied for the erection of ducts and
chutes and hot air ducts on DAP 107 - Line D/E/F project.

2. SCOPE :

This method of statement covers the sequence of activities for chute erection, and to ensure the compliance
of work with the contractual & HSE requirements.

3. Reference Document:

The contract: N° JESA -4500001316 / 4500001317-2020

Annexes:
 Annexe A
 Annexe B
 Annexe G
 Annexe X
 Annexe Z
 Annexe S
 Quality Assurance Plan: 00092- JCM- JESA -QUA-QAP-0001
 John Cockerill Maroc Manuel Assurance Qualité: MAQ-V01
 Risk Assessment: 0092-JCM-JESA-HSE-RAS-0001

johncockerill.com 4/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

4. SITE ORGANIZATION CHART

5. CONCERNED PARTIES:

5.1. Company
JESA: JACOBS ENGINEERING SA

5.2. Contractor 2
JOHN COCKERILL MAROC (CMI MAROC)

johncockerill.com 5/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

6. RESPONSIBILITIES

6.1. Company
Company will be responsible to ensure availability of drawings and the necessary specifications to
Contractor2.
Company will be responsible to ensure availability of preassembling area as required by Contractor 2.

6.2. Contractor 2
The contractor 2, John Cockerill Maroc will be responsible on the application of this procedure and
requirements during the execution of DAP107 – Line D/E/F project.
It will be ensured that the suppliers, subcontractors and other service providers of the contractor 2 involved
in the project, are mandated in compliance with the requirements of the project DAP107 D, E & F
The Contractor 2 organization will establish as required detailed execution procedures to avoid the
appearance of non-conformities during execution.

6.3. Project Manager


The main responsible for the well going of the project.
Assign adequate resources to the needed actions.
Insure project control and monitoring.
Ensure acquisition of material at needed time.
Coordinate between the different stakeholders.
Assign the subcontractors for the needed works.
Overall responsibility and authority for the total project management.
Coordination and decisions for the project.
Administration of the project organization.
Risk management for overall project management.

6.4. Construction Manager


Execute quality and safety management during construction.

johncockerill.com 6/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

Ensure site survey is done before the work commencement.


Recruit the qualified personnel to do the works.
Coach workers into their best performance.
Make sur that the work is done following the drawings and specifications.
Ensure that the places of work are organized and cleaned.

6.5. Project Control Manager


Prepare and update the schedule.
Execution of construction progress management.
Establishing schedule strategy.
Issuing and maintaining schedule control procedures.
Administration of contract.
Planning the optimal resource mobilization.
Actual status monitoring and data collection.
Analyzing schedule trends, physical progress and resource performance.
Planning and initiating corrective actions.
Monitoring of the current progress of respective team.
Maintenance of the project Control System.
Preparation of monthly progress report.
Management of variations.
Risk management for schedule, Progress and contract.

6.6. Quality Manager


Preparation, review and approval of the Quality Procedures
Performance of Worksite evaluation for service (test, examination)
Training of personnel for QMS
Issuance for Corrective and Preventive Action Request (CAR/PAR)
Reporting the routine quality activities to the Project Manager.
Administration, supervision and coordination of Site QC Inspectors
Site surveillance
Issue the inspection log in a weekly manner
johncockerill.com 7/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

Performance of receiving inspection. & issue the RIR log in a weekly manner
Maintenance of the records and documents after work completion
Preparation and review of the Inspection and Test Plan
Performance of in-process inspection and test
Control of Non-destructive Testing (NDT) & issue the welding log
Review of Work Procedure for construction
Coordination of quality problems with the Customer
Control of measuring and test equipment & communicate the calibration log
Qualification of Welding Procedure Specification and welder
Welding material control & ensure the proper storage for welding consumable
Project inspections review (Initial, end of each phase)
Review of material requisition
Communicate fabrication documents for review

6.7. HSE Manager


Overall responsibility and authority for site HSE management.
Establishment and maintenance for HSE system.
Train, check and verify to ensure that all operations are conducted in safe manner.
Maintain the safety of site personnel, material and equipment.
Identification of HSE objectives and responsibilities.
Planning and organization of hazard identification and environmental reviews.
Working closely with Engineering, Procurement, Construction and Commissioning to communicate and HSEs
objectives and processes through all phases of the project.
Monitoring of HSE performance and reporting to project management

7. Resources:

7.1. Human resources:


All activities will be carried out by a team composed of:
 Construction Manager
 Technical supervisor

johncockerill.com 8/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

 Topographic surveyor
 Team leader
 HSE animator
 Welders
 Quality controller
 Helpers
 Scaffolding team

7.2. Equipment & tools

 Crane, Forklift, Manlift,


 Chain hoist, Wire rope puller, Shackles
 Slings different length.
 Transportation track.
 Personal Protective Equipment.

8. Procedures

8.1. General
Ensure that the document received bear the stamp “Issued for Construction” and are of latest revision.

The documents submitted/referred with this method statement shall be considered as an integral part of
this method statement and shall be read in conjunction with it.

The engineering drawings and documents received shall be clearly understood to find out the service,
material specification, Weight, QA/QC requirements etc.

Make sure that all the Quality control and Pre-Construction formalities, approvals, and preparations are
done sufficiently in advance to start the construction activity as per the schedule.
A checklist of all requirements shall be made internally to avoid any omission.

johncockerill.com 9/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

9. Material Receiving

All materials will be inspected immediately upon receipt by JCM Inspector to determine that all items
included in the Bill of Materials have been received and to check for any damage in accordance with
Also dimensional check according to JESA
« Material receiving procedure » N° 0092-JCM-JESA-QUA-MRP-0001.
drawing
All materials shall be requested or received as per erection sequence or site requirements in good
condition. JC shall ensure the preservation of material on site.

10. Work Preparation

 All personnel assigned for the work are required to attend the necessary courses arranged by our
Safety Coordinator/Supervisor and obtain the project ID pass.

 Safety Coordinator/Supervisor must check for compliance with project’s HSE plan and lifting
operations procedure while preparing for the use of mobile crane for the erection works.

 Construction Manager/ Site Supervisor and Lifting Supervisor shall study the site for work access and
ground condition for mechanical equipment and crane parking location. identify any partial road
closure area and mark up clearly on the plot plan. Separate lifting permit required for lifting work.

 Licensed Electrical Workers (LEW) shall check and certify all electrical tools
are in good working condition and according to the relevant HSE Standards as stated in the
Construction HSE plan.

 Mechanics shall check, inspect and ensure that all mechanical construction equipment are in good
working condition prior to mobilization. Checklist shall be endorsed and pass to the safety
supervisor/coordinator for record keeping.

 Construction Manager to prepare and submit all necessary procedure such as: Method Statement,
Lifting Plan and Risk Assessment and obtain approval prior to execution of the work.

johncockerill.com 10/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

11. Safe Work Procedure

 Apply and obtain relevant permit to work clearance from John Cockerill by authorized permit applicant.
(Working at Height Permit, Hot Work Permit and other statutory requirements.) Permit to be validated
on a daily basis.
 Upon receiving of work permit, Supervisor should conduct daily tool box meeting explaining the
details of work activity for the day including the methodology from the method statement and risk
assessment. Any additional safety precaution mentioned in the work permit must be clearly explained.
Daily toolbox meeting briefing records and attendance must be submitted to the Safety Supervisor.
 Barricade the work area, put up signboard to warn other adjacent working crews/contractors and
ensure that only relevant personnel are allowed to enter.
 Remove barricade and relocate the crane from the work site to the designated parking area.
 Upon completion of the entire work at each location, remove all the barricade ensuring safety and
proper housekeeping to be done.

12. Sequence of Assembly

Assembly of chut shall be done in strict conformity to the requirements of the job specifications and
applicable drawing.

Only duly qualified and competent personnel shall be allowed to conduct the job.

Whenever there are more than two fasteners securing a part, it’s important to alternate the tightening among
them. Here is the correct procedure: start all bolts or nuts a few threads and run them hand-tight.

Before members are assembled, thoroughly clean all surfaces which will be in permanent contact with
connection bolts.

johncockerill.com 11/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

13. Sequence of Erection

 Assembly of duct sections, installation and tightening of bolts, including joints between sections.
 Installation and welding of lifting rings on the insert plates.
 Installation of lifting tools (such as pull-lift, Wire rope puller, Chain hoists, etc.) as per steps below:

 Lifting of the chute in horizontal position

johncockerill.com 12/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

 Installation of the wire rope puller


 Pull the chute in finale toward finale position

johncockerill.com 13/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

 Installation of the additional chain hoist in order to adjust the chute in the final position.
 Pull the chute in finale toward finale position

johncockerill.com 14/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

 Installation of the additional chain hoist in order to adjust the chute in the final position.
 Pull down the chute in final position.

johncockerill.com 15/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

 Removal of the lifting accessories.

johncockerill.com 16/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

 Final adjustment according to axis X/Y.

johncockerill.com 17/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

14. Health, safety & Environment

14.1. At Site
JC HSE Manager shall ensure that the work is performed accordance to the approved Construction Safety
Manual and precautions specified in the work permit. He shall ensure that barricades, warning tapes,
warning signs, firefighting equipment and first aid kits are readily available at the working area.

Tool box talk shall be conducted on a daily basis to inform the workers of the recent safety issues and
incidents and to get feedback of any unreported unsafe acts. Feedback will then be processed and resolved.

14.2. Accident Prevention Safety Procedures:


Area shall be barricaded adequately with warning barriers prior to any lift.

All Equipment shall be checked for good conditions before commencing the work.

Unauthorized persons shall be excluded from the area.

Lifting equipment capacity and correct load slinging will be verified.

When lifting, the personnel shall not remain in the lifting equipment work area.

Adequate standards shall be adopted for the construction of stages, planks, scaffolds, etc.

Adequate caution boards and warning signs shall be provided.

All lifting equipment shall have valid certificates.

Only trained and authorized personnel shall operate the hydraulic lift.

All lifting gears and shackles used shall be approved type with valid load test certificates.

Electrical installations and equipment shall conform to standards.

Rained fire watchers shall be appointed as per requirement.

Sufficient fire extinguishers shall be provided close to the welding, cutting and other hot works.

Welding areas shall be covered with fire blankets.

Consumable materials within 15 meters of welding operation shall be cleared.

johncockerill.com 18/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

Do not stand under suspended loads.

On completion of job, the area shall be cleared of any materials and keep clean and tidy.

Hazard analysis for hazardous operation shall be carried out prior to commencing the work.

14.3. Risk Assessment:

johncockerill.com 19/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this
document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

johncockerill.com 20/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this document or its contents without specific written prior permission of John Cockerill Maroc.
JCM Ref : 00092-JCM-JESA-CON-WMS-0006 Contract Nº: JESA-4500001316/
Jesa Ref : 4500001317-2020
Rev : 00 Project : DAP 107 D, E & F
Code : C
Title :
WMS DUCTS AND CHUTES

johncockerill.com 21/21
This document is the propriety of John Cockerill Maroc, it may not be used, disclosed or reproduced for other purpose pertaining to this document or its contents without specific written prior permission of John Cockerill Maroc.