Four Laning of Munger to Mirzachauki (NH-80) Section from Kharia Village junction to start of existing Bhagalpur Bypass (Design

Km 95+580 to Km
Project Name:
125+000) (Pkg-02) on Hybrid Annuity Mode the state of Bihar.
Client National Highway Authority of India
Concessionaire Apco Magadh Expressway Pvt. Ltd.
Independent Engineer LEA Associates South Asia Pvt. Ltd. (LEA INDIA)
EPC Contractor Apco Infratech Pvt. Ltd. (APCO)
REQUEST FOR INSPECTION SUMMARY
S. Date of Inspection Chainage Responsible Contact
RFI No Time Side Structure Activities
No Submission Dated From To Person Number
Reinforcement Shuttering Checking & Pouring of M-30 Concrete
1 31-Mar-2022 APCO/MMP2/STR/285 1-Apr-2022 9.00 AM 121+795 LHS B.CUL Suresh Chand 9451445208
for Bottom Haunch of Box Culvert
Reinforcement Shuttering & Pouring of M-30 Checking for Raft of
2 31-Mar-2022 APCO/MMP2/STR/286 1-Apr-2022 9.30 AM 120+865 LHS B.CUL Suresh Chand 9451445208
Box Culvert
Reinforcement Shuttering Checking & Pouring of M-30 Concrete
3 31-Mar-2022 APCO/MMP2/STR/287 1-Apr-2022 10.00 AM 118+565 RHS B.CUL Suresh Chand 9451445208
for Bottom Haunch of Box Culvert
Reinforcement Shuttering & Pouring of M-30 Checking for Wall
4 31-Mar-2022 APCO/MMP2/STR/288 1-Apr-2022 10.30 AM 122+800 LHS B.CUL Suresh Chand 9451445208
1st Lift of Box Culvert
Checking of Cage Reinforcement, Lowering & Concrete pouring of
5 31-Mar-2022 APCO/MMP2/STR/289 1-Apr-2022 10.30 AM 122+350 LHS MJB Suresh Chand 9451445208
working Pile P/3 at P1 for MJB
Checking of Cage Reinforcement, Lowering & Concrete pouring of
6 31-Mar-2022 APCO/MMP2/STR/290 1-Apr-2022 11.30 AM 122+350 RHS MJB Suresh Chand 9451445208
working Pile P/4 at P1 for MJB
Checking of Cage Reinforcement, Lowering & Concrete Pouring of
7 31-Mar-2022 APCO/MMP2/STR/291 1-Apr-2022 10.30 AM 124+572 RHS MNB Suresh Chand 9451445208
Anchor Pile A1

8 31-Mar-2022 APCO/MMP2/STR/292 1-Apr-2022 9.00 AM 123+000 LHS MNB Layout & Level Checking with Laying of PCC for MNB Suresh Chand 9451445208

9 31-Mar-2022 APCO/MMP2/STR/293 1-Apr-2022 9.30 AM 123+000 RHS MNB Layout & Level Checking with Laying of PCC for MNB Suresh Chand 9451445208

10 31-Mar-2022 APCO/MMP2/STR/294 1-Apr-2022 02.00 PM 103+600 LHS B.CUL Layout & Level Checking with Laying of PCC for Box Culvert Sanjay Tyagi 9131774033

11 31-Mar-2022 APCO/MMP2/STR/295 1-Apr-2022 02.30 PM 103+600 RHS B.CUL Layout & Level Checking with Laying of PCC for Box Culvert Sanjay Tyagi 9131774033

12 31-Mar-2022 APCO/MMP2/STR/296 1-Apr-2022 03.00 PM 104+400 LHS B.CUL Layout & Level Checking with Laying of PCC for Box Culvert Sanjay Tyagi 9131774033

13 31-Mar-2022 APCO/MMP2/STR/297 1-Apr-2022 03.30 PM 104+400 RHS B.CUL Layout & Level Checking with Laying of PCC for Box Culvert Sanjay Tyagi 9131774033

Reinforcement Shuttering & Pouring of M-30 Checking for A1&A2


14 31-Mar-2022 APCO/MMP2/STR/298 1-Apr-2022 11.30 AM 111+982 LHS B.CUL Dinesh Paswan 8709307284
Wall 1st Lift of Box Culvert
Reinforcement Shuttering & Pouring of M-30 Checking for A1&A2
15 31-Mar-2022 APCO/MMP2/STR/299 1-Apr-2022 10.30 AM 111+982 RHS B.CUL Dinesh Paswan 8709307284
Wall 1st Lift of Box Culvert

16 31-Mar-2022 APCO/MMP2/HW/164 1-Apr-2022 02.00 PM 102+000 102+300 LHS HWY FDD Checking of Embankment 1st layer Sanjay Tyagi 9131774033

17 31-Mar-2022 APCO/MMP2/HW/165 1-Apr-2022 04.00 PM 102+000 102+300 RHS HWY FDD Checking of Embankment 1st layer Sanjay Tyagi 9131774033

18 31-Mar-2022 APCO/MMP2/HW/166 1-Apr-2022 04.30 PM 114+150 114+600 LHS HWY FDD Checking of Embankment 1st layer Vikash Shukla 9005099389

19 31-Mar-2022 APCO/MMP2/HW/167 1-Apr-2022 04.00 PM 114+150 114+600 RHS HWY FDD Checking of Embankment 1st layer Vikash Shukla 9005099389