1- A carbon steel ASTM A 53 Grade B material is being impact tested. What is the minimum
energy requirement for this material (average for 3 specimens-fully deoxidized steel)?
a. 7 ft-lbs
b. 10 ft-lbs
c. 13 ft-lbs
d. 15 ft-lbs
2- Two different thickness to be welded, say 10mm and 6 mm, What is the permitted angle
and misalignment?
a. 30° and 1.5 mm
b. 37.5° and 1.5 mm
c. 30° and 2.4 mm
d. 37.5° and 2.4 mm
3- When two different materials (say P1 and P3) are joined by welding, Which preheating
temperature will be dominant:
a. P1
b. P3
c. Average of P1 and P3
d. P1 and P3 can’t be welded
Answer: B, ASME B31.3, 330.2.1 (When welding two different P-No. materials, the preheat
temperature shall be the higher temperature for the material being welded)
4- The joint factor can be increased by additional examination on which of the following
pipe joint:
a. Electric fusion weld
b. ERW
c. Furnace butt weld
d. Casting
7- For welding 8 mm base metal, what is the maximum allowable weld height is:
a. 1.5 mm
b. 4.5 mm
c. 2.0 mm
d. 3.0 mm
9- For pneumatic test, the pressure shall be gradually increased until a gage pressure that
is the lesser of ------- test pressure or 170 kPa (25 psi) is attained
a. 25%
b. 10%
c. 50%
d. 5%
10- Unless otherwise specified by the engineering design, the following records shall be
retained for at least 5 years after the record is generated for the project:
a. examination procedures
b. examination personnel qualifications
c. examination reports
d. All of the above
Answer: D, ASME B31.3, 346.3
11- For impact testing, each set of impact test specimens shall consist of ---- specimen bars:
a. 3
b. 2
c. 4
d. 1
Answer: A, ASME B31.3, 323.3.3
12- NPS 2 schedule 80 (0.218” wall) is welded into a NPS 6 Schedule 40 (0.0.280” wall)
header. What size cover fillet weld is required around the fully penetrated groove weld
of the branch into the header? (Express answer to nearest hundredth)
a. 0.15”
b. 0.20”
c. 0.22”
d. 0.25”
13- Pneumatic test pressure shall be not less than ------- the design pressure
a. 140%
b. 133%
c. 110%
d. 150%
Answer: B, ASME B31.3, Fig 328.4.4 (m= lesser of 3.2 mm or ½ branch thickness)
15- At the owner ’s option, a piping system, which Category may be subjected to an initial
service leak test
a. Category M
b. Lethal
c. Normal Category
d. Category D
16- Flange bolt holes shall be aligned within ------ maximum offset
a. 3 mm
b. 1.5 mm
c. 0.8 mm
d. 2 mm
Answer: D, ASME B31.3, 331.1.7 (2010 edition), and API 577, 9.10.1
Answer: B, ASME B31.3, Appendix C, Table C-1 (Sequence of material from highest to lowest :
Aluminum, Brass, Bronze, Copper, SS, Monel, Nickel, low alloy steels, carbon steel, Titanium)
20- Material for components that meet the requirements for more than one specification or
grade, The multiple marking shall be in accordance with the guidelines set out in:
a. ASME B16.5
b. AMSE B16.47
c. ASME ASME BPVC Section II,Part D
d. ASME B31.3
24- Ring Joint side wall surface finish shall not exceed --------- roughness
a. 125 µin
b. 63 µin
c. 250 µmm
d. 1.6 µin
25- Class 150 flanged joints may develop leakage problems above temperature:
a. 750° F
b. 300° F
c. 400° F
d. 600° F
27- Fitting local areas having less than minimum wall thickness could be accepted if:
a. 0.50 √dtm , 1.25 √dtm
b. 0.30 √dtm , 1.95 √dtm
c. 0.35 √dtm , 1.75 √dtm
d. 0.35 √dtm , 0.75 √dtm
28- For B16.5 scope, which of the following class rating is not covered?
a. 150
b. 300
c. 1500
d. None of the above
30- Fitting shell pressure rating shall be rounded off to the next higher:
a. 1 bar
b. 25 PSI
c. A & B
d. None of the above
31- Flanged joints and flanged fittings may be subjected to system hydrostatic tests at :
a. 1.1 design test pressure
b. 1.5 Operating pressure
c. 1.5 times the 38°C (100°F) rating.
d. Not required
33- Flanged fitting (A105N Class 150 material) will be subjected to fluid of 370°C temp, what
should be the pressure testing value?
a. 220 PSI
b. 430 PSI
c. 450 PSI
d. 600 PSI
Answer: C, ASME B16.5, 2.6, Table II-2-1.1 (1.5*285 = 427.5 (rounded to next 25 psi) 450 PSI)
34- An item that is not in accordance with specified codes, standards or other requirements
a. Non-conformance
b. Non-standard
c. Non applicable item
d. Non compatible
Answer: A, API 570, 3.1.61
35- Which NDT method is very often technique of choice on NPS 8 and under when
localized corrosion is suspected?
a. UT
b. PAUT
c. PRT
d. ACFM
Answer: C, API 570, 5.7.1 (Bonus: UT scanning is preferred for larger than NPS 12)
39- As part of Piping Stress Analysis, what is not required to verify Piping is supported and
guided:
a. Its weight is carried safely
b. It does not vibrate excessively
c. Accounts for other loads (e.g. those included in the original code of construction)
d. Pressure loads and other applicable loads
Answer: D, API 570, 7.8
40- Soil-to-air interface generally is considered to be at least --------- below to 6 in. (150 mm)
above the soil surface:
a. 3”
b. 12”
c. 10”
d. 3D
42- Components of a piping system that normally have little or no significant flow
a. Dummy leg
b. Blanked branches
c. Auxiliary piping
d. Dead-legs
Answer: C, API 570, 5.11.4 (Note: in ASME B31.3 max testing temp is 49 °C)
45- Decrease in the design temperature, design pressure or both to provide increased
corrosion allowance:
a. Rerating
b. Alteration
c. Derating
d. Major repair
Answer: C, API 570, 3.1.91
46- Minimum allowed pipe wall thickness needed to hold the design pressure at the design
temperature:
a. Pressure design thickness
b. Structural thickness
c. Nominal thickness
d. Mill Thickness
Answer: A, API 570, 3.1.81
47- The holiday pipe coating survey can be used to:
a. Relative classification of the soil corrosivity
b. Locate external coating defects on buried coated pipes
c. Girth welds surface defects
d. Joint leakage
48- Which NDE method used to check for fouling and internal plugging:
a. ACFM
b. PT
c. UT
d. RT
49- As per API 570, Flange fasteners should be fully engaged, Any fastener failing to do so
is considered acceptably engaged if:
a. Nut and fastener end are flushed
b. lack of engagement is one thread
c. lack of engagement is two threads
d. Two threads appearing outside nut surface
Answer: B, API 570, 5.15 (if ASME B31.3 used, then A is correct answer , check 335.2.3)
50- Bodies of valves that operate in severe cyclic temperature service shall be checked for:
a. Fouling and corrosion build-ups
b. Erosion
c. Local corrosion
d. Internally for cracks
51- Water may not be suitable as a test fluid in some piping systems, such as:
a. Oil-transfer lines
b. Hot or volatile oil lines
c. Toxic and lethal service
d. Acid lines, cryogenic systems, and air-drier systems
57- Surface As an alternative to the hydrostatic test, it is permissible for the full body of pipe
to be tested with:
a. Nondestructive Electric Test
b. UT
c. RT
d. Pipe must be hydrotested.
60- Procedure is a specified way to carry out an activity or process, it includes all of the
following except:
a. Materials to be used
b. Personnel qualifications
c. Equipment used
d. Documents and records
api 570 3.1.83 A procedure may include methods to be employed, equipment or
Answer: B, ISO 10005, 3.5 Note 7 materials to be used, qualifications of personnel involved, and sequence of work.
Additional Notes:
• Check API 570 for Terms, Definitions, Acronyms, and Abbreviations
• Check ASME B 16.5
• Check ASTM A-106 (focus on tolerances and ranges)