You are on page 1of 42

Digitally signed

MINAL by MINAL
SANDIP PARAB
SANDIP Date:
PARAB 2021.08.31
15:06:40 +0530

WP1366_09.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY


ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION NO.1366 OF 2009

H.I.M.S. Botawala Charities and another … Petitioners


Vs.
State of Maharashtra and others … Respondents

WITH

INTERIM APPLICATION NO.799 OF 2020


IN
WRIT PETITION NO.1366 OF 2009

Sarah Housing Development Pvt. Ltd. … Applicant

IN THE MATTER BETWEEN

H.I.M.S. Botawala Charities and another … Petitioners


Vs.
State of Maharashtra and others … Respondents

Mr. Sharan Jagtiani, Senior Advocate a/w. Ms. Surabhi Agarwal,


Mr.Kaizer Merchant and Ms. Nidhi Salian i/b. Apex Law Partners for
Petitioners.
Mr. Himanshu B. Takke, AGP for Respondent Nos.1, 2 and 7-State.
Mr. P. G. Lad a/w. Ms. Aparna Kalathil and Ms. Priyanka Naik for
Respondent Nos.3 to 6-MHADA.

CORAM : UJJAL BHUYAN &


MADHAV J. JAMDAR, JJ.
Reserved on : JULY 28, 2021
Pronounced on : AUGUST 31, 2021

JUDGMENT AND ORDER : (Per Ujjal Bhuyan, J.)

Heard Mr. Jagtiani, learned senior counsel for the petitioners;


Mr. Takke, learned AGP for respondent Nos.1, 2 and 7-State; and
Mr. Lad, learned counsel for respondent Nos.3 to 6-MHADA.

2. By filing this petition under Article 226 of the Constitution of


India, petitioners seek quashing of order dated 21.12.2006 issued by the

1/42
WP1366_09.doc

Special Land Acquisition Officer, Maharashtra Housing and Area


Development Authority, Mumbai i.e., respondent No.6 and further seeks
a direction to the respondents for release of the entire property of the
petitioners from acquisition.

3. Be it stated that vide order dated 21.12.2006, respondent No.6 in


exercise of powers conferred by sub-section (5) of section 93 of the
Maharashtra Housing and Area Development Act, 1976 (briefly “the
MHADA Act” hereinafter) sanctioned the acquisition proposal
forwarded by the Mumbai Building Repairs and Reconstruction Board
for compulsory acquisition of the land described in the schedule thereto.

4. Before adverting to the impugnment, it would be apposite to


briefly set out the relevant facts as pleaded as well as the orders passed
by this Court from time to time in the present writ proceeding.

4.1. Petitioner No.1 is a public charitable trust duly registered under


the erstwhile Bombay Public Trusts Act, 1950, having its office at
Mumbai. Petitioner No.2 is a private limited company incorporated
under the provisions of the Companies Act, 1956 and having its office at
Mumbai.

4.2. Sometime in the year 1914, petitioner No.1 by a registered deed


of conveyance had purchased the properties bearing C.S.Nos.641 and
642 of Mazgaon Division admeasuring near about 4721.60 sq.mtrs. In
that year itself, petitioner No.1 constructed certain buildings on the said
property and further constructed three other buildings on the said land in
the year 1922. Be it stated that all these structures comprised of ground
plus two floors.

4.3. Petitioners have stated that altogether six structures were


constructed on the said plot of land having municipal house
Nos.289/299, 299A, 299B, 299C, 299D and 299E. All the buildings

2/42
WP1366_09.doc

together are known as ‘Botawala Chawl’ having the address at R.


Bhogale Marg, Mazgaon, Mumbai (briefly referred to hereinafter as the
“petitioners’ property”). According to the petitioners there are about 423
occupants residing in the six buildings (petitioners have furnished a list
of such occupants / tenants which has been annexed to the writ petition).

4.4. Since all the buildings on the petitioners’ land were constructed
prior to 01.04.1940, Bombay Municipal Corporation (BMC) categorized
the said buildings as ‘A-cess category’ and issued corresponding
certificates to that effect.

4.5. On 19.08.2000, Mumbai Building Repairs and Reconstruction


Board (briefly “the Board” or alternatively “respondent No.5”
hereinafter) issued certificate in respect of building No.299A under
section 88(3) of the MHADA Act inter alia certifying that the said
building was not capable of being repaired to render it fit for habitation
within reasonable expenses and therefore the said building was not
considered for repairs under the MHADA Act. Similar certificate dated
20.06.2001 was issued by respondent No.5 in respect of building
No.299B. This was followed by another certificate dated 02.07.2003
issued by respondent No.5 under section 88(3) of the MHADA Act
regarding building No.289/299.

4.6. The 423 occupants residing in the six buildings on the petitioners’
property formed a co-operative housing society and requested petitioner
No.1 to develop the property under Development Control Regulation
(DCR) No.33(7) of the Development Control Regulations for Greater
Mumbai, 1991. It is stated that 319 occupants out of 423 occupants gave
written consent in favour of petitioner No.1 for development of the said
property which is more than 70% of the total number of occupants, thus
fulfilling one of the essential requirements of that provision.

4.7. Despite the aforesaid development, respondent Nos.3 to 5 decided

3/42
WP1366_09.doc

to acquire the petitioners’ property. In this connection, respondent No.6


issued show cause notice dated 25.05.2005 calling upon the persons
interested to show cause as to why the said properties should not be
acquired under the provisions of MHADA Act. Petitioner No.1 filed
objection before respondent No.6 on 27.06.2005. It was stated that the
chawls were very much repairable and strong enough to sustain far more
time which was supported by a certificate of the structural engineer. It
was pointed out that the tenants were opposed to the redevelopment
scheme of Maharashtra Housing and Area Development Authority (for
short “MHADA” hereinafter). It was further pointed out that in case
tenants were interested, petitioner No.1 could carry out the repairs or
reconstruction. Petitioner No.1 also stated that the list accompanying the
show cause notice contained only a part of the total number of residents
being 423. While objecting to the acquisition proceedings, petitioner
No.1 called upon respondent No.6 to afford a reasonable opportunity of
hearing and thereafter to drop the acquisition proceedings.

4.8. In the meanwhile petitioner No.1 invited tenders for sale of the
said property. Offer made by petitioner No.2 was the highest and was
accordingly accepted. Petitioner No.1 agreed to sell the said property to
petitioner No.2 on ‘as is where is basis’. In this connection, on an
application filed by petitioner No.1 the concerned Charity Commissioner
passed an order dated 31.05.2007 according sanction / allowing
petitioner No.1 to sell the said property to petitioner No.2 for an amount
of Rs.1,30,00,000.00. Following the same and upon payment of the
aforesaid amount by petitioner No.2 together with the amount covering
stamp duty and registration charges, petitioner No.1 executed deed of
conveyance dated 15.12.2007 transferring the right, title and interest in
respect of the said property in favour of petitioner No.2.

4.9. Since more than 70% of the occupants had given consent for
redevelopment through petitioner No.1, petitioners submitted proposal
on 29.03.2006 before respondent Nos.3 to 5 for issuance of no objection

4/42
WP1366_09.doc

certificate (NOC) for development of the entire property under DCR


33(7). At the time of filing the writ petition, the said proposal of the
petitioners was stated to be pending consideration before respondent
Nos.3 to 5.

4.10. It is stated that respondent No.6 vide letter dated 18.11.2006 had
informed respondent Nos.3 to 5 that more than 70% of the occupants
were objecting to the redevelopment through MHADA. He accordingly
requested the said respondents to drop the acquisition proceedings.

4.11. However, contrary to the content of the above letter respondent


No.6 issued the impugned order dated 21.12.2006 acquiring a part of the
petitioners’ property under section 93(5) of the MHADA Act.
Subsequently, the said order was published in the Government gazette.

4.12. According to the petitioners, by the impugned order dated


21.12.2006 respondent No.6 had not acquired the entire petitioners’
property; only the land and three out of the six buildings i.e., building
Nos.289/299, 299A and 299B were acquired.

4.13. Aggrieved by the issuance of the impugned order dated


21.12.2006, petitioners instituted S.C.Suit No.881 of 2007 in the City
Civil Court, Bombay for a declaration that the order dated 21.12.2006
was illegal, bad in law and, therefore, should be set aside and quashed.

4.14. It may be mentioned that respondent No.5 had time and again
addressed letters to respondent No.2 pointing out that the acquisition
order was defective in as much as three out of the six buildings on the
acquired land were not acquired. Such letters were issued on 08.03.2007,
01.06.2007 and 20.10.2007 requesting respondent No.2 to issue
corrigendum. Again on 28.11.2007 respondent No.5 wrote to respondent
No.2 stating that proper notice was required to be given to all the tenants
for acquisition which could not be done as only three out of the six

5/42
WP1366_09.doc

buildings were acquired. Therefore corrigendum was required to be


issued.

4.15. It may be mentioned that petitioners under legal advice that


challenge to the acquisition proceedings may not be maintainable in the
City Civil Court sought leave to withdraw the suit. City Civil Court vide
order dated 23.11.2007 was pleased to grant leave to the petitioners to
withdraw S.C.Suit No.881 of 2007 and to file fresh proceedings subject
to limitation.

4.16. Thereafter, the present writ petition came to be filed seeking the
reliefs as indicated above.

5. On behalf of respondent Nos.3 to 5, a reply affidavit was filed by


Mr. Pralhad Pandurang Mahishi, Deputy Engineer on 26.03.2010. Stand
taken in the affidavit is that there is delay and laches in filing the writ
petition. The suit was withdrawn by the petitioners on 23.11.2007 with
liberty to file a fresh suit subject to limitation. Instead of filing a fresh
suit, petitioners filed the present writ petition belatedly on 06.07.2009.
Reason given for the delay is not at all convincing.

5.1. It is stated that the lands bearing C.S.Nos.641 and 642 were
acquired by MHADA on 21.12.2006 by virtue of the impugned
notification issued under section 93(5) of the MHADA Act. On and from
the date of publication of the said notification in the official gazette the
said lands stood vested absolutely with respondent No.3 free from all
encumbrances. Under DCR 33(9), respondent Nos.3 to 5 are empowered
to carry out reconstruction of cessed buildings.

5.2. Reference has been made to a decision of this Court reported in


2002 (5) BCR 653 to the effect that redevelopment of the acquired
property be carried out by MHADA alone. When the matter was carried
to the Supreme Court, State Government filed an affidavit requesting

6/42
WP1366_09.doc

that appropriate guidelines may be laid down for the purpose of


implementation of redevelopment scheme by availing floor space index
(FSI) in accordance with DCR 33(9). Supreme Court vide order dated
07.03.2003 approved the scheme in respect of redevelopment, setting
aside the order passed by this Court.

5.3. Pending Government’s decision to frame guidelines MHADA in


principle issued letters of intent in respect of acquired properties for the
purpose of undertaking redevelopment in joint venture. Petitioners too
had applied for redevelopment in joint venture with MHADA for
redevelopment of the property. In this connection, letter of intent came
to be issued to the petitioners on 10.08.2007.

5.4. However, it is stated that DCR 33(9) was amended with effect
from 02.03.2009. Following the same petitioners made an application to
the High Power Committee constituted thereunder for obtaining NOC
for redevelopment of the property. It is stated that Housing Department
had approved the said proposal in principle and thereafter forwarded the
same to the Urban Development Department.

5.5. According to the deponent land measuring about 4000 sq.mtrs.


acquired under the MHADA Act empowered respondent No.3 to carry
out redevelopment under the amended DCR 33(9) in joint venture. It is
contended that on and from 21.12.2006, the acquired land and buildings
stood vested with respondent Nos.3 to 5. Notwithstanding the same,
petitioner No.1 entered into agreement for sale of the acquired land with
petitioner No.2. Post acquisition such agreement for sale is void ab
initio.

5.6. On or about 20.06.2009 petitioners had submitted proposal to


respondent No.5 through their architect for redevelopment of the said
plot under the amended DCR 33(9). Said proposal was also earlier
submitted by the petitioners pursuant to notice issued by the

7/42
WP1366_09.doc

Government of Maharashtra on 19.05.2009 proposing to amend DCR


33(7) whereby the acquired properties were permitted to be redeveloped
in joint venture with MHADA.

5.7. In the circumstances, it is contended that petitioners had


acquiesced to the acquisition of the land covered by C.S.Nos.641 and
642. Therefore, they are estopped from challenging the legality and
validity of the acquisition proceedings.

5.8. Respondents have further contended that the acquisition made is


legal and valid. It is for a public purpose. Question of setting aside the
acquisition and restoring the acquired land and buildings back to the
petitioners does not arise.

6. This Court by order dated 19.03.2010 directed the parties to


maintain status-quo. Thereafter vide order dated 19.07.2010 as corrected
on 02.08.2010 this Court admitted the writ petition for hearing by
issuing Rule. Petitioners were permitted to carry on joint development of
the property as per sanction given by the High Power Committee under
DCR 33(9) subject to the approval that might be granted by the State
Government and further subject to the condition that within a period of
eight weeks from the approval of the Government petitioners would
deposit in the Court the amount payable as per DCR 33(9). This Court
directed that on payment being made by the petitioners, the same should
be kept in fixed deposit by the Registry in a nationalized bank to the
credit of the petition. This Court also directed that upon grant of
approval by the government within a period of two weeks, MHADA and
/ or the Competent Authority should inform the petitioners about the
amount of premium to be paid whereafter petitioners should deposit the
same in the Court within a period of six weeks thereafter.

6.1. On 02.11.2012, learned AGP informed the Court that Government


of Maharashtra had approved the proposal on 06.01.2012 whereafter a

8/42
WP1366_09.doc

letter was addressed by MHADA to the architect of the petitioners on


19.04.2012 calling upon the petitioners to deposit an amount of
Rs.3,96,61,760.00. When learned AGP raised the objection that the
aforesaid amount was required to be deposited by the petitioners within
six weeks of communication which period had expired, the order records
that learned counsel for the petitioners had stated that the aforesaid
amount would be deposited within three weeks with the observation that
liability of the petitioners to pay interest, if any, for the delayed payment
would be decided at the time of hearing.

6.2. On 23.11.2012, Court was informed that petitioners had already


deposited an amount of Rs.2,00,00,000.00 out of Rs.3,96,61,760.00
within time. Petitioners were given liberty to deposit the remaining
amount within two weeks. It was clarified that such deposits were
without prejudice to the rights and contentions of the respondents.

6.3. Petitioners informed this Court on 14.12.2012 that the balance


amount of Rs.1,96,61,760.00 was already deposited on 07.12.2012.

6.4. By order dated 13.08.2019 corrected on 03.09.2019, petitioner


No.2 was permitted to withdraw a sum of Rs.2,00,00,000.00 within two
weeks. Petitioner No.2 was further given liberty to withdraw the balance
amount of Rs.1,96,61,760.00 after construction of both the rehabilitation
buildings. It was clarified that the withdrawals would be subject to
written undertaking of petitioner No.2 that in the event the Court so
orders, petitioner No.2 would re-deposit the withdrawn amount.

6.5. On an interim application filed by the State objecting to the


permission granted to the petitioners for withdrawal of the deposited
amount, learned counsel for the petitioners informed the Court on
10.12.2020 that petitioners would redeposit Rs.2,00,00,000.00 in two
installments; first installment of Rs.50,00,000.00 on or before
14.12.2020 and second installment of Rs.1,50,00,000.00 within six

9/42
WP1366_09.doc

weeks. This was accepted by the Court and petitioners were permitted to
redeposit the withdrawn amount. On the aforesaid basis, the interim
application filed by the State was disposed of.

7. Petitioner No.2 filed Interim Application No.799 of 2020 seeking


a declaration that the impugned order dated 21.12.2006 is bad in law
and, therefore, should be set aside and quashed. Further prayer made is
for a direction to the respondents to release petitioners’ property from
acquisition.

7.1. It is stated that after filing of the writ petition and after
amendment of the same, additional relief was sought for seeking
approval for redevelopment of the petitioners’ property under the
provisions of DCR 33(9). As the proposal submitted by the petitioners
was accepted by the High Power Committee in principle in its meeting
held on 28.07.2009, this Court upon consideration of the provisions of
DCR 33(9) passed order dated 19.07.2010 (corrected by order dated
02.08.2010) permitting the petitioners to undertake redevelopment of the
property in joint venture with MHADA on deposit of the amount to be
determined by MHADA. When MHADA determined the amount to be
paid by the petitioners at Rs.3,96,61,760.00, the same was deposited by
the petitioners before this Court in two tranches on 22.11.2012 and
07.12.2012. The amount so deposited was invested in fixed deposit by
the Prothonotary and Senior Master of the Court.

7.2. Thereafter petitioners pursued the matter of redevelopment with


the High Power Committee under DCR 33(9). High Power Committee
sanctioned the scheme of redevelopment following which Municipal
Corporation of Greater Mumbai (MCGM) issued letter of intent dated
14.01.2013 in favour of the applicant / petitioner No.2. In terms of
condition No.35 of the said letter of intent, a joint venture agreement
dated 10.03.2014 was executed between petitioner No.2 and Mumbai
Building Repairs and Reconstruction Board, already referred to as the

10/42
WP1366_09.doc

“Board” hereinbefore. This was followed by scrutiny and verification of


tenants / occupants whereafter the list of certified / verified tenants was
published in newspaper on 19.06.2015. Following scrutiny and
verification of the list of tenants / occupants, Board issued NOC for
redevelopment of the petitioners’ property under DCR 33(9) on
22.09.2015. Upon receipt of such NOC, petitioner No.2 submitted plans
for approval before the MCGM which granted intimation of disapproval
dated 02.01.2017 approving the plans submitted by petitioner No.2
whereafter petitioner No.2 received first commencement certificate on
29.04.2017.

7.3. It is stated that in view of change in the policy under DCR 33(9),
Board and petitioner No.2 executed supplementary agreement on
24.07.2017 whereby certain terms of the original agreement were
modified. In view of above, petitioner No.2 applied for modification of
the NOC dated 22.09.2015 whereafter the Board issued revised NOC
dated 13.06.2018.

7.4. According to petitioner No.2 construction of the rehabilitation


buildings had already commenced. All the 422 (sic) tenants have been
re-accommodated by the petitioners at their cost in temporary transit
camps or have been provided transit rents. The transit camps have been
taken on lease from MHADA in New Hind Mills Compound, Cotton
Greens, Mumbai. Construction activity is going on in full swing in the
petitioners’ property. Seven slabs of car parking had been constructed;
further twenty slabs of the rehabilitation wing and twelve slabs of the
sale wing were constructed at the time of filing the interim application.
Petitioners had executed nearly 301 permanent alternate accommodation
agreements with tenants / occupants. Execution of permanent alternate
accommodation agreements with the remaining tenants / occupants was
in progress.

7.5. Thus petitioners have contended that the objective of the

11/42
WP1366_09.doc

respondents of providing alternate accommodation to the tenants /


occupants on the petitioners’ property has been fulfilled. It is in the
above circumstances that the interim application has been filed seeking
the reliefs as indicated above.

8. Respondent Nos.1 and 2 filed reply affidavit on 08.10.2020


opposing the said interim application. Respondent Nos.1 and 2 have
stated that petitioners cannot approbate and reprobate at the same time.
Petitioners cannot be permitted to derive benefits and incentives under
DCR 33(9) which is applicable only in respect of acquired properties
under the MHADA Act admeasuring more than 4000 sq.mtrs. and at the
same time continuing the challenge to the acquisition proceedings.

9. Respondent Nos.3, 4 and 5 in their reply affidavit to the interim


application filed on 13.03.2020 have stated that the reason for
petitioners’ withdrawing the suit and filing the writ petition was the
change in DCR 33(9) as per which under the urban renewal scheme
cluster redevelopment would be applicable to properties admeasuring
more than 4000 sq.mtrs. It is stated that attention of the Court was drawn
to letter dated 20.06.2009 of MHADA which recorded that it would be
in the interest of all the parties to carry out redevelopment on petitioners’
property jointly under DCR 33(9). By order dated 19.07.2010 as
corrected on 02.08.2010 this Court permitted the petitioners to undertake
redevelopment in joint venture with MHADA on deposit of the amount
determined by MHADA in this Court. Rs.3,96,61,440.00 was the
amount quantified by respondent No.3 and intimated to the petitioners
which amount was thereafter deposited by the petitioners before this
Court.

9.1. The said respondents thereafter referred to the developments


leading to issuance of letter of intent and execution of joint venture
agreement which was followed by issuance of NOC by respondent No.3
for redevelopment of petitioners’ property under DCR 33(9). Upon

12/42
WP1366_09.doc

modification in the scheme of redevelopment in view of amendment in


DCR 33(9) a supplementary agreement was executed which was
followed by issuance of revised NOC by respondent No.3.

9.2. They have admitted that petitioners have taken on lease from
respondent No.3 rooms at New Hind Mills Compound for the purpose of
transit accommodation of the tenants / occupants. All the 422 (sic)
tenants have been either provided alternate accommodation or are being
paid rent in lieu thereof. It is also acknowledged that none of the
tenants / occupants have complained against the petitioners regarding
transit accommodation or rent.

9.3. It is also stated that during the course of the acquisition


proceedings and in the course of the events subsequent thereto
respondent No.3 had made correspondence with respondent No.6 to
issue corrigendum reducing the land area mentioned in the initial notice
as well as in the impugned order dated 21.12.2006 from 4721.60
sq.mtrs. to 2140 sq.mtrs., covering only the three acquired buildings and
the land thereunder. However, no steps were taken by respondent No.6
in this regard.

9.4. According to respondent Nos.3, 4 and 5, objective of the


acquisition proceedings carried out under sections 92 and 93 of the
MHADA Act was to acquire the property for the purpose of
redevelopment and re-accommodation of the tenants. However before
possession of the petitioners’ property could be taken over by respondent
No.3 for redevelopment, petitioners submitted a scheme to the High
Power Committee to undertake redevelopment under DCR 33(9). This
Court also permitted redevelopment in joint venture between petitioners
and respondent No.3. Thus the objective and purpose of redevelopment
and obligations of MHADA and Board on account of redevelopment
have been taken over by petitioners. It is stated that MHADA / Board
would have had to provide transit accommodation to 422 (sic) tenants
and also would have had to construct buildings at their cost for re-

13/42
WP1366_09.doc

accommodating 422 (sic) tenants in permanent alternate accommodation


on ownership basis. The entire responsibility has now been fulfilled by
the petitioners.

9.5. Finally, respondent Nos.3, 4 and 5 have stated that construction


activity on the petitioners’ property is going on in full swing. Petitioners
have not defaulted on any conditions of redevelopment.

10. Respondent Nos.1 and 2 have also filed reply affidavit to the writ
petition very recently on 18.02.2021 through Ramchandra K.
Dhanawade, Deputy Secretary to Government of Maharashtra in the
Housing Department. At the outset it is stated that the writ petition
involves disputed questions of fact and contractual obligations of the
petitioners. Therefore, this Court may not entertain the writ petition
under Article 226 of the Constitution of India. It is further stated that the
reliefs sought for in the writ petition have been rendered infructuous in
as much as petitioners had sought to redevelop the property under DCR
33(7) vide proposal dated 29.03.2006. However, they undertook the
redevelopment under DCR 33(9). Thus it is contended that petitioners
have acquiesced to the acquisition of the property and taken benefits
under DCR 33(9) which pertains to the acquired property. In view of
such acquiescence, petitioners are estopped from pursuing the writ
petition. In any view of the matter since approval sought for by the
petitioners for redevelopment of the property has been granted by the
Government, the writ petition does not survive.

10.1. It is stated that out of the six buildings standing on the petitioners’
property, building Nos.289/299, 299A and 299B were declared as being
beyond economic repairs under section 88(3)(a) of the MHADA Act.
Building Nos.299A and 299B were demolished by respondent No.5.
Tenants / occupants of the said two buildings were shifted by respondent
No.5 to transit camps. Building No.289/299 is adjacent to Rambhau
Bhogale Marg. Access to the remaining five buildings was through

14/42
WP1366_09.doc

building No.289/299. Accordingly, respondent No.5 prepared composite


layout of all the six buildings which was approved by the MCGM on
02.09.2002. The composite redevelopment scheme would not be
possible without including building Nos.299C, 299D and 299E in the
composite redevelopment scheme.

10.2. On 21.12.2006, respondent No.6 issued notification under section


93(5) of the MHADA Act acquiring petitioners’ property. Upon
publication of the said notification petitioners’ property stood vested in
respondent No.5.

10.3. Government of Maharashtra in the Urban Development


Department amended DCR 33(9) on 02.03.2009 for implementing the
urban renewal scheme. It is stated that for implementation of such
scheme, minimum plot area should be 4000 sq.mtrs.

10.4. Petitioners submitted proposal to the Government for cluster


redevelopment under amended DCR 33(9) on 12.06.2009. Since the
petitioners’ land stood vested with respondent No.5 upon acquisition on
21.12.2006, petitioners could undertake cluster redevelopment under
urban renewal scheme only in joint venture with respondent No.3 in
terms of DCR 33(9). Further, the area of petitioners’ acquired property
was 4721.60 sq.mtrs. It is thus contended that petitioners’ undertook
redevelopment scheme under DCR 33(9) in respect of the petitioners’
property to obtain the benefits thereunder.

10.5. On 28.07.2009, the High Power Committee approved petitioners’


proposal under DCR 33(9).

10.6. Respondent Nos.1 and 2 have contended that right from the
beginning petitioners were fully aware of the fact that redevelopment
scheme under DCR 33(9) was undertaken by them on the petitioners’
property since acquired and thereafter belonging to respondent No.5 in

15/42
WP1366_09.doc

joint venture.

10.7. Reference has been made to letter of intent dated 04.07.2013


issued by the MCGM to petitioner No.2 in respect of the joint venture
cluster redevelopment upon grant of approval by the Government.
Clause 2 of the said letter of intent clearly stated that owner of the
property is MHADA and hence land premium or built up area to be
surrendered in lieu of land cost would be as decided by MHADA,
besides reimbursing expenditure incurred by the Board towards
structural repairs, demolition etc. before issue of commencement
certificate.

10.8. Petitioners undertook redevelopment under DCR 33(9) without


any demur qua clause 2 of the letter of intent as well as knowing fully
well that such redevelopment was possible in joint venture only upon
acquisition and thus there was acknowledgment that the property stood
vested with respondent No.5. This position became more clear upon
amendment of DCR 33(9) which made it clear that redevelopment was
to be undertaken only upon acquired lands. Petitioners having accepted
such condition and having bound themselves with the same, now stand
estopped from challenging the acquisition. Petitioners by their own
conduct have acquiesced to the acquisition of the land by undertaking
redevelopment under DCR 33(9).

10.9. Answering respondents have denied that there were flaws in the
acquisition process. However, while not admitting any such flaws as
alleged it is contended that even if flaws were there in the acquisition
process those would be deemed to have been waived by the petitioners
by undertaking redevelopment scheme under DCR 33(9). Prior to
acquisition, hearing notices were issued to the petitioners. Those who
had attended the hearing were personally heard. Thus, due process was
followed. Therefore, impugned notification dated 21.12.2006 is legal
and valid.

16/42
WP1366_09.doc

10.10. It is contended that merely because proposal was submitted


by the petitioners for redevelopment under DCR 33(7), respondent No.5
was not precluded from acquiring the petitioners’ property under section
93(5). However, the said grievance of the petitioners no longer survives
as petitioners have been permitted to undertake redevelopment under
DCR 33(9). MHADA Act does not contemplate obtaining consent of
tenants / occupants for respondent No.5 to acquire property.

10.11. In the above context, respondent Nos.1 and 2 submitted


that no case is made out by the petitioners for this Court to exercise its
extra ordinary jurisdiction under Article 226 of the Constitution of India.
Accordingly, the writ petition is liable to be dismissed with cost.

11. Mr. Sharan Jagtiani, learned senior counsel for the petitioners at
the outset submits that the impugned order dated 21.12.2006 suffers
from fundamental errors rendering the same null and void. He submits
that the total land area of petitioners’ property would be approximately
4721.60 sq.mtrs. with six structures standing thereon. However, only
three of the structures bearing Nos.289/299, 299A and 299B were
acquired along with the land leaving out the other three structures
bearing municipal house Nos.299C, 299D and 299E. In other words,
though the land was acquired, all the structures standing thereon were
not acquired. Resultantly, the tenants / occupants of the remaining three
buildings were not given notice and were not heard prior to acquisition.
This was brought to the notice of MHADA by its various authorities
including respondent No.6 requesting MHADA to issue necessary
corrigendum to rectify the defect in the acquisition process. But that was
not done. For lack of completeness as well as for denial of opportunity
of hearing to the tenants / occupants of the three left out structures, the
acquisition process stood vitiated. Thus there is clear violation of the
principles of natural justice and fair procedure. Therefore, the impugned
order cannot be sustained and should be declared as void.

17/42
WP1366_09.doc

11.1. Mr. Jagtiani’s further contention is that more than 70% of the
tenants / occupants of the six structures had objected to development
through MHADA. They wanted petitioners to develop the property.
Initially petitioners had submitted proposal prior to issuance of the
impugned order before respondent Nos.3 to 5 seeking permission for
development of the property under DCR 33(7). He submits that when
DCR 33(9) was amended, petitioners submitted proposal to respondent
No.5 for redevelopment under the amended DCR 33(9).

11.2. Mr. Jagtiani, learned senior counsel has referred to order of this
Court dated 19.07.2010 as corrected on 02.08.2010 and submits that
after admission of the writ petition, petitioners were permitted to carry
out joint development as per sanction given by High Power Committee
under DCR 33(9). He submits that after approval was granted by the
State Government and the amount of premium to be deposited by the
petitioners was quantified, petitioners deposited total amount of
Rs.3,96,61,760.00 in two tranches on 22.11.2012 and 07.12.2012. After
receipt of NOC and letter of intent from the competent authorities,
petitioners commenced construction of the rehabilitation buildings.
Regarding the status of construction as on 22.07.2021, he submits that
nine commercial tenants of ground floor have already been handed over
possession; in so far ‘A’ Wing (rehabilitation building) of 35 floors is
concerned, construction of all 35 floors is complete. Petitioners are in a
position to handover possession of the completed floors as soon as it
receives occupancy certificate. Regarding ‘B’ Wing (rehabilitation
building), out of 35 floors, slab cast has been done upto 8 th floor; as
regards the ‘C’ Wing (sale wing) is concerned, out of total 45 floors
already 28 floors have been completed. He submits that construction is
in progress on day to day basis and petitioners would be in a position to
complete construction shortly.

11.3. In the circumstances, learned counsel for the petitioners submits

18/42
WP1366_09.doc

that having regard to the subsequent developments leading to


rehabilitation of the tenants / occupants, the very purpose and object
behind acquisition of the petitioners’ property vide impugned order dated
21.12.2006 has been achieved. Therefore, what remains is only the
formality of completion of construction by the petitioners. He submits
that the impugned order dated 21.12.2006 having lost its force and effect
should be declared as redundant and consequently should be set aside.

11.4. Learned senior counsel for the petitioners have filed a compilation
of case laws to support his submissions. In so far acquisition under
MHADA Act is concerned, he has placed reliance on a Division Bench
decision of this Court in Bhalchandra Datey Vs. State of Maharashtra,
2012 (2) Mh.L.J. 543. Relying upon this judgment he submits that in
the said case Court had set aside the acquisition of the property after the
Court found that the tenants for whose benefit the property was acquired
did not want the acquisition. He further submits that this Court observed
that no useful purpose would be served by continuing the property under
acquisition because the property was being acquired basically for the
benefit of the tenants who did not want such acquisition or that the
purpose for which acquisition was sought for had been achieved
otherwise.

11.5. In support of his submissions that the impugned acquisition


proceedings suffers from violation of the principles of natural justice and
that principles of natural justice would have to be followed in such
decision making, he has placed reliance on the decision of the Supreme
Court in Maneka Gandhi Vs. Union of India, (1978) 1 SCC 248 and a
Division Bench decision of this Court in Harakchand Misrimal Solanki
Vs. Collector, (2008) SCC Online Bom.1067.

12. Mr. Takke, learned AGP for respondent Nos.1, 2 and 7 has
referred to the orders passed by this Court and submits that there is clear
acquiescence on the part of the petitioners to redevelopment of the

19/42
WP1366_09.doc

property in joint venture with MHADA under DCR 33(9). He has


referred to the memorandum of understanding dated 20.09.2006 entered
into between petitioner Nos.1 and 2 and submits that clause 2 of the said
agreement would clearly reveal full knowledge of the petitioners about
acquisition of the property by MHADA for redevelopment of the
existing structures. His submission is that it was for a public purpose i.e.,
rehabilitation of the tenants that the property was acquired for
redevelopment. Redevelopment of the property presently is underway
under the amended DCR 33(9) which would indicate that petitioners
have accepted ownership of the land and property by MHADA through
acquisition. In such circumstances, it is not open to the petitioners to
pursue the challenge to the impugned order dated 21.12.2006.

13. Supporting Mr. Takke, Mr. Lad, learned counsel appearing for
MHADA submits that as a matter of fact following the turn of events
after this Court’s order dated 19.07.2010 as corrected on 02.08.2010,
nothing survives in the writ petition. Though the writ petition was filed
challenging the order of acquisition dated 21.12.2006, at the intervention
of the Court petitioners have accepted joint redevelopment with
MHADA under amended DCR 33(9). Mr. Lad has referred to various
provisions of the MHADA Act and submits that acquisition under the
MHADA Act is different. In the course of his submissions, Mr. Lad also
raised a technical objection regarding belated filing of the writ petition
after withdrawal of the suit which cast aspersions on the bonafides of the
petitioners. Reverting back to the arrangement or course of action
directed by this Court vide order dated 19.07.2010 as corrected on
02.08.2010, he submits that redevelopment of the property under DCR
33(9) is not an interim arrangement. Such a course of action by its very
nature has attained finality. All that remains is payment of premium by
the petitioners to MHADA.

14. In his reply submissions, Mr. Jagtiani, learned senior counsel for
the petitioners strongly refuted the contention that there was

20/42
WP1366_09.doc

acquiescence to the acquisition by the petitioners and that the


arrangement suggested by the Court vide order dated 19.07.2010 as
corrected on 02.08.2010 is a final arrangement. His submission is that
when Rule was issued it would mean that all contentions raised by the
petitioners in the writ petition were admitted for final hearing and,
therefore, the course of action suggested by the Court in the order dated
19.07.2010 as corrected on 02.08.2010 cannot but be an interim
arrangement. He has referred to various documents on record to contend
that the course of action suggested by the Court and all subsequent
events were subject to outcome of the present writ proceeding.
Therefore, question of acquiescence does not arise. Challenge to the
impugned order of acquisition remains and the same is required to be
decided on its own merit. On a query by the Court he submits that if the
acquisition fails, the consequence would be that the petitioners would
not be required to pay premium to MHADA since it would be construed
that petitioners had carried out redevelopment on their own land.

14.1. In support of his contentions that there was no acquiescence or


waiver on the part of the petitioners, learned counsel has relied upon the
following decisions:-
1. M/s. Power Control Appliances Vs. Sumeet Machines
Private Limited, (1994) 2 SCC 488;
2. Emcure Pharmaceuticals Limited Vs. Corona Remedies Private
Limited, 2014 SCC OnLine Bom 1064; and
3. Kalpraj Dharamshi Vs. Kotak Investment Advisors Limited,
2021 SCC OnLine SC 204.

15. Submissions made by learned counsel for the parties have


received the due consideration of the Court.

16. At the outset we may advert to the stand taken by MHADA and
its authorities i.e., respondent Nos.3, 4 and 5 in the reply affidavit filed
to the interim application of the petitioners. This is because this affidavit

21/42
WP1366_09.doc

reflects the stand of the said respondents as recent as on 13.03.2020.


After acknowledging that petitioners had taken on lease rooms from
MHADA at New Hind Mills Compound for the purpose of transit
accommodation of the tenants, it is stated that all the tenants have either
been provided alternate accommodation or are being paid rent in lieu
thereof by the petitioners. None of the tenants / occupants have
complained against the petitioners regarding transit accommodation or
rent. As to the acquisition proceedings, it is stated that respondent No.3
had exchanged correspondence with respondent No.6 to issue
corrigendum to reduce the area of the land mentioned in the initial notice
and the impugned order dated 21.12.2006 from 4721.60 sq.mtrs. to 2140
sq.mtrs. However, no steps were taken by respondent No.6 in this
regard.

16.1. Proceeding further respondent Nos.3, 4 and 5 have admitted that


the objective of the acquisition proceedings was to acquire the property
for the purpose of redevelopment and re-accommodation of the tenants.
But before possession of the property could be taken over by respondent
No.3, petitioners submitted scheme to the High Power Committee for
redevelopment under DCR 33(9) which was permitted by this Court to
be carried out jointly with respondent No.3. In the circumstances, the
said respondents have fairly admitted that the objective and purpose of
redevelopment and obligations of MHADA / Board arising from such
redevelopment have been taken over by the petitioners and all the
responsibilities have been fulfilled by the petitioners including providing
transit accommodation to the tenants and constructing buildings at their
cost for the purpose of re-accommodating all the tenants. Paragraph 13
of the reply affidavit of respondent Nos.3, 4 and 5 to the interim
application of the petitioners is relevant and the same is extracted
hereunder:-
“13. I further say that it is true that acquisition proceedings
had been initiated under section 92 read with 93 of the
MHADA Act at the instance of the tenants / occupants of the
suit property since the previous landlord had failed to keep the

22/42
WP1366_09.doc

building on the suit property in tenantable repairs and habitable


conditions. The entire objective of the acquisition proceedings
under section 92 read with 93 of the MHADA Act is to acquire
the property for the purpose of redevelopment and re-
accommodation of the tenants. However, in the present case,
before the possession of the property could be taken by
respondent No.3 for the purpose of redevelopment, the
applicants submitted a scheme to the High Power Committee
set up under Regulation 33(9) of DCR 1991 to undertake the
redevelopment work of the suit property. This Hon’ble Court
also permitted redevelopment of the suit property in terms of
joint venture between respondent No.3 and the applicants. The
objective and purpose of redevelopment and obligations of
MHADA / MBRRB arising from such redevelopment have
been taken over by the applicants. MHADA / MBRRB would
have had to provide 422 tenants transit accommodation and
also construct buildings at its costs for the purpose of re-
accommodating 422 tenants in permanent alternate
accommodation on ownership basis. The entire responsibility
has been fulfilled by the applicants.”

16.2. The said respondents have also admitted that construction activity
on the petitioners’ property is being carried out in full swing. Petitioners
have not defaulted on any conditions of redevelopment.

17. In view of the fair stand taken by respondent Nos.3, 4 and 5 in


their reply affidavit to the interim application of the petitioners, the writ
petition can be disposed of accordingly. However, since petitioners have
pursued the challenge to the acquisition proceedings and since
respondent Nos.1 and 2 and at the hearing learned counsel for
respondent Nos.3, 4 and 5 as well have taken the stand that there is
acquiescence by the petitioners to the acquisition proceedings in view of
their opting for redevelopment under DCR 33(9), we are of the view that
we should also deal with the above two aspects. But before proceeding
further it would be apposite to deal with the relevant legal provisions.

18. The Maharashtra Housing and Area Development Act, 1976,


already referred to as the ‘MHADA Act’ hereinabove, is an act to unify,
consolidate and amend the laws relating to housing, repairing and
reconstructing dangerous buildings and carrying out improvement works

23/42
WP1366_09.doc

in slum areas. The objective behind enactment of the MHADA Act has
been explained in section 1A by declaring that MHADA Act is for
giving effect to the policy of the state towards securing the principle
specified in Article 39(b) of the Constitution of India and for execution
of proposals, plans or projects therefor and acquisition of the lands and
buildings and transferring the lands, buildings or tenements therein to
the needy persons and the co-operative societies of occupiers of such
lands or buildings.

18.1. Various words and expressions used in the MHADA Act are
defined in section 2. As per section 2(3), ‘authority’ has been defined to
mean the Maharashtra Housing and Area Development Authority
(MHADA) established under section 3. ‘Board’ has been defined under
section 2(6) to mean a Board established under section 18. Section 18
deals with establishment of Boards. Clause (c) says that the state
government shall by notification in the official gazette establish two
Boards for carrying out the activities of repairs and reconstruction and
slum improvement having the area of jurisdiction in the districts as
shown against each of them. Amongst the two Boards established the
one relevant for the present purpose is the Mumbai Repairs and
Reconstruction Board, already referred to as the ‘Board’ hereinabove for
the city of Mumbai.

18.2. Going back to the definitions, we find that under section 2(7)
building for the purpose of Chapter VIII has been defined to mean
building in respect of which cess is levied under that chapter and
includes a tenement let or intended to be let or occupied separately and a
house, out-house, stable, shed, hut and every other such structure but
does not include unauthorized or temporary building or structure.
Section 2(13) defines ‘development’ to mean carrying out of building,
engineering, mining or other operations in or over or under any land or
the making of any material change in any building or land and includes
redevelopment and lay out and sub-division of any land and also the

24/42
WP1366_09.doc

provision of amenities. Amongst existing boards mentioned in section


2(14) is included the Bombay Building Repairs and Reconstruction
Board constituted under the Bombay Building Repairs and
Reconstruction Board Act, 1969.

18.3. ‘Land’ has been defined in section 2(16) as including open sites
and land which is being built upon or is already built upon, benefits to
arise out of land and things attached to the earth or permanently fastened
to anything attached to the earth and also includes land under sea, creek,
river, lake or any other water.

19. Chapter VIII of the MHADA Act comprising of sections 74 to 103


deals with repairs and reconstruction of dilapidated buildings. Section 74
says that the Mumbai Repairs and Reconstruction Board established
under section 18 of the MHADA Act shall be the Board for carrying out
the purposes of Chapter VIII. However, section 75 clarifies that the
Board shall exercise its powers and perform its duties and functions
under Chapter VIII subject to the superintendence, direction and control
of MHADA. Section 76 lays down the duties of the Board relating to
repairs and reconstruction of dilapidated buildings.

19.1. Section 88 deals with the power of the Board to undertake


structural repairs to buildings which are in ruinous condition and likely
to deteriorate and fall. As per sub-section (1) which is subject to other
provisions of Chapter VIII, where the Board on consideration of
information given by the Municipal Commissioner or on a report of its
authorized officer or on other information in its possession, is satisfied
that any building, which is occupied by persons, is in such ruinous or
dangerous condition, that it is imminently likely to fall unless structural
repairs are urgently done which will render it fit and safe for habitation,
then in such cases the Board shall undertake such repairs subject to
provisions of sub-section (3). As per sub-section (2), the Board may
prepare a list of such buildings in order of priority or urgency. Under

25/42
WP1366_09.doc

sub-section (3), if the Board is of the opinion that, (a) the cost of
structural repairs to a building per square meter will exceed such amount
as may be specified by the State Government by notification in the
official gazette to be the structural repairs cost per square meter, or (b)
the cost of structural repairs to a building per square meter will exceed
the amount specified under clause (a) but the size of the land on which
such building is standing is such that for some reason or the other it
would not be possible or economical to erect any new building thereon
and there is an adjoining building but the cost of structural repairs to
such building per square meter does not exceed the amount specified
under clause (a), then in such cases falling under both the clauses, the
Board may not consider such building or buildings for repairs and
instead may issue a certificate to that effect to the owner thereof, fix a
copy of the relevant certificate in some conspicuous part of the building
or buildings for the information of the occupiers and proceed to take
action as provided in Chapter VIII. As per the first proviso, in cases of
special hardship, the Board may consider a building for structural repairs
even if the cost of such repairs is likely to exceed the limits specified. As
per the second proviso, where the occupiers of the building undertake
that they shall bear the cost of such repairs which are in excess of the
amounts specified under clause (a) and abide by such terms and
conditions for payment of the excess cost to the Board, the Board may
carry out structural repairs to such building.

19.2. The procedure to be undertaken before carrying out structural


repairs is laid down in section 89. Section 90 deals with temporary
accommodation pending structural repairs.

19.3. Submission of proposal for acquisition is dealt with in section 92.


As per sub-section (1), if in respect of any building the Board has issued
a certificate under sub-section (3) of section 88 or the Municipal
Commissioner under section 354 of the Mumbai Municipal Corporation
Act, 1888 has issued a written notice requiring the owner or occupier

26/42
WP1366_09.doc

thereof to pull down the building with a view to preventing all causes of
danger therefrom and the Board is of the opinion that such building is
not capable of being repaired or rendered fit for habitation at reasonable
expense and is dangerous or injurious to the health or safety of the
inhabitants thereof or where the Mumbai Corporation under section 354-
R of the Mumbai Municipal Corporation Act, 1888 has passed a
resolution declaring the area in which any such building is situated as
the clearance area, the Board may submit to the State Government a
proposal to acquire the land including a proposal for issue of a clearance
and compulsory acquisition order to clear and acquire the land with the
existing building in whatever condition and for constructing a new
building on the same site and simultaneously prepare plans and
estimates for the same. As per sub-section (2) in preparing the plans and
estimates of the building to be reconstructed, it shall be the duty of the
Board to see that all the occupiers in the building proposed to be
demolished shall as far as practicable be provided in the reconstructed
building accommodation with a floor area equivalent to their floor area
in the old building.

19.4. Pausing here for a moment, from a conjoint reading of sub-


sections (1) and (2) of section 92, we find that the proposal to acquire
the land which is to be submitted by the Board to the State Government
should include the land with the existing building thereon in whatever
condition and for constructing a new building on the same site. While
preparing the plan and estimate, the Board shall see to it that all the
occupiers in the building proposed to be demolished are provided
accommodation with equivalent floor area in the reconstructed building
as far as practicable. Thus sub-section (1) of section 92 read with section
2(16), which defines land, would go to show that acquisition of land has
to be with the existing building standing thereon in whatever condition.

19.5. Section 93 deals with clearance and compulsory acquisition. This


section being relevant is quoted in its entirety:-

27/42
WP1366_09.doc

“ 93. Clearance and compulsory acquisition.- (1)


Notwithstanding anything contained in the Corporation Act, if
on receipt of an acquisition proposal under section 92, the
State Government is satisfied about the reasonableness of the
proposal and of the resources available with the Board for
constructing a new building, it may approve the proposal and
communicate its approval to the Board.

(2) On receipt of the Government approval, the


Board shall forward the acquisition proposal to the Land
Acquisition Officer for initiating land acquisition proceedings.

(3) On receipt of the acquisition proposal from the


Board, the Land Acquisition Officer shall publish
simultaneously in the Official Gazette, and in at least four
newspapers circulating within Brihan Mumbai a notice stating
the fact of such proposal having been made by the Board and
approved by the Government and alternative accommodation
proposed to be provided to the occupiers affected by the
proposal and the time before which the building must be
vacated.

(4) The Land Acquisition Officer shall serve the


notice referred to in sub-section (3) on the occupiers and
owner of the building and, so far as it is reasonably practicable
to ascertain such persons, on every mortgagee of the building,
and call upon them to submit objections and suggestions, if
any, why the land should not be acquired, so as to reach him on
or before a date specified in the notice.

(5) On considering the objections and suggestions


and on giving a reasonable opportunity of being heard to the
persons affected by the proposal, the Land Acquisition Officer
may sanction the proposals with or without any modification
(the modifications being approved by the Board) and shall
publish a notification in the Official Gazette fixing a date on
which the proposal as approved shall become operative and the
land specified therein, shall, on and from the date of such
publication, vests absolutely in the Board on behalf of the
Authority free from all encumbrances.

(6) The notification published under sub-section (5)


shall be sufficient authority for the Collector to give notice to
the person in possession of the land to surrender or deliver
possession thereof within a specified period and on his refusal
or failure to do so to take possession of the land and for that
purpose to use such force as may be necessary, and to hand
over possession thereof to the Board, and for the Board to take
further action to get the building vacated in accordance with
the next succeeding sub-sections. No person interested in the
land shall have any right to object to taking such possession or

28/42
WP1366_09.doc

to vacating of the building merely on the ground that the


amount of acquisition has not been fixed or paid.

(7) After the proposal becomes operative, the


occupiers of the building shall vacate their premises within the
time allowed for that purpose under the proposal.

(8) After expiry of the time referred to in sub-section


(7), the Board shall, for the purpose of vacating the building or
such part thereof, as has remained occupied take or cause to be
taken such steps and use or cause to be used such force as may
in the opinion of the Board be reasonably necessary therefor.

(9) The Board may, after giving seven clear days’


notice to the persons evicted under sub-section (8), remove or
cause to be removed or dispose of by public auction any
property remaining in such building.

(10) Where the property is sold under sub-section (9),


the sale proceeds shall, after deducting the expenses of sale, be
paid to such person or persons as may appear to the Board to
be entitled to the same:

Provided that, where the Board is unable to decide as to


the person or persons to whom the balance of the amount is
payable or as to the apportionment of the same, it shall refer
such dispute to a civil court of competent jurisdiction, and the
decision of the court shall be final.

(11) After the building is completely vacated, the


Board shall proceed to construct a new building on the site
according to the proposal.”

19.6. As per sub-section (1), if the state government is satisfied about


the reasonableness of the acquisition proposal submitted under section
92 and is also satisfied of the resources available with the Board for
constructing a new building, it may approve the proposal and
communicate its approval to the Board. Under sub-section (2), on receipt
of the government approval, the Board shall forward the acquisition
proposal to the land acquisition officer for initiating land acquisition
proceedings. Sub-section (3) requires that upon receipt of the acquisition
proposal from the Board, the land acquisition officer shall publish a
notice stating about such proposal made by the Board and approved by
the government and alternative accommodation proposed to be provided

29/42
WP1366_09.doc

to the occupiers affected by the proposal. The notice should also indicate
the timeline for vacating the building. Such a notice shall be published
by the land acquisition officer simultaneously in the official gazette and
in at least four newspapers having circulation within Greater Mumbai.
Under sub-sections (4) and (5), the land acquisition officer shall serve
the notice referred to in sub-section (3) upon the occupiers and owner of
the building as well as on the mortgagee of the building calling upon
them to submit objections and suggestions as to why the land should not
be acquired. On objections and suggestions being made, the land
acquisition officer shall provide a reasonable opportunity of being heard
to the persons affected by the proposal whereafter the land acquisition
officer may sanction the proposal with or without any modification. This
shall be followed by publishing a notification in the official gazette
fixing a date on which the proposal as approved shall become operative
and on and from such a date the land in question shall vest absolutely in
the Board on behalf of MHADA free from all encumbrances.

19.7. Section 94 provides for temporary and alternative accommodation


to the affected occupiers where property is acquired. As per sub-section
(1), the Board shall allot temporary accommodation to occupiers of
building acquired by it for constructing new building.

19.8. Under section 96, on publication of the notification under sub-


section (5) of section 93, the land acquisition officer shall determine the
amount of acquisition in accordance with the provisions of Chapter V.

19.9. Thus from a careful and conjoint reading of section 93 what


transpires is that notice is required to be served by the land acquisition
officer on the occupiers and owner of the building sought to be acquired
under sub-section (3) calling upon them to submit objections and
suggestions as to why the land should not be acquired. The use of the
word shall in sub-section (4) is indicative of the obligatory character of
notice being served upon all the occupiers of the building sought to be

30/42
WP1366_09.doc

acquired. Upon receipt of objections and suggestions, it is also the duty


of the land acquisition officer to give a reasonable opportunity of being
heard to the affected persons. Occupiers of the building sought to be
acquired are certainly persons affected. Therefore, what can be deduced
from the above is that if notice is not served on all the persons affected
and resultantly they are not given a reasonable opportunity of being
heard then in such a case, the acquisition proposal may fall through. Not
only that after the persons affected are given reasonable opportunity of
hearing, the land acquisition officer shall publish a notification in the
official gazette fixing a date on which the acquisition proposal shall
become operative and it is from such notified date that the property shall
vest with the Board. Additionally, upon publication of such a notification
under sub-section (5) of section 93, it is also the duty of the land
acquisition officer to determine the amount of acquisition. That apart,
after the building is completely vacated, the Board shall proceed to
construct a new building on the site according to the proposal.

20. Having analyzed the above, we may now advert to the facts of the
present case.

20.1. Show-cause notice was issued by respondent No.6 on 25.05.2005


to the petitioners for acquisition of land admeasuring approximately
4721.60 sq.mtrs. with building Nos.289/299, 299A and 299B of survey
Nos.641 and 642. The said notice was issued under sub sections (3) and
(4) of section 93 of the MHADA Act. The occupiers of the buildings
and the owners were called upon to submit objections and suggestions
within thirty days. In the list of tenants/occupants as per ‘schedule-C’
appended to the notice, names of tenants/occupants of only the three
buildings i.e. building Nos.289/299, 299A and 299B were mentioned.
Petitioners in their objection dated 27.06.2005 strongly objected to the
acquisition process. It was pointed out that the chawls were strong
enough to be sustained for some more time as per report of structural
engineer. That apart, the chawls were very much repairable. Tenants

31/42
WP1366_09.doc

were opposed to redevelopment by MHADA. If tenants were interested,


it was pointed out, petitioners could carry out repairs/reconstruction.
Further it was brought to the notice of respondent No.6 that the list
appended to the show-cause notice did not contain names of all the
tenants/occupants. Therefore, respondent No.6 was requested to drop
the acquisition proceedings.

20.2. Respondent No.5 also wrote to respondent No.2 on 26.08.2005


stating that reconstruction of only three buildings was taken up at the
first stage for which acquisition of only 2140 sq.mtrs. area out of the
total of 4721.60 sq.mtrs. area was required. Therefore, respondent No.2
was requested to issue necessary corrigendum rectifying the mistake in
land area. This was followed by subsequent letter dated 24.07.2006. It
may be mentioned that in both the letters total number of buildings in the
petitioners property was mentioned as five though it should have been
six.

20.3. As a matter of fact, respondent No.6 had written to respondent


No.5 on 18.11.2006 pointing out that 70% of the occupants of the
buildings had objected to re-development through MHADA which was
submitted in writing during the hearing carried out under section 93(3)
and (4) of the MADA Act. Therefore, respondent No.6 requested that
the proposal for acquisition be dropped.

20.4. Surprisingly and contrary to what the respondent No.6 wrote to


and requested respondent No.5, he issued the impugned order dated
21.12.2006 sanctioning the acquisition proposal under sub section (5) of
section 93 of MHADA Act in respect of land admeasuring 4721.60
sq.mtrs. with building Nos.289/299, 299A and 299B (already referred to
as “the petitioners property”). Thus from the above, it is evident that
though the entire plot of land was sought to be acquired, only three
buildings out of the six buildings standing thereon were sought to be
acquired.

32/42
WP1366_09.doc

20.5. Respondent No.5 continued to correspond with respondent No.2,


firstly on 08.03.2007, thereafter on 01.06.2007 and again on 20.10.2007
requesting the latter to issue corrigendum for reducing the area of the
land acquired from 4721.60 sq.mtrs. to 2140 sq.mtrs. as only three of the
buildings were sought to be acquired. It was pointed out that issuance of
the corrigendum was necessary to enable respondent No.6 to take over
possession of the land and the buildings in terms of section 93(6) of the
MHADA Act. In fact, this was made more specific in the letter dated
28.11.2007 written by respondent No.5 to respondent No.2 where it was
pointed out that only that portion of the land acquired under the three
buildings may be considered as valid.

20.6. Respondent No.3 in its letter dated 20.06.2009 addressed to


respondent No.2 pointed out that only three out of the six buildings were
acquired. In this way, hearing was not given by respondent No.6 to the
tenants/occupants of the remaining three buildings.

20.7. Finally, we may refer to the stand taken by respondent Nos.3, 4


and 5 in their reply affidavit filed on 13.03.2020 to the interim
application of the petitioners. In the said affidavit besides stating that it
is the petitioners who had provided transit accommodation or rent in lieu
thereof to the tenants/occupants, it is admitted that correspondences
were made with respondent No.6 for issuance of corrigendum to reduce
the land area from 4721.60 sq.mtrs. to 2140 sq.mrs.. However, no steps
were taken by respondent No.6. It is also admitted that possession of the
property could not be taken over by respondent No.3 for the purpose of
re-development. Prior to that petitioners submitted scheme before the
High Power Committee for redevelopment under 33(9) which was
permitted by the Court. Therefore, the objective sought to be achieved
by MHADA by way of acquisition has been achieved by the petitioners.

21. Thus, from the factual narrative as above, it is evident that the

33/42
WP1366_09.doc

procedure prescribed for acquisition under section 93 of the MHADA


Act, more particularly under sub sections (4), (5), (6) and (11), has not
been followed. That apart, the provisions of section 96 has also not been
complied with. In addition, the temporary alternate accommodation to be
provided to the tenants/ occupants by the Board under section 94 has not
been provided by the Board; instead the same has been done by the
petitioners. Thus, it is crystal clear that respondent Nos.3 to 6 have not
followed the procedure for acquisition laid down under sections 93, 94
and 96 of the MHADA Act. Because of the faulty show-cause notice
and the impugned order, respondent No.6 has not been able to take
possession of the property. The same has clearly vitiated the acquisition
proceeding.

22. It is a salutary principle of administrative law that when the law


requires a thing to be done in a particular manner, it has to be done in
that particular manner or not at all. For failure to adhere to the
procedure laid down in sections 93, 94 and 96 of the MHADA Act more
particularly in not serving notice under sub section (3) of section 93
upon all the occupiers of the buildings standing on the petitioners
property and not giving them reasonable opportunity of being heard,
respondent No.6 has acted in violation of the principles of natural justice
which has clearly vitiated the acquisition proceedings.

23. For the aforesaid reasons, the impugned order dated 21.12.2006
cannot be sustained and on this ground alone, the same is liable to be set
aside and quashed.

24. However, since respondents have raised the issue of acquiescence


by the petitioners to the process of acquisition by proceeding with
redevelopment under DCR 33(9), we feel that the said aspect may also
be addressed. But before that we may refer to DCR 33(7) and DCR
33(9).

34/42
WP1366_09.doc

25. In exercise of the powers conferred by sub section (1) of section


31 of the Maharashtra Regional and Town Planning Act, 1966, the
Development Control Regulations (DCR) have been framed. At the
relevant point of time, Development Control Regulations for Greater
Mumbai, 1991 were in force. The same has since been replaced by the
Development Control and Promotion Regulations for Greater Mumbai,
2034 which have come into force with effect from 01.09.2018. DCR 33
deals with additional floor space index (FSI) which may be allowed in
certain categories. DCR 33(7) deals with reconstruction or
redevelopment of cessed buildings in Mumbai by co-operative housing
societies or of old buildings belonging to the MCGM or of old buildings
belonging to the police department. We have seen that petitioners had
initially submitted proposal for redevelopment under DCR 33(7) but
subsequently fresh proposal was submitted under DCR 33(9). Prior to
02.03.2009, DCR 33(9) provided for repairs and reconstruction of
cessed buildings and urban renewal scheme. It stated that for repairs and
reconstruction of cessed buildings and urban renewal scheme undertaken
by MHADA or by the Mumbai Housing and Area Development Board
or by the MCGM, the FSI should be 1.00 or the FSI required for
rehabilitation of existing tenants/occupiers, whichever was more. After
02.03.2009, there was change in DCR 33(9). Amended DCR 33(9) read
as under :-
“(9) Reconstruction or redevelopment of cessed
buildings/Urban Renewal Schemes on extensive area.-
For reconstruction or redevelopment of cessed
buildings/Urban Renewal Schemes in Island City,
undertaken by (a) the Maharashtra Housing and Area
Development Authority or Municipal Corporation of
Greater Mumbai either departmentally or through any
suitable agency or (b) MHADA/MCGM jointly with land
owners and/or Co-operative Housing Societies of
tenants/occupiers of buildings or Developer or Co-operative
Housing Society of hutment dwellers therein (c)
independently by land owners and/or Co-operative Housing
Societies of tenants/occupiers of buildings or Developer, the
FSI shall be 4.00 or the FSI required for rehabilitation of
existing tenants/occupiers plus incentive FSI as given in
Appendix III-A, whichever is more.”

35/42
WP1366_09.doc

25.1. It may be mentioned that DCR 33(9) came to be further amended


on and from 09.09.2014 in the following manner:-
“(9) Reconstruction or redevelopment of Cluster(s) of
Buildings under Urban Renewal Scheme(s).- For
reconstruction or redevelopment of Cluster(s) of buildings
under Urban Renewal Scheme(s) in the Island City of
Mumbai undertaken by (a) the Maharashtra Housing & Area
Development Authority (MHADA) or the Municipal
Corporation of Greater Mumbai (MCGM) either
departmentally or through any suitable agency, or (b)
MHADA/MCGM, jointly with land owners and/or Co-op.
Housing Societies of tenants/occupiers of buildings and/or
Co-op. Housing Society of hutment dwellers therein, or (c)
land owners and/or Co-op. Housing Society of
tenants/occupiers of buildings and/or Co-op. Housing
Society of hutment dwellers, independently or through a
Promoter/Developer, the FSI shall be 4.00 or the FSI
required for rehabilitation of existing tenants/occupiers plus
incentive FSI as per the provisions of Appendix-III-A,
whichever is more.”

26. Thus reconstruction or redevelopment of cessed buildings or


under the urban renewal scheme could be carried out in the following
manner :-
(a) by MHADA or MCGM either departmentally or through
any suitable agency; or
(b) by MHADA/MCGM jointly with land owners and/or Co-
operative Housing Societies of tenants/occupiers of
buildings or Developer or Co-operative Housing Society of
hutment dwellers; or
(c) independently by land owners and/or Co-operative Housing
Societies of tenants/occupiers of buildings or Developer or
as per amendment on 09.09.2014 by Co-operative Housing
Society of hutment dwellers independently or through a
Promoter / Developer.

27. Therefore what is deducible from the above is that the amended

36/42
WP1366_09.doc

DCR 33(9) provides that reconstruction or redevelopment could be


independently carried out by the land owners and/or co-operative
housing societies of tenants/occupiers of the buildings or by the
developer. Though under the Development Control and Promotion
Regulations for Greater Mumbai 2034, DCR 33(9) has undergone
substantive changes, it may not be necessary to deal with the same as the
redevelopment has taken place under the amended DCR 33(9) of
Development Control and Promotion Regulations for Greater Mumbai,
1991, as extracted above. Because the reconstruction or redevelopment
has been carried out by the land owners (in this case petitioners) with
MHADA, it does not mean that there is acceptance by the petitioners to
the acquisition by MHADA.

28. This brings us to the concept of acquiescence or waiver.

29. Black’s Law Dictionary, Eighth Edition has defined ‘acquiesce’ as


to accept tacitly or passively; to give implied consent to an act.
‘Acquiescence’ has been explained as a person’s tacit or passive
acceptance; implied consent to an act.

29.1. Acquiescence as a principle of substantive law is grounded in the


concepts of good faith and equity.

30. Supreme Court in M/s. Power Control Appliances (supra) in the


context of infringement of trade mark held that acquiescence is sitting by
when another is invading the rights and spending money on it. It is a
course of conduct inconsistent with the claim for exclusive rights in a
trade mark etc. It implies positive acts and not merely silence or
inaction. It was held as follows:
“26. Acquiescence is sitting by, when another is invading the
rights and spending money on it. It is a course of conduct
inconsistent with the claim for exclusive rights in a trade mark,
trade name etc. It implies positive acts; not merely silence or
inaction such as is involved in laches. In Harcourt v. White Sr.
John Romilly said: "It is important to distinguish mere

37/42
WP1366_09.doc

negligence and acquiescence." Therefore, acquiescence is one


facet of delay. If the plaintiff stood by knowingly and let the
defendants build up an important trade until it had become
necessary to crush it, then the plaintiffs would be stopped by
their acquiescence. If the acquiescence in the infringement
amounts to consent, it will be a complete defence as was laid
down in Mouson (J. G.) & Co. v. Boehm. The acquiescence
must be such as to lead to the inference of a licence sufficient
to create a new right in the defendant as was laid down in
Rodgers v. Nowill.”

30.1. Elaborating on the law of acquiescence, reference was made to


English decisions. It was held that to support a plea of acquiescence in a
trade mark case, it must be shown that the plaintiff has stood by for a
substantial period and thus encouraged the defendant to expend money
in building up a business associated with the mark. Again referring to
Halsbury's Laws of England, Fourth Edition, Volume 24 at paragraph
943, it has been held that an injunction may be refused on the ground of
the plaintiff's acquiescence in the defendant's infringement of his right.
Though the principles on which the court will refuse interlocutory or
final relief on this ground are the same but a stronger case is required to
support a refusal to grant final relief at the hearing. This is because at the
time of hearing it is the court’s duty to decide upon the rights of the
parties and the dismissal of the action on the ground of acquiescence
amounts to a decision that a right which once existed is absolutely and
forever lost.

31. In State of Punjab Vs. Davinder Pal Singh Bhullar, (2011) 14


SCC 770, Supreme Court after referring to M/s. Power Control
Appliances (supra) clarified that inaction in every case does not lead to
an inference of implied consent or acquiescence. Court has to examine
the facts and circumstances in an individual case. Acquiescence being a
principle of equity must be made applicable where a party knowing all
the facts of bias etc. surrenders to the authority of the Court / Tribunal
without raising any objection. It has been held that acquiescence is
sitting by when another is invading the rights. The acquiescence must be
such as to lead to the inference of a licence sufficient to create rights in

38/42
WP1366_09.doc

other party.

32. A Single Bench of this Court in Emcure Pharmaceuticals


Limited (supra) which was also a case of trade mark infringement held
that the question of acquiescence arises where a mark’s proprietor being
aware of his rights and being aware that the infringer may be ignorant of
these does some affirmative act to encourage the infringer’s
misapprehension so that the infringer worsens his position and acts to his
detriment. A mere failure to sue without a positive act of encouragement
is no defence and is no acquiescence. It has been held that a man cannot
sit indolent and idle, aware of the invasion of his rights by another, and
then complain of that invasion. Elaborating further it has been held that
acquiescence is a species of estoppel, a rule in equity and a rule of
evidence. Essential to the acquiescence doctrine is that it is accompanied
by an encouragement or an inducement. Acquiescence is sitting by when
another invades his rights and spends money in the doing of it. It is a
conduct incompatible with claims of exclusivity but it requires positive
acts, not mere silence or inaction. Acquiescence is not mere negligence
or oversight. There must be abandonment of the right to exclusivity.

33. Supreme Court in the case of Kalpraj Dharamshi (supra) held


that for constituting acquiescence or waiver it must be established that
though a party knows the material facts and is conscious of his legal
rights in a given matter but fails to assert his rights at the earliest
possible opportunity, it creates an effective bar of waiver against him.
On the one hand, acquiescence would be a conduct where a party is
sitting by when another is invading his rights and acquiescence must be
such as to lead to the inference of a licence sufficient to create a new
right in the defendant, on the other hand, waiver is an intentional
relinquishment of a right. It involves conscious abandonment of an
existing legal right, advantage, benefit, claim or privilege. It is an
agreement not to assert a right; there can be no waiver unless the person
who is said to have waived is fully informed as to his rights and with full

39/42
WP1366_09.doc

knowledge about the same, he intentionally abandons them.

34. Having noticed the above, we find that in the instant case,
petitioners had initially submitted proposal on 29.03.2006 before
respondent Nos.3 to 5 for development of the entire property under DCR
33(7) which had the support of 70% of the tenants. The said proposal
was stated to be pending. When respondent No.6 issued the impugned
order dated 21.12.2006, this order dated 21.12.2006 came to be
challenged by the petitioners in the present writ proceeding.

35. We have already discussed about the exchange of


communications between different authorities pointing out the defects in
the acquisition notice and order. We have mentioned that DCR 33(9) was
amended with effect from 02.03.2009. Following the same petitioners
had submitted proposal on 20.06.2009 to respondent No.5 for
redevelopment under amended DCR 33(9). We have also seen that under
amended DCR 33(9) there is provision for the land owner to carry out
redevelopment independently.

36. This Court by order dated 19.07.2010 as corrected on 02.08.2010


had admitted the writ petition by issuing Rule. In the meanwhile,
petitioners were permitted to carry out joint development of the property
under DCR 33(9) with MHADA. Petitioners have carried out
redevelopment jointly with MHADA as per order of this Court. When
this Court had issued Rule by admitting the writ petition and thereafter
passed the order in the above terms, such order would necessarily be
construed to be an order in the interregnum. When the petitioners acted
upon the said order it cannot be construed that petitioners had abandoned
their challenge to the acquisition proceedings by going ahead with the
redevelopment jointly with MHADA. As already noticed above, there is
no sitting by of the petitioners to the invasion of their rights by
MHADA. As a matter of fact in several subsequent documents which
have been placed on record it has been clarified that such redevelopment

40/42
WP1366_09.doc

was subject to outcome of the writ petition. In the letter dated


22.09.2015 written by the Board to the High Power Committee it was
pointed out that this Court had permitted redevelopment of the property
under DCR 33(9) as cluster on assumption that the property had been
acquired by MHADA. However, it was mentioned that the present writ
petition was pending for final hearing and the final outcome of the writ
petition would be binding upon the petitioners and MHADA. Again in
the supplementary agreement dated 24.07.2017 entered into between the
Board and petitioner No.2, it was mentioned that the purported order of
acquisition by MHADA dated 21.12.2006 was challenged by the
petitioners in the present writ petition which was pending for final
hearing and disposal. It was also mentioned that the redevelopment was
subject to final outcome of the pending writ petition.

36.1. We may also mention that once a writ petition is admitted for
hearing by issuing Rule, it would be highly unjust and inequitable to
non-suit the petitioners on the ground of delay and laches after a decade
or so at the stage of final hearing. However, in the given facts and
circumstances of the case, we are of the opinion that there was no undue
delay by the petitioners.

37. Thus having regard to the above we are of the considered view
that the plea of acquiescence by the petitioners as raised by the
respondents is without any substance and is accordingly rejected.

38. Though learned counsel for the petitioners had referred to and
relied upon the Division Bench decision of this Court in Bhalchandra
Datey (supra), in view of the conclusions reached, it may not be
necessary for us to dwell on the same.

39. For the reasons already indicated we are of the unhesitant view
that the impugned order dated 21.12.2006 cannot be sustained.
Accordingly the same is hereby set aside and quashed.

41/42
WP1366_09.doc

40. Petitioners succeed and consequently the writ petition is allowed


to the above extent. Interim Application is also disposed of. However,
there shall be no order as to cost.

(MADHAV J. JAMDAR, J.) (UJJAL BHUYAN, J.)

Minal Parab

42/42

You might also like