PLAN PIPE TEST AT BOILER-A AND HRSG-A

TEST PRESSURE TEST PRESSURE TEST SAFE UNIT


No. AREA TP NUMBER LINE NUMBER PLAN FOR TEST TIME REMARKS
Kg/Cm2 (g) (Psi) METHODE DISTANCE (M)

1 HRSG-A 331-HRSGA-FG-0002 331-AV-916A-2"-1CB2B81-NI 14 203,1 PNEUMATIC 14,41 M 09.30 - 10.30


Monday, Jan 30, 2022 ( TENTATIVE)
331-FG-903A-10"-1CB2B81-NI 14.00 - 13.00
2 Boiler-A 331-BoilerA-BDW-0011 331-BDW-501A/B/C/D/E-2"-6CB2S07-HC-40 114 1653,4 HYDRO 0,52 M 09.30 - 10.30
Thursday, Feb 02, 2022 ( TENTATIVE)
14.00 - 13.00
3 Boiler-A 331-BoilerA-CH-0002 331-CH-501A/B/C/D/E-1"-6SD1S01-PP-25 129 1871,0 HYDRO 0,9 M 09.30 - 10.30
Wednesday, Feb 01, 2022 ( TENTATIVE)
14.00 - 13.00
4 Boiler-A 331-BoilerA-PN-0002 331-PN-501A-1"-1CB1S01-NI 10,8 156,6 PNEUMATIC 0,67 M 09.30 - 10.30
Wednesday, Feb 01, 2022 ( TENTATIVE)
331-PN-502A-3/4"-1CB1S01-N 14.00 - 13.00