Professional Documents
Culture Documents
Publisher
South African Institution of Civil Engineering
Block 19, Thornhill Office Park,
Bekker Street, Vorna Valley, Midrand, South Africa
Private Bag X200, Halfway House, 1685, South Africa
Tel +27 (0)11 805 5947/48, Fax +27 (0)11 805 5971
http://www.saice.org.za
civilinfo@saice.org.za
Contents
Editor-in-chief
Prof Gerhard Heymann
University of Pretoria
Tel +27 (0)12 420 3627
gerhard.heymann@up.ac.za
joint Editor-in-chief
Prof Chris Clayton
University of Southampton
2 Centrifuge modelling of railway embankments
c.clayton@soton.ac.uk under static and cyclic loading
MANAGING Editor
Verelene de Koker P Vorster, P J Gräbe S W Jacobsz DOI: 10.17159/2309-8775/2017/v59n3a1
Tel +27 (0)11 805 5947, Cell +27 (0)83 378 3996
verelene@saice.org.za
11 Interpreting DPSH penetration values in sand soils
journal editorial Panel
Prof G Heymann – University of Pretoria C J MacRobert DOI: 10.17159/2309-8775/2017/v59n3a2
Prof CRI Clayton – University of Southampton
Prof Y Ballim – University of the Witwatersrand
Prof W Burdzik – University of Pretoria 16 Seepage column hydraulic conductivity
Dr P Day – Jones & Wagener (Pty) Ltd
Prof J du Plessis – University of Stellenbosch tests in the geotechnical centrifuge
Prof GC Fanourakis – University of Johannesburg
Prof M Gohnert – University of the Witwatersrand W D van Tonder, S W Jacobsz DOI: 10.17159/2309-8775/2017/v59n3a3
Prof PJ Gräbe – University of Pretoria
Dr C Herold – Umfula Wempilo Consulting
Prof A Ilemobade – University of the Witwatersrand
25 Exploring the relationship between
Prof SW Jacobsz – University of Pretoria
Prof EP Kearsley – University of Pretoria
vertical and lateral forces, speed and
Prof C Roth – University of Pretoria superelevation in railway curves
Prof W Steyn – University of Pretoria
Mr M van Dijk – University of Pretoria A F Powell, P J Gräbe DOI: 10.17159/2309-8775/2017/v59n3a4
Prof JE van Zyl – University of Cape Town
Prof C Venter – University of Pretoria
Prof A Visser – University of Pretoria 36 Alternative wall‑to‑slab connection systems
Dr E Vorster – Aurecon South Africa (Pty) Ltd
Prof J Wium – University of Stellenbosch in reinforced concrete structures
Prof A Zingoni – University of Cape Town
Prof M Zuidgeest – University of Cape Town J D Gerber, G P A G van Zijl DOI: 10.17159/2309-8775/2017/v59n3a5
Peer reviewing
The Journal of the South African Institution of 48 Sewer network design:
Civil Engineering is a peer-reviewed journal
that is distributed internationally Heuristic algorithm for hydraulic optimisation
Design and reproduction
N de Villiers, G C van Rooyen, M Middendorf DOI: 10.17159/2309-8775/2017/v59n3a6
Marketing Support Services, Ashlea Gardens, Pretoria
Printing
Fishwicks, Pretoria 57 Soft water attack on concrete tunnel linings in
Papers for consideration should be submitted the Ingula pumped storage hydro-power scheme:
online at: http://journal.saice.org.za
Assessment of concrete resistance and protection
The South African Institution of Civil Engineering accepts no
responsibility for any statement made or opinion expressed M Otieno, M Alexander, J du Plessis DOI: 10.17159/2309-8775/2017/v59n3a7
in this publication. Consequently, nobody connected with
the publication of this journal, in particular the proprietor,
the publisher and the editors, will be liable for any loss or
damage sustained by any reader as a result of his or her action
upon any statement or opinion published in this journal.
© South African Institution of Civil Engineering
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 1
TECHNICAL PAPER Centrifuge modelling of
Journal of the South African
Institution of Civil Engineering railway embankments under
ISSN 1021-2019
Vol 59 No 3, September 2017, Pages 2–10, Paper 1568 static and cyclic loading
PAUL VORSTER studied at the University of P Vorster, P J Gräbe S W Jacobsz
Pretoria where he obtained a BEng degree in
Civil Engineering. He completed his BEng (Hons)
in Geotechnical Engineering in 2014 at the same
university, and is currently employed in the With past embankment failures on the heavy haul coal export railway line between Ermelo and
Railway Division at GIBB (Pty) Ltd. Richards Bay in South Africa, a study was conducted focusing on the modelling of embankments
in a geotechnical centrifuge. This was done in order to investigate the influence of static and
cyclic loading on settlement, and to evaluate the potential failure of the embankment under the
Contact details:
Railway Engineering Division loading conditions. The effect that moisture has on the slope stability was also investigated. A
GIBB (Pty) Ltd suitable loading system was developed that could be used to apply static and cyclic loading to a
Woodmead North Office Park model embankment in the centrifuge. Embankment models representing a standard slope and
54 Maxwell Drive using one material type with varying moisture content were built and tested in the centrifuge.
Woodmead 2191
Clayey sand material was sampled from one of the sites where a failure occurred on the coal
South Africa
T: +27 11 519 4600 line and was used for the tests. The loading system simulated the loading created by a heavy
E: pvorster@gibb.co.za haul coal train with a 26 t per axle load along the length of an embankment. The results from
the tests conducted in the geotechnical centrifuge indicated that settlement resulting from
PROF HANNES GRÄBE Pr Eng, FSAICE, is a civil the cyclic loading was on average 67% higher than that of the static loading when considering
engineer with experience in the fields of track loaded time. It was observed that the tests with increased moisture content exhibited
technology, geotechnology, advanced significantly reduced stability. A completely developed slip surface failure was not observed.
laboratory testing, field investigations,
However, cracks formed at the crest of the embankment along its length, which indicated a
maintenance models and numerical analysis of
track structures. He is currently employed by the downward shift of material. The research therefore concluded that cyclic loading on railway
University of Pretoria as Associate Professor: embankments increases permanent vertical settlement of the embankment compared to static
Transnet Freight Rail Chair in Railway loading. As the moisture content was increased for the different tests, there was a clear increase
Engineering, where he lectures under- and post-graduate courses in railway in crack development at the crest of the embankment along its length.
engineering. He is also responsible for railway research, as well as for
continuing professional development in the form of short courses presented
to industry.
INTRODUCTION settlements associated respectively with static
Contact details:
The failure of a railway embankment can and cyclic loading. The effect of moisture on
Transnet Freight Rail Chair in Railway Engineering
Department of Civil Engineering result in large financial losses if the line has the stability of the slope was also investigated.
University of Pretoria to be closed for remedial measures, rehabili- Furthermore, triaxial tests were conduct-
Pretoria 0001 tation or if a derailment occurs. The design ed and soil moisture characteristic curves
South Africa of embankments is usually done with slope were determined to characterise the material
T: +27 12 420 4723
E: hannes.grabe@up.ac.za
stability analysis methods of slices (Selig & used in the model study, to enable limit equi-
Waters 1994; Li et al 2016). The analysis is librium stability analyses to be carried out
based on a combined factor of safety defined for comparison with the observations from
PROF SW JACOBSZ Pr Eng, MSAICE, graduated
with an MEng degree in Civil Engineering from as the ratio of available shear strength to the the centrifuge tests.
the University of Pretoria in 1996 and a PhD from shear strength that has to be mobilised to
the University of Cambridge in 2002. He is maintain the condition of limit equilibrium.
Associate Professor in the Department of Civil
In the case of railway embankments, a BACKGROUND
Engineering at the University of Pretoria. His
research interests include physical modelling of
uniformly distributed load is applied over a The investigation was based on embank-
geotechnical and soil-structure interaction central ballast width of the embankment to ments of the heavy haul coal export railway
problems in the geotechnical centrifuge. represent the load induced by the train. This, line between Ermelo and Richards Bay in
Contact details:
however, represents a static load and does South Africa. As a result of the large demand
Department of Civil Engineering not incorporate the effect of cyclic loading. for coal export through Richards Bay, the
University of Pretoria Physical modelling in a centrifuge is a line currently carries heavy axle loads of 26
Pretoria 0001 powerful tool available to geotechnical engi- t/axle and long trains of 200 four-axle coal
South Africa
neers. It allows the study of complex design wagons per train. The tractive effort avail-
T: +27 12 420 3124
E: sw.jacobsz@up.ac.za problems using geotechnical materials to able for these long trains is a limiting factor
create a more realistic representation of the and therefore the grade should be kept to a
stresses in the soil (Taylor 1995). The main minimum. In order to do this, large embank-
objective of this study was to investigate the ments had to be built on the line. Numerous
influence of static versus cyclic loading on cases of slope failures were reported by
railway embankments by testing models in Transnet during 2007 on the Ermelo –
Keywords: geotechnical centrifuge, railway embankments, cyclic loading, the geotechnical centrifuge. This was done Richards Bay line as a result of high rainfall.
static loading to investigate the failure mechanisms and the Shallow slip surface failures, as well as
2
Vorster P, Gräbe PJ, Jacobsz SW. Centrifuge modelling of railway embankments under static and cyclic loading.
J. S. Afr. Inst. Civ. Eng. 2017:59(3), Art. #1568, 9 pages. http://dx.doi.org/10.17159/2309-8775/2017/v59n3a1
deep-seated failures, occurred (Lourens & 10 6
Maree 1997). The objective of the current
research was to investigate whether the
"Tightly
cyclic nature of load application affected the
Adsorbed" 105
failure mode observed on the embankments. regime
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 3
heavy haul coal line where the slope failures
12 m
occurred. The material was sampled at the
Moolman slope failure site at kilometre 117, 5m 6m
mast pole 14 (km 117/14) on Line 2, close to
1:1
Piet Retief. The standard embankment slope
was designed at a 1:1.5 ratio. The top of the
embankment allowed for a 5 m wide ballast 0.5 m 0.5 m
section with 0.5 m shoulder on either side, as 1:1.5
12 m
well as a 6 m wide service road. A schematic
of the embankment cross-section is shown
in Figure 2. The failures that occurred
in the case studies were all on the upper
12 m of the embankments, and therefore
it was decided to scale the embankment Figure 2 Standard embankment design cross-section, coal line (South Africa)
model accordingly.
The bulk earthworks of the embank-
ments were designed to be compacted to
93% Mod AASHTO density. The research
Pneumatic piston
conducted by Lourens and Maree (1997)
showed that the density of problematic
embankments on the coal line did not meet LVDT positions on plate
this level of compaction. A conservative
value of 90% Mod AASHTO relative density
was therefore selected for the embankment Loading block
models. The material was compacted in
Track structure plate
34 mm thick layers and scarified to create a
good bond between the layers. The material
was compacted to the required embankment Embankment
height in the strongbox at the specified
density; thereafter the required embankment
shape was carved out. Strongbox
Due to embankment cross-section sym-
metry, only one side of the embankment
cross-section was modelled. This is seen
as the worst-case scenario and represents Figure 3 Final model assembly in strongbox
a double-line embankment section on the
coal line. The final cross-section used for the In order to calculate the loading time, the embankment during the test. The static
tests, with the simplified loading arrange- dynamic time scaling factor tdyn was used, loading was applied for three hours after the
ment in place, is shown in Figure 3. The which has a scaling factor of 1/N (where N is stabilisation period.
model was scaled at 1:50 and was therefore the model scale).
tested at an acceleration of 50 g in the geo- The approximate time taken by a train Centrifuge tests conducted
technical centrifuge. to pass over a section on an embankment The first four tests conducted in the study
at 80 km/h is therefore 1.8 minutes. This (A1 to A4) served as an iterative process
Loading methodology corresponds to a loaded time of 2.16 s in to establish the turning point between a
The loading methodology simulated the the centrifuge. Taking into account the stable embankment model and an unstable
entire train load on the embankment for time for the pneumatic piston to lift and to embankment model in terms of soil moisture
the duration that it takes the entire train to lower the loading block, a cycle time of 20 s content. The final six tests (B1 to B6) were
pass at a single location along the embank- was chosen. conducted at three moisture contents (two
ment. This meant that a low-frequency A separate loading plate was machined tests per moisture content) close to the
loading cycle was considered. The loading to replicate the loading created by the track established turning point. These tests were
block was manufactured from a solid alu- structure on the embankment, i.e. the conducted at moisture contents of 21%, 22%
minium section that represented a uniformly rails, sleepers and ballast. The weight from and 23%, with one test modelling the static
distributed load exerted by a fully loaded PY-sleepers (282 kg/sleeper) and 60 kg/m loading scenario and the other the cyclic
26 t/a xle wagon (total mass 104 t). The load rails was modelled assuming a conservative loading scenario.
application was controlled using a pneumatic ballast density of 2 000 kg/m3.
piston, lifting and lowering the loading Two loading methodologies were followed
block onto the embankment at a specific during the tests conducted, namely static Material Analysis
loading cycle. loading and cyclic loading. A stabilisation Comparing the parameters of the
The time per loading cycle was calculated period of one hour was allowed once the material obtained from site to the para
using the time it takes a train to pass a cer- centrifuge reached 50 g acceleration before meters required by the S410 Earthworks
tain point on the embankment. This was cal- any loading was applied to the model. This Specification (Transnet 2006) revealed
culated using the train speed of 80 km/h and was done to reduce the effect of initial certain shortcomings. The comparison can
the train length of approximately 2.5 km. settlement due to the self-weight of the be seen in Table 1. The plasticity index of the
4 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
100 material was adequate for bulk earthworks,
while the CBR results of the two samples
taken on site were well below the required
value. This could be due to the significant
80
amount of mica observed in the material.
Tubey and Bulman (1964) showed that the
content of mica in the soil significantly
Percentage passing (%)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 5
Limit equilibrium analysis 4.5
Matric suction plays an important role in the
stability of slopes. Slope stability analyses
4.0
using the Morgenstern-Price method of sli
ces were carried out to assess the stability of
a loaded versus unloaded embankment under 3.5
Factor of safety
suction values in the material, as discussed
below. The material properties used in the 2.5
analyses were obtained from the triaxial tests
and the soil moisture characteristic curve.
2.0
The material properties used in the analyses
were as follows:
■■ Unit weight: 19.6 kN/m3 1.5
■■ Friction angle: 34°
■■ Cohesion intercepts (modelling matric 1.0
suction): 0 kPa, 2 kPa, 5 kPa, 10 kPa and
80 kPa 0.5
■■ Loading = 38 kN/m 2 0 20 40 60 80 100
It was decided to perform the analyses up Cohesion (kPa)
to 80 kPa suction based on the results of Loaded Unloaded
the soil moisture characteristic curve. The
matric suction at 22% moisture content was Figure 6 Factor of safety values obtained for different suctions for loaded and unloaded scenarios
116 kPa. To convert this to additional shear
strength given by cohesion, the following
formula/calculation was used:
τ = (σ – u)tanφ’(1)
6 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
the soil and non-uniform settlement. The
position of these cracks correlated relatively
well with the location of critical slip surfaces
from the limit equilibrium slope stability
analysis conducted. The shallow slip surface
calculated from the slope stability analysis
also started at the crest of the embankment
for both loaded and unloaded conditions,
and corresponds with the formation of
cracks at the crest of the embankment in the
Indication of cracks centrifuge tests before the loading started.
The analyses conducted with higher cohe-
sion intercepts showed deep-seated failures
with larger factors of safety. This illustrates
how cohesion in the soil, which can be used
Indication of
upward lift to represent matric suction, significantly
affects slope stability. The SMCC showed
that, for the moisture content range in the
centrifuge tests (21% – 23%), there was a
significant amount of suction present in the
soil. The effect of the soil drying during the
Figure 8: I ndication of cracks created during Test B5 (23.0 % MC) joining at the top of the embankment tests significantly increased the soil suction
strength on the surface of the embankment
model, thereby reducing the likelihood of a
0 slope failure occurring.
The embankment settlement during the
–5 centrifuge acceleration to 50 g is shown for
each test in Figure 9. The graph includes
–10 Test A4 conducted at 24% moisture content.
Settlement (mm)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 7
Further comparison between the static
0
and cyclic loading was made by taking into
account only the actual time that the load
–0.5
was in contact with the embankment during
the cyclic loading tests. During the 20 s load-
–1.0
Settlement (mm)
ing and unloading cycle, the embankment
was under-loaded for approximately 2.5 s to
3.5 s only. In order to compare the settle- –1.5
ment magnitude under cyclic and static load-
ing for the duration that the embankment –2.0
was physically loaded, a conservative value
of 4 s of loading per 20 s cycle was chosen. –2.5
The settlement curves for the cyclic loading
tests were therefore shortened by a factor –3.0
of 5 to produce comparable graphs with 0 1 000 2 000 3 000 4 000 5 000 6 000 7 000 8 000 9 000 10 000 11 000
regard to the actual loaded time. Therefore, Time (s)
the 12 h settlement time of cyclic loading B1 – Static (21% MC) B3 – Static (22% MC) B5 – Cyclic (23% MC)
is compared to the 2.4 h settlement during B2 – Cyclic (21% MC) B4 – Cyclic (22% MC) B6 – Cyclic (23% MC)
the corresponding suction value decreases B1 – Static (21% MC) B3 – Static (22% MC) B5 – Cyclic (23% MC)
significantly to 49 kPa. B2 – Cyclic (21% MC) B4 – Cyclic (22% MC) B6 – Cyclic (23% MC)
8 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
The settlement difference between static
6
and cyclic loading with regard to loaded
time increased by 8.7% for the 21% and 22%
moisture content tests. However, a 51%
5
increase in the settlement difference was
observed for the 22% and 23% moisture
content tests. This emphasises the effect
4
that the moisture content of a soil has on its
Settlement (mm)
8 ACKNOWLEDGEMENTS
Transnet Freight Rail is gratefully acknow
7
ledged for financial support to the Chair
Settlement (mm)
1
REFERENCES
0 Blackall, T E 1952. A. M. Atterberg 1846–1916.
21 22 23
Geotechnique, 3(1): 17–19.
Moisture content (%)
Fredlund, D G & Rahardjo, H 1993. Soil Mechanics for
Acceleration period Stabilisation period Static Loading Cyclic loading
Unsaturated Soils. New York: Wiley Interscience.
Gräbe, P J & Clayton, C R I 2009. Effects of principal
Figure 13: Final centrifuge testing settlement for each period during the tests for the same effective stress rotation on permanent deformation in rail
loaded time track foundations. Journal of Geotechnical and
Geoenvironmental Engineering, 135(4): 555–565.
content after three hours of loading. The embankment was physically loaded. The set- Gunn, D A, Haslam, E, Kirkham, M, Chambers, J E,
settlement curve for the cyclic loading test tlement resulting from the cyclic loading was Lacinska, A et al 2009. Moisture measurements in an
at 23% moisture content, however, showed on average 67% higher than that of the static end-tipped embankment: Application for studying
a 48% increase in settlement from the static loading, when considering the loaded time. long-term stability and ageing. Proceedings, 10th
loading settlement at 23% moisture content. This can be attributed to continuous particle International Conference on Railway Engineering,
A settlement comparison between cyclic rearrangement during the cyclic loading 24–25 June, London.
and static loading was done considering process, as well as changes in the pore water Jacobsz, S W, Kearsley, E P & Kock, J H L 2014. The
only the contact time during which the pressures or suctions. geotechnical centrifuge facility at the University of
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 9
Pretoria. In Springman, S M, Laue, J & Seward, L. McQueen, I S & Miller, R F 1974. Approximating Transnet 2006. Specification for Railway Earthworks
Physical Modelling in Geotechnics. London: Taylor & soil moisture characteristics from limited data: S410. Johannesburg: Transnet Ltd.
Francis, 169–174. Empirical evidence and tentative model. Water Tubey, L W & Bulman, J N 1964. Micaceous soils:
Li, D, Hyslip, J, Sussmann, T & Chrismer, S 2016. Resources Research, 10(3): 521–527. Methods of determining mica content and the
Railway Geotechnics. Boca Raton, F L: CRC Press/ Rahardjo, H, Lee, T T, Leong, E C & Rezaur, R B use of routine tests in the evaluation of such soils.
Taylor and Francis. 2005. Response of a residual soil slope to rainfall. Proceedings, 2nd Conference of the Australian Road
Lourens, J P & Maree, J S 1997. Rehabilitation design of Canadian Geotechnical Journal, 42(2): 340–351. Research Board, Melbourne, 2, 880–901.
high embankments and a coal line track formation. Rahardjo, H, Lim, T T, Chang, M F & Fredlund, D G Turner, A K & Schuster, R L 1996. Landslides –
Proceedings, 6th International Heavy Haul 1995. Shear-strength characteristics of a residual Investigation and mitigation: National Research
Conference, 6–10 April, Cape Town, 1: 57– 75. soil. Canadian Geotechnical Journal, 32(1): 60–77. Council, Transportation Research Board Special
Lu, N & Likos, W J 2004. Unsaturated Soil Mechanics. Selig, E T & Waters, J M 1994. Track Geotechnology and Report 247. Washington: National Academy Press.
Hoboken, N J: Wiley. Substructure Management. London: Thomas Telford. Weinert, H H 1980. The Natural Road Construction
Malvern Instruments Ltd 2012. Mastersizer 2000. Taylor, R N 1995. Geotechnical Centrifuge Technologies, Materials of Southern Africa. Cape Town: H & R
Available at: www.malvern.com 1st ed. London: Blackie Academic & Professional. Academica.
10 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Interpreting DPSH TECHNICAL PAPER
penetration values Journal of the South African
Institution of Civil Engineering
Specific work per blow (kJ/m 2) 240 240 Keywords: site investigations, in-situ testing, penetrometers, soil classification,
statistical analysis
11
MacRobert CJ. Interpreting DPSH penetration values in sand soils.
J. S. Afr. Inst. Civ. Eng. 2017:59(3), Art. #1551, 5 pages. http://dx.doi.org/10.17159/2309-8775/2017/v59n3a2
Table 2 R
elative density N descriptor Table 3 Descriptive geology of each site
boundaries for sand soils Average relative
Site Description Water table
(after Terzaghi & Peck 1948) density
where x̄ is the sample mean and s is the sam- that the average COV in sand was 54% and in the former study predominantly reflects
ple standard deviation. ranged between 19% and 62%. The larger variation within the testing procedure. No
variability in the later study reflects lateral studies on variability in the DPSH are appar-
Phoon and Kulhawy (1999), considering variation in site soil profiles and various ent in literature; however, similar variability
published site investigation data, suggested hammer mechanisms, whereas the variability to that reported for the SPT is likely.
Chloorkop, South Africa 0.9 5.6 8.1 3 33% (55 – 15%) 2 19% (54 – 6%)
Namakwa, South Africa 2.1 11.7 26.7 2 (2) - 8 (2) 33% (127 – 5%)
Matutuíne, Mozambique 0.9 3.1 6.6 4 (2) 29% (76 – 6%) 19 (2) 68% (96 – 4%)
Mt Edgecombe, South Africa 1.5 9.2 15.3 15 (6) 17% (64 – 1%) 18 (6) 19% (90 – 2%)
Parktown, South Africa 0.9 4.1 6.3 8 105% (164 – 78%) 19 139% (222 – 88%)
Milnerton, South Africa 0.9 3.0 3.9 2 14% (35 – 2%) 2 26% (56 – 1%)
Chicalla, Angola 1.2 7.2 10.8 3 31% (47 – 12%) 8 27% (56 – 4%)
Umdloti, South Africa 1.2 3.7 6.3 3 42% (88 – 8%) 10 37% (96 – 6%)
Gope, Botswana 1.2 6.5 9.3 5 23% (46 – 3%) 11 43% (84 – 28%)
Matola Mozambique 1.5 9.6 13.8 17 26% (33 – 19%) 17 22% (41 – 7%)
12 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Correlation between for all strata at each site and gives the average. N30SB N
N and N30SB The average values are generally towards the 200 150 100 50 0 50 100
lower range of the limits (19% to 62%) reported 0
Strata:
Test sites by Phoon and Kulhawy (1999). This suggests
1 1.5
To investigate the correlation between N and that there was limited lateral variation in the
N30SB, data from 13 site investigations were soil profiles. One site that exhibited signifi-
2 3
analysed. Data was collected from various cantly greater variability was the Parktown
engineering and contracting companies, site. This site was characterised by material
3 4.5
with probing carried out according to best of mixed origin that included coal, ash and
practice in southern Africa (MacRobert et al refuse which contributed to the large variation
4 6
2010). Consequently, relationships developed observed. Disregarding this site as anomalous,
Depth (m)
may not be applicable for different hammer the average COV for N30SB was 32% and for
5 7.5
efficiencies and where probing practices N was 25%. Although the average COV values
differ. Table 3 shows that all profiles probed for the N30SB and N are similar, it is clear from 6 9
consisted of sand soils, with Table 4 giving the ranges of COV values for the two tests that
details of the probing undertaken at each N30SB showed greater variability. 7 10.5
site. Most sites were small and borehole logs
indicated similar soil profiles, and so all N Statistical methodology 8 12
and N30SB profiles for such sites could be In light of the variability in penetration
compared. For sites where probing was over values, individual values were not compared. 9 13.5
a large area, N and N30SB profiles were sepa- Rather, the range of N values were compared
rated into subsites with similar soil profiles to the corresponding range of N30SB values 15
based on borehole logs. within a stratum across a site. Consequently
Soil profiles below sites (or subsites) were energy corrections, such as proposed by Figure 1 Matola strata
divided into 1 m thick strata centred at the Skempton (1986), were not applied, as these
depths where N values were determined. An are more appropriate when considering assigned a relative density based on which
example of these strata for the Matola site is individual N values. Assuming N values to relative density resulted in the highest prob-
given in Figure 1. The average and standard be normally distributed, the probabilities of ability. A comparison was then made between
deviation of all N values within a stratum each stratum being classified into each of the relative density assigned by N values and
were then determined. For sites with only the five relative density ranges (Table 2) were N30SB values. The N30SB boundaries were sub-
one N profile, the standard deviation was calculated. Each stratum was then assigned sequently optimised, using the entire data set,
calculated assuming a COV of 25%. The cor- a relative density based on which relative to maximise the number of strata assigned the
responding range of N30SB values was deter- density resulted in the highest probability. same relative density by both tests.
mined as the average and standard deviation Equivalent N30SB relative density
of all N30SB values within each 1 m thick boundaries (Table 6) were calculated using the
stratum. This resulted in a series of strata for empirical correlation proposed by MacRobert Results
which average N and N30SB values and asso- et al (2011) from N boundaries in Table 2. Prior to considering the entire data set,
ciated standard deviations were known. Assuming N30SB values to be normally distrib- results for the Matola site are discussed.
For each of these strata the COV values uted, the probabilities of each stratum being For each of the strata (Figure 1) average
of the N and N30SB values were calculated. classified into each of these relative density and standard deviation of N and N30SB
Table 4 summarises the range of COV values ranges were calculated. Each stratum was then values are given in Table 5. The calculated
1 25 8 32 15 0.004 0.026 0.704 0.265 0.001 41 17 41 39 0.013 0.021 0.834 0.132 0.023 0.033 0.933 0.011
2 27 11 41 17 0.018 0.043 0.546 0.374 0.018 64 24 38 39 0.006 0.007 0.422 0.566 0.009 0.010 0.729 0.252
3 35 8 23 15 0.000 0.001 0.265 0.704 0.030 86 28 33 39 0.002 0.002 0.173 0.823 0.002 0.003 0.410 0.585
4 39 10 26 17 0.000 0.002 0.182 0.680 0.136 107 23 21 39 0.000 0.000 0.020 0.979 0.000 0.000 0.120 0.880
5 36 8 22 15 0.000 0.001 0.226 0.733 0.040 124 17 14 31 0.000 0.000 0.000 1.000 0.000 0.000 0.005 0.995
6 39 12 31 17 0.002 0.006 0.219 0.594 0.180 138 13 9 24 0.000 0.000 0.000 1.000 0.000 0.000 0.000 1.000
7 37 8 22 16 0.000 0.000 0.190 0.757 0.052 140 13 9 12 0.000 0.000 0.000 1.000 0.000 0.000 0.000 1.000
8 50 13 26 15 0.000 0.001 0.061 0.438 0.500 143 5 3 6 0.000 0.000 0.000 1.000 0.000 0.000 0.000 1.000
9 57 28 49 6 0.029 0.017 0.121 0.234 0.599 149 1 1 3 0.000 0.000 0.000 1.000 0.000 0.000 0.000 1.000
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 13
probability for each relative density, for Table 6 Relative density N30SB descriptor boundaries for sand soils
each stratum, based on N values is given.
N30SB boundaries by
Each stratum’s assigned relative density and Relative density Optimised N30SB boundaries
MacRobert et al (2011)
associated probability are indicated by bold
Very loose 0–3 0–7
type. Results from calculations performed
on N30SB values are presented in a similar Loose 3 – 10 7 – 14
fashion. Based on the MacRobert et al (2011) Medium-dense 10 – 60 14 – 80
boundaries, 6 stratum are assigned the same
Dense > 60 > 80
relative density by both tests, 1 is assigned a
higher relative density by N30SB values and 2
are assigned a lower relative density by N30SB define a single equation to obtain equivalent strata assigned a lower relative density by
values. With the optimised boundaries, N from N30SB. However, it is possible to N30SB values than by N values. Ordinates are
7 stratum are assigned the same relative assign a relative density to a stratum with the probabilities that the N values would give
density by both tests and 2 are assigned some confidence. the same lower relative density. In this case,
a lower relative density by N30SB values. With the MacRobert et al (2011) descrip- the average probability that N values would
Considering the two strata assigned lower tor boundaries, 49% of the strata were give the same lower relative density is 0.15.
relative densities by N30SB values, the prob- assigned the same relative density by both Whilst this probability is small, it is greater
abilities that these strata would be assigned tests, 29% were assigned a lower relative than 0.05, suggesting there is nevertheless a
the same lower relative density by N values density by N30SB values (i.e. a conservative significant chance that the strata are correct-
are significant (> 0.05). This suggests that estimate), and 22% were assigned a higher ly defined by N30SB values. Figure 3(c) shows
the optimised boundaries are adequate for relative density by N30SB values. With the strata assigned a higher relative density by
categorising strata. optimised descriptor boundaries, 57% of the N30SB values than by N values. Ordinates
Figure 2 illustrates the average N and strata were assigned the same relative density are the probabilities that the N value would
N30SB values for each stratum and for each by both tests, 31% were assigned a lower give the same higher relative density. In this
site. In general, N30SB values are greater than relative density by N30SB values (i.e. a con- case, the average probability that N values
respective N values. This is due to N30SB servative estimate), and 12% were assigned a would give a similar higher relative density
values increasing with depth at a greater rate higher relative density by N30SB values. is 0.07, so there is a much lower chance that
than N values. Harrison and A’Bear (2011) Calculated probabilities associated with the strata are correctly defined by N30SB
attributed this to rods bowing during prob- defining a stratum’s relative density by N values. Referring to Figure 2 it is evident
ing, causing jamming and sidewall collapse. values and N30SB values (optimised descrip- that most of the strata assigned a higher
This suggests that a correlation varying with tor boundaries) are considered in Figure 3. relative density based on N30SB are from the
depth may be appropriate. However, no such Figure 3(a) considers strata assigned the Chicalla site. As pointed out by MacRobert
relationship was apparent when analysing same relative density by both tests. As et al (2011), the ground profile at this site
the data. It is evident that the equation expected, the confidence with which these contained numerous shell fragments which
proposed by MacRobert et al (2011) is not strata are assigned a relative density is high may have resulted in the higher N30SB values.
sufficiently accurate to obtain equivalent N in both tests. However, individual prob- This highlights the need for a local know
values from N30SB values. From the scatter abilities are not comparable, as points do not ledge of geology when interpreting N30SB
in the graph, it is evidently impossible to lie along a line of equality. Figure 3(b) shows values. Points marked with a red asterisk in
70
Bellville
Glenhazel
50
Matutuine
MacRobert et al (2011)
40 Namakwa
Mt Edgecombe
N
30 Parktown
Optimised boundaries
Milnerton
20
Chicalla
Umdloti
10
Gope
Matola
0
0 20 40 60 80 100 120 140 160
N30SB
14 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Probability based on N 1.0 1.0 1.0
Probability based on N
Probability based on N
0.5 0.5 0.5
0 0 0
0 0.5 1.0 0 0.5 1.0 0 0.5 1.0
(a) Probability based on N30SB (b) Probability based on N30SB (c) Probability based on N30SB
Figure 3 P
robability associated with assigning the same relative density to a stratum by N and N30SB for: (a) similar cases, (b) conservative cases and
(c) unconservative cases
Figure 2 indicate strata where the probability kindly provided valuable comments on testing. Proceedings, 17th International Conference
N would give the same relative density, as the manuscript. on Soil Mechanics and Geotechnical Engineering,
N30SB is less than 0.05. These points make up Alexandria, Egypt. Amsterdam: IOS Press,
12% of the data set. 2777–2872.
References Phoon, K-K & Kulhawy, F H 1999. Characterization
Broms, B B & Flodin, N 1988. History of soil penetration of geotechnical variability. Canadian Geotechnical
Conclusions testing. Proceedings, 1st International Symposium on Journal, 36(4): 612–624.
A statistical analysis of 13 site investigations, Penetration Testing, ISOPT-1, 20–24 March, Orlando, Robertson, P 2009. Interpretation of cone penetration
in which 65 SPT and 121 DPSH profiles FL. Rotterdam: AA Balkema, 157–220. tests – a unified approach. Canadian Geotechnical
were determined, was undertaken. This Byrne, G & Berry, A D 2008. A guide to practical Journal, 46(11): 1337–1355.
was used to propose new N30SB relative geotechnical engineering in southern Africa. Sandton: Robertson, P & Cabal, K 2012. Guide to cone
density descriptor boundaries for sand Frankipile South Africa. penetration testing for geotechnical engineering.
soils. Considering the inherent variability of Harrison, B & A’Bear, T 2011. The dynamic probe Signal Hill, CA: Gregg Drilling & Testing Inc.
penetration values obtained from penetro super heavy penetrometer and its correlation with Serota, S & Lowther, G 1973. Discussion: Accuracy of
meters, it is clear that defining a single the Standard Penetration Test. In: Quadros, C & relative density measurements. Géotechnique, 23(2):
equation to determine equivalent N values Jacobsz S W (Eds.), Proceedings, 15th African 301–303.
from N30SB values is futile. The practice Regional Conference on Soil Mechanics and Shahien, M M & Farouk, A 2013. Estimation of
of using N30SB values to obtain anything Geotechnical Engineering, Maputo, Mocambique. deformation modulus of gravelly soils using dynamic
more than an estimate of relative density is Amsterdam: IOS Press, 571–579. cone penetration tests. Ain Shams Engineering
therefore unwarranted. MacRobert, C, Kalumba, D & Beales, P 2010. Journal, 4(4): 633–640.
Penetration testing: Test procedures and design use Shukla, S K 2015. Core concepts of Geotechnical
in South Africa. Civil Engineering, 18(3): 29–38. Engineering. London, ICE Publishers.
AcknowledgEments MacRobert, C, Kalumba, D & Beales, P 2011. Skempton, A 1986. Standard penetration test
The author acknowledges the various geo- Correlating standard penetration test and dynamic procedures and the effects in sands of overburden
technical consultants and contractors for probe super heavy penetration resistance values in pressure, relative density, particle size, ageing and
kindly providing the analysed data. Stuart sandy soils. Journal of the South African Institution overconsolidation. Géotechnique, 36(3): 425–447.
Hoepper’s assistance in collecting the data of Civil Engineering, 53(1), 46–54. Terzaghi, K & Peck, R B 1948. Soil Mechanics In
is acknowledged; his untimely passing is a Mayne, P W, Coop, M R, Springman, S M, Huang, A-B Engineering Practice. New York: Wiley.
reminder of life’s fragility. Dr Irvin Luker & Zornberg, J G 2009. Geomaterial behavior and
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 15
TECHNICAL PAPER Seepage column hydraulic
Journal of the South African
Institution of Civil Engineering conductivity tests in the
ISSN 1021-2019
Vol 59 No 3, September 2017, Pages 16–24, Paper 1525 geotechnical centrifuge
WARREN VAN TONDER, who graduated with an W D van Tonder, S W Jacobsz
MSc in Hydrogeology from the University of
Pretoria in 2016, is currently employed as a
professional in training by Exxaro Resources. His
work experience includes both underground Provided that inter-particle flow remains laminar, hydraulic conductivity tests can be carried out
and surface coal mining operations, and he is in a centrifuge to accelerate flow, allowing the hydraulic conductivity of relatively impervious
currently based at Grootegeluk Coal Mine in materials to be measured within a reasonable time. It is well documented that the inter-particle
Lephalale (previously Ellisras). His postgraduate
flow velocity in the centrifuge increases linearly with acceleration, and a debate in the literature
studies focused on the physical modelling of fracture flow, as well as the
permeability of coal mine backfill material, in the geotechnical centrifuge. deals with whether hydraulic conductivity also scales with acceleration or not. A number
of hydraulic conductivity tests were carried out using seepage columns in the geotechnical
Contact details:
centrifuge in which pore pressures were recorded within the samples during testing. When
Geology Department Hydrogeologist in Training
University of Pretoria Exxaro Resources Ltd hydraulic conductivity is calculated from the hydrostatic potentials measured during testing,
Pretoria 0001 PO Box 3583 the hydraulic conductivity is found to be independent of the imposed acceleration. It is
South Africa Middelburg 1050 therefore advocated that the hydrostatic potential is scaled in the centrifuge rather than the
South Africa hydraulic conductivity. It must therefore be recognised that the hydraulic gradient used in the
T: +27 14 763 9945
conductivity calculation does not remain constant, but changes with the imposed acceleration.
E: warren.vantonder@exxaro.com OR warrenvt@hotmail.com
16
Van Tonder WD, Jacobsz SW. Seepage column hydraulic conductivity tests in the geotechnical centrifuge.
J. S. Afr. Inst. Civ. Eng. 2017:59(3), Art. #1525, 9 pages. http://dx.doi.org/10.17159/2309-8775/2017/v59n3a3
The negative symbol denotes the reducing length of the medium (often taken as the N times in the centrifuge, Taylor (1995)
hydrostatic potential along the flow path. The effective particle size, typically assumed to be and Thusyanthan and Madabhushi (2003)
hydraulic conductivity (often also referred D10 (Singh & Gupta 2000)). proposed that the hydraulic gradient is N
to by engineers as the coefficient of perme- times larger than in the prototype. The
ability) has units of velocity, and is a measure Scaling laws increased acceleration results in an increase
of the resistance of a porous medium to the As with the geometry and material proper- in the potential energy per unit volume of
flow of water. The hydraulic conductivity (k) ties of a centrifuge model, the flow in the fluid. This results in the change in head
is largely dependent on the size of the pore model needs to be representative of that (∆h) having to occur over a length N times
spaces within the porous medium. Hence, in the prototype. To achieve the required smaller than in the prototype. Therefore,
k is related to the particle size distribution, similitude between the model and prototype, the gradient (i) will be directly proportional
the shape of the particles and the manner the flow of water needs to be properly scaled to acceleration with a scaling factor of N
in which these particles are arranged in the (Nakajima & Stadler 2006). As mentioned so that k can be seen as a material constant
porous medium (structure and density), by numerous authors (e.g. Taylor 1995; (k m = kp ), as displayed by Equation 7.
with a finer porous medium having a lower Dell’Avanzi & Zornberg 2002; Thusyanthan
hydraulic conductivity (see for example the & Madabhushi 2003; Nakajima & Stadler vm = Nip kp = Nvp(7)
traditional texts by Hazen (1892) and Kozeny 2006), the primary scaling law for flow in a
(1927), and more recently Alyamani and Sen centrifuge is that of seepage velocity (v), as From the above discussion it may seem
(1993) and Chakraborty et al 2006)). shown in Equation 5. irrelevant whether i or k is the fundamental
However, the hydraulic conductivity is parameter affected by the elevated accel-
as much dependent on the properties of the vm = Nvp(5) eration field generated in a centrifuge, as
permeant as the properties of the porous both arguments still satisfy the scaling law
medium. For example, temperature will have The seepage velocity in the centrifuge model for seepage velocity. However, when using
a direct effect on k as it alters the viscosity of (vm ) will be N times greater than in the centrifuge models to determine the hydraulic
a fluid. As demonstrated by Equation 3, k is prototype (vp ) it represents (Taylor 1995). conductivity of soil material, it becomes
inversely proportional to the fluid dynamic As stated by Thusyanthan & Madabhushi important to understand the effect of cen-
viscosity (μ) and directly proportional to K (2003), this scaling law has been proven tripetal acceleration on both i and k in order
(the intrinsic permeability with units of m2) experimentally, provided that the prototype to relate the model results to the prototype
and fluid density ρ. soil is used in the model and the soil is fully with the appropriate scaling laws.
saturated (Taylor 1995).
k=
Kgρ
(3)
However, when one considers Darcy’s Assessing hydraulic conductivity
μ equation governing seepage flow, two oppos- using seepage column experiments
ing issues arise. The debate deliberates in the geotechnical centrifuge
The intrinsic permeability (K) is an absolute whether the hydraulic conductivity (k) or The hydraulic conductivity of a granular
coefficient which depends on the character- the hydraulic gradient (i) is the fundamental medium can be measured using a seepage
istics of the porous medium only. Hence, k parameter affected by increased acceleration column in the centrifuge. The option exists
will decrease with an increase in dynamic (Taylor 1995; Thusyanthan & Madabhushi to conduct either a falling head or a constant
viscosity at lower temperatures. 2003). Some researchers (e.g. Singh & Gupta head experiment. During model prepara-
Darcy’s law requires that all flow should 2000) consider hydraulic conductivity (k) to tion, the granular material is placed at the
be laminar so that resistive viscous forces be directly proportional to acceleration, and required density in a suitable cylindrical
dominate at low fluid velocities (Culligan- suggest that the gradient (i) is independent container which is filled with water, and
Hensely & Savvidou 1995; Singh & Gupta of acceleration as it is dimensionless. Thus, measures are taken to ensure saturation of
2002). When flow velocities increase, the if i is independent of acceleration, then the sample. The centrifuge is accelerated
inertial forces are sufficiently high to over- im = ip and k is a function of the accelera- to the required acceleration and an outlet
come the resistive viscous forces, and the tion imposed by the centrifuge. Based on control valve at the bottom of the column is
flow is said to be turbulent. Hence, at high this argument, opened to initiate downward flow.
fluid velocities, turbulent flow dominates and Prior to the opening of the outlet valve,
Darcy’s law is invalid. To determine whether vm = ip Nkp = Nvp(6) full hydrostatic pressure corresponding to
flow is laminar or turbulent, four factors are the depth of the seepage column will occur
considered in the calculation of the Reynolds This results in the scaling law for seepage throughout the column. The distribution
number (Re) (Equation 4). For Darcy’s law velocity being satisfied. of hydrostatic pore pressure and potential
to be valid, Fetter (2001) states that the As outlined by Taylor (1995) and (total head) is illustrated in Figure 1. During
Reynolds number (Re) should be less than 1 Thusyanthan and Madabhushi (2003) the a hydraulic conductivity test, opening of the
to 10, depending on the granular medium. problem with this argument is that soils outlet valve results in the pore pressure at
In most cases seepage flow in porous media would appear to be impermeable under zero the bottom of the seepage column dropping
is slow enough for Darcy’s law to be valid, gravity. This is due to the assumption of all rapidly to the head maintained at the outlet
except where there are large cavities/fractures seepage flow being gravity-driven and at (in the case of Figure 1 it is atmospheric).
or steep hydraulic gradients (Fetter 2001). zero gravity there would not be any pressure The base of the column is usually taken as
gradient to induce seepage flow through the the test datum, so that the hydrostatic poten-
ρvd soil (Taylor 1995). tial at the outlet is maintained at zero during
Re = (4)
μ However, based on the definition of flow and the pressure head and potential
the hydraulic gradient (Equation 2), and distributions change, as shown in Figure 1.
In Equation 4 v is the specific discharge velo as stresses are equal to those of the pro- In the case of a falling head test, the drop in
city and d is the characteristic microscopic totype, while the lengths are condensed potential, reflected by the drop in water level
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 17
over a period of time (∆t), is subsequently
Elevation head (h0)
recorded and the hydraulic conductivity is
calculated using Equation 8.
Pr
es
L h0 su
k= ln (8) Free re
water he
∆t h1 ad
(h
yd
PPT3 r os
In Equation 8 L is the height of the speci- ta
t ic
w)
material )
the original hydrostatic potential measured
g f lo
f low
from the datum level and h1 the potential i ng
in
r
h0 (du
(du r
after time ∆t. Equation 8 assumes a seepage ad
he
al
h e ad
column of constant cross-sectional area. PPT2 t
To
Examining Equation 8 in the context of a
s u re
hydraulic conductivity test carried out in a
P re s
centripetal acceleration field leads to a num-
ber of observations:
■■ In the derivation of the expression the
Filter PPT1 45°
initial hydraulic gradient was taken as
h0/L reducing over time (∆t) to h1/L
under free drainage. For the expression Total head Elevation head
to be valid there may not be any obstruc- Pressure head
tion to the flow, e.g. an outlet that is too
narrow. Should such constrictions occur, Figure 1 P
ressure head and hydrostatic potential (total head) profiles respectively during
the measured hydraulic conductivity will hydrostatic conditions and during flow
reflect this influence and the measure-
ment will not be a result of only the mate-
rial’s hydraulic conductivity. 50 mm
■■ The centripetal acceleration exerted
300 mm
400 mm
given drop in potential (∆h) will reduce 2
as acceleration is increased. This will
200 mm
18 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
100 the solenoid valves were closed and the pore
pressures were allowed to stabilise before the
90
centrifuge was stopped. Once the centrifuge
80
had stopped, the sample thickness and final
Percentage passing (%)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 19
Calculated pore pressure (kPa) Calculated pore pressure (kPa)
0 50 100 150 200 250 0 50 100 150 200 250
0 0
0.1 0.1
0.2 0.2
0.3 0.3
Depth in model (m)
0.5 0.5
3 hz3 = a + b
0.6 0.6 h0
0.7 0.7 h1
b
0.8 0.8
2 hz2 = a
0.9 0.9
1.0 1.0
(a) (b) a
1
Varying acceleration Constant acceleration hz1 = 0
Figure 5 Matching pore pressure distributions in constant and linearly variable acceleration fields
Figure 6 T heoretical model configuration used
surface and ω is calculated according to (hz) when flow velocity is disregarded. Under to demonstrate the estimation of k
Equation 13. Na is the set centripetal accelera- hydrostatic conditions, before flow is initiated, from pore pressure data
tion in multiples of gravitational acceleration. the total head (or hydrostatic potential) at any
point in the cylinder is equal to the total head Provided that the material does not com-
Na ∙ g at the bottom of the cylinder where the maxi- press significantly during testing, these
ω= (13)
r mum pore pressure is measured. Therefore: elevation heads remain constant for the
H1 = H2 = H3. duration of a test and are required for the
The pore pressure distribution plotted As the acceleration varies with radial determination of the hydrostatic potential,
using Equation 12 in Figure 5(a) illustrates distance from the centrifuge axis, the eleva- together with the pore pressure changes
that the water pressure distributions for a tion head cannot be simply taken as its eleva- during flow, as illustrated for PPT 2 in
varying and constant inertial acceleration tion above the datum. Using the measured Equation 15.
do not align. The centripetal acceleration is hydrostatic pore pressures for each PPT (hp)
usually adjusted to ensure that the amount and the total head (H1), the elevation head H2 = hz2 + hp2(15)
of under-stress relative to the linear stress (hz) for each PPT can be calculated from
distribution is equal to the amount of over- Equation 14, as illustrated, for example, Therefore, the hydrostatic potential at each
stress. This is achieved when the radial dis- for PPT 2. PPT during flow can be determined, and the
tance in Equation 13 is set to r 0 + H/3, with difference in potential (ΔH) between two
H the depth of soil in the model (Schofield hz2 = H1 – hp2(14) individual PPTs calculated, to determine the
1980). Stresses will then match at a depth of
2/3H below the model surface, and Na will
represent the corresponding model scale. As 200
23 g test acceleration reached
demonstrated by Figure 5(b), the stress dis- 180
Values opened
tributions do not match perfectly and there
160 PPT3
is both some over and under-stress. However,
Measured pore pressure (kPa)
100
Processing pore pressure data for PPT1
80
hydraulic conductivity determination
A practical example, using a hypothetical 60
model configuration illustrated by Figure 6, 40
is included to demonstrate the calculation of
20
hydraulic conductivity values from the pore Steady flow
pressure measurements. In Figure 6 three PPTs 0
are separated by distances a and b, and the ini- –20
tial and final heads recorded before and after a 0 200 400 600 800 1 000 1 200 1 400
test are denoted by h0 and h1 respectively. Time (seconds)
20 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
similar to that of the 23 g test. Pore pressures
10
Valves opened and seepage velocities were much lower due
to the test being conducted at 1 g. The jag-
8 ged appearance of the graph is attributed to
Measured pore pressure (kPa)
PPT3
the PPTs measuring near the limit of their
resolution.
6
The water head decreased by a combined
PPT2
0.237 m in 219 seconds over the two separate
4 Steady flow runs of the 23 g test. Flow was significantly
Valves closed
PPT1 slower for the 1 g tests and the water head
fell by 0.240 m over 1 913 seconds. Potential
2
differences (ΔH) between the PPTs were
calculated from the pore pressures in
0 Figures 7(a) and 7(b).
0 500 1 000 1 500 2 000 2 500 3 000 The volumetric discharge rate (Q) in each
Time (seconds) test was calculated from the drop in water
PPT1 PPT2 PPT3 level and the cylinder dimensions assuming
constant flow. Hydraulic conductivity values
Figure 7(b) Pore pressure response during Test 1 (1 g) between the PPTs were calculated using
Darcy’s equation (Equation 16) and are pre-
Table 1 Calculated hydraulic conductivities between PPTs at 23 g and 1 g (Test 1) sented in Table 1. The values fell within the
same order of magnitude with the hydraulic
Test PPT l (m) Q (m3/s) A (m 2) ΔH (kPa) i k m (m/s)
conductivity of the 1 g test, on average only
1 to 2 0.2 11.4 5.83 1.86 E-04 1.12 times greater than those of the 23 g test.
23 g 2 to 3 0.2 1.76 E-05 0.0163 14.6 7.45 1.45 E-04 Hence, the acceleration of the centrifuge
appears to have had a minimal effect on the
1 to 3 0.4 26.16 6.643 1.63 E-04
hydraulic conductivity, indicating that the
1 to 2 0.2 0.142 0.710 1.77 E-04 material underwent only limited compres-
1g 2 to 3 0.2 2.04 E-06 0.0163 0.134 0.669 1.87 E-04 sion at high accelerations.
Test 1 50
The pore pressure records for the 23 g and Valves closed
1 g tests are illustrated in Figure 7. After 0
acceleration commenced, the pore pressures
increased and stabilised rapidly once the –50
required acceleration was reached, as shown 0 500 1 000 1 500 2 000 2 500 3 000 3 500 4 000
in Figure 7(a). The pore pressure rapidly Time (seconds)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 21
Table 2 Calculated hydraulic conductivities between PPTs at 29 g (Test 2) with the bottom of the column. Under
unobstructed flow the pore pressure at the
γw (kN/
Test PPT l (m) Q (m3/s) A (m 2) ΔH (kPa) k m (m/s) bottom of the column should therefore have
m3)
reduced to atmospheric when the outlet
1 to 2 0.1 79.1 5.24 E-07
valves were opened. It can be seen from
2 2 to 3 0.2 6.88 E-07 0.0163 9.81 87.3 9.49 E-07 Figures 7, 9 and 10 that, after opening of
the valves, the pressure head at the base of
1 to 3 0.3 166 7.47 E-07
the column was still substantial, indicat-
ing that the outlet posed an obstruction
Table 3 C
alculated Reynolds numbers for each pressure data using Darcy’s equation to free flow. The falling head formulation
centrifuge test configuration (Equation 16) as before. The values calculated for calculation of hydraulic conductivity
for the sample do not vary significantly and all is therefore not valid. Had the falling head
Test Reynolds number
fall within the same order of magnitude. formulation been used, a hydraulic con-
Test 1 (23 g) 0.103 ductivity of 2.2 E-05 m/s would have been
Test 1 (1 g) 0.012 calculated compared to the correct value of
DISCUSSION 1.6 E-04 m/s, a difference of an order of mag-
Test 2 (29 g) 1.90 E-04
nitude. Without pore pressure measurement
Validity of Darcy’s law in at the base of the column, the user would not
subsequently by PPTs 2 and 1, reflecting centrifuge tests have been aware of this discrepancy.
their respective drainage path lengths. The hydraulic conductivities presented The potential gradients at 23 g between
Once the pore pressures had stabilised, above assumes laminar flow, a requirement respectively PPT 1 and PPT2, and PPT2 and
the valves were opened. As illustrated for Darcy’s law to be valid (e.g. Fetter 2001; PPT3, were very similar, indicating that the
by Figure 8, PPT 1 showed the quickest Singh & Gupta 2000). This requires the hydraulic conductivity of the material was
response and the greatest drop in pore pres- Reynolds number to be less than unity. not affected appreciably by compression
sure, while PPT 3 measured the smallest Using a characteristic length corresponding under high acceleration.
pore pressure drop and took the longest to to a D10 of 0.85 mm for the sand (Test 1) A comparison of the results from the 1 g
reach equilibrium after opening the valves. and 0.004 mm for the silty sand (Test 2), and 23 g tests in sand provided the opportu-
After the pressure drop following opening of Reynolds numbers (see Table 3) were cal- nity to address the scaling law for hydraulic
the valves, the pore pressures decreased at a culated assuming the standard density and conductivity in the centrifuge. The flow rate
constant rate while steady flow occurred. dynamic viscosity of water at 25°C and the in the 23 g test was significantly faster than
Despite the higher acceleration (29 g), specific discharge for each test. The Reynolds in the 1 g test. Despite this difference, the
the test took significantly longer than Test 1 numbers fell well below unity, confirming calculated hydraulic conductivities from the
(23 g). The water level reduced by 90.5 mm the validity of Darcy’s law. 23 g test were on average only 1.12 times
in 2 124 seconds. Consequently no 1 g test less than those at 1 g. This demonstrates
was conducted, as the rate of evaporation Centrifuge Test 1 that the hydraulic conductivity calculated
from the model was judged to be significant, The pore pressure and total head distribu- from Darcy’s law is not N times greater at
relative to the low seepage rate. tions for Test 1 at 23 g and 1 g are illustrated an increased acceleration of N g. Clearly the
Hydraulic conductivity values, presented in Figures 9 and 10 respectively. The eleva- pore pressures are increased N times at N g.
in Table 2, were calculated from the pore tion of the seepage column outlet coincided The induced prototype pore pressures need
(a) (b)
0.45 0.45
0.40 0.40
0.35 0.35
0.30 0.30
Elevation (m)
Elevation (m)
0.20 0.20
0.15 0.15
PPT2
0.10 0.40
0.05 0.05
PPT1
0 0
0 50 100 150 200 0 50 100 150 200
Pore pressure (kPa) Hydrostatic potential or total head (kPa)
Before flow (calculated) Before flow (measured) Before flow
During flow (measured) During flow
Figure 9 T est 1 (23 g): (a) Distribution of the calculated and measured pore pressures before and during flow, and (b) distribution of hydrostatic
potential before and during flow
22 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
(a) (b)
0.45 0.45
0.40 0.40
0.35 0.35
0.30 0.30
Elevation (m)
Elevation (m)
0.25 0.25
PPT3
0.20 0.20
0.15 0.15
PPT2
0.10 0.40
0.05 0.05
PPT1
0 0
0 2 4 6 8 10 0 2 4 6 8 10
Pore pressure (kPa) Hydrostatic potential or total head (kPa)
Before flow (calculated) Before flow (measured) Before flow
During flow (measured) During flow
Figure 10 T est 1 (1 g): (a) Distribution of the calculated and measured pore pressures before and during flow, and (b) distribution of hydrostatic potential
before and during flow
to be dissipated over a flow path length that valves were opened, the pore pressures above formula and Darcy’s equation could therefore
has been condensed N times in the centri- the column base were notably slower to react be used to assess the hydraulic conductivity.
fuge model. This supports the approach that than at the base, due to the lower hydraulic The hydraulic conductivities calculated using
the hydraulic gradient is scaled N times in conductivity for the material in Test 2. both approaches are summarised in Table 4,
the centrifuge, and not the hydraulic con- The pore pressure and total head distri- showing little difference.
ductivity. This approach was also preferred butions measured and calculated for Test 2 Figure 11(b) shows the hydrostatic poten-
by Taylor (1995), and Thusyanthan and are presented in Figure 11. The elevation of tial gradient between PPT 1 and PPT 2 to
Madabhushi (2003). the seepage column outlet was marginally be greater than between PPT 2 and PPT 3,
below that of the bottom of the column. indicating a lower hydraulic conductivity.
Centrifuge Test 2 Once the outlet valves were opened, the pore This suggests that compression of the mate-
Compared to Test 1, the pore pressures pressure at the base of the column dropped rial under high accelerations resulted in a
in Test 2 dissipated more slowly after the to near atmospheric pressure, indicating that reduction in hydraulic conductivity.
test acceleration had been reached, and the outlet valve did not pose a restriction The hydraulic conductivity values in
the sample took considerably more time to to flow. A true falling head test was there- Test 2 were two orders of magnitude lower
consolidate (see Figure 8). Also, when the fore carried out, and both the falling head than in Test 1. This was to be expected, given
(a) (b)
0.35 0.35
0.30 0.30
0.25 0.25
Elevation (m)
Elevation (m)
0.15 0.15
PPT2
0.10 0.40
0.05 0.05
PPT1
0 0
–50 0 50 100 150 200 250 –50 0 50 100 150 200 250
Pore pressure (kPa) Hydrostatic potential or total head (kPa)
Before flow (calculated) Before flow (measured) Before flow
Before flow (measured) During flow
Figure 11 T est 2 (29 g): (a) Distribution of the calculated and measured pore pressures before and during flow, and (b) distribution of hydrostatic
potential before and during flow
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 23
Table 4 H
ydraulic conductivity values from Darcy’s equation, the falling head and Hazen’s formulas Bear, J 1972. Dynamics of Fluid in Porous Media. New
for Test 2 York: Elsevier.
Chakraborty, D, Chakraborty, A, Santra, P, Tomar,
Hydraulic conductivity k m
R K, Garg, R N et al 2006. Prediction of hydraulic
Test PPT
Darcy’s law Falling head formula Hazen’s formula D102 conductivity of soils from particle-size distribution.
(m/s) (m/s) (m/s)
Current Science, 90(11): 1527–1531.
1 to 2 5.24 E-07 Culligan-Hensley, P J & Savvidou, C 1995.
Environmental geomechanics and transport
2 2 to 3 9.49 E-07 5.27 E-07* 1.60 E-07
processes. In: Taylor, R N (Ed.), Geotechnical
1 to 3 7.47 E-07 Centrifuge Technology, Glasgow: Blackie Academic
and Professional, 196–264.
*Value calculated from Equation 8 and divided by 29 (the acceleration in g)
Dell’Avanzi, E & Zornberg, Z G 2002. Scale factors for
centrifuge modelling of unsaturated flow, In: Jucá,
the respective grading curves (Figure 4). significantly under the increased acceleration J F T, de Campos, J M P & Marinho, F A M (Eds.),
Hazen’s formula predicted a similar value in the centrifuge. Unsaturated Soils, Vol. 1. Lisse, Netherlands: A A
(see Table 4.) It is advocated that, in contrast with Balkema, 425–430.
the recommendation by Singh and Gupta Fetter, C W 2001. Applied Hydrogeology, 4th ed.
(2000) that hydraulic conductivity from Chapter 4: Principles of groundwater flow. Upper
CONCLUSIONS a centrifuge test scales with the imposed Saddle River, NJ: Prentice-Hall, 113–124.
The geotechnical centrifuge can be used acceleration, it can be assumed instead that Hazen, A 1892. Some physical properties of sands
to reduce the time necessary to conduct it is the hydrostatic potential driving the and gravels. Massachusetts State Board of Health,
hydraulic conductivity tests on fine-grained flow which is increased by acceleration, Annual Report, 539–556.
granular materials. The increased accelera- leaving the calculated hydraulic conductiv- Kozeny, J 1927. Uber kapillare leitung des wassers
tion imposed using the centrifuge serves to ity unchanged compared to that measured im boden. Sitzungsberichte, Akademie der
increase the potential energy per unit volume under normal gravity. Wissenschaften in Wien, 136: 271–306.
of water and therefore the hydrostatic poten- When applying falling head formulas in Nakajima, H & Stadler, A T 2006. Centrifuge modelling
tial driving flow. This results in an acceler- which the actual hydrostatic potential is not of one-step outflow tests for unsaturated parameter
ated inter-particle flow velocity vm = Nvp explicitly incorporated, it is important to estimations. Hydrogeology and Earth System
where N is a multiple of gravitational ensure that no obstruction to flow or other Sciences, 10: 715–729.
acceleration. The time required to complete deviations from the assumptions made in the Schofield, A N 1980. Cambridge Geotechnical
the test will also be accelerated by a factor N, derivation of the equations are present, e.g. Centrifuge Operations. Geotechnique, 30(3):
assuming that the same volume of water outlet valves restricting flow. Such obstruc- 227–268.
flows through the sample. tions will render the calculated hydraulic con- Singh, N & Gupta, A K 2000. Modelling hydraulic
In calculating hydraulic conductivity ductivities inaccurate. Without pore pressure conductivity in a small centrifuge. Canadian
from the results of centrifuge tests, equations measurement at the base of the column the Geotechnical Journal, 37(5): 1150–1154.
in which the increased hydrostatic potential user will not be aware of such obstructions. Singh, N & Gupta, A K 2002. Modelling hydraulic
does not feature (e.g. the falling head for- Equations catering for the actual hydrostatic conductivity in a small centrifuge: Reply 1. Canadian
mula, Equation 8) will produce a hydraulic potential, taking into account the acceleration Geotechnical Journal, 39(2): 488–489.
conductivity that appears to vary with the level, and which are based on the actual flow Taylor, R N 1995. Centrifuges in modelling: Principles
imposed acceleration level km = N kp. On rate, do not suffer from this shortcoming and and scale effects. In: Taylor, R N (Ed.), Geotechnical
the other hand, should the actual hydro- can accommodate obstructed flow. Centrifuge Technology, Glasgow: Blackie Academic
static potential as measured by, for example, and Professional, 19–34.
pressure transducers, be incorporated into Thusyanthan, N I & Madabhushi, S P G 2003. Scaling
Darcy’s equation (Equations 9 or 16), the REFERENCES of seepage flow velocity in centrifuge models. Report
calculated hydraulic conductivity should be Alyamani, M S & Sen, Z 1993. Determination of No. CUED/D-SOILS/TR326, Cambridge University,
the same as that calculated at normal gravity, hydraulic conductivity from complete grain-size Engineering Department.
provided that the material does not compress distribution curves. Ground Water, 31(4): 551–555.
24 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Exploring the relationship TECHNICAL PAPER
between vertical and Journal of the South African
Institution of Civil Engineering
in railway curves
South African Institution of Civil Engineering
and a Candidate Engineer with the Engineering
Council of South Africa. He obtained the
following degrees: BEng Civil Engineering, BEng
Hons Geotechnical Engineering, BEng Hons
A F Powell, P J Gräbe Environmental Engineering, and MEng
Transportation Engineering. He has been
employed by Bombela Maintenance (Pty) Ltd since 2012 as the track engineer
responsible for technical inputs regarding track maintenance on the Gautrain
The research described in this paper is based on an experiment which involved running a Rapid Rail Link. He started his career in railway engineering in 2006 at
test train through a curve at various speeds, changing the cant of the curve by tamping and Transnet Freight Rail in their Track Testing Centre in Jeppestown,
repeating the train runs. The cant was changed due to high wheel wear rates. The curve already Johannesburg, and was with Transnet Freight Rail until his move to Bombela
Maintenance (Pty) Ltd.
had a cant deficiency, and this cant deficiency was subsequently increased by reducing the
curve’s cant. Assessing the before and after tamping test data validated the existence of the Contact details:
expected relationships between the vertical and lateral rail forces, the speed and the cant. Bombela Maintenance (Pty) Ltd
Gautrain Depot
The change in cant had a minimal effect on the magnitude of the vertical forces, although
Waterval K60 Road
a transfer of loading between the high and low legs did occur. The theory indicates that the Midrand
14% reduction in cant in this curve, given all of the other curve characteristics, should have South Africa
resulted in an increase in the lateral forces. There was, however, a roughly 50% reduction in the T: +27 11 253 0136
maximum lateral forces, after the cant had been reduced, which can be explained from a train E: alex.powell@bombardiersa.co.za
dynamics point of view. In addition, there was an increase in safety, due to a reduced derailment
ratio at this curve’s normal operating speed of 85 km/h. It is not unreasonable to presume that a PROF HANNES GRÄBE Pr Eng, FSAICE, is a civil
engineer with experience in the fields of track
50% reduction in the maximum lateral forces could lead to a halving of the wear rate of the rail
technology, geotechnology, advanced
and wheels in this curve, with similar results to be expected in other curves on the rail network. laboratory testing, field investigations,
maintenance models and numerical analysis of
track structures. He is currently employed by the
INTRODUCTION between Johannesburg and the OR Tambo University of Pretoria as Associate Professor:
Transnet Freight Rail Chair in Railway
Track geometry is a critical facet of any International Airport. Travelling at speeds
Engineering, where he lectures under- and post-graduate courses in railway
railway system, directly affecting the per- of up to 160 km/h, the Gautrain system is engineering. He is also responsible for railway research, as well as for
formance of the railway track itself and the the first of its kind in South Africa, and in continuing professional development in the form of short courses presented
behaviour of the railway vehicles using the fact in Africa. The Gautrain airport service to industry.
system. Superelevation (also known as cant) has been operational since June 2010 and Contact details:
is the term used to denote the raising of the the commuter service has been operational Transnet Freight Rail Chair in Railway Engineering
outer rail on curved track to allow higher since August 2011. The relative newness and Department of Civil Engineering
University of Pretoria
speeds than if the two rails were level. In uniqueness of this state-of-the-art railway
Pretoria 0001
curves, cant is one of the most important engineering project in the South African South Africa
track geometry parameters, which can context therefore provided an excellent T: +27 12 420 4723
change the wheel/rail contact relationship opportunity for carrying out this research. E: hannes.grabe@up.ac.za
and then influence the dynamic interaction After the opening of the Gautrain system
(Wang et al 2013), including the vertical and the initial wear rates of the Gautrain wheels
lateral forces experienced by both the track were higher than expected. Specifically
and the railway vehicles. the wheel flange wear resulted in more
This paper presents an investigation into frequent wheel re-profiling needing to be
the relationship between vertical and lateral done than originally planned as part of the
forces, speed and cant in railway curves maintenance schedules. Assuming that the
that was undertaken on the Gautrain Rapid track gauge of a railway system is within an
Rail Link. acceptable tolerance range (which is the case
for the Gautran system), then it is known
that wheel flange wear predominantly takes
BACKGROUND place in curves.
The Gautrain Rapid Rail Link is a rail An experimental curve was selected and
transit system that links the two c ities this curve was found to be experiencing high
of Johannesburg and Pretoria in the leg contact to the gauge side of the rail, while
province of Gauteng, South Africa. The the low leg contact was to the field side of the
system also provides an airport service rail. In order to move the high leg contact Keywords: vertical forces, lateral forces, superelevation (or cant), speed
25
Powell AF, Gräbe PJ. Exploring the relationship between vertical and lateral forces, speed and superelevation in railway curves.
J. S. Afr. Inst. Civ. Eng. 2017:59(3), Art. #1736, 11 pages. http://dx.doi.org/10.17159/2309-8775/2017/v59n3a4
lateral accelerations, and, given a situation with
sufficient cant deficiency, the train may derail
due to rail roll over, the car rolling over or sim-
Tra ns
v er s e v ply derailing to the outside of the curve.
e er tica
al pl a n l pla n
e The balance speed is the speed at which the
r t ic
i na l ve
it u d Cant or compensation due to cant balances the accel-
g
L on superelevation eration due to curving. Relative to the track
plane, the perceived lateral acceleration is then
zero. The cant which gives lateral accelerations
equal to zero at a given radius (R) and given
Twist vehicle speed (v) is called the equilibrium cant
e
(heq) and is calculated by Equation 1.
t ba
se pl a n
s ta l
Tw i or i s
on
H 2a ∙ v 2
heq = (1)
g∙R
R∙g∙h
veq = (2)
2a
26 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
A A C A
A B 10
D B
A C
A SECTION A-A B
Figure 3 Vertical and lateral gauge configuration for base chevron method
(a) (b)
Experimental curve
Figure 5 Calibration rig for lateral strain gauges (a) and vertical strain gauges (b)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 27
Table 2 Gautrain car descriptions
Car type Description
Speed after tamping (km/h) 85.0 85.0 85.0 85.0 The decision to reduce the cant, thereby
further increasing the cant deficiency in the
heq after tamping (mm) 210.5 206.8 206.8 206.8
curve, was made based on on-board train
veq after tamping (km/h) 64.2 56.7 56.5 56.9 observations that, at the normal operating
speed of the test curve, the wheels were
hd after tamping (mm) 90.5 114.8 115.3 114.0
generating flanging noise emanating from
the low leg. Top-of-rail noise is significantly
It is believed that the web-bending tech- instrument used with the strain gauges was different in nature to flanging noise, and the
nique of strain gauging the rail to measure a Quantum X, MX840A 8-channel universal side of the train from which the noise was
the lateral rail force is subject to cross talk amplifier, and the collection of data through- emanating indicated low leg flanging. This
from the vertical rail force. The initial results out the experimental process was done at a same observation had already been detected
of tests conducted by Transnet Freight Rail sampling rate of 1 200 Hz. by the Gautrain track maintenance teams
(Reitmann 2013) indicate that the base In terms of sign convention for the lateral (also through on-board train observations),
chevron method measures lateral forces forces, any force pulling the outer or inner which is why the curve cant before tamping
more accurately. rail of the curve towards the middle of the was already set to a lower value than the
Calibrations for the vertical strain track was considered to be a negative force, design value of 120 mm.
gauges and lateral strain gauges were while any lateral force to the outside of the
undertaken using a loadtech 10 t load cell, track was considered to be positive. For the Characteristics of the test trains
model LT200, and a 10 t hydraulic jack. vertical forces, any force pushing down onto A typical Gautrain Bombardier Electrostar
The lateral calibration rig can be seen in the rail was considered to be positive. From four-car commuter train set was used
Figure 5(a), while the vertical calibration rig a practical point of view, rails should never for the test runs through the instru-
can be seen in Figure 5(b). The amplification experience a negative vertical force, with the mented experimental curve. The standard
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
HIGH LEG RAIL
28 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Gautrain four-car commuter train con- then allowed an accurate assessment of the Maximum and minimum vertical
figuration is as follows (descriptions relationship between the vertical and lateral force wheel positions
of the car names are given in Table 2): forces, speed and superelevation in the The maximum vertical force on the high leg
DMOS A + MOS + PTOS + DMOS B experimental curve. remained in the absolute same bogie, axle
Figure 7 shows the configuration of For testing purposes, directions were and wheel position (DMOS B 8) on the train
the wheels (W) and axles on the four-car also assigned to the various test train runs. for both directions of travel. In the down
commuter train. Trains running through the experimental direction DMOS B 8 was on the leading axle
curve from Hatfield towards Pretoria were of the leading bogie of the leading vehicle of
Test train runs considered as being in the “Down” direc- the four-car train (DMOS B), whereas in the
For the before-tamping tests a test train tion, while trains running through the up direction DMOS B 8 was on the trailing
was run through the experimental curve at experimental curve from Pretoria towards axle of the trailing bogie of the rear vehicle
speeds varying from 10 km/h to 110 km/h in Hatfield were considered as being in the of the four-car train (DMOS B).
10 km/h increments. For the after-tamping “Up” direction. The maximum vertical force on the low
tests the speeds varied from 10 km/h to leg remained in the absolute same bogie
105 km/h in 10 km/h increments, with the position, and remained in the same rela-
final sets of test runs being done at 100 DATA COLLECTION tive axle position in relation to this bogie,
km/h and 105 km/h. A speed of 105 km/h The data collected from each test run was namely DMOS B 1 in the down direction and
was set as the limit for the after-tamping assessed to determine the maximum and DMOS B 2 in the up direction. In the down
test runs, due to the decreased cant and the minimum (both positive and negative) forces direction DMOS B 1 was on the leading axle
extraordinarily high risks associated with that occurred at each wheel on the test train of the leading bogie of the leading vehicle of
taking a train at too high a speed through at each test run speed. A tabular representa- the four-car train (DMOS B), whereas in the
a curve. The on-site conditions needed to tion of the assessed before-tamping lateral up direction DMOS B 2 was on the leading
be taken into account, with the possibility force data for a test train travelling from axle of the trailing bogie of the rear vehicle
of track irregularities, such as proud or Hatfield to Pretoria at Site 1 is shown in of the four-car train (DMOS B).
dipped welded rail joints and track geometry Table 3 (on page 30). A three-colour scale The minimum vertical force on the high
defects. Travelling from Hatfield towards was used to visually present the results for leg remained in the absolute same bogie, axle
Pretoria, the curve that immediately follows each test run, in order to provide an indica- and wheel position (PTOS 3) on the train
the experimental curve (see Figure 2) has tion of the trend as to where the maximum for both directions of travel. In the down
a design radius of 264.5 m and is curved in and minimum (both positive and negative) direction PTOS 3 was on the trailing axle
the opposite direction to the experimental forces occur. The lowest value of the 32 of the leading bogie of the second vehicle of
curve, and therefore the test trains running measured wheel forces for each test train is the four-car train (PTOS), whereas in the up
in this direction needed to slow down highlighted in red, while the highest value is direction PTOS 3 was on the leading axle of
sufficiently to safely negotiate this adjacent highlighted in green. The palest shade shows the trailing bogie of the third vehicle of the
curve. Travelling in the opposite direction the midpoint value, with the scale progress- four-car train (PTOS).
the trains also needed a sufficient length ing through lighter shades of red and green The minimum vertical force on the low
of track once exiting this adjacent curve towards the midpoint value. For ease of ref- leg remained in the absolute same bogie,
in order to get up to the target speed erence, the maximum and minimum values axle and wheel position (MOS 5) on the train
before reaching the experimental curve. for each run are also shown in bold italics for both directions of travel. In the down
These various on-site conditions therefore and are underlined. direction MOS 5 was on the leading axle
governed the maximum test speeds of All in all a total of 16 such tables were of the leading bogie of the third vehicle of
110 km/h and 105 km/h before and after generated from the collected data, covering the four-car train (MOS), whereas in the up
tamping respectively. In order to have some both vertical and lateral forces, before and direction MOS 5 was on the trailing axle of
data redundancy, at least two test runs after tamping, in the up and down train the trailing bogie of the second vehicle of the
were done in each direction as close to each travelling directions at Sites 1 and 2. four-car train (MOS).
target speed as possible, and the required In order to interpret the measured data, In summary it is therefore interesting to
data was successfully collected for all the a selection process had to be undertaken note that, of the four vertical forces under
test runs. For the purpose of detailed data in order to assess which wheels, on which consideration (vertical, maximum and
analysis, one run in each direction at each axle, on which bogie and on which car were minimum for both the high leg and the low
speed for test runs before and after tamping contributing to the greatest loadings (both leg), three of them (DMOS B 8, PTOS 3 and
was selected based on which of the test runs positive and negative) on each rail leg. MOS 5) stayed in the exact same absolute
was closest to the target speed. As a starting point the before-tamping position on the train for both the down
The test train drivers attempted to data was analysed in order to determine and the up directions, while the other one
accurately achieve the target speed for which wheels to focus the analyses on, and (DMOS B 1 vs DMOS B 2) stayed in the
each test run, but given the nature of train from the before-tamping wheel selections absolute same bogie position and the same
handling, achieving the exact target speed the same wheels were assessed after tamping relative axle position in relation to this bogie
was not practically possible. Therefore, in and compared to the before-tamping results. for the down versus the up direction.
order to accurately determine the speed Figure 8 (on page 31) shows which wheels
of each test run, the distance between were chosen for analyses for the test runs in Maximum and minimum lateral
Axle 1 of DMOS A and Axle 1 of DMOS B the down and up directions. force wheel positions
(75.843 m), as well as the time taken from The locations of the various analysed The maximum lateral force on the high
the recording of the greatest vertical and wheel positions, specifically with reference leg remained in the same relative position
lateral forces on the high and low legs at to the direction in which the test trains were (DMOS A 4 vs DMOS A 1) on a specific vehi-
each of these two axles, was taken. This travelling, are discussed below. cle for the down versus the up direction. In the
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 29
Table 3 Lateral forces before tamping (wheels) – down direction Site 1
km/h
Hatfield to Pretoria (down)
km 3.215 (Site 1) before tamping
11.04 20.75 30.65 40.11 49.64 59.56 68.83 79.17 89.02 101.78 109.18
Car type
Wheel and Rail Leg Lateral Force (t)
and axle
Wheel 8 – High Leg 1.40 1.51 1.63 1.37 1.62 1.66 1.59 1.77 1.83 2.04 2.24
DMOS B Axle 1
Wheel 1 – Low Leg 3.04 3.21 3.31 3.09 2.99 2.93 2.81 2.66 2.49 2.17 2.14
Wheel 7 – High Leg –0.75 –0.68 –0.64 –0.51 –0.44 –0.38 –0.25 –0.22 0.33 0.61 0.72
DMOS B Axle 2
Wheel 2 – Low Leg 0.93 0.68 0.64 0.49 0.35 0.26 –0.18 –0.38 –0.59 –0.83 –0.99
Wheel 6 – High Leg 1.19 1.34 1.46 1.39 1.70 1.52 1.55 1.33 1.49 1.46 1.64
DMOS B Axle 3
Wheel 3 – Low Leg 2.81 2.93 3.08 2.93 2.94 2.85 2.69 2.54 2.10 1.73 1.60
Wheel 5 – High Leg –0.78 –0.51 –0.44 –0.45 –0.28 –0.24 –0.15 0.16 0.38 0.78 0.99
DMOS B Axle 4
Wheel 4 – Low Leg 0.82 0.38 0.25 0.25 –0.06 –0.13 –0.31 –0.43 –0.63 –0.92 –0.92
Wheel 4 – High Leg 1.93 2.02 2.20 2.12 2.04 2.15 2.03 2.14 2.10 2.09 2.27
PTOS Axle 4
Wheel 5 – Low Leg 3.04 3.09 3.26 3.25 2.91 2.92 2.70 2.54 2.32 2.07 1.95
Wheel 3 – High Leg –0.85 –0.58 –0.54 –0.53 –0.35 –0.30 –0.24 –0.15 0.29 0.49 0.63
PTOS Axle 3
Wheel 6 – Low Leg 1.35 0.58 0.48 0.38 0.13 –0.04 –0.18 –0.34 –0.50 –0.65 –0.72
Wheel 2 – High Leg 1.28 1.29 1.34 1.31 1.38 1.47 1.41 1.59 1.65 1.54 1.85
PTOS Axle 2
Wheel 7 – Low Leg 3.18 3.22 3.32 3.31 3.05 3.10 2.98 2.73 2.51 2.14 1.89
Wheel 1 – High Leg –0.81 –0.44 –0.37 –0.36 –0.23 –0.23 0.20 0.42 0.48 0.73 0.83
PTOS Axle 1
Wheel 8 – Low Leg 0.80 0.21 0.19 –0.05 –0.27 –0.39 –0.52 –0.68 –0.72 –0.86 –0.96
Wheel 4 – High Leg 1.57 1.78 1.77 1.74 1.80 1.96 1.88 1.85 1.72 1.73 1.84
MOS Axle 4
Wheel 5 – Low Leg 2.86 3.04 3.06 2.95 2.81 2.66 2.55 2.34 2.18 1.88 1.78
Wheel 3 – High Leg –0.92 –0.64 –0.61 –0.60 –0.41 –0.32 –0.27 –0.14 0.25 0.52 0.70
MOS Axle 3
Wheel 6 – Low Leg 1.10 0.55 0.47 0.39 0.20 –0.07 –0.19 –0.38 –0.51 –0.68 –0.76
Wheel 2 – High Leg 1.72 1.84 2.03 1.98 2.13 2.21 2.28 2.16 2.26 2.09 2.02
MOS Axle 2
Wheel 7 – Low Leg 2.91 2.99 3.10 3.03 2.85 2.91 2.81 2.81 2.39 2.21 1.94
Wheel 1 – High Leg –0.70 –0.57 –0.57 –0.55 –0.50 –0.43 –0.30 –0.26 0.17 0.32 0.46
MOS Axle 1
Wheel 8 – Low Leg 1.18 0.89 0.78 0.73 0.61 0.58 0.47 0.32 0.21 –0.32 –0.39
Wheel 4 – High Leg 2.02 2.19 2.22 2.28 2.44 2.37 2.28 2.17 2.07 1.97 1.91
DMOS A Axle 4
Wheel 5 – Low Leg 3.25 3.39 3.42 3.33 3.13 3.11 3.01 2.83 2.42 2.26 2.11
Wheel 3 – High Leg –0.88 –0.62 –0.65 –0.63 –0.45 –0.37 –0.29 –0.16 0.27 0.45 0.80
DMOS A Axle 3
Wheel 6 – Low Leg 1.19 0.64 0.56 0.48 0.21 0.09 –0.12 –0.28 –0.46 –0.61 –0.77
Wheel 2 – High Leg 1.66 1.80 1.83 1.84 1.95 2.01 2.07 2.00 1.81 1.97 2.03
DMOS A Axle 2
Wheel 7 – Low Leg 3.33 3.43 3.45 3.33 3.23 3.20 3.10 2.89 2.70 2.44 2.06
Wheel 1 – High Leg –0.96 –0.71 –0.73 –0.67 –0.47 –0.38 –0.34 –0.25 0.26 0.52 1.07
DMOS A Axle 1
Wheel 8 – Low Leg 1.33 0.90 0.85 0.83 0.59 0.49 0.41 0.26 –0.22 –0.52 –0.78
Note: T
his three-colour scale visually presents the results for each test run, to provide an indication of the trend as to where the maximum and minimum (both
positive and negative) forces occur. The lowest value of the 32 measured wheel forces for each test train is highlighted in red, while the highest value is
highlighted in green. The midpoint value is the palest shade, with the scale progressing through lighter shades of red and green towards the midpoint value.
For ease of reference, the maximum and minimum values for each run are also shown in bold italics and are underlined.
30 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
SITE 1: LOW LEG RAIL – Before tamping (Down direction: Hatfield to Pretoria)
W1 W2 W3 W4 W5 W6 W7 W8 W5 W6 W7 W8 W5 W6 W7 W8
Axle 1
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Pretoria DMOS B = PTOS = MOS = DMOS A Hatfield
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
SITE 1: HIGH LEG RAIL – Before tamping (Down direction: Hatfield to Pretoria)
SITE 1: LOW LEG RAIL – After tamping (Down direction: Hatfield to Pretoria)
W1 W2 W3 W4 W5 W6 W7 W8 W5 W6 W7 W8 W5 W6 W7 W8
Axle 1
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Pretoria DMOS B = PTOS = MOS = DMOS A Hatfield
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
SITE 1: HIGH LEG RAIL – After tamping (Down direction: Hatfield to Pretoria)
SITE 2: LOW LEG RAIL – Before tamping (Down direction: Hatfield to Pretoria)
W1 W2 W3 W4 W5 W6 W7 W8 W5 W6 W7 W8 W5 W6 W7 W8
Axle 1
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Pretoria DMOS B = PTOS = MOS = DMOS A Hatfield
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
SITE 2: HIGH LEG RAIL – Before tamping (Down direction: Hatfield to Pretoria)
SITE 2: LOW LEG RAIL – After tamping (Down direction: Hatfield to Pretoria)
W1 W2 W3 W4 W5 W6 W7 W8 W5 W6 W7 W8 W5 W6 W7 W8
Axle 1
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Pretoria DMOS B = PTOS = MOS = DMOS A Hatfield
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
SITE 2: HIGH LEG RAIL – After tamping (Down direction: Hatfield to Pretoria)
SITE 1: LOW LEG RAIL – Before tamping (Up direction: Pretoria to Hatfield)
W1 W2 W3 W4 W5 W6 W7 W8 W5 W6 W7 W8 W5 W6 W7 W8
Axle 1
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Pretoria DMOS B = PTOS = MOS = DMOS A Hatfield
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
SITE 1: HIGH LEG RAIL – Before tamping (Up direction: Pretoria to Hatfield)
SITE 1: LOW LEG RAIL – After tamping (Up direction: Pretoria to Hatfield)
W1 W2 W3 W4 W5 W6 W7 W8 W5 W6 W7 W8 W5 W6 W7 W8
Axle 1
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
SITE 1: HIGH LEG RAIL – After tamping (Up direction: Pretoria to Hatfield)
SITE 2: LOW LEG RAIL – Before tamping (Up direction: Pretoria to Hatfield)
W1 W2 W3 W4 W5 W6 W7 W8 W5 W6 W7 W8 W5 W6 W7 W8
Axle 1
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
SITE 2: HIGH LEG RAIL – Before tamping (Up direction: Pretoria to Hatfield)
SITE 2: LOW LEG RAIL – After tamping (Up direction: Pretoria to Hatfield)
W1 W2 W3 W4 W5 W6 W7 W8 W5 W6 W7 W8 W5 W6 W7 W8
Axle 1
Axle 2
Axle 3
Axle 4
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
Axle 4
Axle 3
Axle 2
Axle 1
W8 W7 W6 W5 W4 W3 W2 W1 W4 W3 W2 W1 W4 W3 W2 W1
SITE 2: HIGH LEG RAIL – After tamping (Up direction: Pretoria to Hatfield)
Maximum vertical force Minimum vertical force Maximum lateral force Minimum lateral force
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 31
down direction DMOS A 4 is on the leading 140
axle of the leading bogie of the trailing vehicle y = 0.0046x 2 – 0.1053x + 77.242
of the four-car train (DMOS A), whereas in y = –0.0041x 2 + 0.0486x + 110.46 R2 = 0.9897
120 R2 = 0.9848
the up direction DMOS A 1 is on the leading
32 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Table 4 Force balancing (four-car trains) – down direction Site 1
Site 1: Down Before tamping After tamping
Δx Δx Δy Δy
(km/h) (%) (t) (%)
Forces Rail x (km/h) y (t) x (km/h) y (t)
Four-car train
high leg
Verticals 56.45 85.96 78.07 89.27 21.62 38.29 3.31 3.85
low leg
high leg
Laterals 85.82 16.77 84.63 7.43 –1.20 –1.39 –9.34 –55.71
low leg
Table 5 Percentage change in forces after tamping (wheels) then enter into a state of hunting in order
to try and achieve their preferred run-
% Change in forces at 85 km/h after tamping (wheels)
Site Leg ning path, with hunting oscillation being
Max verticals Min verticals Max laterals Min laterals defined as a periodic motion in lateral
high leg 0.0 –6.6 –47.5 124.9 displacement. Hunting could therefore
Site 1 Down have a significant effect on the lateral
low leg 28.9 23.8 –36.3 –1.4
loads, and to a certain degree the vertical
high leg –8.8 –13.9 25.4 612.2 loads as well, dependent on the wheel
Site 1 Up positions on the rail heads of both the
low leg 9.0 2.5 –18.7 0.0
high and low legs at the location of the
high leg –2.3 9.2 –112.6 48.6 strain gauges.
Site 2 Down
■■ Driver behaviour, such as braking or
low leg 9.4 6.0 –57.6 63.7
accelerating in the vicinity of the strain
high leg 11.3 5.2 –112.5 581.1 gauges, could also influence the measured
Site 2 Up
low leg 6.1 –0.5 –46.6 40.9 values, thus also undermining a good
coefficient of determination value for the
High leg average 0.0 –1.5 –61.8 341.7
data (shown in Figures 9 and 10 as R2),
Low leg average 13.4 7.9 –39.8 25.8 while nonetheless still providing insights
into the general trend line shapes, albeit
Overall average 6.7 3.2 –50.8 183.7
with a less than ideal R2 value. In this
experiment the drivers were cautious
Table 6 Percentage change in vertical forces after tamping – summary not to compromise the integrity of the
data, driving as consistently as possible,
% Change in vertical forces at 85 km/h after tamping (overall average)
but nonetheless, varying a train’s speed
WHEELS from 10 – 110 km/h through a 318 m long
Max verticals Min verticals curve will invariably incorporate some
inconsistencies between test runs.
6.7 3.2
■■ With specific reference to the analysis
LEADING BOGIES dealing with lateral forces, possible expla-
nations for discontinuities in the data
DMOS B PTOS MOS DMOS A
could be due to the low forces involved
–1.1 –5.0 –3.3 –4.6 when dealing with lateral forces. One
TRAILING BOGIES train could measure a maximum lateral
wheel force of -0.5 t, while the next train
DMOS B PTOS MOS DMOS A
measures a maximum lateral wheel force
–0.9 –2.5 –2.1 –3.6 of +0.5 t, which is only an absolute differ-
ence of 1 t, but equates to a 200% increase
CARS
in force. Several train runs could then
DMOS B PTOS MOS DMOS A fluctuate between negative and positive
2.6 –0.1 0.4 0.8 values, which would have a noticeably
detrimental effect on the R2 value.
FOUR-CAR TRAIN
Vertical
RESULTS AND DISCUSSION
1.0
The operational speed of the experimental
curve is one of the variables that remained
Similar detailed assessments were done Discontinuities that can be seen in constant both before and after tamping,
at wheel, bogie, car and four-car train level Figures 9 and 10 most likely arise from one and there is no intention of changing the
for both sites, in both directions and the of the following situations: operational speed, due to the effect that this
summarised results of these analyses are ■■ Under certain operating conditions train will have on the timetable, signalling system,
presented in the Results and Discussion sec- wheels may not simultaneously find their etc. Therefore the specific effect that chang-
tion below. desired or preferred running path, and ing the cant had on the rail forces at a train
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 33
speed of 85 km/h was assessed in detail, and Table 7 Percentage change in lateral forces after tamping – summary
the percentage change in vertical and lateral
% Change in lateral forces at 85 km/h after tamping (overall average)
forces after tamping at wheel level are shown
in Table 5, and at wheel, bogie, car and four- WHEELS
car train level in Tables 6 and 7 respectively. Max laterals Min laterals
In Tables 6 and 7 the highlighted values
–50.8 183.7
indicate the largest changes at each level of
assessment. The summarised information LEADING BOGIES
presented in Tables 6 and 7 shows good con-
DMOS B PTOS MOS DMOS A
sistency between the changes in vertical and
lateral forces at the various levels of assess- –53.5 –38.2 –52.4 –43.3
ment (wheel, bogie, car and four-car train). TRAILING BOGIES
Although the changes in vertical and lateral
DMOS B PTOS MOS DMOS A
forces after tamping were not empirically
predictable, the relatively small range of the –34.6 –48.4 –61.0 –45.9
after-tamping vertical force changes (–5.0%
CARS
to 6.7%) and the relatively small range of the
after-tamping lateral force changes (–61.0% DMOS B PTOS MOS DMOS A
to –50.8%) indicates that the data at the vari- –50.5 –46.6 –51.8 –44.0
ous levels of assessment is reliable.
FOUR-CAR TRAIN
34 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Table 8 Maximum derailment ratio values for each site in both directions assistants (Mr P Vorster, Mr R Vandoorne,
Mr R du Plooy and Mr A Ronda), as well as
Before tamping After tamping % Change after tamping
Site the Wayside and Services teams at Bombela
DR Speed (km/h) DR Speed (km/h) DR Speed Maintenance (Pty) Ltd for their invaluable
S1 Down 0.66 79.17 0.52 30.50 –21.4 –61.5 assistance.
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 35
TECHNICAL PAPER Alternative wall‑to‑slab
Journal of the South African
Institution of Civil Engineering connection systems in
ISSN 1021-2019
Vol 59 No 3, September 2017, Pages 36–47, Paper 1633 reinforced concrete structures
JOHANN GERBER (MEng) received his Master’s J D Gerber, G P A G van Zijl
degree in Structural Engineering from
Stellenbosch University in December 2016. He is
currently employed at Aurecon and works in the
Buildings Unit, Cape Town, as a structural In many reinforced concrete structures the walls precede the construction of the connecting floors.
engineer, specialising in the design and A system is, therefore, required to connect the floors to the already cast walls. There are many
detailing of structural components in buildings. different floor-to-wall connection systems available in South Africa, but their behaviour and capacity
Contact details: are not always fully understood, especially when the moment capacity of the joint is to be utilised.
Aurecon This study focuses on four systems: continuous starter-bars, pre-bent site-installed starter-bars, pre-
PO Box 494 assembled starter-bars and cast-in anchors with mechanical couplers. The design procedure for the
Cape Town 8000 continuous starter-bar system is well understood and documented in design codes, but not enough
South Africa
information is available on the design procedure for the other systems. Certain practical aspects of
T: +27 21 526 9513
E: johann.gerber@aurecongroup.com the installation process are also not fully understood. Cold-bending and straightening of the starter-
bars are inevitable in both bend-out systems. Previous research shows that this cold-working of the
PROF GIDEON VAN ZIJL (DEng, PrEng) is
reinforcement can reduce the yield stress and E-modulus of the steel. In order to investigate these
professor of Structural Engineering at findings, a series of tensile tests are conducted. The results indicate that a significant reduction can
Stellenbosch University. His research interests be expected in both the yield stress and modulus of elasticity of the steel. Low-cycle fatigue tests
are structural and computational mechanics, further suggest that cold-bent steel also has a reduced ductility. The tensile tests are followed by the
structural durability and advanced
construction and testing of the systems in full-scale wall-to-slab connections. The effect of the cold-
cement-based construction materials.
Concurrently, structural design guidelines for
bending on the starter-bars is clearly visible, as both the responses of the bend-out systems are less
cement-based construction materials are satisfying than the results from the continuous starter-bar system. The experimental phase is followed
developed in his research group, the Centre for Development of Sustainable by numerical analysis of the connection systems. The finite element analyses show that the structural
Infrastructure (CDSI). performance is significantly more sensitive to a reduction in the yield stress of the starter-bars, than
Contact details: to the use of a lower concrete grade. It is concluded that all the alternative connection systems can be
Department of Civil Engineering implemented successfully in a moment-fixed wall-to-slab connection, but that the site-installed bend-
Stellenbosch University out system is the preferred method. However, in order to ensure that the system performs on the
Private Bag X1
same level as conventional systems, it is recommended that the design should be conducted with a
Matieland 7602
South Africa set of modified steel properties to allow for the negative effect of the cold-working on the starter-bars.
T: +27 21 808 4436
E: gvanzijl@sun.ac.za
INTRODUCTION AND BACKGROUND walls normally precede the construction of
In the construction of multi-storey buildings, the RC floors, the former being cast using
the reinforced concrete (RC) core or shear slip or jump formwork. These systems
RC wall
RC floor slab
Starter-bars
fixed to
Lap leng
wall rebar th
Wall rebar
36
Gerber JD, Van Zijl GPAG. Alternative wall-to-slab connection systems in reinforced concrete structures.
J. S. Afr. Inst. Civ. Eng. 2017:59(3), Art. #1633, 12 pages. http://dx.doi.org/10.17159/2309-8775/2017/v59n3a5
are designed to increase the construction
speed and efficiency, while minimising the
cost of labour and material (Rupasinghe &
Nolan 2007). The sliding nature of these
90°
systems requires that no elements may 90°
be protruding from the wall while under
construction. This requirement prohibits the 90°
use of the conventional system where starter-
bars are cast directly into the wall and fixed
90°
through the formwork, as seen in Figure 1.
The result of this limitation is that alterna-
tive methods are used to ensure rebar con-
tinuity between the floor and wall, without Figure 2 B
end-out bar shape: site-installed (reworked from Ancon Building Products 2011)
compromising the operation of the sliding
formwork. Alternative systems are also used
in cantilever balconies or walkways, or any Shape code 99 starter-bar
structure where the wall is cast ahead of the
connecting floor.
Currently, the most commonly used Dimpled steel casing
method in South Africa to ensure this con-
tinuity is a rebar bend-out system. Rebar is
pre-bent and fixed to the wall reinforcement,
and only straightened after the formwork is
removed. The shape of the pre-bent bars is
shown in Figure 2. This system is relatively
simple to install and can be assembled on site
using regular rebar ordered from a bending
yard. Although this system does not require Steel lid
highly skilled workers, the installation process
can still be tedious and time-consuming. Each Straightened rebar. Only done after
box is cast inside the wall
starter-bar has to be securely placed at the
correct position in the wall in order to line up
with the connecting floor, while individual
holes need to be drilled in the formwork at the Figure 3 B
end-out starter-bar unit (reworked from Ancon Building Products 2011)
position of each starter-bar leg.
In order to make the installation process
of the bent-out bars easier and faster, a Steel anchor with thread
modified approach is adopted in which the
pre-bent rebar is placed inside a steel casing,
as illustrated in Figure 3. This modification
improves the ease and speed of installation,
but in turn makes the system more expen-
sive. Another drawback is that only a few
companies locally manufacture this system,
and it is therefore not readily available Temporary
throughout South Africa. screw to keep Timber carrier
In the case of the bend-out systems, plas- anchor in
place
tic deformation of the steel is unavoidable
during the cold-bending and straightening
of the rebar. Furthermore, the mechani-
cal properties of rebar are more prone to Figure 4 C
ast-in anchors, pre-assembled in timber carriers (reworked from Ancon Building
changes during cold-bending. This change Products 2014)
in mechanical properties has been observed
to cause a reduction in the tensile yield the steel casing has on the bond strength of anchor is one example of such a mechanical
strength, modulus of elasticity and even the concrete connection, as it is permanently splice, as shown in Figure 4.
the ultimate strength of the steel (Chun & cast inside the structure. The failure mode for direct tensile
Ha 2014). Currently there is not enough The only reference in South African codes anchors is based on a model with a breakout
information available for engineers to to bend-out bars is found in SABS 10144, prism with an angle of approximately 35°
accurately take this effect into account when where it is recommended that the size of as shown in Figure 5. This can roughly
designing a connection. the bend-out bars is limited to Y10 or R16, be translated to a cone shape with a base
Considering the modified bend-out and that mechanical splices should be used equal to three times the effective anchor
system with the rebar encased in a steel box, if greater strength is required (SANS 2012). embedment depth, i.e. 3 × heff (Cairns 2010).
further uncertainty arises as to what effect Rebar couplers connected to a cast-in steel This pull-out model is referred to as a cone
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 37
RC wall
RC wall
heff
Tensile
force ‘Modified’ cone shape
heff RC floor
Cast-in anchor
Tensile force
1.5heff
Cast-in
z Coupled moment
anchor d
Tensile
force ‘Full’ cone boundary Compressive force
1.5heff 1.5heff
Approximately
35°
Figure 5 C
one failure for cast-in anchor in
direct tension (reworked from Ancon
Building Products 2014) Figure 6 M
odified cone failure for cast-in anchor in moment connections (reworked from Ancon
Building Products 2014)
failure mechanism. The design procedures
for anchors in direct tension are well esta to the relatively high price of this system, its The investigation includes a study of each
blished and documented in several design use is usually limited to projects where struc- individual system in order to gain an under-
codes, such as the New Zealand design tural alterations or extensions necessitate the standing of the critical aspects and para
codes (NZS 2006) and American Concrete anchoring of rebar in existing concrete. meters that will affect their structural per-
Institute codes (ACI 2008). In the case of epoxy-based adhesive formance. Preliminary tests are conducted to
These existing procedures, however, do dowels, the performance and installation quantify these aspects, followed by full-scale
not cover anchors within moment-resisting procedures are well researched and docu- testing and finite element modelling (FEM)
connections, such as wall-to-slab applica- mented in the reference material provided by to confirm any local phenomena observed
tions. A recent research investigation at the manufacturers. The structural engineer with the preliminary tests.
Heriot Watt University tested moment con- has enough information to properly design A comparison is drawn between the prac-
nections using cast-in anchors to determine a connection and prescribe the necessary tical aspects of the systems, including ease
the degree of enhancement in concrete installation procedures to ultimately have and time of installation, cost, quality control
pull-out capacity, and to establish a design enough confidence that the connection and availability of products.
method based on the results (Cairns 2010). will perform adequately. With most of the The main objective of this study is to pro-
In moment connections, such as wall- other advanced methods this information is vide the engineer with recommendations on
to-slab joints, the bottom portion of the not available. how to choose the most appropriate system
slab will create a compression block in From the above it is evident that there for a wall-to-slab moment connection and
close proximity to the bearing surface of are a number of different systems available conduct the design to be as cost-effective as
the anchor. The transmission of the force in reinforced concrete wall-to-slab connec- possible, without compromising the margin
between the bearing face and the compres- tions. The challenge for the design engineer of safety as defined in typical design codes.
sion force, forming part of the moment remains to choose the most suitable system Secondly, construction guidelines are
couple in the slab, will tend to be taken by a for the specific application at hand. In to be provided for safe application of these
direct compression strut rather than by shear order to make an informed decision, more systems on site, in order to comply with the
or tension. This will decrease the break-out information is needed to understand how designed connection.
plane resisted by tension and will therefore these systems perform structurally and
create a modified cone shape, as illustrated what the aspects to consider are when
in Figure 6. As concrete is stronger in com- designing them. EXPERIMENTAL DESIGN
pression than tension, the cone pull-out The focus of this research is to investigate
resistance will be increased. The tests also how different types of connection systems Full-scale tests
indicated that the enhancement is greatly compare to the conventional system. The In order to compare the different connection
impacted by the ratio of the depth of anchor research investigation includes the com- systems within the time constraint of this
head embedment (heff ) to the effective depth parison between four different wall-to-slab research, a best practice approach was adopt-
of the anchor in the slab (d), the specific connection systems, namely: ed in the physical experimental phase. Four
ratio being heff /d (Cairns 2010). ■■ Continuous starter-bar (Model A) full-scale models of the different connec-
Epoxy-based adhesive dowels are also ■■ Site-installed bend-out bar (Model B) tion systems were built in the Stellenbosch
widely used in South Africa to anchor rebar in ■■ Pre-assembled bend-out bar (Model C) University Structural Laboratory. The
already cast concrete elements. However, due ■■ Cast-in anchor (Model D) models represent a wall-to-slab moment
38 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
than the nominal bar diameter to ensure that
300
the effective area is not compromised. The
anchor length was 115 mm, with a 40 mm
diameter head and an embedment depth of
250
142 mm.
Fixed In order to simulate practice as closely as
possible and to ensure continuity, a typical
reinforcement configuration for all the wall
sections was used. The vertical reinforce-
ment was Y12 bars spaced at 150 mm (c/c)
Applied load on both sides of the wall. Similarly, the
horizontal reinforcement was Y12 bars
1 700
200
spaced at 200 mm c/c. This configuration
complies with the detailing requirements of
250
Specimen
combination of 19 mm and 13 mm Hornfells
(1 000 wide)
stone was used as aggregate, and the sand
Fixed component consisted of both dune sand and
crusher dust. The concrete was delivered to
the laboratory in two separate batches – the
All dimensions in millimetres Fixed first batch was used to cast the walls for all
four models, and seven days later the second
Figure 7 F ull-scale specimen with boundary conditions and applied load batch was used for the cantilever floors.
The concrete compressive strength was
connection found in a typical high rise for the variable actions. The procedure can determined by casting and curing 100 mm
office block. be summarised through the following steps: cubes from the concrete batches for the
The models were all identical, with a ■■ Step 1: Determine forces acting on the walls and the slabs. The cubes were stripped
250 mm thick cantilever floor connected to structure. after one day and cured under the same
a 300 mm thick wall. The systems were all ■■ Step 2: Calculate possible load conditions in the laboratory. On the day of
designed to have the same moment and shear combinations. the wall-to-slab connection tests, the cubes
capacity, based on the actions associated ■■ Step 3: Analyse structure to determine were tested in a Contest 1 MN materials
with a typical office environment. design forces and moments at ULS. testing machine. Extra cubes were prepared,
When designing RC structures, the ■■ Step 4: Design section for flexure. and tested at the age of seven days to moni-
ultimate limit state (ULS) design usu- ■■ Step 5: Design section for shear. tor the strength development, to ensure a
ally governs (Robberts & Marshall 2010). ■■ Step 6: Choose rebar configuration (size high likelihood that the required 40 MPa
Therefore the design procedure for the and spacing). strength would be attained at the time of the
conditions at ULS, and the principles as set ■■ Step 7: Check anchorage and lap lengths. actual wall-to-slab tests. A set of three cubes
out in SANS 10100-1:2000 (SANS 2000), ■■ Step 8: Detail connection reinforcement. representing the walls and the slabs respec-
were followed to design the connection All the calculations for the models that tively were tested on the day of the actual
between the wall and the slab in the full- contained the bend-out systems were based wall-to-slab tests, with an average compres-
scale models. Detailed design calculations on the assumption that the rebar had already sive strength of 40.5 MPa and coefficient of
were performed for a typical office building been straightened, and therefore reflected variation of 0.011 for the walls, and 40.8 MPa
to ensure relevance of the chosen specimen the conventional system. The only differ- (CoV 0.009) for the slabs.
geometry and loading position. The loading ence was in the detailing of the starter-bars. After 28 days the models were individu-
position caused a realistic combination of The design procedure for the cast-in anchor ally tested in a special steel frame designed
internal shear and bending moment at the system followed the approach as set out in to ensure that the desired boundary condi-
wall-to-slab connection. For the ULS the the CEB Design Guide and making use of the tions are met. An illustration of the applied
load was 49.5 kN and for the SLS service- modified cone behaviour (CEB 1997). loads, boundary conditions and a full-scale
ability limit state (SLS) it was 40.5 kN. The reinforcement configuration that specimen, is presented in Figure 7, with the
These values are based on a variable action satisfied the connection design for Models test configuration in Figure 8.
of 3 kPa and additional permanent actions A, B and C comprised six Y12 starter-bars During the experimental testing a load
equal to 3.5 kPa to account for the weight spaced at 150 mm centre-to-centre (c/c), cell was used to capture the applied load,
of screed, ceiling, lighting and air-condi- with 25 mm cover. The cast-in anchor while seven HBM linear variable differential
tioning equipment. For the ULS, the partial system installed in Model D had a similar transformers (LVDTs) were used to measure
factor for the variable actions was taken as arrangement, with six anchors also spaced at the structural response of the specimens.
1.6, while 1.2 was used for the permanent 150 c/c. The anchors were supplied by Ancon The LVDTs were located at specific points
actions, including the self-weight of the Building Products. The continuation bars along the specimens in order to calculate
slab. The partial factors used for the SLS, were also 12 mm in diameter, each with a the relative wall-to-slab displacement. An
were 1.1 for the permanent actions and 1.0 threaded end, the thread being a size larger additional LVDT was located at the back
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 39
of specimens. Significant care was taken
to avoid geometrical imperfection in the
specimen dimensions and in the positioning
A-frame
Instron of the steel reinforcing bars and the con-
nection systems. The fresh concrete showed
Specimen tied to A-frame no segregation, nor leakage from the form-
work. The low variability in concrete cube
A-frame fixed
strengths reported above indicated good
to laboratory control. The actual stress-strain behaviour
strong floor of the steel bars was carefully measured, as
reported in subsequent sections of this paper.
The authors postulate that, given the care
Specimen in controlling the material and geometry of
the specimens, a reasonable reflection of the
various connection systems is given by the
results of the tests on a single specimen of
each type. Variability in the supplied connec-
Instron head
tion systems is not reflected in the results,
and will be tested in a next phase.
Ball-bearing
Steel bars tensile tests
154 × 154 × 35 In order to understand the effect of cold-
H-section spreader beam
bending and straightening on the material
properties of reinforcement, a series of
Specimen tensile tests were also conducted. The
specimens included a set of Y10 and Y12
Figure 8: Full-scale test configuration deformed bars. These are typical diameters
used in wall-to-slab connections, as larger
diameters are not suitable for cold-bending
on site. Half of each set was tested as straight
bars, while the remaining bars were cold-
bent and straightened after two weeks before
being tested.
Specimen All the tensile tests were performed
with a Zwick Universal Testing Machine
and complied with the specifications of
SANS 6892-1:2010 (SANS 2010).
LVDT clamp
Both sets of Y12 and Y10 rebar were
ordered from a local bending yard. The
reinforcement was locally manufactured
at Arcelor Mittal, under the registered
Top of bracket Machined portion trade name NOSTRAR, to comply with
of specimen the specifications of SANS 920:2011
(SANS 2011) for 450 MPa deformed
reinforcement bars.
3x LVDTs All the bars in a set were cut from the
same batch of steel. Half of the bars in each
set were bent to a 90° angle. The bars were
3x Bracket spacers Bottom of bracket bent with a standard bending table, and the
bending radius complied with the values as
prescribed in SANS 920:2011 (SANS 2011).
The bent bars were all straightened after
Figure 9: Tensile testing LVDT set-up 14 days, simulating the usual time lapse
between the bending of the rebar and the
of the specimens to record the horizontal The results were presented through load straightening on site. The bars were placed
movement of the A-frame at a height of displacement curves and crack patterns in a table vice clamp and straightened using
525 mm. observed at applied loads associated with the a pipe as lever arm. A constant force was
A standard concrete crack width ruler was SLS, ULS and the load at failure. applied in a single motion until the bar was
used to measure the width of all visible cracks Due to the size and complexity, one reasonably straight. In some cases the bars
at three different stages during the tests. An specimen of each wall slab connection type were further clamped and straightened,
Aramis camera was also installed to con- was tested. To address the inherent vari- within a tolerance of 3°, to ensure they are
tinuously track the crack development in the ability in reinforced concrete behaviour, best straight enough to fit between the cross
vicinity of the wall-to-slab joint (GOM 2003). practice was followed in the manufacturing heads of the testing machine.
40 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Stress-strain curve
Wall Wall
Stress
fy
E Floor Floor
1
Strain
Figure 10: D
etermination of yield stress – Model A Model B
Continuous starter-bar system Site-installed bend-out bar system
direct method
Stress-strain curve
0.2% offset line Wall Wall
Stress
fy
Floor Floor
E
1
0.002
Strain
Model C Model D
Pre-assembled bend-out bar system Cast-in anchor system
Figure 11: D
etermination of yield stress –
offset method Figure 12: Cracks at Stage 1 – wall joint
It should be noted that, in order to During the tensile testing the applied tensile EXPERIMENTAL RESULTS
apply the principle of best practice, the force was measured with the load cell of the
bars were not hammered or tampered testing machine, while the extension over the Full-scale test results
with during the straightening process. It is gauge length of the specimens was recorded Figure 12 presents the crack patterns at
acknowledged that, in practice, some ham- by three LVDTs, as shown in Figure 9. By Stage 1 of the tests (SLS). Photos captured
mering may occur on site, but this was not taking the average reading between the three by the Aramis camera are superimposed
simulated in this experimental investigation. LVDTs any eccentricity in the alignment of with rendered images indicating the strains
The results are, therefore, a comparison the specimen was taken care of. The record- measured on the specimens. From these ren-
between the material properties under best ing frequency was 10 Hz. dered images the crack patterns are clearly
practice conditions. The methods as set out in SANS 68921:2010 visible. The location of the major cracks in
A summary of the specimen sets are pre- (SANS 2010) were used to determine the all four systems corresponds to the position
sented in Table 1, with the abbreviations that material properties of each specimen. The and shape of the construction joint of the
will be used hereafter. E-modulus (E) was determined by first plotting particular system used. All the specimens
a trend line for the data in the linear portion of recorded one major crack of between 0.1 mm
Table 1 A
bbreviations for tensile testing the stress-strain graph, and then using the gra- and 0.4 mm, with Model A recording the
specimen sets dient of that line as the value for E (SANS 2010). widest crack of 0.4 mm. This crack was
The yield stress (fy) was determined by one of observed on the rear side of the wall and is
Preliminary tensile testing
two possible methods, based on the shape of therefore not visible in Figure 12. Apart from
Y10 straight bars (machined) Y10-S the stress-strain curve. When the curve had this crack, all the other cracks fell within
Y10 bent and straightened bars Y10-B a definite linear portion up to a certain point the general limit of 0.3 mm for structures
and then flattened, as seen in Figure 10, the exposed to a serviceability load (SANS 2000).
Y12 straight bars (machined) Y12-S
yield stress (fy) was taken as the stress value Once the tests went past Stage 2 (ultimate
Y12 bent bars Y12-B corresponding to that point on the graph. If, limit state) the crack development in the
however, the stress-strain curve had no definite first three systems was similar, both in size
Full-scale model rebars
point at which it flattened and the gradient for and pattern, and was clearly indicative of a
Wall bars Y12-WR the linear portion just gradually reduced to cre- connection where the rebar was starting to
Model A starter-bars (machined) Y12-FRA ate a curved graph, then the offset method was yield. In contrast to this, the pattern that
used as seen in Figure 11. was observed in Model D strongly sug-
Model B starter-bars Y12-FRB
The ultimate stress ( fu) was recorded gested a cone pull-out failure. Looking at the
Model C starter-bars Y12-FRC as the highest applied load during the test photos in Figure 13, taken at the final stage
divided by the original cross-sectional area of the tests, the cone-shaped crack pattern
Model D starter-bars (machined) Y12-FRD
of the rebar. in Model D is clearly visible. Although the
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 41
after which there is a sudden drop in the
load. This drop in resistance is followed by a
Wall Wall gradual softening response. Consequently it
has a significantly lower ultimate resistance
and the earliest onset of deflection softening
of the four models. This behaviour is associ-
Floor Floor ated with a pull-out cone failure mechanism.
Table 2 presents a summary of the
displacements and rotations recorded at the
first two stages of the tests.
B 3.2 1.6
C 4.6 2.4
D 3.6 2.3
Floor Floor
Displacement at ULS (Stage 2)
A 3.8 2.2
B 4.8 2.4
40
Table 3 Ultimate capacity summary
Specimen A
Specimen B Specimen number Applied load (kN)
20
Specimen C
A 98.12
Specimen D
0
B 93.56
0 20 40 60 80 100
Displacement (mm) C 87.86
Specimen A Specimen B Specimen C Specimen D
D 75.86
42 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
The average yield strength ( fy) for the
Stress-strain curve
Y10-S bars was 550 MPa, which is well above
700
the characteristic value of 450 MPa used in
600
design codes. However, according to the Joint
Committee on Structural Safety (JCSS 2001),
500 the average strength of rebar is expected to
be around 2 standard deviations above the
Stress (MPa)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 43
Table 6 Finite element model summary
Element types
Mesh configuration
Concrete 50 × 50 × 50 mm elements
Reinforcement Automated
Material models
Compressive behaviour –
Thorenfeldt (a) (b)
translation
Load conditions
Convergence Figure 17: Comparison of experimental data with FEA data of Model A
Energy – 0.001 tolerance
criteria
44 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Crack width (m)
+4.07928e-004
0.0%
+3.82432e-004
Wall Wall 0.1%
+3.56937e-004
0.1%
+3.31441e-004
0.1%
+3.05946e-004
0.1%
+2.80450e-004
0.4
0.1%
+2.54955e-004
0.6%
Floor +2.29459e-004
Floor 0.6%
+2.03964e-004
1.1%
+1.78468e-004
1.3%
+1.52973e-004
2.0%
+1.27477e-004
2.2%
+1.01982e-004
2.3%
+7.64864e-005
3.9%
+5.09910e-005
Physical experiment Numerical analysis 5.3%
+2.54955e-005
Crack pattern and width at SLS Crack pattern and width at SLS 80.0%
+0.00000e+000
0.3%
+2.91425e-004
Floor Floor 0.6%
+2.59044e-004
0.9%
+2.26664e-004
1.2%
+1.94283e-004
0. 3
2.0%
+1.61903e-004
2.1%
+1.29522e-004
2.3%
+9.71417e-005
3.9%
+6.47611e-005
5.5%
Physical experiment Numerical analysis +3.23806e-005
Crack pattern and width at ULS Crack pattern and width at ULS 80.5%
+0.00000e+000
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 45
for this system is three times that of the pre-
Cantilever end displacement –Y12-S rebar
assembled bend-out system, as presented in
100
Table 7.
90 Table 7 presents a summary of the
80
material costs for the respective systems,
determined in August 2016. Both the local
70 rates and the rates in the United Kingdom
Applied load (kN)
30
Table 7 Combined material cost comparison
20 Rate Rate
System (UK) (RSA)
10 (£/m) (R/m)
Figure 20: Results for finite element analyses – S-series models Cast-in anchor 83 *
46 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
performance of the site-installed system that they have not been damaged in any Available at: http://www.ancon.co.uk (accessed in
is slightly superior and the material costs way during the straightening process. June 2016).
47% less, practical considerations and ■■ Any reinforcement that has been Cairns, J 2010. Design analysis for moment connections
project-specific aspects might be of greater cold-bent past 45° should be consid- with KS Threaded Anchors. Technical Report
influence when choosing the most desir- ered to have a reduced capacity and (unpublished). Edinburgh: Heriot Watt University.
able system. It is therefore recommended ductility, and the design of the specific CEB 1997. Design of Fastenings in Concrete. London:
that the suitability of a specific alternative element should be checked, using the Thomas Telford.
system should be evaluated against all the modified yield stress and E-modulus as Chun, S & Ha, T 2014. Cyclic behavior of wall-slab
aspects for any given project. recommended above. joints with lap splices of cold- straightened rebars
■■ If one of the bend-out systems is chosen, ■■ The use of cast-in anchors could be a and mechanical splices. Journal of Structural
the design should be conducted with a feasible option in highly congested walls Engineering [Online], 141(2).
modified yield stress and E-modulus for or when larger moment capacities are Deaton, J B 2013. Nonlinear finite element analysis of
the flexural reinforcement in the joint. The required. The enhancing effect of the reinforced concrete exterior beam-column joints
recommended value for the yield stress modified cone behaviour can be adopted with nonseismic detailing. PhD thesis. Atlanta, GA:
is 0.8* f y and 150 GPa for the E-modulus. to produce more economical designs, but Georgia Institute of Technology.
The design engineer should also strive to once again larger deflections and cracks Diana 2014. Diana User’s Manual. Delft: TNO Diana.
keep the elongation of the reinforcement should be expected and accounted for. GOM 2003. GOM Aramis User Manual. 3.11 Software,
in the connection to a minimum. ■■ The manufacturer’s specifications and Vol. 49. Braunschweig, Germany: GOM.
■■ The size of the reinforcement to be used installation procedures should also be JCSS (Joint Committee on Structural Safety) 2001.
in any bend-out system should be limited strictly followed when using the cast-in Probabilistic Model Code for New and Existing
to a diameter of 12 mm. anchor system. A proper tightness check Structures, Part 3.2 Limit State Function. Available
■■ When using site-installed bend-out of all the continuation rebar should at: http://www.jcss.byg.dtu.dk/-/media/Subsites/.../
systems, good site supervision and quality be conducted, before the fixing of the probabilistic_model_code (accessed in June 2016).
control are necessary to ensure that the reinforcement for the floor commences. NZS (New Zealand Design Codes) 2006. NZS 3101.
starter-bars are fixed securely and at the The tightness can be checked by using a Concrete Structures Standard. Part 1: 2006. The
correct level. It is recommended that the standard hand wrench. Design of Concrete Structures. Wellington, NZ:
future floor level is clearly indicated on the ■■ The thread at the end of the continuation Standards New Zealand.
horizontal wall reinforcement to help iden- reinforcement, supplied by the manu- Robberts, J M & Marshall, V 2010. Analysis and design
tify starter-bars that are fixed out of place. facturer, should be a size larger than the of concrete structures. Johannesburg: Nuclear
■■ Care should be taken when chipping nominal diameter of the bar. Couplers Structural Engineering.
away the concrete surrounding the pre- with tapered threads should be avoided Rupasinghe, R & Nolan, É 2007. Formwork for Modern,
bent rebar in the site-installed bend-out as they only obtain their tensile capacity Efficient Concrete Construction. Garston-Watford,
system. The pre-bent rebar should first when they are fully screwed in. The con- UK: IHS BRE Press.
be fully exposed, with at least 30 mm stant diameter couplers, as used in this SANS (South African National Standard) 2000.
clear spacing behind the bend, before any study, gradually build up their capacity SANS 10100–1:2000. The Structural Use of Concrete,
form of straightening is considered. A with each turn of the continuation bar. Part 1: Design. Pretoria: SABS Standards Division.
steel pipe should be used to straighten the SANS (South African National Standard) 2010. SANS
bars. The pipe should be placed over the 68921–1:2010. Metallic materials – Tensile Testing.
reinforcement and continuously pushed REFERENCES Part 1: Method of Test at Room Temperature.
inwards as far as possible, while straight- ACI (American Concrete Institute) 2008. ACI 318-08: Pretoria: SABS Standards Division
ening the rebar in one smooth motion. If Building Code Requirements for Structural Concrete SANS (South African National Standard) 2011. SANS
the bar is not entirely straight after the and Commentary, Appendix D. Michigan, MI: ACI. 920:2011. Steel Bars for Concrete Reinforcement.
first attempt, not more than one further Ancon Building Products 2011. Reinforcement Pretoria: SABS Standards Division
adjustment should be considered. continuity systems for the construction industry – SANS (South African National Standard) 2012. SABS
■■ Once the starter-bars are straightened, the Eazistrip. Available at: http://www.ancon.co.uk 0144:1995. Detailing of Steel Reinforcement for
concrete at the joint should be properly (accessed in June 2016). Concrete, 2nd ed. Pretoria: SABS Standards Division.
scabbled to ensure aggregate interlock. All Ancon Building Products 2014. Reinforcement continuity Schreppers, G & Frissen, C & Kang, H 2011. Prediction of
starter-bars should be checked to verify systems for the construction industry – KSN Anchors. crack-width and crack-pattern. Delft: TNO Diana BV.
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 47
TECHNICAL PAPER Sewer network design:
Journal of the South African
Institution of Civil Engineering Heuristic algorithm for
ISSN 1021-2019
Vol 59 No 3, September 2017, Pages 48–56, Paper 1327 hydraulic optimisation
NICO-BEN DE VILLIERS obtained a degree in Civil N de Villiers, G C van Rooyen, M Middendorf
Engineering in 2011 from Stellenbosch University,
and immediately commenced postgraduate
studies in Civil Engineering Informatics at the
same institute. He is currently concluding his PhD, For a given sewer network layout and choice of pipe material, the total installed cost of the
which focuses on optimisation of sewer network network is determined mainly by the pipe diameters and slopes. Hydraulic design optimisation
design. He is also the Technical Director of is the task of determining suitable pipe diameters and slopes so as to minimise the installed cost
Convirt (Pty) Ltd, a software company specialising
of the network. This is a complex problem for which numerous solution approaches have been
in engineering and construction management solutions for the global market.
proposed. Recently the use of metaheuristic algorithms, like Ant Colony Optimisation (ACO)
Contact details: for example, has gained popularity, and they perform well for a given static layout. However,
Department of Civil Engineering
their computational complexity precludes their use in simultaneous layout and hydraulic
Stellenbosch University
Private Bag X1 optimisation, where a complete hydraulic optimisation has to be performed for each layout.
Matieland 7602 This paper proposes a computationally efficient method for near optimal hydraulic design of
South Africa a gravity sewer network. It makes use of required minimum slope information to heuristically
T: +27 83 609 9323 determine optimal pipe sizes and slopes. The method is used to solve two benchmark problems
E: ndv@sun.ac.za
and is shown to obtain good solutions while being computationally extremely efficient.
E: ndv@convirt.co.za
Therefore it is ideally suited to be used in combination with a metaheuristic algorithm aimed at
optimising the network layout.
Dr GC van Rooyen studied science and
engineering at the Universities of the Orange
Free State, Pretoria and Stellenbosch, holding a
PhD from the latter. He is currently responsible INTRODUCTION OPTIMISATION CONSTRAINTS
for Civil Engineering Informatics at the Sewer networks form a vital part of public AND ANALYSIS
Department of Civil Engineering at Stellenbosch
health in urban areas and constitute one of Sewer networks comprise manholes con-
University. Before joining the lecturing staff at
Stellenbosch in 1992 he worked as construction the most capital-intensive infrastructure nected by sewer pipes and other compo-
engineer for the Department of Water Affairs, and as researcher at the investments (Wirhadikusumah et al nents, such as pumping stations and rising
Institute for Structural Engineering and the Bureau of Mechanical 2001). Consequently the ability to improve mains. The network is used to collect waste
Engineering at Stellenbosch University. sewer network designs through the use of water from various facilities, such as houses,
Contact details: metaheuristic optimisation algorithms could schools and industrial buildings, and convey
Department of Civil Engineering potentially yield a significant reduction in it to a sewage processing plant where the
Stellenbosch University
capital expenditure. Simultaneous sewer waste water is purified. The design is to be
Private Bag X1
Matieland 7602
network layout and hydraulic design optimised, in this paper, in terms of capital
South Africa optimisation using these algorithms has investment cost. The objective function
T: +27 21 808 4437 been investigated in recent times. However, for the optimisation of simultaneous sewer
E: gcvr@sun.ac.za the algorithms are computationally network layout and hydraulic design optimi-
very expensive, since the optimisation sation is as per Equation 1 (Moeini & Afshar
PROF DR MARTIN MIDDENDORF received the procedure responsible for the hydraulic 2012), while Figure 1 shows the definition of
Diploma in Mathematics and the Dr. rer. nat.
design has to be completed for a very depth variables.
degree from the University of Hannover,
Germany, in 1988 and 1992, respectively, and the
large number of layout attempts. Lejano
N M
(2006) found that, due to the complexity of
Professorial Habilitation degree from the Minimise C = ∑ LiKi (di , Eiave ) + ∑ Kj (hj )(1)
University of Karlsruhe, Germany, in 1998. He has simultaneous optimisation algorithms, most i=0 j=0
worked at the University of Dortmund and the research has been done on the hydraulic
University of Hannover as Visiting Professor, and
optimisation sub-problem, while the layout Where:
was Professor at the Catholic University of Eichstätt. He is currently Professor
of Swarm Intelligence and Complex Systems at the Leipzig University,
remains static. This paper focuses on the C = cost function of sewer network
Germany. His research interests include swarm intelligence, algorithms from development of a computationally efficient Li = length of pipe i, i ∈ {1, … , N}
nature, optimisation and bioinformatics. heuristic optimisation algorithm by which, Ki = unit cost function of pipe i defined in
Contact details: for a given layout, all constraints of the terms of its diameter (di) and average
Department of Mathematics and Computer Science hydraulic design are systematically satisfied cover depth (Eiave )
University of Leipzig using slope information. The method is Kj = unit cost function of manhole j, defined
Postfach 10 09 20 applied to two benchmark problems in in terms of its height (hj)
D-04009 Leipzig
the literature and shown to obtain near N = number of pipes in the network
Germany
T: +49 341 97 32275 optimal hydraulic designs, while requiring M = number of manholes in the network
E: middendorf@informatik.uni-leipzig.de very little computational effort. These
characteristics make it ideal for combination Sewer network design is subject to a multi-
Keywords: gravity sewer network, heuristic optimisation, hydraulic with a metaheuristic algorithm for optimal tude of constraints of varying complexity, as
optimisation, contributor hydrograph, pipe size and slope layout creation. described below.
48
De Villiers N, Van Rooyen GC, Middendorf M. Sewer network design: Heuristic algorithm for hydraulic optimisation.
J. S. Afr. Inst. Civ. Eng. 2017:59(3), Art. #1327, 9 pages. http://dx.doi.org/10.17159/2309-8775/2017/v59n3a6
Bakhshipour 2015) use a maximum relative optimisation problem, in which element
Ground elevation
flow-depth constraint rather than percentage sizes, installation depths and slopes are
spare capacity. This is merely a different for- determined for a given layout. Due to the
mulation of the same constraint. Moeini and highly constrained nature of hydraulic
Afshar (2012) enforce a minimum relative optimisation and the complexity of simul-
flow depth. In this implementation no such taneous solution algorithms, this part has
constraint, or an equivalent, is enforced. seen considerably more work than the layout
Cover depth (Ei)
Excavation depth (ECi)
This constraint is not common engineering optimisation problem. Mays and Wenzel
practice; furthermore, near the sources of (1976) applied dynamic programming (DP)
the network it becomes almost impossible to to the design of gravity sewer networks with
Diameter (di)
Manhole
enforce this constraint, due to unavoidable the assumption that the direction of flow is
low-flow rates. fixed, severely restricting the set of problems
to which their concepts may be applied.
Q full – Q peak Robinson and Labadie (1981) also applied DP
SC = (2)
Q full to develop an optimisation procedure. Miles
and Heaney (1988) developed a storm water
Where: drainage design method using a spreadsheet
Pipe SC = spare capacity ratio package which may be applied to static lay-
Q full = full-flow rate (m3/s) outs. More recently non-classic optimisation
Figure 1 Definition of depths Q peak = partially full-flow rate at peak algorithms have been developed. Diogo and
conditions (m3/s) Graveto (2006) developed a comprehensive
1. Cover depth enumeration model and simulated annealing
Both minimum and maximum cover depth his constraint results in partially full-flow
T (SA) algorithm for the layout and component
constraints are enforced. Minimum cover conditions in all pipes; to solve for the size optimisation of sewer networks. Afshar
depths protect pipes from imposed loads, hydraulic parameters, Manning’s equation is (2006; 2012) and Afshar et al (2011) have
such as vehicle loads where sewer pipes pass used to estimate velocities throughout this applied numerous non-classic optimisation
under roads. The minimum cover depth investigation. techniques to the sewer network hydraulic
also prevents cross-contamination between design problem, namely an ant colony
water distribution networks by ensuring that 5. Commercially available diameters algorithm (ACO) (2006), cellular automata
sewer pipes are placed below water mains. Diameters may only be selected from a (CA) (2011), a rebirthing genetic algorithm
Furthermore, the minimum cover depth discrete set of commercially manufactured (RGA) (2012), and more recently a hybrid
ensures an adequate drop for house connec- diameters. genetic algorithm (GA) and general hybrid
tions. Similarly, the maximum cover depth cellular automata (GHCA) were proposed
prevents pipe failure under excessive soil and 6. Progressive pipe diameters for the efficient and effective optimal design
imposed loads. Maximum cover depth may The diameter of a pipe may only be equal of pumped sewer networks with fixed
also be enforced to avoid excessive excavation, to or larger than any of the pipes directly layouts (Rohani & Afshar 2015). The lack of
specifically where soil conditions are adverse. preceding itself. This is to prevent pos- computational efficiency of these algorithms
sible blockage, damming of waste water restricts combining them with a non-classic
2. Velocity and sudden increase in flow velocities in optimisation algorithm for layout optimisa-
Both minimum and maximum velocity con- the network. tion, due to the resulting computation times.
straints are enforced at the peak design flow Some hydraulic optimisation algorithms
rate. The minimum velocity prevents the 7. Progressive pipe depths have been developed and successfully com-
deposition of solid particles. The maximum The outflow pipe of any manhole may not be bined with layout optimisation algorithms, all
flow velocity is enforced to prevent erosion placed above the deepest inflow pipe. This with different advantages and disadvantages.
of the pipe material. prevents permanent damming of waste water Walters (1985) used DP for simultaneous
and solid deposition in the manhole. layout and size optimisation, and his method
3. Slope could be used to drain a set of sources with
A minimum slope is enforced on all pipes. Contributor Hydrograph Theory is used in fixed positions. Li and Matthew (1990) used
This is to prevent inaccurate placement dur- this implementation for accumulated flow rate discrete differential dynamic programming
ing construction, or adverse slopes resulting calculations, taking time delays into account. (DDDP), which utilised an iterative procedure
from pipe settlement. The minimum slope The contributing hydrograph at each node is to generate the layout, and then to size the
requirement also ensures that, during full- routed down the network to the outfall man- sewers and pumps while keeping the layout
flow conditions, the minimum flow velocity hole. Theoretically this downstream routing fixed. DDDP has some significant drawbacks
is achieved. should be done using full hydrodynamic flow – it restricts the search space and reduces the
analysis. However, Stephenson and Hine probability of locating the global optimum.
4. Required spare capacity (1982) have demonstrated that ordinary time- The DDDP stages must be manually divided
A percentage spare capacity is enforced at lag routing is of sufficient accuracy for sewer for each individual problem and this reduces
peak-flow conditions to ensure that pressur- network design purposes. its practicality. Pan and Kao (2009) used a
ised flow does not occur. The constraint has genetic algorithm (GA) combined with qua-
the additional benefit of providing a margin dratic programming (QP). In their approach
of safety if storm water ingress is experi- HYDRAULIC OPTIMISATION a majority of the constraints were formulated
enced during peak-flow times. Some inves- Hydraulic optimisation of a sewer net- in QP, while other parameters, such as layout
tigators (Moeini & Afshar 2012; Haghighi & work is one part of the two-part network and pipe diameters, were determined by the
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 49
(1 – SC)Af5/3 Pp2/3
Minimum allowed Ap5/3 = (3)
Velocity
P f2/3
Spare capacity
Where:
Minimum cover depth
Cover
Ap = partial-flow area (m2)
SC = spare capacity ratio
Af = full-flow area (m2)
Pp = partially wetted perimeter (m)
P f = wetted perimeter at full flow (m)
1 (1 – SC)Af5/3
Qp = S (4)
n P f2/3
Where:
Q p = f low rate at partial-flow conditions
(m3/s)
S = slope of the pipe (m/m)
Figure 2 Minimum required slopes n = Manning Roughness Coefficient
GA. Moeini and Afshar (2012) proposed an unable to recognise that a good layout has All other variables are as defined in Equation 3.
ant colony optimisation (ACO) algorithm, been found. To overcome this drawback, a Equation 4 ensures that the conditions of
combined with a tree growing (TG) algorithm, hydraulic optimisation procedure is required constraint 4 are satisfied if used to calculate
which performs both the layout construction which is well suited to be combined with the slope, while additionally allowing for the
and selects diameters simultaneously. In their an algorithm responsible only for layout calculation of slopes in terms of the full-flow
approach an assumption of sewer flow at construction. It must be able to compute all area and wetted perimeter. Constraint 6
maximum relative depth is made, allowing for hydraulic design parameters. To this end (progressive pipe diameters) can be directly
the calculation of pipe slopes. Haghighi and a new heuristic optimisation algorithm is enforced during the diameter selection pro-
Bakhshipour (2015) combined previous works, proposed, which uses a systematic iterative cess. This is done by selecting diameters in
namely the loop-by-loop cutting algorithm approach to select diameters while satisfy- sequence, ensuring that all upstream pipes of
(Haghighi 2013) and an adaptive genetic ing all hydraulic design constraints. The the current pipe already have their diameters
algorithm (Haghighi & Bakhshipour 2012), algorithm operates under the heuristic that selected, and adjusting the lower-bound of
with a tabu search (TS) algorithm to create an increasing diameters, in order to reduce the the set of eligible diameters for the current
effective hybrid algorithm for simultaneous required slope by a significant margin, leads pipe accordingly.
layout and element size optimisation. to economic decisions. The algorithm relies The lower-bounding slope of a pipe is
The approach followed by both Moeini entirely on this heuristic to obtain near- influenced by a number of constraints, as
and Afshar (2012), and Pan and Kao (2009) optimal costs. The cost of the final design indicated in Figure 2. All of the constraints
to use a single selection algorithm for both is only calculated once the entire design has have to be satisfied simultaneously, as
layout and element sizing has the advantage been completed. The mathematical deriva- described below.
of computational efficiency while suffering tions, formulae and engineering concepts
from what will be termed here as fitness relevant during the heuristic procedure are Minimum required slope
warping. With this approach a layout is con- described hereafter. This value is specified.
structed, and simultaneously element sizes Referring to constraint 4 above (under
(in this case diameter of pipes) are selected. Optimisation Constraints and Analysis), Minimum allowable cover depth
In the initial iterations of an evolutionary Manning’s equation for partially full-flow Cover depth requirements may enforce a
optimisation algorithm the population often conditions is used. From Manning’s equation steep slope on pipes in order to achieve the
comprises entirely randomly selected solu- it is clear that flow rate, diameter and slope necessary depth at the downstream manhole,
tions. It is therefore unlikely that good solu- are interdependent variables. As described as shown in Figure 2.
tions have been found, or that the algorithm earlier, the accumulated flow rates are
has started to converge around a good or dependent on network layout. The diameter Minimum velocity
optimal region in the search space for either selections are limited to a set of commer- The minimum velocity constraint, combined
sub-problem. If the algorithm produced cially available diameters, while the slope is a with Manning’s equation, yields:
a very good layout during, especially, but continuous variable with an upper and lower
not limited to, its early iterations it is very 1 A2/3
bound. Once flow rates and diameters are vmin = S(5)
unlikely that the accompanying diameters known, the required slope can be calculated n P 2/3
will also fall within a very good region of the directly to satisfy Manning’s equation, i.e.
search space. The result is that the overall partially full flow that provides the required As vmin is a known constant, the flow
fitness of the solution is poor, due to the spare capacity of constraint 4. Substituting area, A, and wetted perimeter, P, can
poor diameter selection, despite the very Manning’s equation into Equation 2, and be determined if the flow depth can be
good layout. Consequently, the algorithm is after some manipulation, yields: determined. Then the required slope, S, to
50 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
0.0180
0.0160
d
θ
A
y
P
0.0140
çç
æy – d æ
2
φ= cos–1 (7)
d 0
è 2 è 0.15 0.20 0.25 0.30 0.35 0.40
Diameter (m)
d2 Spare capacity Partial flow velocity
A= (θ – sin (θ)) (8)
8
Figure 4 E ffect of diameter increase on slope
⇒
ç çç
æ æ y – d ææ interval-halving algorithm is used. Once the is the diameter, which at this stage is known.
d2 –1 2 flow depth is known, it is used in Equation 5 Using Equations 2 and Manning’s equation,
A= 2π – 2cos
8 d to solve for the minimum required slope an expression for the required slope is found:
è è 2 èè
ç çç
to achieve the minimum allowed velocity.
ç ç
æ Q pnP f2/3 æ2
æ æ y – d ææ Increasing the slope increases the flow veloc- S= (11)
2 ity. It should be noted that in all equations è (1 – SC)A 5/3 è
– sin 2π – 2cos–1 (9) f
d of this section vmin could be substituted
è è 2 èè
for vmax , or any other known velocity, to Where:
ç çç
æ æ y – d ææ obtain the required slope to achieve the S = required slope to achieve minimum
d d –1 2 specified velocity. spare capacity (m/m)
P = θ = 2π – 2cos (10)
2 2 d Q p = flow rate at partial-flow conditions
è è 2 èè Required spare capacity (m3/s)
The required spare capacity constraint also n = Manning roughness coefficient
Substituting the expressions for the area allows for the calculation of a minimum P f2/3 = wetter perimeter at full flow (m)
in terms of the flow depth into Equation 6 required slope. Increasing the slope above SC = spare capacity ratio
yields a highly implicit equation in terms this minimum value does not violate the Af5/3 = full-flow area (m2)
of both the diameter and flow depth. constraint. Using Equation 4 the required
Diameters are selected beforehand, so the slope can be calculated in terms of the flow After accounting for all the lower-bounding
flow depth can be solved for using a line area and wetted perimeter. The only design slope constraints, the next step is to
search algorithm. In this implementation an parameter required to calculate these values determine when increasing the diameter is
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 51
potentially beneficial, i.e. when an increment beneficial. Consequently the change in slope layout graph, which can always be found, as
in diameter leads to a reduction in slope and is evaluated by parameter γ: only gravity sewer networks with no cycles
consequently an expected reduction in cost. are considered. Inflow hydrographs are
For the first two cases, namely minimum Si–1 – Si defined at all manholes, thus the flow rate
γ= (13)
allowable slope and cover requirements, Si–1 of the outgoing pipe of any manhole with no
increasing the diameter obviously has no inflow pipes is immediately known. Starting
effect on the required slope. In the other Where: the design from these manholes, the hydrau-
cases, namely velocity and spare capacity, γ = slope change factor lic design and placement of the outgoing
increasing the diameter may prove to be Si = required slope for the current dia pipe can be completed using the equations
beneficial. This is tested by keeping the meter (m/m) described in this section. The hydrograph of
flow rate and Manning roughness constant, Si–1 = required slope for the previous dia this outgoing pipe can then be added to the
and varying the diameter while calculating meter (m/m) hydrograph of the target manhole, with time
required slopes. Using Q = 15 ℓ/s, n = 0.015, delay included, since all the required hydrau-
v = 0.75 m/s and SC = 0.3, the required slopes If γ ≥ γb , where 0.0 ≤ γb ≤ 1.0, the increase lic parameters have been determined. This
for various diameters are shown in Figure 4. in diameter is considered beneficial, i.e. the procedure is continued downstream until all
Figure 4 (p 51) shows that increasing diameter increment leads to a sufficient network components have been designed.
the diameter affects the required slopes enough reduction in slope that a reduction Determining the topological sort order can
differently. The required slope to maintain in capital expenditure can be expected. be combined with the design procedure. In
a minimum spare capacity decreases, while Otherwise the previous diameter is accepted the topological sorting algorithm, vertices
the required slope to achieve a specified if it resulted in a feasible design. If the cur- with no incoming edges are placed first,
velocity increases. This increase in slope rent diameter is the first eligible diameter, thereafter vertices are only added once all
for velocity is counter to what is common this evaluation step is simply skipped. their preceding vertices have been included
in engineering practice. When Equation 5 γb , the beneficial slope change factor, is in the ordering. In this case manholes may
is used to calculate the required slope, the a predefined variable of the optimisation be added if they have no incoming pipes, or if
assumption of full-flow conditions is often procedure, similar to the evaporation rate the hydraulic design of all its incoming pipes
made. If the assumption of full-flow condi- of ACO or the mutation rate of a GA, which has been completed. Manhole depths are
tions is made, then increasing the diameter must be calibrated for a specific problem. γb set to the maximum excavation depth of all
reduces the required slope to achieve the is best understood by evaluating the effects incoming pipes.
minimum velocity. Using the hydraulic equa- of its extreme values on the final solution. Some rare special cases may be
tion Q = vA, if both the flow rate, Q, and the At γb = 0 any reduction in slope is always encountered during the procedure, which
velocity, v, remain constant, then the flow considered beneficial, i.e. the least buried compromise the feasibility of the design. The
area, A, also remains constant. When assum- depth solution is obtained. At γb = 1 the special cases, listed below, are dealt with as
ing full-flow conditions under the same steepest feasible slope is used, as no reduc- described:
minimum velocity for a larger diameter, tion in slope is ever considered beneficial, i. The minimum allowable slope exceeds
the flow area increases and consequently so i.e. the smallest diameter which results in a the maximum allowable velocity slope:
does the flow rate. It is due to this increase feasible slope is used for each pipe. In most The diameter must be increased to
in flow rate and flow area that the required cases this results in capacity being the active restore feasibility.
slope decreases. In the case of Figure 4, the minimum slope constraint. This is similar ii. The slope is dictated by minimum
flow rate and velocity are kept constant, to the assumption Moeini and Afshar (2012) cover: The active slope constraint is
and consequently so is the flow area. When make in their hydraulic analysis procedure, cover, and is exceeding the maximum
the diameter increases, the flow area is where the flow depth is assumed to always allowable velocity slope. Increasing the
maintained by a decrease in flow depth. This be the maximum allowable. However, their diameter would increase the maximum
increase in diameter leads to an increase in diameter is not necessarily the smallest fea- allowable velocity slope to restore feasibil-
wetted perimeter, despite the reduction in sible. Li and Matthew (1990) found in their ity. Alternatively, it is possible to increase
flow depth. Referring again to Equation 5, work that a balance between minimum bur- the upstream depth of both the pipe and
rewriting in terms of the slope yields: ied depth and other feasible slopes resulted manhole to accommodate the required
in better results than either extreme. The slope. This decision is again evaluated
ç ç
æ vminnP 2/3 æ2
S= (12) optimisation procedure should be repeated by γ. It is possible that this increased
è A2/3 è for multiple values of γb to determine the cover depth may exceed the maximum
best value. Figure 8 (p 56) shows a sensitiv- allowable cover depth, in which case
All the variables in this equation remain ity analysis of the γb parameter for the two increasing the diameter is the only option
constant during a diameter increment, benchmark problems discussed further on to restore feasibility.
apart from wetted perimeter, P, which (under Results). Figure 5 shows a simplified flow chart of
increases. As P is directly proportional to In all cases when determining the the pipe diameter selection procedure.
the slope, S, this leads to an increase in the required slopes from hydraulic parameters, This procedure is repeated for all pipes, as
required slope. the peak design flow rate is required. The described above, in the topological sort order
This implies that increasing the diameter accumulated flow rates, calculated with of the layout.
may be beneficial in two cases: (i) when spare contributor hydrograph theory, are not
capacity is the active lower-bound slope only dependent on the network layout, but Where:
constraint, and (ii) when maximum velocity also the network elements, as time delay D = the eligible set of diameters, satisfy-
is the active upper-bound slope constraint. is considered. This problem is addressed ing constraints 5 and 6, in ascending
These possibilities should be evaluated by performing the hydraulic design of the order
before accepting any diameter increase as network in the topological sort order of the di = the current diameter in D
52 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
If the previous diameter resulted in a feasible
slope, it is accepted as the diameter for the
Start pipe. If it did not, the active slope constraints
are checked to determine if a diameter incre-
ment may be beneficial.
Once a pipe has its diameter and slope
di = Next diameter calculated, using the procedure above, the
upstream hydrograph of the pipe is routed
downstream, with time-delay, and added to
the cumulative flow rate in the downstream
Determine Sactive manhole. This procedure is continued down-
Yes
stream until all pipes have had their slope
and diameter calculated. Once the entire
design of the network is completed, the cost
function, Equation 1, is used to determine
Yes
γ ≥ γb Sactive = Scap | Svmax the total cost of the design.
No
No
RESULTS
Two benchmark problems are used to
determine the effectiveness of the heuristic
diameter selection algorithm. In both cases a
di–1 Feasible? maximum relative flow depth and static flow
No
values are specified. In order to ensure the
Yes proposed heuristic procedure is accurately
compared to the preceding algorithms, the
relative flow depth of the result cannot
exceed the specified value. The maximum
End relative flow-depth parameter is never direct-
ly incorporated. The spare capacity is set to
a value which results in a maximum relative
Figure 5 Diameter selection procedure flow depth very close to, but still below, the
specified maximum. The static flow rates
di–1 = the previous diameter in D Svmax, another diameter increment is applied are incorporated by simply disabling the
Sactive = the active, or critical, minimum slope and the procedure restarted. If neither was downstream routing of flow rates during the
Scap = required slope to achieve spare the active slope, the current diameter is optimisation of the benchmark problems to
capacity accepted. If no diameter increment was pos- allow direct comparison of results.
Svmax = required slope to achieve maximum sible the current diameter is accepted and The first example is a network originally
velocity the maximum velocity slope prioritised over designed by Mays and Wenzel (1976), which
γ = slope change factor spare capacity. Where the diameter incre- has since been solved by other investigators.
γb = beneficial slope change factor ment is not considered beneficial, γ < γb , the The network, shown in Figure 6, has 21 man-
previous diameter is checked for feasibility. holes and 20 pipes. The unit cost functions
Referring to Figure 5, the procedure starts
by selecting the smallest eligible diameter
in D, and is then incremented by one with
10
each iteration. The minimum required
slopes for cover, minimum and maximum
velocity, and spare capacity are calculated as
described in this section. The largest of all 17 16
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 53
Table 1 Data of benchmark problem 1 Table 3 Heuristic solution of benchmark problem 1
1-0 136.55 135.64 186.54 2.6617 1-0 0.0043 Capacity 1219.2 2.6013 0.8188 2.5326 2.4231
2-1 137.46 136.55 152.40 2.5201 2-1 0.0078 Capacity 1066.8 3.2168 0.8188 2.40 2.6850
3-2 138.65 137.46 121.92 2.4635 3-2 0.0098 Cover 1066.8 3.5489 0.7251 2.4 2.4
4-3 140.21 138.65 105.23 0.2548 4-3 0.0194 Capacity 381.0 2.5513 0.8184 2.4 2.8861
5-4 141.43 140.21 91.44 0.1699 5-4 0.0107 Cover 381.0 1.8777 0.7402 2.6420 2.4
6-5 142.65 141.43 121.92 0.1132 6-5 0.0126 Capacity 304.8 1.7710 0.8184 2.4 2.7182
7-3 141.73 138.65 172.21 2.0104 7-3 0.0120 Max Vel 914.4 3.5914 0.7949 3.4133 2.4
8-7 143.26 141.73 106.68 0.5663 8-7 0.0160 Capacity 533.4 2.8930 0.8184 2.4 2.5730
9-8 144.78 143.26 106.68 0.4530 9-8 0.0142 Cover 533.4 2.6901 0.7051 2.4 2.4
10-9 147.83 144.78 152.40 0.2548 10-9 0.0200 Cover 381.0 2.5857 0.8066 2.4 2.4
11-7 143.26 141.73 152.40 1.2459 11-7 0.0115 Capacity 762.0 3.1188 0.8184 2.7016 2.9289
12-11 144.78 143.26 106.68 0.4530 12-11 0.0142 Cover 533.4 2.6901 0.7051 2.4 2.4
13-12 147.83 144.78 137.16 0.3398 13-12 0.0222 Cover 457.2 2.9854 0.6543 3.0723 2.4
14-13 149.35 147.83 147.64 0.2265 14-13 0.0154 Capacity 381.0 2.2679 0.8184 2.4 3.1485
15-11 146.30 143.26 167.68 0.6229 15-11 0.0193 Capacity 533.4 3.1822 0.8184 2.7316 2.9302
16-15 147.83 146.30 131.08 0.2275 16-15 0.0154 Capacity 381.0 2.2679 0.8184 2.4 2.8840
17-16 149.35 147.83 121.92 0.1132 17-16 0.0126 Capacity 304.8 1.7710 0.8184 2.4 2.4182
18-15 148.49 146.30 106.68 0.2548 18-15 0.0205 Cover 381.0 2.6218 0.7949 2.4 2.4
19-18 150.88 148.49 121.92 0.1982 19-18 0.0196 Cover 381.0 2.4822 0.6602 2.4 2.4
20-19 152.40 150.88 106.68 0.1132 20-19 0.0142 Cover 304.8 1.8741 0.7715 2.4 2.4
ïï
Mays and Wenzel (1976) 265 775 –
ì 10.98d + 0.8E – 5.98
Robinson and Labadie (1981) 275 218 – if d ≤ 3ft and E ≤ 10ft
Miles and Heaney (1988) 245 874 – 5.94d + 1.166E + 0.504Ed – 9.64
Ki = í
ï
ï
if d ≤ 3ft and E > 10ft
Afshar (2006) ACO 241 496 29 900
30.0d + 4.9E – 105.9
Afshar et al (2011) CA 253 483 50 î if d > 3ft
Afshar (2012) RGA 241 896 100 000
2
Kj = 250 + hm (14)
Proposed Heuristic Method 246 795 –
Where:
d = the diameter of pipe i ( ft)
0 1 2 3 4 5 6 7 8 9 10 E = the average cover depth of pipe i ( ft)
Sink hm = the height of manhole m ( ft)
54 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Table 4 Data of benchmark problem 2 Table 6 Heuristic solution of benchmark problem 2
1-0 65.42 64.50 320 0.1473 1-0 0.0029 Cover 500 1.1286 0.6309 2.45 2.45
2-1 65.82 65.42 340 0.1047 2-1 0.0012 Cover 500 0.7344 0.6816 2.45 2.45
3-2 66.22 65.82 350 0.1012 3-2 0.0011 Cover 500 0.7214 0.6719 2.45 2.45
4-3 67.28 66.22 470 0.0967 4-3 0.0023 Cover 400 0.8985 0.7988 2.45 2.45
5-4 68.24 67.28 400 0.0387 5-4 0.0023 Cover 300 0.7354 0.6973 2.4932 2.45
6-5 69.85 68.24 450 0.0366 6-5 0.0038 Capacity 250 0.8530 0.8164 2.45 2.5432
7-6 71.19 69.85 300 0.0340 7-6 0.0045 Cover 250 0.9109 0.7109 2.45 2.45
8-7 72.10 71.19 260 0.0324 8-7 0.0035 Cover 250 0.8161 0.7539 2.45 2.45
9-8 73.66 72.10 460 0.0304 9-8 0.0034 Cover 250 0.7957 0.7266 2.45 2.45
10-9 74.59 73.66 260 0.0279 10-9 0.0036 Cover 250 0.8008 0.6680 2.45 2.45
11-1 66.10 65.42 590 0.0446 11-1 0.0012 Cover 400 0.5949 0.5762 2.45 2.45
12-11 66.80 66.10 400 0.0403 12-11 0.0018 Cover 300 0.6537 0.8145 2.45 2.45
13-12 68.60 66.80 500 0.0319 13-12 0.0036 Cover 250 0.8211 0.7383 2.45 2.45
14-13 70.10 68.60 400 0.0300 14-13 0.0038 Cover 250 0.8286 0.6914 2.45 2.45
15-14 71.50 70.10 400 0.0264 15-14 0.0032 Cover 250 0.7628 0.6641 2.5541 2.45
16-15 73.00 71.50 400 0.0211 16-15 0.0041 Capacity 200 0.7684 0.8164 2.45 2.6041
17-4 68.40 67.28 440 0.0596 17-4 0.0025 Cover 400 0.8628 0.5391 2.45 2.45
18-17 69.30 68.40 310 0.0580 18-17 0.0029 Cover 400 0.9277 0.4980 2.8274 2.45
19-18 69.90 69.30 260 0.0562 19-18 0.0034 Capacity 300 0.9076 0.8184 2.6162 2.9274
20-19 70.70 69.90 300 0.0549 20-19 0.0032 Capacity 300 0.8866 0.8184 2.45 2.6162
Table 5 Results of benchmark problem 2 The Manning coefficient for all pipes is con-
sidered as 0.013. The maximum allowable
Model Cost (US$) Function Evaluations y
relative flow depth, (d ), is considered as 0.82.
Mansuri, Khanjani 83 116 – The minimum allowable cover depth, Emin, is
BFGS 82 732 – considered as 2.45 m. The minimum velocity,
vmin , and maximum velocity, vmax , are con-
Fletcher-Reeves 81 553 –
sidered as 0.3 m/s and 3.0 m/s respectively.
GA 77 736 100 000 The minimum allowable slope is 0.001 (m/m).
Cellular Automata 80 879 20 The set of commercially available pipes,
{D} = {150 mm, 200 mm, 250 mm, 300 mm,
Proposed Heuristic Method 78 779 –
400 mm, 500 mm, 600 mm, 700 mm}.
The necessary data for the definition of
1 066.8 mm (42 in), 1 219.2 mm (48 in)}. allowable velocity slope is encountered. The benchmark problem 2 is shown in Table 4.
Table 1 shows the necessary data for the cover depth of the pipe at the source end and The problem is solved using the proposed
benchmark problem. the depth of its source manhole are increased heuristic method. Table 5 shows the results
Table 2 shows the results obtained by to achieve the required slope. obtained by various methods while solving
various methods for the problem. The The second problem, shown in Figure 7, the problem. All values shown in Table 5,
proposed heuristic method is able to is part of the “Kerman” network in Iran except for the newly proposed heuristic
achieve a result similar to the metaheuristic (Afshar et al 2011). For this example the method, were presented by Afshar et al (2011).
optimisation methods, while requiring unit cost functions given in Equation 15 Table 5 shows the algorithm’s ability to
6 milliseconds of computation time using a (Afshar et al 2011) are used in conjunction obtain a near-optimal solution while also
personal computer with 3rd generation Intel with Equation 1 for cost calculations. only requiring 6 milliseconds of computation
Core i7-3630QM. time. Table 6 shows the detailed solution
Table 3 shows the detailed solution Ki = 1.93e3.43di + 0.812Ei1.53 + 0.437diEi1.47 produced by the heuristic method for bench-
obtained by the proposed heuristic method. Kj = 41.46hj (15) mark problem 2.
Table 3 indicates the method’s ability to dif- Figure 8 shows a sensitivity analysis of
ferentiate between the benefit of minimum Where: the γb parameter for both problems. From
possible slopes and diameter increments. di = the diameter of pipe i (m) this figure it is clear that the value of γb is
Note that for pipe 7-3 the special case where Ei = the average cover depth of pipe i (m) not very sensitive to small changes around
the cover slope exceeds the maximum hj = the height of manhole j (m) the optimum. However, some improvement
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 55
Diogo, A & Graveto, V 2006. Optimal layout of sewer
(a)
85 000 systems: A deterministic versus a stochastic model.
Journal of Hydraulic Engineering, 132(9): 927–943.
83 000
Haghighi, A & Bakhshipour, A E 2012. Optimization of
81 000 sewer networks using an adaptive genetic algorithm.
Cost
56 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Soft water attack on TECHNICAL PAPER
concrete tunnel linings in Journal of the South African
Institution of Civil Engineering
the Ingula pumped storage ISSN 1021-2019
Vol 59 No 3, September 2017, Pages 57–67, Paper 1723
resistance and protection He received his PhD and MSc (Eng) degrees
from the University of Cape Town, South Africa,
and his BSc (Civil Eng) degree from the
University of Nairobi, Kenya. His research
interests include concrete durability, service life prediction, steel corrosion in
M Otieno, M Alexander, J du Plessis reinforced concrete structures, and repair and rehabilitation of concrete
structures.
Contact details:
The resistance of the concrete tunnel linings at the Ingula Pumped Storage Scheme (IPSS) School of Civil and Environmental Engineering
to soft water attack was investigated. Concrete disc specimens obtained from cores taken University of the Witwatersrand
from selected locations of the tunnel lining were exposed to a simulated soft water attack Private Bag 3
testing regime in a site laboratory using the actual (soft) water to which the tunnel linings Wits 2050
South Africa
will be exposed when in service. The assessment was carried out for around four months. The
T: +27 11 717 7117
aggressivity of the soft water was quantified using Basson Indices. The results showed that E: mike.otieno@wits.ac.za
the water is readily aggressive and will lead to corrosion of the concrete tunnel lining. The
experimental work showed the average surface rate loss of the linings to be approximately PROF MARK ALEXANDER Pr Eng, who is a Fellow
1.1 mm/a, which, if sustained in the concrete linings, would amount to an average loss of about of SAICE, is Emeritus Professor of Civil
10 mm in a 10-year period. This will result in increased surface roughness and hence higher Engineering at the University of Cape Town. He
head losses due to increased friction coefficients. It was recommended that a protective epoxy holds BSc (Eng), MSc (Eng) and PhD degrees
from the University of the Witwatersrand,
coating be applied on the tunnel lining to limit the reduction in power generation efficiencies.
Johannesburg. His research interests are in
cement and concrete materials, with experience
in fundamental and applied research relating to
INTRODUCTION between the concrete structure (quality) design and construction.
In the recent past, the South African govern- and its exposure environment (aggressivity). Contact details:
ment has invested heavily in a number of Ultimately, lack of durability results not only Department of Civil Engineering
power generation projects to augment existing in a reduction in the service life of the con- University of Cape Town
Private Bag X3
ones. This huge economic investment is crete structure, but also in increased expendi-
Rondebosch 7701
mainly driven by the increasing electricity ture of resources (both human and monetary) Cape Town
demand from both the growing South African to restore the structure to the desired service- South Africa
population and the projected economic ability (or functional) and structural health T: +27 21 650 4012
growth, which will demand a steady and states. The risk of durability failure is quite E: mark.alexander@uct.ac.za
sustainable supply of electricity if the country high for major infrastructural developments,
is to meet its millennium development such as electrical power plants. Therefore JACQUES DU PLESSIS Pr Eng holds a BEng
degree from the University of Pretoria. He has
goals. Currently, South Africa relies mainly engineers and asset owners should be cog-
twenty-three years’ civil consulting engineering
on coal-fired (> 90%) electricity generating nisant of this, and put measures in place to experience, specialising in the water field, with
plants as the source of its industrial and avoid its occurrence. These measures should particular focus on dams and hydropower, and
domestic electricity. Other electricity sources be considered at the design and construction has been the Approved Professional Person for
include gas-turbine, hydro, wind, nuclear stages, and also during the service life of the a number of Category II dam designs. He joined
the Ingula team in 2005 as senior dam design
and solar, among others (www.energy.gov. structure through planned maintenance. In
engineer, after which he supervised construction of the upper dam from
za). Substantial progress has been made in the case of the IPSS, this paper focuses on the April 2008, followed by supervision of the headrace tunnels during 2011.
recent years in the roll-out of major wind and durability (or resistance) of the concrete tun- From May 2012 he led the construction supervision team for the main
solar power generating facilities, and there are nel linings with respect to soft water attack to underground civil contract of the project. Currently he is Senior Dams
plans to expand the nuclear power generation which it will be exposed when in service. Engineer at GIBB Engineering & Architecture.
capacity in the future. A number of new coal Soft waters occur naturally in springs Contact details
and hydro-powered electricity generation emanating from igneous or acid rock forma- GIBB Engineering & Architecture
plants are also currently under construction, tions in mountainous areas, or in lowland P O Box 2700
Rivonia 2128
with some partly completed. This paper streams or rivers which have not passed
South Africa
focuses on the new Ingula Hydroelectric through calcareous strata, and are aggres- T: +27 11 519 4654
Pumped Storage Scheme (IPSS). sive to concrete primarily because of their E: jduplessis@gibb.co.za
A critical aspect of new (and existing) ‘ion hungry’ nature. They are characterised
concrete structures is their durability, which by their low dissolved ion content. When
is fundamentally affected by the interaction Portland cement-based concrete is in contact Keywords: soft water attack, Ingula, hydro-electricity, durability, service life
57
Otieno M, Alexander M, Du Plessis J. Soft water attack on concrete tunnel linings in the Ingula pumped storage hydropower scheme: Assessment of concrete
resistance and protection. J. S. Afr. Inst. Civ. Eng. 2017:59(3), Art. #1723, 11 pages. http://dx.doi.org/10.17159/2309-8775/2017/v59n3a7
Bedford Dam Surge shaft
National grid
Pu
Su
mp
rge
sh a
ft
Ge Ge
ne
ne r at Electricity flow Pumping mode
rat e
Bramhoek Dam
i on (during low electricity demand)
Underground
power station
Reversible
pump-turbines
Generating mode
(during high electricity demand)
Figure 1 S chematic layout of the Ingula Pumped Storage Scheme (adopted from www.eskom.co.za)
di
In
Western Cape
ic O
58 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Table 1 I nterpretation of water aggressiveness aggressiveness of the soft waters to which the aggressiveness of the waters in the initial
index values (Basson & Ballim 1994) concrete tunnel lining will be exposed when measurements in 2005–2006 indicates much
Aggressiveness in service was assessed. In the second stage, more aggressive conditions than the 2014
Aggressiveness
Index (AI) the resistance of the concrete tunnel lining to values. The reasons for this relate to the
< 300 None to mild deterioration by the soft waters was assessed. sampling sources of waters taken for analysis:
400 – 700 Mild to moderate in 2005–2006 these were the natural streams,
Quantification of the while in 2014 they were the Devil’s Culvert
800 – 1 000 High
aggressiveness of the (natural Stream, and the Bedford and Bramhoek dams.
≥ 1 100 Very high
and laboratory) soft waters Note that if the in-situ-measured temperature
Water samples were collected from selected of 12.5°C for the natural waters was used to
and poker vibrators were used to consolidate sources on site and assessed for aggressivity correct all the LCSI values, the 2014 results
concrete and, importantly, a controlled with respect to soft water attack. The water for composite (various sources), Devil’s
permeability formwork liner was applied to used in the laboratory during the testing was Culvert, and lab test bath mean, all show sen-
the shutter below the tunnel spring line to collected from the natural water sources. It sibly the same overall Aggressiveness Index
alleviate concrete blowhole formation. From was therefore important to ascertain that the of approximately 800–900. However, in this
a construction programming point of view, water used in the laboratory closely simulated case, the Lab Test Bath mean was corrected
it was important to achieve high early-age the natural waters. The aggressivity of the using a higher mean laboratory-measured
compressive strengths to allow collapsing of waters was quantified using corrosion indices, temperature of 17°C, hence the higher LCSI
the shutter, in preparation for the next sec- popularly known as Basson Indices, proposed value of 1 130 (up from 831 if 12.5°C is used).
tion’s concrete placement as soon as possible. by Basson (Basson & Ballim 1994), typically This illustrates the influence temperature has
Concrete compressive strengths of around the leaching corrosion sub-index (LCSI) on the aggressivity of the water, and hence
1.0 MPa were achieved eight hours after which was corrected for ‘turbulence’ and on the rate of corrosion of the concrete,
placement, and the consequential effect of ‘temperature’ to give an overall Aggressivity especially in warmer seasons. In general,
this was that it was not uncommon to achieve Index (AI). The interpretation of the AI is the aggressivity of the test bath water (i.e.
28-day compressive strengths of ≥ 60 MPa. given in Table 1. Typical values of selected AI = 1 130) lies in the range of aggressivity of
salient properties of the aggressive waters over the natural waters (i.e. ~ 800 > AI > ~1 400).
a number of years are presented in Table 2. The general conclusion from Table 2 and the
ASSESSMENT OF SOFT Based on the results in Table 2, it was analyses of water aggressivity is that the test
WATER ATTACK OF CONCRETE clear that the concrete tunnel lining will be bath waters are appropriately aggressive and
TUNNEL LINING exposed to waters with high (800–1 000) to mimic the site waters adequately.
The experimental programme was carried very high (≥ 1 100) aggressiveness. Closer Based on the AI values presented in
out in two stages. In the first stage, the examination of the results shows that the Table 2, it was concluded that the water used
Table 2 T ypical average measured values of selected properties of aggressive water over the indicated periods
Value
Calcium hardness (as CaCO3)* (mg/ℓ) 14.6 17.2 2.8 30.0 14.0 3.0
Leaching corrosion sub-index (LCSI) 1 926 821 748 965 1 263 760
Temp adjustment = 0.625 # except for lab test bath which is 0.85 ## 2 107 898 818 1 055 1 381 1 130
* Index values are not very sensitive to the calcium hardness value in the ranges given
# Assuming mean water temperature = 12.5°C
## Average measured water temperature (based on October 2014 values) = ~ 17°C (standard deviation = 1.6°C, 48 readings)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 59
in the laboratory – which was stirred by the
All surfaces epoxy-coated
circulation provided by a small water pump
Partially coated Fully coated
(see next section) as opposed to the flowing specimens specimens
natural waters – mimicked the aggressiveness
(a) Fully epoxy-coated specimen
of the natural waters adequately. The (labora-
tory) water in the baths was replenished from All surfaces epoxy-coated
except this surface
time to time, i.e. approximately every 24 hours
using water from Devil’s Culvert Stream (up
to day 27) and Bramhoek Dam (up to end of
(c)
testing), to ensure its aggressivity was main- (b) Partially epoxy-coated specimen
tained. Various water quality properties were
measured frequently to quantify the aggres- Figure 3 F ully (a) and partially (b) epoxy-coated specimens, and photograph of specimens in an
sivity of the water and hence give guidance as aggressive water tank (c)
to when to replenish the water.
60 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
remained sufficiently aggressive. Initially, it
Source of natural soft water for use in laboratory testing was intended that the pH and conductivity
(Devil’s Culvert Stream and Bramhoek Dam) of the aggressive water be controlled within
± 0.1 and 10% respectively. However, this
proved unfeasible, based on the initial results
Quantification of aggressiveness of soft water
(using Basson Indices)
of this monitoring, and the aggressive water
was thereafter replenished daily. The tanks
in which the specimens were submerged
Sourcing of concrete tunnel lining test specimens were placed in a controlled temperature
(tunnel crown, tunnel invert and side of tunnel)
(Total: 50 test specimens)
environment of between 16 and 18°C in
the laboratory.
Saturated surface dry mass loss/gain
Specimen preparation prior to testing measurements for both the partially and fully
( fully and partially epoxy-coated)
coated specimens were taken concurrently.
The measurements were taken on a daily
Tests on specimens basis, but the frequency was adjusted from
time to time to suit availability of laboratory
personnel. Prior to taking mass measurements
in the partially coated specimens, the exposed
Modified water
Concrete porosity Concrete density Soft water attack surfaces were hand-brushed with a soft
sorptivity test
nylon bristle brush to remove loose corrosion
products. Each specimen was subjected to ten
Figure 5 S ummary of testing programme up-and-down strokes of brushing carried out
under flowing tap water. During this process,
Table 3 Summary of water sorptivity index, porosity and density of test specimens care was taken not to unnecessarily dislodge
small aggregate particles.
Location Density (kg/m3) Porosity (%) WSI (mm/√hr)
18 18
16 16
14 14
Porosity (%)
Porosity (%)
12 12
10 10
8 8
6 6
4 4
1 2 3 4 5 6 7 8 2 250 2 350 2 450 2 550 2 650
WSI (mm/√hr) Density (kg/m3)
Figure 6 C
orrelation between porosity and WSI (for all locations) Figure 7 C
orrelation between porosity and concrete density (for all locations)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 61
10 20
8 16
14.2
12.6
12.1
WSI (mm/√hr)
6 12
Porosity (%)
4.8 9.7
4.1 3.9
4 8
2.9
2 4
0 0
Invert Side of tunnel Top of tunnel All (combined) Invert Side of tunnel Top of tunnel All (combined)
(a) Water sorptivity index (b) Porosity
Error bars: 9 5% confidence interval, t = 2.3 for invert specimens (n = 9), t = 2.4 for side of tunnel specimens (n = 8), and t = 2.4 for invert specimens (n = 7),
t-values for two-tailed student t distribution; n = number of specimens
Figure 8 C
omparison of average WSI and porosity results for the various locations
Density vs porosity
The concrete density ranges between 2 444 Partially coated specimens (invert)
5
and 2 605 kg/m3. Such high density values
Average cumulative mass-loss (-ve) or
62 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
Concrete deterioration (mass
Invert specimens – corrected for mass gain by fully coated specimens
6 loss/gain) results
Figure 9 shows the average cumulative mass
Average net cumulative mass-loss (-ve)
4
to determine the mass gain per unit surface
2 area (g/cm2) of epoxy coating, which was
or mass-gain (+ve) (g)
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 63
of the concrete to the extent of starting
Corrected for mass gain by fully coated specimens
0.5 to expose the coarse aggregate, and some
specimens showed pronounced surface voids
or pores which were not visible at the begin-
Average net cumulative percentage
0
ning of the aggressivity testing. This surface
porosity is likely the result of preferential dis-
change in mass (%)
–0.5
solution of the cement paste phase, creating
‘craters’ in the surface and leaving behind the
–1.0 insoluble aggregates, both fine and coarse,
still embedded in the hardened cement paste.
–1.5
Invert specimens
–2.0 Side of tunnel specimens
EFFECT OF CONCRETE
Top of tunnel specimens
DETERIORATION ON THE SERVICE
–2.5
LIFE OF CONCRETE TUNNEL LININGS
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 AND SYSTEM PERFORMANCE
Days after submersion in aggressive water
Effect of concrete deterioration on
Figure 14 Comparison of average net cumulative percentage change in mass of partially coated service life of concrete tunnel linings
specimens from the different locations Figure 17(a) presents the trend for the average
rate of mass loss in all the specimens during
the experimental period. The average rates
All partially coated specimens – corrected for mass gain by fully coated specimens of mass loss (between days 20 and 130) for
6
specimens from specific locations are pre-
Average net cumulative mass-loss (-ve)
2
earlier. The results show that there were no
0 significant differences between the mass
loss rates in the specimens from the three
–2 tunnel locations, i.e. invert, side of tunnel
–4 and top of tunnel. The rate of mass loss was
calculated assuming an exposed surface of a
–6 68 mm diameter specimen (3 632 mm2) and
95% confidence interval bands
–8
concrete density of 2 500 kg/m3. The results
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 showed that the rate of mass loss decreased
Days after submersion in aggressive water with time, but was levelling off. This may be
attributed to the presence of a poorer qual-
Figure 15 A
verage net cumulative mass loss of all partially coated specimens ity, paste-rich (laitance) layer (Neville 2011)
initially on the concrete surface relative to the
underlying concrete. This phenomenon may
explain the substantially higher rate of mass
loss measured in the specimens after just
one day of exposure in the aggressive water
(see Figure 17(a)). This is also evident from
Figure 18 where the 0–5 minutes WSI values
are much higher than the 7–240 minutes
values; this confirms the somewhat poorer
quality of the near-surface concrete (from
the 0–5 min WSI values, the thickness of the
(a) Exposure time = 0 days (b) Exposure time = 65 days (c) Exposure time = 130 days
laitance layer was estimated to range between
Figure 16 T ypical condition of exposed concrete surface after different exposure durations 0.7 and 4.2 mm, with an average of 1.6 mm
(standard deviation = 0.8 mm)).
There was no notable difference in mass Visual assessment of the A comparison of the average rate of mass
loss as a result of change in source of the corroded specimens loss between days 20 and 130 for specimens
aggressive water used in the testing, i.e. Visible deterioration was observed on the from the different locations is shown in
from Devil’s Culvert Stream, and thereafter exposed surfaces of the partially coated Figure 17(b) where it is clear that, statistically
from Bramhoek Dam. However, between specimens at the end of the testing period – (at a 95% confidence interval), there is no
days 29 and 35 kinks were observed in an indication of corrosion of the concrete by significant difference in the rate of deteriora-
the trends, possibly signifying a change in the aggressive (soft) water. Photographs of tion (corrosion) of the concrete in the three
aggressivity of the water; the water from some of the partially coated specimens after locations, i.e. invert, side of tunnel and top
Devil’s Culvert Stream was less aggres- exposure to the aggressive water for different of tunnel. In assigning the calculated mass
sive than that from Bramhoek Dam (see durations are shown in Figures 16(a), (b) and loss rate to the real structure, it was borne in
Table 2). (c). In general, there was visible corrosion mind that this mass loss rate is only realistic
64 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
30 3.0
28.8
20 2.0
5
0.5
1.0
0
0 20 40 60 80 100 120 140 0
Time after exposure in aggressive water (days) Invert Side of tunnel Top of tunnel All (combined)
(a) (b)
Figure 17 ( a) Variation of rate of mass loss with time – all specimens combined, (b) average mass loss rates for specimens from the different locations
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 65
Roughness factors (ε) were estimated based on
0.030
data from a number of almost similar existing
deteriorated/aged concrete tunnels (Basson
0.025
95.5
are presented in Figure 20 for different flow
rates through the turbines. Save for the cal-
culations being presented in this paper, the 95.0
drop in tunnel efficiency due to deterioration
of the concrete lining by soft water attack
94.5
is expected to result in a drop in the overall
power-generating efficiency by 0.93% if a
concrete protective coating is not applied on 94.0
the tunnel lining to curb deterioration.
93.5
80 82 84 86 88 90
CONCLUSIONS Flow per machine (m3/s)
The investigations carried out in this study Rough tunnel surface Smooth tunnel surface
were aimed at assessing the resistance of the
concrete tunnel linings at the Ingula Pumped Figure 20 T unnel efficiencies for new and deteriorated tunnel
Storage Scheme (IPSS) to deterioration by
soft water attack, and hence to inform a deci- locations (invert, side and top of tunnel) the initial cost of application of the epoxy
sion on whether a concrete protective surface showed similar trends of deterioration. coating will easily be set off against the loss
coating was needed or not. The investiga- ■■ Service life predictions based on the in revenue that could result from reduced
tions showed that: deterioration results, taking into account power-generation efficiencies caused by con-
■■ When in service, the concrete tunnel the high variability, show that a loss of crete degradation and higher friction losses.
lining will be exposed to aggressive soft approximately 10 mm depth of concrete
waters with aggressiveness indices (Basson could take place over a period varying
Indices) ranging from ~ 800 (high) to from less than 1 year to 22 years. Acknowledgements
~ 1 400 (very high), and hence posing a ■■ The deterioration of the concrete tunnel The authors would like to acknowledge
high risk of corrosion of the concrete. lining by soft water attack will lead to the input and support of Eskom and the
■■ Even though the concrete used to make an increase in its surface roughness and Braamhoek Consultants Joint Venture,
the tunnel lining is of good quality (low an overall decrease in power-generating including Mr Colin Logan, Mr Alain Truyts
sorptivity, i.e. 2.1 – 6.8 mm/√hr), it shows efficiency by 0.93%. and Mr Gordon Nefdt and their dedicated
high variability and is still prone to It was therefore recommended that a con- site-based laboratory team, in carrying out
deterioration by the soft waters. This was crete protective coating (epoxy paint) be the laboratory experiments.
evident from the mass loss (and visual applied on the tunnel lining to curb its dete-
assessment) results. rioration and the potential effect this could
■■ The high variability in the deterioration have on the power-generation efficiency of END NOTE
of the concrete tunnel lining by the soft the system. Ideally, a life cycle cost analysis 1. Part of the information provided here has been
waters must be taken into account in of the consequence of this, taking other adopted from the article “Ingula Pumped Storage
service life predictions. However, the con- factors (e.g. maintenance) into considera- Scheme”, published in Civil Engineering, November
cretes obtained from the different tunnel tion, is required, but it can be expected that 2016 [24(10): 12–15].
66 Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017
REFERENCES Basson, J J & Ballim, Y 1994. Durability of concrete, Otieno, M, Alexander, M & Du Plessis, J 2016.
Ballim, Y, Alexander, M & Beushausen, H 2009. Chapter 10. In: Addis, B J (Ed.). Fulton’s Concrete Ingula Pumped Storage Scheme: Assessment of
Durability of concrete, Chapter 9. In: Owens, G Technology, 7th ed. Midrand: Portland Cement deterioration of concrete tunnel linings. Proceedings,
(Ed.). Fulton’s Concrete Technology, 9th ed. Midrand: Institute, 160–164. Hydropower and Dams Conference (Hydro 2016),
Cement & Concrete Institute, 155–188. DI-Manual 2010. Durability index testing procedure 10–12 October 2016, Montreux, Switzerland.
Basson, G R, Visagie, M & Malan, J G 2003. Dealing manual, Version 2.0. Department of Civil
with tunnel ageing. Report to the Water Research Engineering, University of Cape Town. Available at:
Commission, WRC Report No. 1088/1/03. Ninham http://www.alturl.com/dq7s6
Shand (Pty) Ltd in Association with the University Neville, A M 2011. Properties of Concrete, 5th ed.
of Stellenbosch and the University of Pretoria. Harlow, UK: Pearson Education.
Journal of the South African Institution of Civil Engineering • Volume 59 Number 3 September 2017 67
Guidelines for the preparation of papers and technical notes
Authors should comply with the following guidelines when preparing papers for publication in the journal
The Journal of the South African Institution of Civil for obtaining permission to publish experimental or should be typed using the Times New Roman
Engineering is published quarterly in March, June, data and other information that may be confidential symbol set.
September and December. Articles submitted for or sensitive. Authors are also responsible for obtain- ■■ Variables in equations (x, y, z, etc, as well as lower
publication are reviewed by a panel of referees under the ing permission from copyright owners when repro- case Greek letters) should be presented in italics.
guidance of the SAICE Journal Editorial Panel. The jour- ducing material that had been published elsewhere. Numbers (digits), upper case Greek letters, sym-
nal publishes research papers covering all the disciplines Proof of such permission must be supplied. bols of metric measurement units (m for metres,
of civil engineering (structural, geotechnical, railway, s for seconds, etc) and mathematical/trigono-
coastal/marine, water, construction, environmental, SUBMISSION PROCEDURES metrical functions (such as sin, cos and tan) are
municipal, transportation) and associated topics that AND REQUIRED FORMAT not written in italics, but in upright type (Roman).
are relevant to the civil engineering profession, and that ■■ Online submission: Manuscripts must be uploaded Variables and symbols used in the body of the text
preferably have particular relevance to civil engineering as PDF files (http://journal.saice.org.za). Individual should match the format used in the equations,
in southern Africa and the African continent. file sizes may not exceed 4 MB. Should you experi- i.e. upright or italics, whichever is applicable.
When preparing articles for publication, authors ence problems uploading your paper, please contact ■■ Metric measurement abbreviations/units should
should please take note of the following and comply with the editor (verelene@saice.org.za). conform to international usage – the SI system of
the guidelines as set out: ■■ Format: Manuscripts should be prepared in MS units should be used.
Word and presented in double line spacing, single ■■ Decimal commas may be used, but decimal points
CLASSIFICATION OF ARTICLES column layout with 25 mm wide margins. Line are preferred.
CONSIDERED FOR PUBLICATION numbers must be applied to the whole document. ■■ Symbols should preferably be defined in the text,
■■ Technical papers are well-researched, in-depth, fully All pages should bear the authors’ names and be but if this is not feasible, a list of notations may be
referenced technical articles not exceeding 6 000 numbered at the bottom of the page. With the excep- provided for inclusion at the end of the paper.
words in length (excluding tables, illustrations and tion of tables and figures (see below) the document ■■ Headings: Sections and paragraphs should not be
the list of references). Related papers that deal with should be typed in Times New Roman 12 pt font. numbered. The following hierarchy of headings
‘softer sciences’ (e.g. education, social upliftment, etc) Contributions should be accompanied by an abstract should be followed:
are accepted if they are of a technical nature and of of not more than 200 words. HEADING OF MAIN SECTION
particular interest to the civil engineering profession. ■■ First page: The first page of the manuscript should Heading of subsection
The latter type of paper will be subject not only to include the title of the paper, the number of words of Heading of sub-subsection
peer-review by civil engineers, but also to review by the main text (i.e. excluding figures, tables and the ■■ References: References should follow the Harvard
non-engineering specialists in the field covered by list of references), the initials and surnames of the system. The format of text citations should be as
the paper. authors, professional status (if applicable), SAICE follows: “Jones (1999) discovered that …” or “recent
■■ Technical notes are short, fully referenced technical affiliation (Member, Fellow, Visitor, etc), telephone results (Brown & Carter 1985; Green et al 1999)
articles that do not exceed 2 000 words. A typical numbers (landline and mobile), and e-mail and indicated that …”
technical note will have limited scope often dealing postal addresses. The name of the corresponding References cited in the text should be listed in
with a single technical issue of particular importance author should be underlined. Five keywords should alphabetical order at the end of the paper. References
to civil engineering. be suggested. by the same author should be in chronological order.
■■ Review papers are considered for publication as ■■ Figures, tables, photos and illustrations: These The following are examples of a journal article, a
either technical papers or technical notes on condi- should preferably be submitted in colour, as the jour- book and a conference paper:
tion that they are the original work of the author nal is a full-colour publication. ■■ Donald, A W 1954. Pore pressure coefficients.
and will assist the reader with the understanding, ■■ Their positions should be clearly marked in the text Géotechnique, 4(4):143–147.
interpreting or applying of the subject under review. as follows: [Insert Figure 1]. ■■ Terzaghi, K 1943. Practical soil mechanics. New
A review paper must contain criteria by which the ■■ Figures, tables, photos, illustrations and equations York: Wiley.
work under review was evaluated, and contribute should be numbered consecutively and should ■■ Smith, A W, Black, C & White, A 1999. Factors
by synthesising the information and drawing new appear in the text directly after they have been affecting the strength of soils. Proceedings, ASCE
conclusions from the dissemination of the previously referred to for the first time. Conference on Shear Strength of Soils, Colorado,
published work. ■■ Illustrations must be accompanied by appropriate pp 503–532.
■■ Discussion on published articles is welcomed up to captions. Captions for tables should appear above Papers published previously in the Journal of the
six months after publication. The length of discus- the table. All other captions should appear below South African Institution of Civil Engineering should
sion contributions is limited to 1 500 words. Where the illustration (figures, graphs, photos). be cited if applicable.
appropriate, discussion contributions will be subject ■■ Only those figures and photographs essential to ■■ Footnotes, trade names, acronyms, abbreviations:
to the normal reviewing process and will be for- the understanding of the text should be included. These should be avoided. If acronyms are used, they
warded to the authors of the original article for reply. All illustrations should be referred to in the text. should be defined when they first appear in the text.
■■ Figures should be produced using com- Do not use full stops after abbreviations or acronyms.
POLICY REGARDING LANGUAGE AND puter graphics. Hand-drafted figures will not be ■■ Return of amended papers: Papers requiring
ORIGINALITY OF SUBMITTED ARTICLES accepted. Lettering on figures should be equiva- amendments will be accepted up to six months after
■■ Language: Manuscripts should preferably be lent to a Times New Roman 9 pt font or slightly the referee reports had been sent to authors, after
presented in English, as the journal is distributed larger (up to 12 pt) if desired. Lettering smaller which the paper will be withdrawn from the system.
internationally. Articles submitted in any of the other than 9 pt is not acceptable.
official South African languages should be accompa- ■■ Tables should be typed in Times New Roman 9 pt FINAL ARTICLE
nied by an expanded abstract in English. font. They should not duplicate information already ■■ Copyright: On acceptance of the paper or technical
■■ Original work: Papers and technical notes must be given in the text, nor contain material that would note, copyright must be transferred by the author/s to
original contributions. Authors must affirm that sub- be better presented graphically. Tabular matter the South African Institution of Civil Engineering on
mitted material has not been published previously, should be as simple as possible, with brief column the form that will be provided by the Institution.
is not under consideration for publication elsewhere headings and a minimum number of columns. ■■ Photos of authors: The final corrected version of
and will not be submitted elsewhere while under ■■ Mathematical expressions and presentation the paper should be accompanied by recent, high-
consideration by the SAICE Journal Editorial Panel. It of symbols: resolution head and shoulders colour photographs
is the responsibility of the authors to ensure that pub- ■■ Equations should be presented in a clear form and a profile not exceeding 100 words for each of
lication of any paper in the journal will not constitute which can easily be read by non-mathematicians. the authors.
a breach of any agreement or the transgression of any Each equation should appear on a separate line ■■ Proofs: First proofs of papers will be sent to authors
law. The corresponding author should confirm that and should be numbered consecutively. in PDF format for verification before publication.
all co-authors have read and approved the manuscript ■■ Symbols should preferably reflect those used in No major re-writes will be allowed, only essential
and accept these conditions. Authors are responsible Microsoft Word Equation Editor or Mathtype, minor corrections.