PT-1 715856.257 2559923.62 2220.687


PT-2 715860.966 2559921.94 2220.534
PT-3 715855.25 2559920.79 2220.687
PT-4 715859.959 2559919.12 2220.534
PT-5 715850.52 2559907.51 2219.666
PT-6 715855.23 2559905.83 2219.514
PT-7 715846.494 2559896.21 2219.666
PT-8 715851.205 2559894.53 2219.514
PT-9 715844.012 2559889.24 2220.766
PT-10 715848.722 2559887.56 2220.614
PT-11 715843.006 2559886.41 2221.212
PT-12 715847.716 2559884.73 2221.06
PT-13 715861.069 2559916.87
PT-14 715857.715 2559907.44
PT-15 715854.36 2559898.02
PT-16 715851.006 2559888.6
PT-17 715851.986 2559904.18 2219.59

PT-18 715873.465 2559924.35


PT-19 715871.828 2559922.55
PT-20 715856.327 2559918.44
PT-21 715848.3 2559915.01
PT-22 715832.401 2559902.22
PT-23 715821.595 2559900.38
PT-24 715824.828 2559886.42
PT-25 715833.862 2559887.6
PT-26 715855.561 2559891.1
PT-27 715869.295 2559902.91
PT-28 715882.708 2559916.13
Area 1164.84 m2

PASO BADÉN 77.362 M2


SOPORTES 18 M2
ENCOFRADO 984.647 M2
1080.009

1157.773 M2
S #ELEM TOTAL
LOSA LS-1 15.978 1 15.978
LOSA LS-2 15.81 1 15.81
DENTELLON DT-1 22.031 2 44.062
ZA-1 4.96 4 19.84
105.742 M2
EXTRAS DT-2 5.4
DT-3 4.652

PB 75.85
AREA H #ELEM TOTAL
ZA-1 4.5 0.3 4 5.4
MR-1 0.9 3.5 2 6.3
MR-2 0.9 3.2 2 5.76
LS-1 1.33 5 1 6.65
LS-2 1.5 5 1 7.5
LS-3 Y DT-1 3.32 33.618 1 111.61176

143.82176 M3

PB
0.6

125.76176
AREA H #ELEM TOTAL
Dentellón DT-1 1.884 33.635 2 126.73668 M3
Losa LS-1 Y 2 21.923 5.6 1 130.864 M3
M3
257.60068 M3

ZA-1 7.56 0.3 4 9.072 M3


MR-1-1 3.24 1.1 1 3.564 M3
MR-1-2 3.24 1.607 1 5.20668 M3
MR-2-1 3.24 1.752 1 5.67648 M3
MR-2-2 3.24 1.779 1 5.76396 M3
MR-1-1 7.56 1.1 1 8.316 M3
MR-1-2 7.56 1.607 1 12.14892 M3
MR-2-1 7.56 1.752 1 13.24512 M3
MR-2-2 7.56 1.779 1 13.44924 M3
DT-1 0.62 37.218 2 46.15032 M3
LS-3 190.96 0.4 1 76.384 M3
LS-2 1.33 6.2 1 8.246 M3
LS-1 1.5 6.2 1 9.3 M3

AS 3.195 5 1 15.975 M3

212.2866 M3

ENCOFRADO 1203.721 1 1 1203.721


LS-1 18.451 0.4 1 7.3804
LS-2 15.12 0.4 1 6.048
LS-3 33.571 0.4 1 13.4284
DT-1 12 1 1 12
1242.5778 M3
PB 156.05532
| AREA H #ELEM TOTAL
Dentellón DT-1 0.909 33.635 2 61.14843 M3
Losa LS-1 0.15 33.635 2 10.0905 M3
Losa Ls-2 2.83 0.6 2 3.396 M3
1.5 0.6 2 1.8 M3
76.43493 M3
LS-1 5.18 0.4 1 2.072 M3
LS-2 5.16 0.4 1 2.064 M3
LS-3 23.569 0.4 1 9.4276 M3
DT-1 22.631 0.53 2 23.98886 M3
MR-1-1 2.34 0.592 1 1.38528 M3
MR-1-2 2.34 0.04 1 0.0936 M3
MR-2-1 2.34 0.218 1 0.51012 M3
MR-2-2 2.34 0.642 1 1.50228 M3
ZA-1 3.06 0.3 4 3.672 M3
35.28814 M3
3.376 3.376

PB 14.67528
sección H L #ELEM TOTAL
BADEN 3.53 33.365 2 244.4569 M2
16 0.5 2 16 M2
260.4569 M2

LS-3 Y DT-1 5.314 33.618 1 178.646052 M2


LS-2 11 0.4 1 4.4 M2
LS-1 11.6 0.4 1 4.64 M2
ZA-1 9 0.3 4 10.8 M2
MR-1 6.6 3.5 2 46.2 M2
MR-2 6.6 3.2 2 42.24 M2
286.926052 M2

PB
187.686052
CONCRETO CICLOPEO
SECCION AREA H #ELEM TOTAL
1 956.562 1 956.562
2 2.226 33.635 74.87151

1031.43351 M3

EXCAVACIÓN
SECCION
1 984.647 1 984.647
2 74.87151 ELIMINAR YA ESTA EN PASO
1059.51851 M3

RELLENO
1 41.585 1 41.585 M3
2
STA EN PASO