Professional Documents
Culture Documents
Version 2
(March 2012)
To receive FREE updates of this
handbook, please refer to the
end of this document where you
will find the relevant registration
form for completion and return.
Preface
The information within this handbook has been collated and assembled by Public
Health Design Consultants currently working in the Gulf Co-operation Council
(GCC) region who believe that it will serve as a supplement to the local design
guides.
The content is based on Public Health Services within the building boundary only; it
is not a definitive guide and is to be used as an aid for Engineers who do not
have day- to-day experience of designing Drainage, Water and Fire services in the
GCC region.
The information contained in the handbook is based on current information and the
best knowledge available at the time of its Launch in October 2011 and subsequent
update in March 2012 and is totally without prejudice.
The information provided within this handbook provides information specific to the
GCC region for those responsible for the design of Public Health Services. It is not
definitive. The authors would recommend that any design work be reviewed and
checked by local Engineering practioners who can advise on any changes that may
have occurred with approval paths and design requirements.
Following the launch of version 1 of the Terrain Fountain Club, Al Khaleej, Middle
East Public Health handbook it is a pleasure to provide the forward for this edition.
Public Health engineering services is an area in the Middle East that is slowly
developing and generating more awareness within the construction industry.
Polypipe Terrain’s continued collaboration with local Public Health Consultants and
Municipalities is reflected by the constant demand for the handbook from within the
GCC region and globally. The handbook is proving to be a valuable source of
information for all those involved in the design, approval and installation of Public
Health Engineering Services.
Each project is unique and the Public Health services information provided in this
document may not be relevant or valid. The project requirements should be
determined with the client and the local authorities in the first instance, Engineers
should exercise their own professional judgment when reviewing the information
contained in the handbook.
Rod Green
Polypipe Gulf Technical Manager
The Fountain Club (Al Khaleej) includes a wealth of expertise within its
membership, and a number of members have stepped forward to make valuable
contributions to this handbook.
Valuable contributions have also been made by the following in the preparation of
this handbook.
We greatly appreciate the contributions received from all contributors and would
also like to thank the support, advice and contribution received from Dubai
Municipality.
2.0 Introduction
4.0 Qatar
4.1 Introduction
4.2 Weather Conditions
4.3 Authorities
4.4 Design Approval Process
4.5 Accepted Standards and Guidance Documents
4.6 Qatar Local Considerations (DOs and DON’Ts)
4.6.1 Soil & Waste Systems
4.6.2 Rain & Storm Water Systems
4.6.3 Domestic Water Services
4.6.4 Gas Services
4.6.5 Fire Protection
4.6.6 Generator Room and Diesel Store
4.6.7 Fire Hydrants
5.0 Kuwait
5.1 Introduction
5.2 Weather Conditions
Middle East Public Health Handbook v2 Page 7
6.0 Bahrain
6.1 Introduction
6.2 Weather Conditions
6.3 Authorities
6.4 Design Approval Process
6.5 Accepted Standards and Guidance Documents
6.6 Bahrain Local Considerations (DOs and DON’Ts)
6.6.1 Soil & Waste Systems
6.6.2 Rain & Storm Water Systems
6.6.3 Domestic Water Services
6.6.4 Gas Services
6.6.5 Fire Protection
6.6.6 Generator Room and Diesel Store
6.6.7 Fire Hydrants
7.0 Oman
7.1 Introduction
7.2 Weather Conditions
7.3 Authorities
7.4 Design Approval Process
7.5 Accepted Standards and Guidance Documents
7.6 Oman Local Considerations (DOs and DON’Ts)
7.6.1 Soil & Waste Systems
7.6.2 Rain & Storm Water Systems
7.6.3 Domestic Water Services
7.6.4 Gas Services
7.6.5 Fire Protection
7.6.6 Generator Room and Diesel Store
7.6.7 Fire Hydrants
National codes were introduced Tables and charts are then used in
based on ‘theoretical assumptions’ conjunction with hydraulic
and ‘what works best’ principles in calculations to determine pipe sizes,
that particular country or region. In flow rates, velocities and, where
the 1900’s the development of fluid necessary, hydraulic mean depths:
mechanics saw further advances in this is not possible with the American
plumbing systems and drainage codes.
principles and design.
In the Middle East, different regions
We now have a number of national have developed local codes or
codes that have been developed to requirements based on local historical
produce the same result, to supply practices that are integral to the
domestic water and convey waste culture of that region. The
water practically, efficiently and safely introduction of external national
to and from the built environment, all codes has created a cocktail of ‘cut
based on different design and and paste’ design and installation
installation criteria. practices that are failing to address
the basic hydraulic principles
There is no ‘right or wrong’ answer as associated with good plumbing and
all the existing codes are based on drainage systems.
probability which is an arguable
science which would require In recent times the Middle East has
extensive research into local habits, seen many complex buildings
customs and predictability. designed and built throughout the
region, creating new challenges for
All the existing codes rely on the use the design and installation of water
of pre-determined tables based on and drainage systems.
Middle East Public Health Handbook v2 Page 9
To overcome these challenges, local
regulations have developed which
incorporate the national codes of
other countries. This has created
additional problems, such as over
sizing in the belief that problems with
poor supply and drainage will be
mitigated.
The Gulf Cooperation Council (GCC), is a political and economic union of the
Arab states bordering the Persian Gulf, namely Bahrain, Kuwait, Oman, Qatar,
Saudi Arabia, and United Arab Emirates.
ADM now have a design review and It is important to note that while it is
approval roll for both Public Health & the responsibility of GASCO to review
Mechanical Building Services and comment on all gas designs, final
systems. The ADM Public Health
Middle East Public Health Handbook v2 Page 17
approval has to be gained form Abu Yas Island for example have private
Dhabi Civil Defense. companies that act under jurisdiction
of the utility company. Full
ADCD (Abu Dhabi Civil Defense) responsibility and approval processes
should be established at an early
ADCD is the organisation responsible stage of the design development.
for reviewing and approving, Fire and
Life Safety Strategy reports and 3.3.2 Dubai
Sprinkler and Fire Protection
systems. Dubai Electricity and Water
Authority (DEWA)
ADCD have the responsibility to also
review LPG systems installation DWEA produces, transmits, and
design and strategy. Any fire fighting distributes electricity and water to
system or LPG system would have to nearly 600,000 customers in Dubai. It
be designed to NFPA Code generates electricity in gas-fired
requirements and ADCD Local power stations located throughout the
requirements over and above NFPA, Emirate. DWEA also maintains and
which would need to be discussed on operates transmission lines at
a ‘case by case’ basis with the voltages of 400 and 132 kV: it
Authority. distributes electricity to customers at
33 and 11 kV. The company
ADCD have stipulated that “no gas produces potable water from
pipe work installations shall be routed desalination plants, where
through a basement area”. It is desalination takes place alongside
required that LPG storage be located the generation of electricity in
externally to the building and riser cogeneration stations. DWEA
pipework be routed on the external transmits water through trunk mains
face of the building. Kitchens pipelines and pumping stations. It
domestic or otherwise must be at also distributes water to customers in
ground level or above and should be remote areas by road tankers.
located so that one wall of the kitchen
is on an external face of the building Further information can be found at
which is provided with an opening www.dwea.gov.ae/
window or balcony door. The point of
entry into a kitchen area should be as Dubai Municipality (DM)
close as possible to the appliances
being served. DM have a design review roll for both
Public Health & Mechanical Building
With discussion and agreement with Services systems. The DM Public
ADCD it may in some cases be Health review team is responsible for
permitted to locate LPG storage on all internal systems and external
the roofs of buildings. If this option is systems up to the building plot
preferred by the design team it is vital boundary. There are three basic
that discussions take place with design packages that are required to
ADCD at early concept stage. be submitted, these are as follows:
Storm Water / Surface Water
There is no website at present for Foul and Waste Water
ADCD. Domestic Hot and Cold Water
Services
Private Companies
When carrying out Public Health
It should be noted that some large Designs for Dubai it is recommended
scale development areas such as that all designs are generally in
Reem Island, Saadiyat Island and
Middle East Public Health Handbook v2 Page 18
accordance with British and
European Standards. 3.3.6 Fujairah
Table 1
It is now acceptable to design for grey The basic design criteria for the
water recycling: however the recycled design of rain and storm water
water is only permitted for use for drainage systems is as follows:
open-to-sky external irrigation, or Typically a 1 in 2 year storm
water features within the plot return period is standard for
boundary. It cannot be used roof areas, using a 5 minute
internally to the building for WC and storm duration: this gives a
urinal flushing. rainfall intensity of 75mm/hr.
For roads and paved areas a
As local sustainable requirements 15 minute storm duration is
develop, the use of treated recycled allowed for, giving a rainfall
grey water for WC flushing is intensity of 40mm/hr.
becoming acceptable: however the For roof areas that are
system proposed will be heavily deemed to be sensitive: a 1 in
scrutinised and all the licensing 5 -10 year storm duration can
requirements would have to be be used: this should be
addressed. Municipalities would discussed and agreed with
Middle East Public Health Handbook v2 Page 31
client and design team at the
concept stage of the project.
The use of plastics or high grade The local water undertaker NOC
stainless steel is acceptable. letter will need to be inserted as part
of the Water Services Design
Approval package to be submitted.
Middle East Public Health Handbook v2 Page 36
Without this NOC letter, any submittal
to the Municipality will be rejected. The local authority requirements are
detailed in the ADNOC Distribution
3.6.4 Gas Services Design Guide entitled “Natural Gas in
Buildings”. In addition the Institute of
Gas services are generally designed Gas Managers Design Guides IGEM
in accordance with the NFPA should be used as a point of
requirements, however, Dubai Civil reference for building gas design.
Defence (DCD) have recently
published a new UAE Fire and Life The procedure is to complete the gas
safety code of Practice that is design in line with the above codes
mandatory within the Emirate of and then submit to a third party gas
Dubai. inspection (TPI) company, this must
be a company that is registered by
Although not formally adopted by Abu ADNOC, fees apply to this process.
Dhabi, this new document is being
referred to by ADCD. Once the design has received a TPI
approved stamp then the package
Discussions with DCD and ADCD are can then be issued to ADNOC for
essential at the early stage of the final approval and the NOC.
project.
The responsibility matrix is split
In Abu Dhabi all gas design is under between three project phases/stages:
the jurisdiction of ADNOC and ADCD
and as such all gas design code Conceptual/Tender Design Stage
compliance checks and the issue of
NOC’s are their responsibility. This stage will be the project’s startup
phase, when documents for project
Within the Emirate of Abu Dhabi there tendering have been prepared by
is a mix of natural gas (NG) networks either the owner or the appointed
and stand-alone LPG based SNG consultant.
systems. ANDOC along with GASCO
plan to continue the plan to expand Upon receipt, review and approval of
the existing NG network reducing the the documents, ADNOC Dist. will
onus on LPG based systems in the issue a conceptual design approval
future. letter including recommendation on
the availability of gas supply to serve
Gas Distribution System(s) consist of the development.
pressure regulating stations;
distribution pipelines, mains and gas Detailed Design Stage
services. The Gas Distribution
System distributes natural gas At this stage the final design and
received from Gas Supply Systems to construction documents and drawings
customer Gas Utilization Systems. need to have been finalized by the
appointed gas contractor. Upon
Gas Utilization Systems consist of receipt, review and approval of the
customer meter installations; documents, ADNOC Dist. will issue a
installation pipework, consumer meter design NOC letter. The project owner
installations and utilization is advised not to allow
equipment. commencement of any construction
work related to the gas distribution
ADCD (Abu Dhabi Civil Defence) and system prior to the receipt of the
ADNOC Distribution Design Guides “Design NOC”.
and design codes need to be taken
into consideration.
Middle East Public Health Handbook v2 Page 37
Pre-commissioning Stage sprinkler systems and NFPA 14 for
standpipe and hose reel systems,
This stage is when the pipework taking into account local
installation has been completed and requirements.
tested ready for commissioning. Upon
receipt, review and approval of the Dubai Civil Defence (DCD) have
documents and after the system has recently published a new UAE Fire
been inspected by Adnoc Dist., a and Life safety code of Practice that
commissioning NOC letter could be is mandatory within the Emirate of
issued. Dubai.
Meetings are also required with Abu Although not formally adopted by Abu
Dhabi Civil Defence, their Dhabi, this new document is being
interpretation of the rules is very referred to by ADCD.
stringent. Nad can be over and above
the ADNOC and IGEM design Until recently a standard NFPA Class
requirements. 3 system was the requirement for all
high- rise buildings: however,
ADCD in general may insist upon the buildings which have or are required
following: to have systems exceeding 15 bar
• Gas pipework must not be working pressure, are now required to
routed through basements, have dedicated risers and pump sets
podiums, underneath for both sprinkler and standpipe
buildings or in common areas risers. Buildings that have a system
of the buildings. below 15 bar working pressure are
• The gas distribution pipe work still required to separate out the
shall not be installed within system risers, but combined sprinkler
the basements areas of and standpipe pump sets are
buildings. acceptable.
if this is the case the gas
distribution pipe work system The Department of Civil Defence is
will have to be installed within the only reference for determining
a purpose service trench, and approving the quantity of fire
within the ground floor water storage / fire water reserve that
structure. Or run at high level is to be allocated for fire fighting
from a level grade or above. purposes.
• NG or SNG gas pipework
routed within buildings must Generally the requirement is for 90
conform to strict ADCD minutes of fire reserve storage. It is
guidelines. advised that designs should meet this
• LPG storage within buildings requirement at early concept stage. It
is not allowed. In this case the has been possible with other projects
LPG storage tanks are to be after direct negotiations with Civil
located ‘off site’ and Defence to reduce this amount to 60
protected, therefore the NFPA minutes, depending on agreement
minimum distance with the overall fire strategy and
requirements from occupied evacuation times, etc for the building /
buildings would be adhered development.
to.
As previously highlighted, it is a
3.6.5 Fire Protection requirement to combine the fire water
reserve with the domestic water
The design for fire protection systems storage; this is to prevent standing
should be based on NFPA 13 for water within the storage tank. Fire
reserves must be completely stored
Middle East Public Health Handbook v2 Page 38
within the ground / first basement supports and joints could fail, which
level tank. would result in another part of a
building being left unprotected:
The best solution for meeting the containing the fire main within a fire
requirement for combined storage in rated conduit/box is not generally
order to keep the fire reserve turning seen as an acceptable solution.
over is to provide a raw / non-drinking
water supply from a combined fire Four way breeching inlet boxes
reserve tank. mounted within the building façade at
street level are required by Civil
The preferred Civil Defence location Defence: connections from the inlet
for the fire reserve tank and boxes must connect directly to both
associated pump sets is at ground the fire reserve tank and into the
floor level, with direct outside access sprinkler systems upstream of the fire
for fire-fighting appliances. pump sets. This allows the fire
It is possible to locate the fire water department to fill the fire reserve
reserve and pump sets at Basement tanks should there be a mains failure,
1: this will require direct, dedicated and also remotely pressurise the
and protected access for the fire crew sprinkler / wet riser system.
from ground floor level / street level. Civil Defence has no objection to the
This would require Civil Defence provision of dual electric pump sets
agreement and approval. being backed from an emergency
generator for either the sprinkler
The firewater reserve has to be equal system or the standpipe system.
to the maximum pump size x the Hose reel and standpipe cabinets are
duration agreed. The NFPA 13/14 to be of the double stack type, one
are not generally used: therefore, for above the other and contain the
most straightforward office buildings following equipment:
this ends up being a 1000gpm pump
for 60 minutes = 60,000 gallon tank. Top cabinet
25dia x 30mtr First Aid Hose Reel
If designed to the minimum
requirements of NFPA the firewater Lower cabinet
reserve may not meet the required 65dia pressure regulating landing
size, the best advice would be to valve
follow NFPA but then check the tank 65dia x 30m canvas hose rack with
size following the rule above. If the nozzle.
firewater reserve is too small, then 1 CO2 5kg fire extinguisher
increase it to meet the local 1 Dry Power 4kg extinguisher
requirement.
Figure 4 on the following page
The incoming main for filling the provides full details for the required
calculated firewater reserve should double stacked cabinet
be sized to replenish the full firewater
reserve within a maximum time frame
of 8 hours, in accordance with NFPA
20, clause 4.31.3.1.4.
Qatar has the world' s largest per rainfall, very high temperatures in
capita production and proven summer and a big difference between
reserves of both oil and natural gas. maximum and minimum
In 2010, Qatar had the world' s temperatures, especially in the inland
highest GDP per capita, while the areas. The coastal areas are slightly
economy grew by 19.40%, the fastest influenced by the Persian Gulf, and
in the world. The main drivers for this have lower maximum, but higher
rapid growth are attributed to ongoing minimum temperatures and a higher
increases in production and exports moisture percentage in the air.
of liquefied natural gas, oil,
petrochemicals and related Summer (June to September) is very
industries. hot with low rainfall. Daily maximum
temperatures can reach 40°C or
With a small citizen population of less more. Winter is cooler with occasional
than 300,000 people, Qatar relies rainfall. Spring and autumn are warm,
heavily on foreign citizens, both for its mostly dry and pleasant, with
protection and generating labour maximum temperatures between
demand. 25°C and 35°C and cooler night
temperatures between 15 and 22°C.
Qatar occupies the small Qatar
peninsula on the northeasterly coast A hot, dust-laden wind, the Shamal,
of the larger Arabian Peninsula. The blows in the spring and summer
Qatari peninsula juts 100 miles period, from March till August; these
(161 km) north into the Persian Gulf winds often cause sandstorms that
from Saudi Arabia. can occur throughout the year,
although they are most common in
Much of the country consists of low the spring. Most rain falls during the
sand covered plains. To the winter months in short, heavy
southeast lies the Khor al Adaid thunderstorms.
(“Inland Sea”), an area of rolling sand
dunes surrounding an inlet of the
Persian Gulf. There are mild winters
and very hot, humid summers.
" #$%&
"
"
" '(%
The designs of soil and waste The use of roof attenuation is a viable
systems in Qatar are similar to the option discharging into a storm water
design requirements highlighted in storage facility. The stored water can
The UAE section of this handbook. be re-used for irrigation of
landscaped areas within the confines
Generally grey and black water of the building plot.
systems are kept separate until the
first manhole. It may also be a requirement to treat
any storm water recycling system to
Disconnecting traps or trapped floor suit local requirements.
gullies must be installed before
connection to the combined manhole. The re-use of storm water can assist
in gaining additional merits for the
All final inspection chambers to QSAS rating system.
extend to the external sewerage
distribution network with a The other items highlighted within the
minimum160mm connection. The UAE section of this handbook are
number of connections from the also relevant to Qatar.
development should be agreed with
Ashgal. 4.6.3 Domestic Water Services
5.1 Introduction
" #$%&
" $)%&
"
"
*
"
6.1 Introduction
" #$%&
" $)%&
"
3. Plumbing Works
7. Water Reuse
6.6.4 Gas Services
• If the capacity of air-
conditioning unit is more than Gas services are generally designed
100 tons, it is advisable that in accordance with the NFPA
the piping network shall be requirements.
appropriately designed at the
concept stage so that the 6.6.5 Fire Protection
condenser drainage water can
be reused as an alternative The design for fire protection systems
source for flushing systems should be based on NFPA 13 for
and or gardening irrigation. sprinkler systems and NFPA 14 for
• It is advisable in industrial standpipe and hose reel systems,
projects such as laundries, car taking into account local
washing booths, garment requirements.
factories etc, to reuse the
waste water after suitable 6.6.6 Generator Room & Diesel
treatment. Store Room
• For major projects, grey water
shall be treated and reused Installation of an automatic foam
for gardening and flushing suppression system should be
purposes, to facilitate this, provided.
there shall be two separate
water supply networks and The generator and diesel store rooms
two drainage systems with should also be provided with sprinkler
stand-by water supply in case protection.
of grey water outage.
6.6.7 Fire Hydrant
• It is advisable to reuse
The hydrant system design should be
rejected water from domestic
NFPA compliant and approved by
desalination units by diverting
Civil Defence.
to a separate ground tank to
" #$%&
" $)%&
"
"
*
"
7.3 Authorities
Middle East Public Health Handbook v2 Page 69
This section give a brief commentary • Raising the standard of living
on the government bodies involved in especially by improving pubic
the design of Public Health Services sanitation and health.
within the construction process and • Providing water for industrial,
the requirement for No Objection commercial, tourism and
Certificates, NOC’s. agricultural purposes guided
by to the principles of
Ministry of Regional Municipalities sustainable development.
and Water Resources • Achieve a balance between
water supply and demand by
The MRMWR oversees the 9 discovering more resources or
municipalities (governorates) of using artificial means such as
Oman, each governorate is ground recharge projects,
responsible for a number of wilayat’s surface dams, water
(provinces) harvesting establishments and
use of non-conventional water
The “Water Master Plan (2000-2020)” resources including
identifies the most important features desalination, treated
of the national strategy, the primary wastewater or brackish water.
goals of water resources
management plan in the Sultanate Further information can be found at
and the different plans and programs www.mrmwr.gov.om/
aimed at water resources
development and management to
ensure its sustainability. Muscat Municipality
The plan takes into account the role The current Building Regulations for
of other relevant government Muscat the Sultanate of Oman were
authorities and the private sector in issued in April 1992 and are still the
achieving the desired objectives at current version to this day, the
the national level. document contains important code
related information for Public Health
The basic constituents of the and Fire Protection services (sections
integrated water resources 21 to 25 inclusive) which must be
management include: adhered to when producing designs
for buildings in the Oman.
• Protecting the use of available
water resources and A full PDF copy of current building
decreasing water loss regulations for Oman can be
• Harmonizing water use and downloaded from the following
renewable resources, website link,
preservation of water http://www.mm.gov.om/linclick.aspx?f
resources from pollution as ileticket=NklQ751Lyxa%3D
well as providing maximum
protection for environment Prior to commencing any form of
elements that depend on construction works to a site, either
water. existing or new build, it is required to
• Providing potable water and obtain from the Municipality a Greater
enhancing ways of collecting Building Permit. Different
and reusing treated departments cover different types of
wastewater to ensure buildings, documents will need to be
provision of water security provided to the relevant department
requirements. for processing.
8.1 Introduction
" #$%&
" $)%&
"
"
*
"
Title
Full Name
Job Title
Company Name
Company Type
Address
City
Region
Country
PO Box
Zip Code
Post Code
Office Tel
Mobile No.
Signature …………………………………………………..
Date …………………………………………………..
Tel: +974 44528394 Tel: +971 (0)4 4548328 Tel: +44 (0)1622 795200
Fax: +971 (0)4 4542949 Fax: +44 (0)1622 716796
www.polypipegulf.com