Professional Documents
Culture Documents
Q3510-00-SCIFCMI-45000013161-317-Z-Z01-0017 Commented CODE B Cladding and Roofing)
Q3510-00-SCIFCMI-45000013161-317-Z-Z01-0017 Commented CODE B Cladding and Roofing)
10
REQUISITION REFERENCE :
Q3510-00-SCIFCMI-4500001316/1317-Z-Z01-0017
HELP
JESA DOCUMENT NUMBERING SYSTEM Project Nbre Code of Sub-Project Sender Code PO Discipline Code Doc Type Number Order / Rev
Please Refer to Annex Q, L & DC
Procedure . Shall you need help to fill-in
this cover page, please contact JESA
Example (Trigram is unique to each contractor) Q3510 00 SCIFCMI 4500001316/1317 Z Z01 17 02
STL STR Granulation Building
107D/E/F
DOC. NO.:
TOTAL 23 S H E E T S (INCL. COVER)
STL STR Granulation
Building 107D/E/F
Summary
I. Object………………………………………………………………………………………3
II. Resources…………………………………………………………………………………..3
a. Manpower
b. Material Required
a. Deliveries to Site
e. Survey of building
f. Material arrangement.
a. Preparation of work
This method of work statement describes Steel structure erection work of roofing and cladding for steel
structure in granulation buildings to be done by SCIF in DAP project (Q3510) line 107DEF Zone Granulation
building in general, the proposed sequence of operations to be employed in the safe work erection of steel
structure frame building.
II.Resources:
b. Manpower
The installation works of roofing and cladding will be carried out by teams composed of:
• Project manager
• Lead Project Engineer:
• Construction manager
• Site Supervisor
• Surveyor
• Forman
• Quality controller
• HSE animator
• Operators
• Erectors
• Material Controller
• Helpers
• Riggers
• Site electrician
• Scaffolders
c. Material Required:
• Tower crane
• Mobile crane
• Man lift 43m minimum height.
• Forklift 4tons
• Drill electric screwdriver.
• Magnetic drill Drill φ10~φ35
• Torque wrench
• Reviter
• Shackles.
• Slings.
3
STL STR Granulation
Building 107D/E/F
• Guiding ropes.
• Scaffold materials.
III.Reference documents
In Order to prepare this Coating Drum method statement, we used the following documents as references:
• Annexes:
▪ Annexe A
▪ Annexe B
▪ Annexe G
▪ Annexe X
▪ Annexe Z
4
STL STR Granulation
Building 107D/E/F
Project Manager:
- The main responsible for the well going of the project.
- Assign adequate resources to the needed actions.
- Assure project control and monitoring.
- Assure acquisition of material at needed time.
- Coordinate between the different stakeholders.
- Assign the subcontractors for the needed works.
- Overall responsibility and authority for the total project management.
- Coordination and decisions for the project.
- Administration of the project organization.
- The Consortium representative to client.
- Risk management for overall project management.
Mechanical Engineer:
- Preparing and submitting the necessary documents.
- Review drawings and specification concerning construction.
- Manage the construction meeting and review construction plan.
- Reporting progress of work.
- Prepare and submit internal and external reports.
Construction Manager:
- Execute quality and safety management during construction.
- Ensure site survey is done before the work commencement.
- Recruit the qualified personnel to do the works.
- Coach workers into their best performance.
- Make sur that the work is done following the drawings and specifications.
5
STL STR Granulation
Building 107D/E/F
- Identifying project activities and integrating engineering, procurement, construction and
commissioning activities into Project Control Plan.
- Administration of contract.
- Planning the optimal resource mobilization.
- Actual status monitoring and data collection.
- Analysing schedule trends, physical progress and resource performance.
- Planning and initiating corrective actions.
- Monitoring of the current progress of respective team.
- Maintenance of the project Control System.
- Preparation of monthly progress report.
- Management of variations.
- Risk management for schedule, Progress and contract.
Quality Manager:
- Preparation, review and approval of the Quality Procedures
- Performance of Worksite evaluation for service (test, examination and commissioning)
- Training of personnel for QMS
- Issuance for Corrective and Preventive Action Request (CAR/PAR)
- Reporting the routine quality activities to the Project Manager.
- Administration, supervision and coordination of Site QC Inspectors
- Site surveillance
- Performance of receiving inspection.
- Maintenance of the records and documents after work completion
- Preparation and review of the Inspection and Test Plan
- Performance of in-process inspection and test
- Control of Non-destructive Testing (NDT)
- Review of Work Procedure for construction
- Coordination of quality problems with the Customer
- Control of measuring and test equipment
- Qualification of Welding Procedure Specification and welder
- Welding material control
- Project inspections review (Initial, end of each phase)
- Review of material requisition
HSE Manager:
- Overall responsibility and authority for site HSE management.
- Establishment and maintenance for HSE system.
- Train, check and verify to ensure that all operations are conducted in safe manner.
- Maintain the safety of site personnel, material and equipment.
- Identification of HSE objectives and responsibilities.
- Planning and organization of hazard identification and environmental reviews.
- Working closely with Engineering, Procurement, Construction and Commissioning to communicate and
promote HSEs objectives and processes through all phases of the project.
- Monitoring of HSE performance and reporting to project management.
6
STL STR Granulation
Building 107D/E/F
Fabricated steel members will deliver to site prior to commencement of erection and unload to lay
down area. Those will be laid out and clearly marked to suit the sequence of construction. Further
deliveries to site will be phased to meet the requirements of the erection sequence and schedule.
b. Loading and Unloading
Loading and unloading will be conducted by a fork lift and a 30T crane.
When the materials are loaded in the trailer, they will be supported by timber supports for each of
When the materials are loaded on the trailer, their quantity will not exceed the capacity of the trailer.
When holding the materials while delivery to the work site, they will be held by sling belt so that the
Unloaded roofing materials should be segregated properly according piece mark number for immediate
identification.
Material that has damage during or after unloading shall be replaced or repaired to the original condition.
For both loading & unloading operations, the supervisor, a flagman and HSE Animator will control the work
in the site.
7
STL STR Granulation
Building 107D/E/F
e. Survey of Building
- The Surveyor shall be responsible to check the verticality alignment of side panel to ensure
that all panel sare aligned.
- QC Inspector shall be responsible of monitoring and inspection of the work to ensure that
the work is performed in accordance with DEC/JGC Technical Scope of work and Standards.
f. Material arrangement.
8
STL STR Granulation
Building 107D/E/F
a. Preparation Work
- Site access shall be done, and safe access for all intended site vehicles including delivery vehicle
and cranes for the area. of structure where to install the roofing and side wall panels.
- Storage and erection area location of area shall be clean, level and ready.
- Clearing of obstructions, below ground, above ground or any overhead obstructions.
- The structure shall be completed and all nescessary inspection shall be completed such as;
Alignment inspection, bolt tightening inspection and all touch up paint for all damage paint shall be
done prior to installation of roofing and sidings.
- Using approved and latest drawings, verification of dimension, locations and alignment of roof and
wall frame including the purlins and side girth, angle, and channel where the panels are supported and
anchored.
- Any unsatisfactory conditions shall be subject for rectification prior to erection of roof and wall
panels.
- Coordinate the availability of materials and accessories in accordance with the proper sequence of
installation works.
- Anticipate any obstruction or interference of installation works, position of the crane and man lift
as per installation plan.
- For the installation of additional structural elements, including the overhead head and terminal
station, we plan to carry out this work as follows:
- The elevation of personnel to the desired level will be primarily provided by a single-mast lift
platform (see brochure).
- It is understood that prior to the installation of the platform, an inspection of the installation area
will be carried out, and a ground lift check will be performed to prevent accidental subsidence. The
mast elements of the platform will be attached every 6.0 m to the existing metal structure according to
the manufacturer’s instructions (see installation and removal instructions for the platform).
- The platform components will be assembled and disassembled by two trained operators and
supervised by a qualified manager. Who is responsible for verifying the proper functioning of the
platform and its safety prior to commencing work.
- In the event of a power failure or any emergency situation, the platform is equipped with a manual
lowering device that allows it to reach the ground manually.
9
STL STR Granulation
Building 107D/E/F
1. Use a lifting platform or a crane to lift the siding sheets and place it in the exact location.
2. The panel should be aligned and secured using riggers mounted in a hand basket, while the
siding sheets are lifted by a crane.
3. The panel must be aligned and fixed using the fitters who will lift the cladding sheets in the
lifting platform at the same time.
4. Position the panels accurately on the steel structure frame, adjust accordingly to the final
position before fix and fastening.
5. After alignment of panels, secure the panels using the fastener with the electric drill
machine, fastener location shall be as shown in the vendor drawing.
6. Install the next panel in accordance with the same procedure and as per vendor
specification such as; lapping of panels and location of fastener.
7. For the installation of gable trim, flashing, ventilator; please refer to the vendor drawing
and specification.
8. For the required opening of roof and wall panels, filed cutting to suit, Extra care for drilling
and cold cutting using cut off machine or tin snip cutter, metal fillings, drill shaving and burr shall
be removed from adjacent surface prior to installation of panels.
9. For the installation of wall panel that cannot be reached by man lift we will use man basket.
10
STL STR Granulation
Building 107D/E/F
1. Ensure lifelines are secured installed at rooftop, Access the rooftop through scaffolding.
2. Using crane or tower crane for the lifting of roof panels at the rooftop, tinsmith and workers at the
rooftop shall be position the panels and installed at the exact locations.
3. Position the panels accurately on supporting frame or structure. Adjust accordingly to final position
with proper bearing before fix or fastener.
4. After alignment is done secure the panel using the fastener with electric drill machine with care.
5. Install the next roof panels in the same procedure as above, ensure the correct orientation of each
panels, anticipate the requirement for the lapping, end trim, joint filler and sealant.
6. Install all accessories in accordance with vendor catalog, drawings and specification.
11
STL STR Granulation
Building 107D/E/F
7. For the installation of roof panel that cannot be reached by man lift we will use man basket or lift
platforms.
8. The first line of cladding panels (known as a tier) should be laid out close to the rafter and
temporarily fixed, starting from the eaves and progressing parallel to the rafter as far as the ridge.
During this operation, care should be taken to avoid walking on the purlins, as this is likely to cause
damage. The cladding installation should then proceed away from the rafter into the span of the
purlins one tier at a time, as shown in Figure 5.4. Each tier of panels should be fixed to the purlins
before the next tier is laid, in order to provide restraint to the purlins and reduce the risk of
damage under construction loads.
9. Installation Rule:
- the placement and installation of rain water gutter corresponding to the customer’s plan.
12
STL STR Granulation
Building 107D/E/F
- Components and accessories to complete the wall panel assembly such as; closure trim, fastener, drip
trim and eave trim, flashing roof to wall corresponding to the customer’s plan.
Type PM200
13
STL STR Granulation
Building 107D/E/F
SAFETY ELEMENTS
14
STL STR Granulation
Building 107D/E/F
15
STL STR Granulation
Building 107D/E/F
16
STL STR Granulation
Building 107D/E/F
17
STL STR Granulation
Building 107D/E/F
18
STL STR Granulation
Building 107D/E/F
19
STL STR Granulation
Building 107D/E/F
20
STL STR Granulation
Building 107D/E/F
21
STL STR Granulation
Building 107D/E/F
22
STL STR Granulation
Building 107D/E/F
23
Page 1
e
Ref.
yp
Risk
Risk
et
Assessment
lT
Activity or Element Hazards Controls Assessment
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
Main activity
Main activity
# Regular inspections of equipment before every use and
records kept.
# Immediate removal and disposal of access equipment
Poor maintenance of access found to be defective prior to use.
work at elevation equipment (e.g. ladders, steps, P 4 4 16 H E/S 3 1 3 L
scaffolds).
# Suitable personal protective equipment must be
available.
# Scaffold to be built by competent person
matrials certificat
# Equipment to be used only where there is a firm, level
surface
# All equipment to be visually inspected before use and
Inappropriate use of tower scaffolds records kept.
work at elevation P 4 4 16 H E/S/A 3 2 6 M
causing trips and falls. # Appropriate footwear to be worn
# Equipment should be suitably stored after use
# Work at height training to be undertaken
# Work at heigt permit to be implemented
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
# implimentation of Work At Height Permit
# Specific risk assessment to be undertaken prior to all
work at height activities
# Staff not to use furniture or other inappropriate
fixed/mobile structures for working at height.
# Consider use of fall arrest systems depending on nature
work at elevation Falls from height. P 4 3 12 H E/S/W/A 2 2 4 L
of task, equipment and duration
# Adequate and appropriate signs in place to warn of
hazards below work area
# Work scheduled to take place when persons/others are
not in the immediate area.
# Ensure operatives trained to work at height
work at elevation Poor weather conditions causing slips. P 2 2 4 L A 2 2 4 L
# No work at height to be done outside in poor weather.
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
# Ensure competent crane driver
# Use lifting signals. Barricade
the area and use tag line
# Ensure proper lifting equipment
used
# Don’t stand under suspended
load
# Ensure crane operator, rigger
Lifting Operations Falling object P/F 2 3 6 M E/S/W 2 1 2 L
and signalman have clear
communication (walkie talkie)
# Use tag line and barricade the
area
# Stop work during foul weather
# Ensure adequate lighting prior
to lifting (maint)
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
# Vehicles and gears exhaust gas # Regularly ensure that vehicles are in good condition
emission in the constuction site
# provide daily watering
Driving - Traffic # Dust emanation due to the E/P 1 2 2 L S/E 1 1 1 L
# Speed limitation on 20km/H
transport vehicle in the site and the
# use a bucket cover fo trucks
work of excavation and clearing
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
equipement and accessery lifting are in good
condition
documentation are in place (certificat,,,)
respect of load limite
respect of center of gravity
regger or a competent person
Assembly and disassembly falling object /falling from height P/F 4 3 12 H W/S/A/E 3 1 3 L
only the autorised person can accede to the work
area
supervision in place
Wearing the anti fall system permanently
housekeeping and rangement
free axces and compliant work platform
erection and disassembly is carried out as per
training and manifatures instrations and supervised
Assembly and disassembly collapse /topple over 3 3 9 M W/S/A/E by a competent person 3 2 6
the fondation is firm,level, and capable of sustaining
the loads imposed
# Use proper tug line
Assembly and disassembly Pinch Points: Hand & Finger Injuries P 4 2 8 M E/S 3 1 3 L
# Wear appropriate PPEs
respect of load limit (25kg)
gesture and posture
Assembly and disassembly back pain and low back pain P 2 1 2 L W/S 2 1 2 L
trainig and awernesses
safety signs
e
Ref.
yp
Risk
Risk
et
Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
A
nt
Co
S P L S P L
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
equipement and accessery lifting are in good
condition
documentation are in place (certificat,,,)
respect of load limite
respect of center of gravity
regger or a competent person
loading and inloading fulling object /falling from height P/F 4 3 12 H W/S/A/E 3 2 6 M
only the autorised person can accede to the work
area
supervision in place
Wearing the anti fall system permanently
housekeeping and rangement
free axces and compliant work platform
free axces compliant work platform
housekeeping and arrangement
loading and inloading slips and trips 2 1 2 L W/S wearing adequate PPE 2 1 2 L
respect of the safety instructions
all openings will be protected and controled
respect of load limit (25kg)
gesture and posture
loading and inloading back pain and low back pain P 2 1 2 L W/S 2 1 2 L
trainig and awernesses
safety signs
Productivity Severity
Environment Property Personnel 1 2 3 4 5
or Downtime Level
Fatality or
Permanent damage beyond project total
> 2 weeks
boundary
Total facility loss
permanent
5 5 10 15 20 25
disability
Productivity Severity
Environment Property Personnel 1 2 3 4 5
or Downtime Level Preliminary Risk Final Risk
e
Ref.
yp
Risk
Risk
et
Fatality or Assessment Assessment
lT
Activity or Element Hazards Controls
Number
ss
ro
Permanent damage beyond project total
A
5 10 15 20 25
nt
> 2 weeks Total facility loss 5
Co
boundary permanent S P L S P L
disability
Asset: P = Personnel, F = Facilities and equipment, E = Environment Control Type: D = Design, E = Engineering control, S = Safety device, W = Warning device, A = Administrative control
Permanent damage within project Damage to an entire facility Permanent
1 week to
2 weeks
boundary or reportable release or loss of multiple systems partial 4 4 8 12 16 20
beyond boundary in a facility disability
Damage to an entire facility
> 1 day to Reportable release within project or multiple systems in a
< 1 week boundary with no permanent damage facility requiring repair or
Days away 3 3 6 9 12 15
replacement
Release within project boundary Damage to a facility element OSHA
½ day to
1 Day
below reporting quantity with clean-up or system requiring repair or Recordable 2 2 4 6 8 10
by external source replacement or E-1
10h00: Victim falls inside the dryer, and the alert is triggered.
10h05: the HSE supervisor informs the HSE manager of the incident and
the seriousness that requires an ambulance intervention.
10h10: SCIF HSE Manager call the ambulance, and give the driver the right
location of the intervention.
10h15: SCIF HSE Manager inform JESA HSE Manager, and SCIF project
Director.
10h20: the IP has been evacuated from inside the dryer using a stretcher,
and then evacuated from the building by using SCIF 35T crane.
10h25: once on the ground, the IP receive first aid treatment by the nurse,
and then transported to SCIF medical facility (TSF)
3. Photos of the simulation