BACOLOD CITY LGU BUILDING PERMIT (Separate application for Admin Building and Power Plant Facility)

Before the start of Construction


Title Documents Needed Remarks
1. Building Permit application form
2. Electrical Permit application
form
3. Sanitary/Plumbing Permit
application form
5. Electronics Permit application
form
6. Sets of Plans
a. Vicinity Map
b. Layout
c. Structural Design (Facilities)
including analysis
d. Electrical Wiring Layout and
Single Line Diagram including
analysis
e. Electronics design including
instrumentation, communication,
cctv, smoke detector, layout
f. Drainage/Plumbing/sanitary Design
g. Firefighting facilities, equipment
including sprinkler design among
other applicable mechanical
plans
7. Bill of Materials and Cost
Estimates
8. Specifications
9. Land Title or TCT (Certified by
Register of Deeds)
10. Latest Tax Receipt
11. Tax Declaration
12. Lot plan certified by Geodetic
Engineer
13. Deed of Sale/Contract of Lease
if application name is not
registered TCT name
14. Structural analysis for 1 storey
building in excess of 20sqm and
all building 2 storey and above
with seismic analysis
15. Certification of structural
engineer in case of additional
floor (structural stability)
16. Plate load test analysis - for 3
storeys and above -2 copies
17. Soil Boring Test Result- for 3
storeys and above - 2 copies
18. Clearance from the government
agencies exercising regulatory
function- such regulatory
agencies are:
a. City Planning and Development
Office - for Zoning Clearance
b. Bureau of Fire Protection- for
Fire Department Clearance
d. Barangay and Sangguniang
Panlungsod resolutions allowing
projects for project near or above
waterways, creeks and rivers
e. Department of Labor and
Employment-for construction
safety and health program