Tiraz Final Handing Over Schedule Plan
TIRAZ 1 MEP T&C Civil Snagging Remarks
64 Flats to be ready out of 77 ( Corner Flats with gypsum board issues
1ST FLOOR - 3rd FLOOR - 1-Mar-24
and vanity drawing changes- 13 flats are excluded)
4th FLOOR 1-Mar-24 4-Mar-24 Corner Flats are excluded (2)
Corner Flats are excluded & the flats with major issues in the 6th floor (
5th FLOOR - 6th FLOOR 7-Mar-24 7-Mar-24
gypsum, leak and joinary)
TIRAZ 2 MEP T&C Civil Snagging
1ST FLOOR - 3rd FLOOR 7-Mar-24 15-Mar-24 Corner Flats are excluded (6)
Corner Flats are excluded & the flats with major issues in the 6th floor (
4th FLOOR - 6th FLOOR 15-Mar-24 23-Mar-24
gypsum, leak and joinary)
TIRAZ 3 MEP T&C Civil Snagging
1ST FLOOR - 6th FLOOR 15-Mar-24 7-Apr-24
TIRAZ 4 MEP T&C Civil Snagging
1ST FLOOR - 6th FLOOR 15-Mar-24 20-Apr-24
GF Plaza Finishing Date
Planters 7-Mar-24
TBC
Plaza 08-Mar-24 (Glass Partition)
TBC
GYM 3-Mar-24
GYM Rubber Flooring 03-Mar-24 (delivery) & 17-Mar-24 (completion)
Subject to the shipment and customs & the subcontractor performance
Roof Cement Board Finishing Date
Tiraz-01 4-Mar-24
Tiraz-02 8-Mar-24
Tiraz-03 7-Apr-24
Tiraz-04 20-Apr-24