Six Weeks lookahead - Week 58@ 63

rev0

WEEK 58 WEEK 59 WEEK 60 WEEK 61 WEEK 62 WEEK 63

FECHA LIBERACION
N° Activity Code ACTIVITY START DATE FINISH DATE DURATION RESTRICCIÓN RESPONSABLE

05/05/14
06/05/14
07/05/14
08/05/14
09/05/14
10/05/14
11/05/14
12/05/14
13/05/14
14/05/14
15/05/14
16/05/14
17/05/14
18/05/14
19/05/14
20/05/14
21/05/14
22/05/14
23/05/14
24/05/14
25/05/14
26/05/14
27/05/14
28/05/14
29/05/14
30/05/14
31/05/14
01/06/14
02/06/14
03/06/14
04/06/14
05/06/14
06/06/14
07/06/14
08/06/14
09/06/14
10/06/14
11/06/14
12/06/14
13/06/14
14/06/14
15/06/14
RESTRICCIÓN

WATER PIT

LOSA

ETAPA 2

F 24-Apr-14 8-May-14 15 ggggg


ggggg
ggggg
ggggg

Moldaje
P 7-Apr-14 11-Apr-14 5

F 28-Apr-14 8-May-14 11 ggggg


ggggg
ggggg
ggggg

Preparación de Juntas
P 12-Apr-14 13-Apr-14 2

F 9-May-14 9-May-14 1 ggggg

Hormigonado
P 14-Apr-14 14-Apr-14 1

F 11-May-14 13-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 16-Apr-14 18-Apr-14 3

ETAPA 3

F 25-Apr-14 4-May-14 10
Moldaje
P 15-Apr-14 17-Apr-14 3

F 27-Apr-14 4-May-14 8
Preparación de Juntas
P 18-Apr-14 19-Apr-14 2

F 5-May-14 5-May-14 1 ggggg

Hormigonado
P 20-Apr-14 20-Apr-14 1

F 7-May-14 9-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 22-Apr-14 24-Apr-14 3

MURO ESTE SECTOR 1 WATER PIT

ELEVACION +2,000

F 7-Apr-14 10-May-14 34 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 19-Jul-14 29-Jul-14 11

F 5-May-14 15-May-14 11 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 29-Jul-14 2-Aug-14 5

F 12-May-14 18-May-14 7 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Hormigonado
P 4-Aug-14 5-Aug-14 2

MURO OESTE SECTOR 1 WATER PIT

F 10-Apr-14 15-May-14 36 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
Suministro y/o definición de insertos
Enfierradura pasadas tuberías 5/10/2014 SK/LOGRO
P 24-Apr-14 9-May-14 16 ggggg
ggggg
ggggg
ggggg
ggggg

F 30-Apr-14 20-May-14 21 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 9-May-14 24-May-14 16 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 16-May-14 23-May-14 8 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Preparación de Juntas
P 19-May-14 21-May-14 3 ggggg
ggggg
ggggg

F 24-May-14 28-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Hormigonado
P 24-May-14 25-May-14 2 ggggg
ggggg

F 26-May-14 1-Jun-14 7 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Descimbre
P 27-May-14 29-May-14 3 ggggg
ggggg
ggggg

MURO NORTE

F 25-Apr-14 20-May-14 26 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 29-May-14 10-Jun-14 13 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 15-May-14 30-May-14 16 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 10-Jun-14 18-Jun-14 9 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 1-Jun-14 8-Jun-14 8 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Preparación de Juntas
P 18-Jun-14 20-Jun-14 3

F 6-Jun-14 10-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Hormigonado
P 20-Jun-14 21-Jun-14 2

F 12-Jun-14 16-Jun-14 5 ggggg


ggggg
ggggg
ggggg

Descimbre
P 23-Jun-14 25-Jun-14 3

MURO INTERMEDIO

F 20-Apr-14 20-May-14 31 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 10-Jun-14 22-Jun-14 13 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 20-May-14 30-May-14 11 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 22-Jun-14 30-Jun-14 9

F 1-Jun-14 10-Jun-14 10 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Preparación de Juntas
P 30-Jun-14 2-Jul-14 3

F 6-Jun-14 10-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Hormigonado
P 3-Jul-14 3-Jul-14 1

F 12-Jun-14 16-Jun-14 5 ggggg


ggggg
ggggg
ggggg

Descimbre
P 5-Jul-14 7-Jul-14 3

UNIDAD 2

LOSA FUNDACIÓN COOLING TOWER

SEGMENTO 1 (Parcial 176 m3, Sector 4 según secuencia)

F 20-Apr-14 4-May-14 15
Moldaje
P 10-May-14 17-May-14 8 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 22-Apr-14 4-May-14 13
Preparación de Juntas
P 18-May-14 23-May-14 6 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 5-May-14 5-May-14 1 ggggg

Hormigonado
P 26-May-14 26-May-14 1 ggggg

F 8-May-14 10-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 27-May-14 29-May-14 3 ggggg
ggggg
ggggg

SEGMENTO 1 (Parcial 175 m3, Sector 5 según secuencia)

F 3-May-14 7-May-14 5 ggggg


ggggg
ggggg

Moldaje
P 10-May-14 17-May-14 8 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 4-May-14 8-May-14 5 ggggg


ggggg
ggggg
ggggg

Preparación de Juntas
P 18-May-14 23-May-14 6 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 10-May-14 10-May-14 1 ggggg

Hormigonado
P 26-May-14 26-May-14 1 ggggg

F 13-May-14 15-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 27-May-14 29-May-14 3 ggggg
ggggg
ggggg

PEDESTALES

SEGMENTO 1 (parcial 96 c/u, sector 1 según secuencia)

F 3-May-14 7-May-14 5 ggggg


ggggg
ggggg

Moldaje
P 6-Jun-14 20-Jun-14 15 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 4-May-14 7-May-14 4 ggggg


ggggg
ggggg

Preparación de Juntas
P 21-Jun-14 25-Jun-14 5

F 8-May-14 8-May-14 1 ggggg

Hormigonado
P 26-Jun-14 26-Jun-14 1

F 11-May-14 14-May-14 4 ggggg


ggggg
ggggg
ggggg

Descimbre
P 29-Jun-14 30-Jun-14 2

SEGMENTO 2 (parcial 60 c/u)

F 3-Apr-14 3-May-14 31
Enfierradura
P 1-Jul-14 12-Jul-14 12

F 9-May-14 15-May-14 7 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 8-Jul-14 19-Jul-14 12

F 16-May-14 16-May-14 1 ggggg

Hormigonado
P 25-Jul-14 25-Jul-14 1

MUROS PERIMETRALES

SEGMENTO 1

F 3-Apr-14 1-May-14 29
Enfierradura
P 4-Jun-14 13-Jun-14 10 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

UNIDAD 1

LOSA FUNDACIÓN COOLING TOWER

SEGMENTO 3 (parcial 91m3, sector 2 según secuencia)

F 24-Apr-14 3-May-14 10
Enfierradura
P 5-May-14 21-May-14 17 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 5-May-14 15-May-14 11 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 8-Jul-14 19-Jul-14 12

F 16-May-14 16-May-14 1 ggggg

Hormigonado
P 5-May-14 21-May-14 17 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 19-May-14 21-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 29-Jun-14 30-Jun-14 2

CAMARAS MENORES

CAMARA MH 15J

F 8-May-14 8-May-14 1 ggggg


Emplantillado
P 28-Sep-14 7-Oct-14 10

F 2-May-14 10-May-14 9 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 8-Oct-14 6-Nov-14 30

F 11-May-14 15-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Moldaje
P 18-Oct-14 16-Nov-14 30

F 17-May-14 17-May-14 1
Hormigonado
P 28-Oct-14 26-Nov-14 30

CAMARA MH 25D

F 30-Apr-14 30-Apr-14 1
Emplantillado
P 28-Sep-14 7-Oct-14 10

F 2-May-14 10-May-14 9 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 8-Oct-14 6-Nov-14 30

F 11-May-14 15-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Moldaje
P 18-Oct-14 16-Nov-14 30

F 17-May-14 17-May-14 1
Hormigonado
P 28-Oct-14 26-Nov-14 30

GIS CONTROL BUILDING

TRINCHERAS

TIPO 2 (ANCHO 1,5 M)

F 7-May-14 7-May-14 1 ggggg


Condicionado por entregas rellenos, se
Emplantillado programa para despues de 5/5/2014 SK
Hormigonados muro
P 1-Apr-14 2-Apr-14 2

F 8-May-14 13-May-14 6 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 2-Apr-14 4-Apr-14 3

F 14-May-14 16-May-14 3 ggggg


ggggg
ggggg

Moldaje
P 4-Apr-14 6-Apr-14 3

F 17-May-14 18-May-14 2 ggggg


ggggg

Hormigonado
P 6-Apr-14 7-Apr-14 2

F 20-May-14 21-May-14 2 ggggg


ggggg

Descimbre
P 9-Apr-14 10-Apr-14 2

TIPO 1 (ANCHO 1,2 M)

F 7-May-14 7-May-14 1 ggggg

Emplantillado
P 2-Apr-14 3-Apr-14 2

F 8-May-14 13-May-14 6 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 4-Apr-14 14-Apr-14 11

F 14-May-14 16-May-14 3 ggggg


ggggg
ggggg

Moldaje
P 7-Apr-14 17-Apr-14 11

F 17-May-14 18-May-14 2 ggggg


ggggg

Hormigonado
P 17-Apr-14 19-Apr-14 3

F 20-May-14 21-May-14 2 ggggg


ggggg

Descimbre
P 21-Apr-14 23-Apr-14 3

FUNDACIONES Y MUROS
Six Weeks lookahead - Week 58@ 63

rev0

WEEK 58 WEEK 59 WEEK 60 WEEK 61 WEEK 62 WEEK 63

FECHA LIBERACION
N° Activity Code ACTIVITY START DATE FINISH DATE DURATION RESTRICCIÓN RESPONSABLE

05/05/14
06/05/14
07/05/14
08/05/14
09/05/14
10/05/14
11/05/14
12/05/14
13/05/14
14/05/14
15/05/14
16/05/14
17/05/14
18/05/14
19/05/14
20/05/14
21/05/14
22/05/14
23/05/14
24/05/14
25/05/14
26/05/14
27/05/14
28/05/14
29/05/14
30/05/14
31/05/14
01/06/14
02/06/14
03/06/14
04/06/14
05/06/14
06/06/14
07/06/14
08/06/14
09/06/14
10/06/14
11/06/14
12/06/14
13/06/14
14/06/14
15/06/14
RESTRICCIÓN

FUNDACIONES Y MUROS

EJE L3

MURO W1

F 5-May-14 8-May-14 4 ggggg


ggggg
ggggg
ggggg

Descimbre
P 3-Apr-14 5-Apr-14 3

PILARES C1

F 5-May-14 8-May-14 4 ggggg


ggggg
ggggg
ggggg

Descimbre
P 3-Apr-14 5-Apr-14 3

EJE LC (ENTRE L2 Y L3)

MURO W1

F 5-May-14 8-May-14 4 ggggg


ggggg
ggggg
ggggg

Descimbre
P 2-Apr-14 4-Apr-14 3

PILARES C1

F 5-May-14 8-May-14 4 ggggg


ggggg
ggggg
ggggg

Descimbre
P 1-Apr-14 2-Apr-14 2

EJE LC (ENTRE L2 Y L1)

ZAPATA WF1 Entrega de trabajos en culvert Eplaz 5/15/2014 SK

F 16-May-14 20-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Enfierradura
P 6-Apr-14 8-Apr-14 3

F 21-May-14 24-May-14 4 ggggg


ggggg
ggggg
ggggg

Moldaje
P 8-Apr-14 10-Apr-14 3

F 25-May-14 25-May-14 1 ggggg

Hormigonado
P 10-Apr-14 11-Apr-14 2

F 28-May-14 30-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 13-Apr-14 14-Apr-14 2

MURO W1 Entrega de trabajos en culvert Eplaz 5/15/2014 SK

F 21-May-14 25-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Enfierradura
P 12-Apr-14 16-Apr-14 5

F 22-May-14 26-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Moldaje
P 16-Apr-14 17-Apr-14 2

F 28-May-14 28-May-14 1 ggggg

Hormigonado
P 17-Apr-14 18-Apr-14 2

F 30-May-14 3-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Descimbre
P 19-Apr-14 21-Apr-14 3

PILARES C1

F 21-May-14 25-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Enfierradura
P 12-Apr-14 14-Apr-14 3

F 22-May-14 26-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Moldaje
P 14-Apr-14 15-Apr-14 2

F 28-May-14 28-May-14 1 ggggg

Hormigonado
P 15-Apr-14 16-Apr-14 2

F 30-May-14 3-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Descimbre
P 18-Apr-14 19-Apr-14 2

EJE LA (ENTRE L3 Y L2)

MURO W1

F 26-Apr-14 26-Apr-14 1
Hormigonado
P 31-Mar-14 31-Mar-14 1

F 30-Apr-14 2-May-14 3
Descimbre
P 2-Apr-14 4-Apr-14 3

PILARES C1

F 26-Apr-14 26-Apr-14 1
Hormigonado
P 25-Mar-14 26-Mar-14 2

F 30-Apr-14 2-May-14 3
Descimbre
P 28-Mar-14 29-Mar-14 2

EJE LA(ENTRE L2 Y L1)

ZAPATA WF1 Entrega de trabajos en culvert Eplaz 5/15/2014 SK

F 16-May-14 20-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Enfierradura
P 6-Apr-14 8-Apr-14 3

F 21-May-14 24-May-14 4 ggggg


ggggg
ggggg
ggggg

Moldaje
P 8-Apr-14 10-Apr-14 3

F 25-May-14 25-May-14 1 ggggg

Hormigonado
P 10-Apr-14 11-Apr-14 2

F 28-May-14 30-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 13-Apr-14 14-Apr-14 2

MURO W1 Entrega de trabajos en culvert Eplaz 5/15/2014 SK

F 21-May-14 25-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Enfierradura
P 12-Apr-14 16-Apr-14 5

F 22-May-14 26-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Moldaje
P 14-Apr-14 15-Apr-14 2

F 28-May-14 28-May-14 1 ggggg

Hormigonado
P 16-Apr-14 17-Apr-14 2

F 30-May-14 3-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Descimbre
P 19-Apr-14 21-Apr-14 3

PILARES C1

F 21-May-14 25-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Enfierradura
P 8-Apr-14 10-Apr-14 3

F 22-May-14 26-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Moldaje
P 10-Apr-14 11-Apr-14 2

F 28-May-14 28-May-14 1 ggggg

Hormigonado
P 11-Apr-14 12-Apr-14 2

F 30-May-14 3-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Descimbre
P 14-Apr-14 15-Apr-14 2

EJE L1

ZAPATA CORRIDA WF1 Entrega de trabajos en culvert Eplaz 5/15/2014 SK

F 16-May-14 16-May-14 1 ggggg

Emplantillado
P 15-Apr-14 16-Apr-14 2

F 17-May-14 20-May-14 4 ggggg


ggggg
ggggg
ggggg

Enfierradura
P 17-Apr-14 20-Apr-14 4

F 21-May-14 24-May-14 4 ggggg


ggggg
ggggg
ggggg

Moldaje
P 21-Apr-14 23-Apr-14 3
Six Weeks lookahead - Week 58@ 63

rev0

WEEK 58 WEEK 59 WEEK 60 WEEK 61 WEEK 62 WEEK 63

FECHA LIBERACION
N° Activity Code ACTIVITY START DATE FINISH DATE DURATION RESTRICCIÓN RESPONSABLE

05/05/14
06/05/14
07/05/14
08/05/14
09/05/14
10/05/14
11/05/14
12/05/14
13/05/14
14/05/14
15/05/14
16/05/14
17/05/14
18/05/14
19/05/14
20/05/14
21/05/14
22/05/14
23/05/14
24/05/14
25/05/14
26/05/14
27/05/14
28/05/14
29/05/14
30/05/14
31/05/14
01/06/14
02/06/14
03/06/14
04/06/14
05/06/14
06/06/14
07/06/14
08/06/14
09/06/14
10/06/14
11/06/14
12/06/14
13/06/14
14/06/14
15/06/14
RESTRICCIÓN

F 25-May-14 25-May-14 1 ggggg

Hormigonado
P 24-Apr-14 24-Apr-14 1

F 28-May-14 30-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 26-Mar-14 28-Mar-14 3

MURO W1

F 21-May-14 25-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Enfierradura
P 20-Apr-14 26-Apr-14 7

F 22-May-14 26-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Moldaje
P 25-Apr-14 1-May-14 7

F 28-May-14 28-May-14 1 ggggg

Hormigonado
P 2-May-14 2-May-14 1

F 30-May-14 3-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Descimbre
P 3-May-14 5-May-14 3 ggggg

PILARES C1

F 21-May-14 25-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Enfierradura
P 21-Apr-14 23-Apr-14 3

Moldaje F 22-May-14 26-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

P 24-Apr-14 26-Apr-14 3

Hormigonado F 28-May-14 28-May-14 1 ggggg

P 27-Apr-14 27-Apr-14 1

F 30-May-14 3-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Descimbre
P 30-Apr-14 30-Apr-14 1

LOSA RADIER

F 20-May-14 26-May-14 7 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
Rellenos perimetrales de trincheras por
Enfierradura otros 5/6/2014 SK
P 14-Apr-14 20-Apr-14 7

Moldaje F 24-May-14 28-May-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

P 20-Apr-14 23-Apr-14 4

Hormigonado F 31-May-14 2-Jun-14 3 ggggg


ggggg
ggggg

P 23-Apr-14 24-Apr-14 2

F 4-Jun-14 8-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Descimbre
P 24-Apr-14 25-Apr-14 2

LOSA SUPERIOR

F 1-Jun-14 7-Jun-14 7 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 25-Apr-14 1-May-14 7

F 8-Jun-14 13-Jun-14 6 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 1-May-14 6-May-14 6 ggggg
ggggg

F 14-Jun-14 14-Jun-14 1 ggggg

Hormigonado
P 6-May-14 7-May-14 2 ggggg
ggggg

F 17-Jun-14 19-Jun-14 3
Descimbre
P 10-May-14 12-May-14 3 ggggg
ggggg
ggggg

START UP SWITCHGEAR CONTAINER

LOSA

F 7-May-14 7-May-14 1 ggggg

Emplantillado Se debe entregar area 5/1/2014 SK


P 25-Apr-14 26-Apr-14 2

F 6-May-14 11-May-14 6 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 26-Apr-14 1-May-14 6

F 8-May-14 13-May-14 6 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 1-May-14 4-May-14 4

F 14-May-14 15-May-14 2 ggggg


ggggg

Hormigonado
P 4-May-14 5-May-14 2 ggggg

F 17-May-14 17-May-14 1
Descimbre
P 5-May-14 5-May-14 1

E/S SWITCHGEAR CONTAINER

LOSA

F 7-May-14 7-May-14 1 ggggg

Emplantillado Se debe entregar area 5/1/2014 SK


P 5-May-14 8-May-14 4 ggggg
ggggg
ggggg
ggggg

F 6-May-14 11-May-14 6 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 8-May-14 15-May-14 8 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 8-May-14 13-May-14 6 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg

Moldaje
P 15-May-14 19-May-14 5 ggggg
ggggg
ggggg
ggggg
ggggg

F 14-May-14 15-May-14 2 ggggg


ggggg

Hormigonado
P 6-May-14 7-May-14 2 ggggg
ggggg

F 17-May-14 17-May-14 1
Descimbre
P 20-May-14 21-May-14 2

245 KV GIS

LOSA RADIER

F 21-May-14 24-May-14 4 ggggg


ggggg
ggggg
ggggg

Emplantillado Se debe entregar area 5/18/2014 SK


P 21-May-14 24-May-14 4 ggggg
ggggg
ggggg
ggggg

F 24-May-14 31-May-14 8 ggggg


ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

Enfierradura
P 24-May-14 31-May-14 8 ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg
ggggg

F 31-May-14 4-Jun-14 5 ggggg


ggggg
ggggg
ggggg
ggggg

Moldaje
P 31-May-14 4-Jun-14 5 ggggg
ggggg
ggggg
ggggg
ggggg

START UP TRANSFORMER

CABLE PIT

LOSA

F 12-May-14 13-May-14 2 ggggg


ggggg

Emplantillado Se debe entregar area 5/10/2014 SK


P 12-May-14 13-May-14 2 ggggg
ggggg

F 13-May-14 14-May-14 2 ggggg


ggggg

Enfierradura
P 12-May-14 13-May-14 2 ggggg
ggggg

F 13-May-14 14-May-14 2 ggggg


ggggg

Moldaje
P 12-May-14 13-May-14 2 ggggg
ggggg

F 14-May-14 14-May-14 1 ggggg

Preparación de Juntas
P 12-May-14 13-May-14 2 ggggg
ggggg

F 15-May-14 15-May-14 1 ggggg

Hormigonado
P 12-May-14 13-May-14 2 ggggg
ggggg

F 17-May-14 17-May-14 1 ggggg

Descimbre
P 12-May-14 13-May-14 2 ggggg
ggggg

MURO

F 14-May-14 17-May-14 4 ggggg


ggggg
ggggg
ggggg

Enfierradura
P 14-May-14 17-May-14 4 ggggg
ggggg
ggggg
ggggg

F 17-May-14 19-May-14 3 ggggg


ggggg
ggggg

Moldaje
P 17-May-14 19-May-14 3 ggggg
ggggg
ggggg

F 19-May-14 20-May-14 2 ggggg


ggggg

Preparación de Juntas
P 19-May-14 20-May-14 2 ggggg
ggggg

F 20-May-14 21-May-14 2 ggggg


ggggg

Hormigonado
P 20-May-14 21-May-14 2 ggggg
ggggg

F 23-May-14 25-May-14 3 ggggg


ggggg
ggggg

Descimbre
P 23-May-14 25-May-14 3 ggggg
ggggg
ggggg

RELLENOS

F 25-May-14 27-May-14 3 ggggg


ggggg
ggggg

Rellenos (por terceros)


P 25-May-14 27-May-14 3 ggggg
ggggg
ggggg
DOCUMENTO Nº
FECHA:
Reporte de Actividades Diarias de Terreno
PAGINA

1 DE 1

Edificio:

Capataz: Especialidad:

REPORTE DE HORAS
HH por actividad
HH TOTAL DÍA
Ítem RUT Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act.6 ACT N° Equipos Utilizados

1 1

2 2

3 3

4 4

5 5

8 Personal HH TOTAL DÍA

9 CAPATAZ

10 MM

11 M1

12 M2

13

DESCRIPCION DE ACTIVIDADES CONTRIBUTIVAS

Nº Act. DESCRIPCIÓN ACTIVIDAD HH TOTALES

10

OBSERVACIONES

Responsable Elaboró Revisó Revisó

Nombre

Cargo

Fecha

Firma
DOCUMENTO Nº
FECHA:

Reporte de Actividades Diarias de Terreno


PAGINA

1 DE 1

Área:

Capataz: Luis Martinez Especialidad: Enfierradura

REPORTE DE HORAS
HH por actividad Equipos
HH Total Dia
Item ROL Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act. Nº Equipos Utilizados

1 6155 Luis Martinez Capataz 1

2 7243 Carlos Munzenmayer M1 2

3 3024 Edwin Carvajal M1 3

4 7223 Alejandro Jorquera M1 4

5 87232 Roberto Jones M1 5

6 87234 Luis Espinoza M1

7 86402 José Retamal M1 Resumen HH

8 88195 Marcos Vasquez M1 CATEGORIA HH TOTAL DIA

9 88202 Luis Caisedo M1 CAPATAZ

10 88249 Isaias Guzman M1 MM

11 89214 Fernando Carrasco M1 M1

12 7334 Victor Ledesma M1 M2

13 AY

OBSERVACIONES

DESCRIPCION DE ACTIVIDADES
Nº Act. DESCRIPCIÓN ACTIVIDAD HH Totales CÓDIGO ITEMIZADO

Responsable Elaboró Revisó Aprobó

Nombre

Cargo

Fecha

Firma
DOCUMENTO Nº
FECHA:

Reporte de Actividades Diarias de Terreno


PAGINA

1 DE 1

Área:

Capataz: José Antonio Navarro Martínez Especialidad: Carpintero

REPORTE DE HORAS
HH por actividad Equipos
HH Total Dia
Item ROL Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act. Nº Equipos Utilizados

1 1

2 2

3 3

4 4

5 5

7 Resumen HH

8 CATEGORIA HH TOTAL DIA

9 CAPATAZ

10 MM

11 M1

12 M2

13 AY

OBSERVACIONES

DESCRIPCION DE ACTIVIDADES
Nº Act. DESCRIPCIÓN ACTIVIDAD HH Totales CÓDIGO ITEMIZADO

Responsable Elaboró Revisó Aprobó

Nombre

Cargo

Fecha

Firma
DOCUMENTO Nº
FECHA:

Reporte de Actividades Diarias de Terreno


PAGINA

1 DE 1

Área:

Capataz: José Antonio Barahona Vega Especialidad: Carpintero

REPORTE DE HORAS
HH por actividad Equipos
HH Total Dia
Item ROL Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act. Nº Equipos Utilizados

1 1

2 2

3 3

4 4

5 5

7 Resumen HH

8 CATEGORIA HH TOTAL DIA

9 CAPATAZ

10 MM

11 M1

12 M2

13 AY

OBSERVACIONES

DESCRIPCION DE ACTIVIDADES
Nº Act. DESCRIPCIÓN ACTIVIDAD HH Totales CÓDIGO ITEMIZADO

Responsable Elaboró Revisó Aprobó

Nombre

Cargo

Fecha

Firma
DOCUMENTO Nº
FECHA:

Reporte de Actividades Diarias de Terreno


PAGINA

1 DE 1

Área:

Capataz: Guillermo Enrique González Arancibia Especialidad: Estructura

REPORTE DE HORAS
HH por actividad Equipos
HH Total Dia
Item ROL Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act. Nº Equipos Utilizados

1 1

2 2

3 3

4 4

5 5

7 Resumen HH

8 CATEGORIA HH TOTAL DIA

9 CAPATAZ

10 MM

11 M1

12 M2

13 AY

OBSERVACIONES

DESCRIPCION DE ACTIVIDADES
Nº Act. DESCRIPCIÓN ACTIVIDAD HH Totales CÓDIGO ITEMIZADO

Responsable Elaboró Revisó Aprobó

Nombre

Cargo

Fecha

Firma
DOCUMENTO Nº
FECHA:

Reporte de Actividades Diarias de Terreno


PAGINA

1 DE 1

Área: Áreas Generales

Capataz: Bernardo Claudio Campos Fuentes Especialidad: Andamios

REPORTE DE HORAS
HH por actividad Equipos
HH Total Dia
Item ROL Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act. Nº Equipos Utilizados

1 3368 Pablo Poblete M2 1

2 3297 Cristian Rojas M1 2

3 5993 Louis Stepherson AYU 3

4 90008 Dagoberto Guzman M1 4

5 93567 Rogelio Muñoz M2 5

6 89162 Rene Zapata M1

7 95085 Jonathan Cataldo M1 Resumen HH

8 3113 Bernardo Campos F Cap CATEGORIA HH TOTAL DIA

9 CAPATAZ

10 MM

11 M1

12 M2

13 AY

OBSERVACIONES

DESCRIPCION DE ACTIVIDADES
Nº Act. DESCRIPCIÓN ACTIVIDAD HH Totales CÓDIGO ITEMIZADO

Responsable Elaboró Revisó Aprobó

Nombre

Cargo

Fecha

Firma
DOCUMENTO Nº
FECHA:

Reporte de Actividades Diarias de Terreno


PAGINA

1 DE 1

Área:

Maestro Mayor: Javier Fernando Canelo Rodriguez Especialidad: Andamios

REPORTE DE HORAS
HH por actividad Equipos
HH Total Dia
Item ROL Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act. Nº Equipos Utilizados

1 3164 Javier Canelo MM 1

2 81771 Hector Osses AYU 2

3 83717 Jorge Garrido M1 3

4 90457 Byjard Valeus M1 4

5 89089 Jairo Larenas AYU 5

7 Resumen HH

8 CATEGORIA HH TOTAL DIA

9 CAPATAZ

10 MM

11 M1

12 M2

13 AY

OBSERVACIONES

DESCRIPCION DE ACTIVIDADES
Nº Act. DESCRIPCIÓN ACTIVIDAD HH Totales CÓDIGO ITEMIZADO

Responsable Elaboró Revisó Aprobó

Nombre

Cargo

Fecha

Firma
DOCUMENTO Nº
FECHA:

Reporte de Actividades Diarias de Terreno


PAGINA

1 DE 1

Área:

Capataz: Pedro Alejo Ruiz Urrea Especialidad: Carpintero

REPORTE DE HORAS
HH por actividad Equipos
HH Total Dia
Item ROL Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act. Nº Equipos Utilizados

1 1

2 2

3 3

4 4

5 5

7 Resumen HH

8 CATEGORIA HH TOTAL DIA

9 CAPATAZ

10 MM

11 M1

12 M2

13 AY

OBSERVACIONES

DESCRIPCION DE ACTIVIDADES
Nº Act. DESCRIPCIÓN ACTIVIDAD HH Totales CÓDIGO ITEMIZADO

Responsable Elaboró Revisó Aprobó

Nombre

Cargo

Fecha

Firma
DOCUMENTO Nº
FECHA:

Reporte de Actividades Diarias de Terreno


PAGINA

1 DE 1

Área:

Capataz: Carlos Alberto Cartes Díaz Especialidad: Andamios

REPORTE DE HORAS
HH por actividad Equipos
HH Total Dia
Item ROL Trabajador Categ. Act.1 Act.2 Act.3 Act.4 Act.5 Act. Nº Equipos Utilizados

1 3150 Carlos Cartes Días Capataz 1

2 84187 Elzon Queupan M1 Andamios 2

3 83838 Patricio Huaiquivil M1 Andamios 3

4 3366 Luis Vergara M2 Andamios 4

5 3368 Pablo Poblete M2 Andamios 5

6 89162 Rene Zapata M1 Andamios

7 93569 Luis Zambrano M1 Andamios Resumen HH

8 CATEGORIA HH TOTAL DIA

9 CAPATAZ

10 MM

11 M1

12 M2

13 AY

OBSERVACIONES

DESCRIPCION DE ACTIVIDADES
Nº Act. DESCRIPCIÓN ACTIVIDAD HH Totales CÓDIGO ITEMIZADO

Responsable Elaboró Revisó Aprobó

Nombre

Cargo

Fecha

Firma