Tiraz Project Completion Timeline

The document outlines the final handing over schedule plan for Tiraz project which includes 4 towers (Tiraz 1-4). It provides the dates for MEP, civil snagging, and remarks for each floor of each tower. It also includes the finishing dates for ground floor plaza elements like planters and gym, as well as roof cement board work for each tower. The schedule spans from early March to mid-April with 64 flats in Tiraz 1 ready by early March and the remaining towers and elements to be completed in stages through April.

Uploaded by

MOHAMMAD
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views1 page

Tiraz Project Completion Timeline

The document outlines the final handing over schedule plan for Tiraz project which includes 4 towers (Tiraz 1-4). It provides the dates for MEP, civil snagging, and remarks for each floor of each tower. It also includes the finishing dates for ground floor plaza elements like planters and gym, as well as roof cement board work for each tower. The schedule spans from early March to mid-April with 64 flats in Tiraz 1 ready by early March and the remaining towers and elements to be completed in stages through April.

Uploaded by

MOHAMMAD
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Tiraz Final Handing Over Schedule Plan

TIRAZ 1 MEP T&C Civil Snagging Remarks

64 Flats to be ready out of 77 ( Corner Flats with gypsum board issues


1ST FLOOR - 3rd FLOOR - 1-Mar-24
and vanity drawing changes- 13 flats are excluded)
4th FLOOR 1-Mar-24 4-Mar-24 Corner Flats are excluded (2)
Corner Flats are excluded & the flats with major issues in the 6th floor (
5th FLOOR - 6th FLOOR 7-Mar-24 7-Mar-24
gypsum, leak and joinary)

TIRAZ 2 MEP T&C Civil Snagging

1ST FLOOR - 3rd FLOOR 7-Mar-24 15-Mar-24 Corner Flats are excluded (6)
Corner Flats are excluded & the flats with major issues in the 6th floor (
4th FLOOR - 6th FLOOR 15-Mar-24 23-Mar-24
gypsum, leak and joinary)

TIRAZ 3 MEP T&C Civil Snagging

1ST FLOOR - 6th FLOOR 15-Mar-24 7-Apr-24

TIRAZ 4 MEP T&C Civil Snagging

1ST FLOOR - 6th FLOOR 15-Mar-24 20-Apr-24

GF Plaza Finishing Date

Planters 7-Mar-24
TBC

Plaza 08-Mar-24 (Glass Partition)


TBC

GYM 3-Mar-24

GYM Rubber Flooring 03-Mar-24 (delivery) & 17-Mar-24 (completion)


Subject to the shipment and customs & the subcontractor performance

Roof Cement Board Finishing Date

Tiraz-01 4-Mar-24

Tiraz-02 8-Mar-24

Tiraz-03 7-Apr-24

Tiraz-04 20-Apr-24